Professional Documents
Culture Documents
Jview TechnicalNote en v1 TotalViewStandardReports
Jview TechnicalNote en v1 TotalViewStandardReports
Jview TechnicalNote en v1 TotalViewStandardReports
Reports 2
Standard Reports
Crew By Hour
The Crew Production Per Hour report provides a view of the amount of loads and tons
per hour, per shift, and per day. The bar graph displayed below the table provides a
graphical representation of this data.
To load the Crew By Hour report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then
choose the desired start date by clicking
it.
1
TotalView
Reports 2
Crew Lineup
The Crew Lineup report is used to display equipment assignments and locations for the
current or oncoming crew.
To load the Crew Lineup report, please use the directions listed below.
Directions Images
Step 1: Click the Select Shift drop-down
menu to open it, choose the desired option
from the list, and then click it.
Step 2: Click the View Report button.
2
TotalView
Reports 2
Crew Production
The Crew Production report displays the load and tonnage per crew as well as per day.
The detailed table shows the production load count and tonnage by origin and material.
3
TotalView
Reports 2
To load the Crew Production report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
4
TotalView
Reports 2
Crusher By Hour
The Crew Loads Per Hour To Crusher report displays the load and tonnage dumped at the
crusher per hour, per shift, as well as per day.
To load the Crew Loads Per Hour To Crusher report, please use the directions listed
below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
5
TotalView
Reports 2
Dumps By Location
The Dumps By Dump Location report displays the number of dumps and tonnage amount
per dump location per shift per day. The bar graph displays each dump location with the
loads and tonnage per shift per day.
6
TotalView
Reports 2
To load the Dumps By Dump Location report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
7
TotalView
Reports 2
Equipment Down
The Equipment Down Detail report displays a list of trucks in the down status, the
duration of time spent in the down status including the time it went down and the time it
went back up, and the reason code for the down status.
To load the Equipment Down Detail report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then
choose the desired start date by clicking it.
8
TotalView
Reports 2
9
TotalView
Reports 2
The Current Down Equipment report provides a graphical display of the current down
equipment, and whether or not it was a scheduled or unscheduled down. It provides a
listing of the equipment type, fleet, and number of trucks per fleet. The detailed view
provides a graphical display of the down reason codes per truck and unscheduled and
scheduled downs.
10
TotalView
Reports 2
To load the Current Down Equipment report, please use the directions listed below.
Directions Images
Step 1: Click the Select EQPType drop-
down menu to open it, and then click the
box located to the left of the desired
equipment type to place a check mark in it.
Step 2: Click the Select Down
TimeCategory drop-down menu to open
it, and then click the box located to the left
of the desired down time category to place
a check mark in it.
Step 3: Click the Select Fleet drop-down
menu to open it, and then click the box
located to the left of the desired fleet to
place a check mark in it.
11
TotalView
Reports 2
Equipment Status
The Equipment Status Detail report provides the fleet, shift, status reason, and duration of
status including the exact time the status occurs per day. In the total summary section of
the report it includes the number of equipment per fleet.
12
TotalView
Reports 2
To load the Equipment Status Detail report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then
choose the desired start date by clicking it.
13
TotalView
Reports 2
The Summary section of the Top Ten States report provides the top ten equipment states
for the date range. It includes the description of the state, time, events, and the average
duration for each state. The pie chart displays a graphical representation of this data. The
detail section of the Top Ten States report provides the top ten equipment states per day
within the date range.
14
TotalView
Reports 2
To load the Top Ten States report, please use the directions listed below.
Directions Images
Step 1: Click the Select End Date calendar
button to open it, and then choose the
desired start date by clicking it.
15
TotalView
Reports 2
16
TotalView
Reports 2
Fuel Detail
The Fuel Detail report provides a per hour view of when each piece of equipment
receives fuel, the amount they get, the exact time of fueling, the duration of time spent
fueling, and the fuel type. The bar graph is a graphical display of the volume of fuel
obtained per shift per fleet.
17
TotalView
Reports 2
To load the Fuel Detail report, please use the directions listed below.
Directions Images
Step 1: Click the Select Date calendar
button to open it, and then choose the
desired start date by clicking it.
18
TotalView
Reports 2
Material Movement
The Material Movement report provides a view of all blast dump source and destination
pairs used during the shift, as well as the total tonnage and load count per pair.
To load the Material Movement report, please use the directions listed below.
19
TotalView
Reports 2
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
20
TotalView
Reports 2
Shovel By Hour
The Shovel Loads Per Hour report provides a display of the total tonnage and total trucks
loaded per hour per shift. The bar graph is a graphical representation of this data.
21
TotalView
Reports 2
To load the Shovel Loads Per Hour report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
22
TotalView
Reports 2
Shovel Shift
The Shovel Shift Summary report provides a per day per shovel view including duration
of time the shovel is in ready status, the tons per operating hour, the trucks loaded and
tonnage received, and the average tonnage per load.
To load the Shovel Shift Summary report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
23
TotalView
Reports 2
24
TotalView
Reports 2
Truck Cycles
The Trucks Cycles report provides a view of the total and average time spent in each
status of the haul cycle.
25
TotalView
Reports 2
To load the Truck Cycles report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
26
TotalView
Reports 2
Truck Haulage
The Truck Haulage report provides a per day view of the fleet and truck haulage.
Including the number of shifts the truck was used, the total loads, the loads per shift, the
total tonnage, and tonnage per shift. The bar graph displays the loads and tonnage for
each truck for each fleet.
27
TotalView
Reports 2
To load the Truck Haulage report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
28
TotalView
Reports 2
Trucks At Shovel
The Trucks Waiting At Shovel report provides a graphical display of the trucks waiting at
a particular shovel during a shift.
29
TotalView
Reports 2
To load the Trucks Waiting At Shovel report, please use the directions listed below.
Directions Images
Step 1: Click the Select Start Date
calendar button to open it, and then choose
the desired start date by clicking it.
30