Kế hoạch tiến độ lắp đặt Pump .27.6

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Check Date : 26-June-2022 P.

1
SUPERVISOR AT SITE FOR PUMP INSTALLATION SCHEDULE CHART Doc No. :

CUSTOM PMS ITEM NO. 190-P-301 A / B, 190-P-302 A / B


ER

FINAL NGHI SON REFINERY AND PETROCHEMICAL LLC JOB NO. -


USER
PROJECT BIOLOGICAL POND SYSTEM PROJECT SERVICE WASTE WATER PUMP TO THE SEA
27/06/2022 28/06/2022 29/06/2022- 01/07/2022 02/07/2022 03/07/2022-04/07/2022 05/07-06/07/2022
WORKS DISCRIPTION \
PERIOD
Alignment for Base plate for 4
Pump 301A/B, 302A/B
User acceptance and Grouting
Work
Maintenance for Best Grouting

Pump installation for 4 pump


301A/B and 302 A/B

Motor Installation, Pump Auxiliary piping


connection For 4 Pump

Adjustment of Axial clearance,


coupling aligment for 4 Pump