2023.03.14-1420-MPL-CZ-3 - To Continue The Ongoing Work at Ch. 74+584 To 74+910 Near Kilomi New Village
2023.03.14-1420-MPL-CZ-3 - To Continue The Ongoing Work at Ch. 74+584 To 74+910 Near Kilomi New Village
(JV)
M/s Manglam Associates C/o - Mr. Inaghi H Achumi, (Near Gogoi Service
Centre),R/o. House no. 127,South Point Colony East,
Hospital Junction,Nagaland-798620
To
The Project Manager,
M/s. Madhucon Project Limited
Chakabama-Zunheboto Road, Package-III
Email: pm.nagaland@madhucon.com
Subject: Consultancy Services for Authority Engineer for Supervision of “Two-lane with hard Shoulders
of Chakabama-Zunheboto Road from: Design Km 50.000 to Km 75.000 (Existing Km 52.370 to Km
79.040)” in state of Nagaland under SARDP-NE on EPC mode: Reg. - “Re-minder to continue the on-
going work in speedy manner including the hindered chainage from Ch 74+584 to 74+910 near
Kilomi new Village.”
Ref.: 1. NHIDCL/PMU-PFU/CZ-III/MPL/VOL-II/58, dated 04.02.2023
2. LR/LAND/SARDP-95/(PT-1)/2018/77, dated 03.02.2023
Sir,
I am writing this letter to express my concerns regarding the slow progress of the ongoing work in
the CZ Road Project, particularly the hindered chainage from Ch. 74+584 to 74+910 near Kilomi new
Village. It has come to my attention that the work progress has been very slow for the last 3-4 days, and
this has affected the project's performance, making it difficult to achieve the milestones. Therefore, I
strongly urge you to expedite the work progress and do the needful for the timely completion of the whole
project.
As per the Deputy Commissioner's letter expressed in his letter cited above, the matter has already been
taken up by him and the concerned department of work and housing, Govt. of Nagaland. However, it has
been more than a month since the matter was taken up, and no concrete progress can be seen so far at
those chainages of the CZ Road Project. Formation cutting needs to be completed as soon as possible to
ensure that the black topping work can be completed as scheduled.
I hope you will take necessary steps to expedite the work progress and complete the project on time.
Thank you,
Sanjay Kumar
(Team Leader)
Almondz Global Infra-Consultant Ltd.
(JV) Manglam Associates.
Chakabama-Zunheboto Road Project
Copy to:
1. The General Manager (Projects), NHIDCL, PMU-Pfutsero, Nagaland - 797107
2. S.O. NHIDCL, Zunheboto
3. The MD, Almondz-Manglam Associates (JV)
4. Office file