Alternatif Soil Reinforcement Pada Pekerjaan Jalan Dan Landasan Pacu
Alternatif Soil Reinforcement Pada Pekerjaan Jalan Dan Landasan Pacu
LANDASAN PACU
Reinforced concrete
panel or cladding
HWS
Geotextile
or
Geogrid
LWS
HWS
Geotextile
or
Geogrid
(or combination
LWS
of both)
HWS
Geogrid
LWS
HWS
Geotextile
and
Geogrid
LWS
Possible circular
sliding plane
Anchorage length
Micropiles (“cerucuk”)
18
Gabion reinforced
with geogrid
Scoured bottom
20
Water level
during flood
APA ITU GEOSINTETIK ?
1
REINFORCEMENT (PERKUATAN)
FILTRATION (FILTER)
DRAINAGE (DRAINASE)
KARAKTERISTIK BAHAN GEOSINTETIK
4
6
3 MULLEN BURSTING TEST
(ASTM D 3786-87)
KARAKTERISTIK MEKANIS
(puncturing & bursting)
pressure
puncturing
bursting
KARAKTERISTIK HIDROLIS
(ukuran pori & permeabilitas)
HUBUNGAN
BENTUK DAN FUNGSI GEOSINTETIK
Bentuk
geotextile geomembrane geogrid geocomposite
Fungsi
filtration - -
separation -
drainage - -
reinforcement
HUBUNGAN
KARAKTERISTIK DAN FUNGSI GEOSINTETIK
Bentuk
separation filtration drainage reinforcement
Fungsi
Tensile
strength
Burst
strength
Hydraulic
flow
Surface
texture
Perkerasan jalan Kerikil (Base)
Tanah Sirtu
(Subbase)
REVIEW
Tanah Lunak
PERANAN TANAH
PADA BANGUNAN
(a) Tanah Sebagai Pondasi Jalan
Geotekstile
tebal rencana
Geotekstile/
geogrid
O
R
q = beban lalu lintas
A
Ti
i
Pa1 Si
S1
B C
i i
Kondisi Internal Stability tercapai bila tidak terjadi
longsor pada lereng AC, dan bila perlu digunakan TANPA GEOTEXTILE :
beberapa lapis geotekstile
Momen Penahan (Mr) = R. i . li
Pa1 (Berat efektif ABC) x tan δ + n. S1
SF
DENGAN GEOTEXTILE :
dimana adalah sudut geser antara tanah
Momen Penahan (Mr) = R. i . li + Ti . Si
timbunan dan material geotekstile dan SF = 1,10
s/d 1,5. = Mr + Mr
SF = 1,10 untuk jalan sementara (semi permanen),
&
SF = 1,50 untuk jalan permanen
S4
H
Pa1 Tahanan oleh ABC + n. S1 S3
S2
dimana S1 adalah kekuatan tarik material S1
geotekstile yang diijinkan = Tallowable Mr = Ti . Si
(3). FOUNDATION STABILITY
timbunan
H
’vo
S2
Tanah lunak, t
Pp Pa2 h
Pp + 2.Su x L
Pa2 & S2 (Su x L) x SF
SF
’vo = q + H.timbunan
FAKTOR-FAKTOR
PENGURANGAN KEKUATAN GEOTEKSTILE
1
Tallow = Tult
FSID x FSCR x FSCD x FSBD
3m 2,5
m
3m 9m
DAYA DUKUNG TANAH DASAR RENDAH 3m
•Hanya mampu mendukung tanah max. 1,5 m
•Bagaimana untuk talud setinggi 3 m ?
STABILITAS TALUD BADAN JALAN KECIL
•SF stabilitas talud hanya 0,809
•Bagaimana untuk mencapai SF = 1,25 ?
0,6 m
2,4 m
8
x
30 cm
1,5 – 2,0
meter
b). As Capilarry Cut-Of
Catatan :
Tanah asli harus dalam kondisi basah / jenuh air pada
sa’at ditutup geomembrane
Tanah isian
1,5
meter
Kondisi semula
RUAS JALAN PONOROGO - PACITAN
Geomembrane
Geomembrane,
(saluran menjadi
kedap air)
Geotekstile
Kondisi semula
RUAS JALAN TOL SURABAYA - GEMPOL
Geomembrane
Gebalan rumput
Subdrain
Kondisi semula
RUAS JALAN KRIAN - GRESIK
Geotekstile
Geomembrane
geotextile woven
wahyu@geosistem.co.id
www.geosistem.co.id
masalah tanah dasar kembang-susut
Geomembrane PVC
wahyu@geosistem.co.id
www.geosistem.co.id
masalah stabilisasi tanah dasar
geotextile woven
wahyu@geosistem.co.id
www.geosistem.co.id
masalah overlay perkerasan aspal
geotextile nonwoven
wahyu@geosistem.co.id
www.geosistem.co.id
masalah perkuatan abutment
geotextile woven
wahyu@geosistem.co.id
www.geosistem.co.id
masalah perkuatan tembok utk
penahan tanah
geotextile woven
wahyu@geosistem.co.id
www.geosistem.co.id
masalah tanah dasar lunak
Permasalahan Tanah
Lempung Lunak
Berat Jenis
Kedalaman Rata γ lab γ air Kadar Air γ sat γ sat γd lab γd lab γ' qu c c ϕ Cv Cv
NSPT Jenis Tanah Konsistensi E μ (GS) e Lab Cc PI
(m) Rata (kN/m³) (kN/m³) (%) (kN/m³) (gr/cm³) (gr/cm³) (kN/m³) (kN/m³) 0 (kN/m²) (kg/cm²) (kN/m²) (°) cm²/s m²/years
MAT
0-2 - 1.00 m 0 Lempung Lanauan 0.00 3000 0.40 15.1 9.81 67% 2.61 15.4 1.568 0.92 9.02 5.6 1.84 0.65 20.4 0.102 10.2 6.516 0.00150 4.73040 56.50
2-4 2 Lempung Lanauan
2.00 3000 0.40 15.1 9.81 67% 2.61 15.4 1.568 0.92 9.02 5.6 1.84 0.65 20.4 0.102 10.2 6.516 0.00150 4.73040 56.50
4-6 2 Lempung Lanauan
6-8 0 Lempung Lanauan
Very Soft
8-10 0 Lempung Lanauan
10-12 0 Lempung Lanauan 0.00 3000 0.40 14.5 9.81 82% 2.64 14.8 1.506 0.81 7.98 5.0 2.25 0.56 7.6 0.038 3.8 3.91 0.00100 3.15360 54.89
12-14 0 Lempung Lanauan
14-16 0 Lempung Lanauan
16-18 12 Lempung Lanauan
18-20 15 Lempung Lanauan
Medium 12.75 7875 0.40 14.8 9.81 74% 2.64 15.1 1.539 0.87 8.50 5.3 2.05 0.66 52.5 0.2625 26.25 3.91 0.00050 1.57680 55.92
20-22 13 Lempung Lanauan
22-24 11 Lempung Lanauan
DATA PERENCANAAN
DATA MATERIAL DAN GEOMETRI TIMBUNAN
Grafik Hubungan
antara tinggi
timbunan dengan
Hakhir
PENENTUAN HINISIAL TERPILIH
Grafik
Hubungan
antara St
dengan Hakhir
PENENTUAN HINISIAL TERPILIH
Tinggi timbunan akhir (HAkhir) = 6,14 m (Tinggi timbunan rencana +
Surcharge)
= 3,65 m
PERENCANAAN GEOTEKSTIL
Lapisan 𝑇
Data Tanah Tanah Dasar 𝑇𝑎𝑙𝑙𝑜𝑤 =
Timbunan 𝐹𝑆𝑖𝑑 ×𝐹𝑆𝑐𝑟 ×𝐹𝑆𝑐𝑑 ×𝐹𝑆𝑏𝑑
(m) (m) (t/m²) (m) (m) (m) (m) (m) (m) (m) (m)
20 (Top) 9.8 0.3 1.02 0.30 0.7 1.00 1.00 4.94 5.94 8 1.00
19 9.8 0.8 1.25 0.50 0.5 1.00 1.00 4.68 5.68 8 1.00
18 9.8 1.3 1.49 0.50 0.4 1.00 1.00 4.42 5.42 8 1.00
17 9.8 1.8 1.73 0.50 0.3 1.00 1.00 4.16 5.16 8 1.00
16 9.8 2.3 1.97 0.50 0.3 1.00 1.00 3.90 4.90 7 1.00
15 9.8 2.8 2.20 0.50 0.3 1.00 1.00 3.64 4.64 7 1.00
14 9.8 3.3 2.44 0.50 0.3 1.00 1.00 3.38 4.38 7 1.00
REKAPITULASI 13 9.8 3.8 2.68 0.50 0.2 1.00 1.00 3.12 4.12 7 1.00
PANJANG GEOTEKSTIL 12
11
9.8
9.8
4.3
4.8
2.91
3.15
0.50
0.50
0.2
0.2
1.00
1.00
1.00
1.00
2.86
2.60
3.86
3.60
6
6
1.00
1.00
10 9.8 5.3 3.39 0.50 0.2 1.00 1.00 2.34 3.34 6 1.00
9 9.8 5.8 3.63 0.50 0.2 1.00 1.00 2.08 3.08 6 1.00
8 9.8 6.3 3.86 0.50 0.2 1.00 1.00 1.82 2.82 5 1.00
7 9.8 6.8 4.10 0.50 0.2 1.00 1.00 1.56 2.56 5 1.00
6 9.8 7.3 4.34 0.50 0.2 1.00 1.00 1.30 2.30 4 1.00
5 9.8 7.8 4.58 0.50 0.2 1.00 1.00 1.04 2.04 4 1.00
4 9.8 8.3 4.81 0.50 0.2 1.00 1.00 0.78 1.78 4 1.00
3 9.8 8.8 5.05 0.50 0.2 1.00 1.00 0.52 1.52 3 1.00
2 9.8 9.3 5.29 0.50 0.2 1.00 1.00 0.26 1.26 3 1.00
1 9.8 9.8 5.53 0.50 0.2 1.00 1.00 0.00 1.00 3 1.00
PERENCANAAN GEOTEKSTIL
KONTROL EXTERNAL STABILITY
L (m) FSguling
4 2,4
5 3,7
6 5,4
7 7,3
8 9,6
9 12,1
10 14,9
11 18,1
12 21,5
13 25,2
14 29,3
15 33,6
16 38,2
17 43,1
18 48,4
19 53,9
20 59,7
PERENCANAAN GEOTEKSTIL
KONTROL EXTERNAL STABILITY
= 11,47 t 𝑆𝐹 =
49,695
W =γxHxL 18,71
L (m) FSgeser
5 2,66
6 3,11
7 3,57
8 4,02
9 4,48
10 4,94
11 5,39
12 5,85
13 6,30
14 6,76
15 7,22
16 7,67
17 8,13
18 8,58
19 9,04
20 9,50
PERENCANAAN GEOTEKSTIL
KONTROL EXTERNAL STABILITY
Tabel Nilai Fsdaya dukung dengan Variasi Panjang Geotekstil Minimum (L)
L (m) FSdayadukung
7 0,85
8 0,90
9 0,94
10 0,97
11 0,99
12 1,02
13 1,04
14 1,06
15 1,08
16 1,11
17 1,14
18 1,16
19 1,19
20 1,21
Panjang geotekstil minimum yang aman pada perhitungan kontrol gaya guling, gaya geser dan daya
dukung adalah L = 20 m. Sehingga pada perencanaan ini, geotekstil yang dipasang adalah sepanjang 20 m
di setiap sisi timbunan
PERENCANAAN GEOTEKSTIL
PENYESUAIAN PANJANG GEOTEKSTIL
Cu
Kedalaman PI Cu Baru
Lama
(m) (%) kN/m2 kN/m2
0 2 56.50 10.2 20.32
2 6 56.50 10.2 22.07
6 16 54.89 3.8 25.70
16 24 55.92 26.25 29.17
PERENCANAAN TIMBUNAN BERTAHAP DENGAN GEOTEKSTIL TAHAP 2
Umur Timbunan
Derajat konsolidasi U%
Po' ∆P1' ∆P2' ∆P3' ∆P4' ∆P5' ∆P6' ∆P7' ∆P8' ∆P9' ∆P10' ∆P11' ∆P12' ∆P13' ∆P14' ∆P15' ∆P16' ∆P17' ∆P18' ∆P19' ∆P20'
Perubahan (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2) (kN/m2)
Tegangan 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Ʃσ'
kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m kN/m
Tinggi Timbunan H=0m H=0,5m H=1m H=1,5m H=2m H=2,5m H=3m H=3,5m H=4m H=4,5m H=5m H=5,5m H=6m H=6,5m H=7m H=7,5m H=8m H=8,5m H=9m H=9,5m H=9.8m (kN/m2)
Umur Timbunan 0 20 mg 19 mg 18 mg 17 mg 16 mg 15 mg 14 mg 13 mg 12 mg 11 mg 10 mg 9 mg 8 mg 7 mg 6 mg 5 mg 4 mg 3 mg 2 mg 1 mg
Kedalaman / U% 100% 83% 82% 80% 78% 76% 74% 72% 69% 66% 63% 59.71% 55.95% 51.83% 47.32% 42.38% 36.97% 31.03% 24.50% 17.31% 9.35%
0 2 5.58 6.56 6.72 6.67 6.55 6.41 6.24 6.04 5.83 5.59 5.32 5.04 4.72 4.37 3.99 3.57 3.11 2.61 2.06 1.45 0.78 99.21
2 6 22.30 6.95 6.85 6.73 6.59 6.43 6.25 6.05 5.83 5.59 5.32 5.03 4.71 4.37 3.98 3.57 3.11 2.61 2.06 1.45 0.78 116.57
6 16 58.30 6.72 6.60 6.47 6.32 6.16 5.98 5.79 5.58 5.34 5.09 4.81 4.50 4.17 3.81 3.41 2.97 2.49 1.97 1.39 0.75 148.62
16 24 104.28 5.83 5.72 5.61 5.48 5.34 5.18 5.01 4.83 4.63 4.40 4.16 3.90 3.61 3.29 2.95 2.57 2.16 1.70 1.20 0.65 182.51
Cu
Kedalaman PI Cu Baru
Lama
(m) (%) kN/m2 kN/m2
0 2 56.50 10.2 22.44
2 6 56.50 10.2 24.17
6 16 54.89 3.8 27.74
16 24 55.92 26.25 30.90
ANALISIS METODE ELEMEN HINGGA DENGAN PLAXIS 2D V20
ANALISIS KONSOLIDASI
Hasil penurunan yang terjadi dengan Hinisial 9,8 meter di BH-15 dengan PVD dan
geotekstil adalah sebesar 3,90 meter dalam waktu 190 hari
HASIL
ANALISIS
ANALISIS
METODE
KONSOLIDASI
ELEMEN HINGGA
MENGGUNAKAN
DENGANSOFTWARE
PLAXIS 2D PLAXIS
V20
ANALISIS KONSOLIDASI
ANALISIS METODE ELEMEN HINGGA DENGAN PLAXIS 2D V20
nilai faktor keamanan (SF) pada timbunan pasca konstruksi yaitu sebesar 1,531,
sehingga timbunan sudah memenuhi aspek stabiitas timbunan karena nilai SF>1,5.