PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

STANDARD PRELIMINARIES

A GENERAL

1 GENERAL (including provisions stated in


Supplementary Preliminaries)
2 ALTERATION TO TEXT

3 CONDITIONS OF CONTRACT

4 LUMP SUM CONTRACT

5 DETERMINATION OF LUMP SUM TENDER PRICE

6 SINGAPORE CURRENCY

7 DISCREPANCIES IN DRAWINGS AND


SPECIFICATIONS

8 SUFFICIENCY OF TENDER OFFER

9 SCHEDULE OF RATES AND FAIR MARKET


RATES AND PRICES

10 ERRORS IN TENDER DISCOVERED DURING


FORMALISATION OF CONTRACT DOCUMENTS

11 ERRORS IN CONTRACT DISCOVERED AFTER


FORMALISATION OF CONTRACT DOCUMENTS

12 WORKERS’ QUARTERS AND CANTEEN

13 METRIC COMPONENTS

14 MOH TENDER OPPORTUNITY SYSTEM FOR


CONTRACTOR

B CONTRACT REQUIREMENTS

15 CONTRACTOR TO VISIT SITE

16 CONTRACTOR’S ACCEPTANCE OF SITE


CONDITIONS

C/F

PP/1
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

17 PRE-CONDITION SURVEY (including provisions


stated in Supplementary Preliminaries)

18 INSURANCE POLICIES (including provisions


stated in Supplementary Preliminaries)

19 SECURITY DEPOSIT AND ADDITIONAL


SECURITY AT TENDER AWARD

20 PRIME COST AND PROVISIONAL SUMS

20.1 Prime Cost Sums

20.2 Provisional Sum Items

21 PROVISIONAL QUANTITIES

22 INTERIM PAYMENTS (including provisions


stated in Supplementary Preliminaries)

22.1 The Reference Schedule

22.2 Payment Claim

22.3 Prescribed Form

22.4 Payment Claim to be furnished with


Supporting Documents

22.5 Particulars of Tax Invoice

22.6 Payment of Preliminaries

23 OVERPAYMENT

24 IRREGULARITY COMMITTED

25 ATTENDANCE

26 EXCEPTIONALLY ADVERSE WEATHER

27 SEVERE HAZE CONDITION

28 CONSTRUCTION PROGRAMME

C/F

PP/2
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

29 CASH FLOW FORECASTS

30 PROGRESS REPORTS

31 SUBSTITUTION OF MATERIALS

32 SITE MEETINGS, PROGRESS AND VARIATION


MEETINGS, ETC. (including provisions stated in
Supplementary Preliminaries)

33 DEEDS OF WARRANTY (including provisions


stated in Supplementary Preliminaries)

34 UNUSED MATERIALS OR GOODS NOT


DELIVERED TO SITE

C CONTRACTOR’S DUTIES, OBLIGATIONS AND


RESPONSIBILITIES

35 SOIL INVESTIGATION REPORTS AND


INFORMATION (including provisions stated in
Supplementary Preliminaries)

36 EXISTING GROUND / ROAD LEVELS

37 CONTRACTOR’S RESPONSIBILITY FOR ALL


SUB-CONTRACTORS AND SUPPLIERS

38 RESPONSIBILITIES OF CONTRACTOR

39 NOTIFICATION OF POTENTIAL DISRUPTION TO


OTHERS

40 STAMP DUTIES AND OTHER CHARGES

41 ENGAGEMENT OF REGISTERED SURVEYOR

42 PERMIT TO COMMMENCE WORKS

43 MISCONDUCT OF WORKMEN, NUISANCE AND


TRESPASSING

C/F

PP/3
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

44 LAND FOR SITE OFFICES AND CONTRACTOR’S


FACILITIES

45 TEMPORARY BUILDINGS ON CONSTRUCTION


SITES

46 SITE LAYOUT & PROVISION OF STORAGE


FACILITIES/TEMPORARY SHEDS

47 LIGHTNING PROTECTION TO TEMPORARY


STRUCTURES AND METAL STRUCTURES

48 ACCESS TO SITE OF WORKS AND EXISTING


BUILDINGS

49 SITE OFFICE, EQUIPMENT AND AMENITIES

50 PROVISION OF TRANSPORT

51 PREVENTION OF DAMAGE TO UNDERGROUND


SERVICES

51.1 Information on Underground Services

51.2 Response to Interruption or Disruption to


Existing Services

52 DAMAGE TO PUBLIC / PRIVATE PROPERTY /


SERVICES

53 PROTECTION OF PROPERTY, ETC

54 LICENSED CABLE DETECTION WORKER

55 BURNING ON SITE

56 PRESERVATION OF TREES

57 CLEARING OF SITE

58 MOSQUITO PREVENTION AND VECTOR


CONTROL

59 WASH BAYS

C/F

PP/4
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

60 EARTH CONTROL MEASURES

61 EARTH RETAINING STABILISING STRUCTURES


(ERSS)

62 EMPLOYMENT OF SECURITY GUARDS

63 SITE SECURTIY

64 PROJECT SIGNBOARD

65 PUBLICITY OF THE WORKS

66 DIVERSION OF EXISTING SERVICES

67 SUBMISSION OF SHOP DRAWINGS, WORKING


DRAWINGS, SERVICES COORDINATION
DRAWINGS AND DETAILS PRIOR TO THE
WORKS

68 MATERIALS

69 PRECAUTION AGAINST MATERIALS BEING


TAKEN OUT OF SITE

70 CONCRETE CUBE TESTS

71 FACTORY ACCEPTANCE TESTS

72 CONFINEMENT OF CONSTRUCTION WORKS

73 TEMPORARY WATER AND ELECTRICITY


SUPPLY (including provisions stated in
Supplementary Preliminaries)

74 TEMPORARY SANITARY FACILITIES

75 TEMPORARY FIRE PROTECTION SERVICES

76 TEMPORARY SITE ACCESS

77 EXISTING MAINS, PIPES, CONDUITS, ETC

C/F

PP/5
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

78 PROTECTION AND MAINTENANCE OF EXISTING


STRUCTURES, ROADS, FOOTPATHS AND
ACCESS WAYS

78.1 Traffic Management and Control

79 DRAINING OF SITE

80 HOUSEKEEPING

81 CLEANING AND LEAVING ON COMPLETION


(including provisions stated in Supplementary
Preliminaries)

82 AS-BUILT DRAWINGS, AS-BUILT MODEL,


FACILITIES MANAGEMENT (FM) MODEL AND
REPORT ON COMPLETION (including provisions
stated in Supplementary Preliminaries)

83 OPERATION AND MAINTENANCE MANUAL

84 EXTENDED MAINTENANCE OF DRAINS, ROADS


AND SEWERS RELATED TO CERTIFICATE OF
STATUTORY COMPLETION (CSC)

85 KEEPING RECORDS OF WORKMEN

86 ILLEGAL FOREIGN WORKERS

87 SAFETY AND HEALTH

87.1 Site Safety Measures

87.2 Requirement for Main Contractor and Sub-


Contractors to be at least bizSAFE Level 3 certified

87.3 Safety Infringement

87.4 Reporting of Accidents and Dangerous


Occurrence

87.5 Safety Helmets, Safety Boots and Respiratory


Masks for Employer’s and Consultants’ use
(including provisions stated in Supplementary
Preliminaries)

C/F

PP/6
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

87.6 Health Measures

87.7 COVID-19 Event

87.8 Provisional Sum for Swab Tests Included in Section 2


– Provisional Sum

87.9A Fire Safety (provisions stated in


Supplementary Preliminaries)

87.9B Contractor’s Scope of Services for ‘Design for


Safety’ (provisions stated in Supplementary
Preliminaries)

88 HOARDING

89 WORK METHODS AND TRADE


DEMONSTRATIONS

90 REQUIREMENTS FOR LEGAL AND FINANCIAL


DUE DILIGENCE

90A ADDITIONAL SECURITY DEPOSIT

90B TEMPORARY OCCUPATION PERMIT (TOP)


(provisions stated in Supplementary
Preliminaries)

90C BUILDING INFORMATION MODELLING (BIM)


(provisions stated in Supplementary
Preliminaries)

D WORKS REQUIREMENTS

91 PHOTOGRAPHS

92 WORKS BY OTHER PARTIES

93 WORKS ADJACENT TO THE SITE (including


provisions stated in Supplementary
Preliminaries)

C/F

PP/7
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

94 LICENSES, PERMITS AND LIAISON WITH OTHER


DEPARTMENTS, ETC

95 NOTICES AND FEES

96 CLEANING UP PERIODICALLY

97 CLEANING AND MAINTENANCE OF ROADS AND


DRAINS

98 VENTILATION

99 TREASURE TROVE

100 NOISE AND DISTURBANCE (including provisions


stated in Supplementary Preliminaries)

100.1 General

100.2 Noise Impact Assessment Recommendations

100.3 Noise Management Plan

100.4 Consideration for School Examination


Periods and Public Feedback

100.5 Noise Mitigation Measures

100.6 Noise Monitoring System

100.7 Public Outreach Program

100.8 NEA’s Quieter Construction Innovation Fund

101 VIBRATION TO ADJOINING / ADJACENT BUILING


/ STRUCTURE

102 AIR AND DUST POLLUTION

103 RISK ASSESSMENT

104 CASE MANAGEMENT SYSTEM

104.1 Overview of CASE Management System

104.2 Platform Requirement(s)

C/F

PP/8
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

104.3 Duties of the Contractor

104.4 Compliance Requirements and Audit

104.5 Project Information and Documents

104.6 Use of the Project Information and


Documents in CMD

104A PROVISION OF TIME LAPSE CAMERA


(provisions stated in Supplementary
Preliminaries)

105 NUISANCE AND IRREGULARITIES

105A GREEN AND GRACIOUS BUILDER SCHEME


(GGBS) (provisions stated in Supplementary
Preliminaries)

106 BIOMETRIC AUTHENTICATION SYSTEM (BAS)

107 CONSTRUCTABILITY SCORE

108 BUILDABILITY SCORE (including provisions


stated in Supplementary Preliminaries)

109 PUBLIC SECTOR CONSTRUCTION


PRODUCTIVITY FUND (PSCPF) APPLICATION

110 PROVISION OF REAL TIME CCTV


SURVEILLANCE FOR PPVC CONSTRUCTION
ONSITE AND OFFSITE (including provisions
stated in Supplementary Preliminaries)

111 MANPOWER PROGRAMME FOR


CONSTRUCTION REGISTRATION OF TRADEMEN
(CORETRADE)

112 BRANCH OFFICE CONTRACTORS

113 SINGAPORE GREEN BUILDING PRODUCT

114 BCA GREEN MARK

C/F

CLAUSE DESCRIPTION AMOUNT (S$)

PP/9
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

Section 1: Preliminaries Pricing for the Whole Construction Works

CLAUSE DESCRIPTION AMOUNT (S$)

B/F

115 SAMPLES

116 DEFECTS MANAGEMENT

117 FLOOD PREVENTION DURING RAINY PERIODS /


SEASONS

118 QUALITY CONTROL AND DEFECTS


MANAGEMENT PLATFORM

119 REPORTING OF PROJECT DATA SECURITY


INCIDENTS

120 ADJUSTMENT OF P.C. SUPPLY RATE FOR


FINISHES (provisions stated in Supplementary
Preliminaries)

TOTAL CARRIED FORWARD TO


SUMMARY OF TENDER

PP/10
PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

SECTION 2 - PROVISIONAL SUM

Item Description Unit Amount


1 Provisional Sum of $ 200,000.00 (Singapore Sum $ 200,000.00
Dollars Two Hundred Thousand Only) for Swab
tests (including but not limited to Polymerase
Chain Reaction (“PCR”) tests and Antigen Rapid
Test (“ART”)) arising from the COVID-19 Event
as prescribed in Clause 87.8 of the Preliminaries.

TOTAL CARRIED FORWARD TO


$ 200,000.00
SUMMARY OF TENDER

Provisional Sums PS/1


Proposed Development of a Nursing Home at Hougang Avenue 3, Singapore

Breakdown Cost of Works

SECTION 3 - PILING WORKS


Item Description Unit Quantity Rate Amount
$ ct

NOTES
All quantities shown are provisional and subject
to final measurement upon completion based on
the rates entered herein.
The pay length for piles shall be measured from
the toe level to the cut-off level of the piles

A MOBILISATION AND DEMOBILISATION OF


PILING EQUIPMENT
1 Allow for the provision of all necessary piling Sum
plants and equipment for piling works (inclusive
of temporary casings) including mobilisation and
demobilisation upon completion. Includes
provision for multiple mobilisations where
required by the project.

B BLIND BORING
1 Blind boring from existing ground levels to cut-
off levels of the cast in-situ bored piles including
backfilling with earth after completion in blind
bore piles to existing ground level.

(a) 600mm diameter piles (in 86 nos) m 215

(b) 800mm diameter piles (in 41 nos) m 103

(c) 900mm diameter piles (in 19 nos) m 48

(d) 1100mm diameter piles (in 19 nos) m 48

C CAST IN-SITU REINFORCED CONCRETE


BORED PILES

1 Supply and install cast in-situ bored piles in


Grade 40 reinforced concrete including all
boring, steel casing and steel reinforcement
cage bars and disposal of excavated materials
all in accordance with the Specifications.
Bored Piles Through all Soil

(a) 600mm diameter piles (in 86 nos) m 1,990

(b) 800mm diameter piles (in 41 nos) m 1,138

(c) 900mm diameter piles (in 19 nos) m 517

(d) 1100mm diameter piles (in 19 nos) m 630

Bored Piles Through all Rock Materials

(a) 600mm diameter piles (in 86 nos) m 1 Rate Only

(b) 800mm diameter piles (in 41 nos) m 1 Rate Only

(c) 900mm diameter piles (in 19 nos) m 1 Rate Only

(d) 1100mm diameter piles (in 19 nos) m 1 Rate Only

Carried Forward

Section 3; Piling Works PL / 1


Proposed Development of a Nursing Home at Hougang Avenue 3, Singapore

Breakdown Cost of Works

SECTION 3 - PILING WORKS


Item Description Unit Quantity Rate Amount
$ ct

Brought Forward $..........................

D CUTTING OFF PILE HEADS


1 Cutting off pile heads by crack inducer and/or
equivalent, to required cut-off level including
cleaning and cutting of projecting reinforcement
and all necessary excavation backfilling to
platform level and carting away all debris from
site.
Bored Piles
(a) 600mm diameter piles (in 86 nos) No 86

(b) 800mm diameter piles (in 41 nos) No 41

(c) 900mm diameter piles (in 19 nos) No 19

(d) 1100mm diameter piles (in 19 nos) No 19

E PILE TEST

Ultimate and Working Compressive Load


Test for Bored Piles
Supply all labour, plant and materials for
carrying out working and ultimate load tests on
selected bored piles. The rates shall include
design, mobilization, hacking to required levels,
preparation of pile head, constructing & removal
of pile-caps, assembly, removal on completion,
and all ancillary works for the completion of the
tests. The rates shall also include analyses and
interpretation of the test results by the
Professional Engineer.

1 (a) For 600mm diameter

(i) Working Load Test as specified. (1 No) ton 426


(ii) PDA Compression as specified (2 Nos) No 2

2 (a) For 800mm diameter

(i) Working Load Test as specified. (1 No) ton 757


(ii) Ultimate Load Test (1 No) ton 1,135
(iii) PDA Compression as specified (1 No) No 1

3 (a) For 1100mm diameter

(i) PDA Compression as specified (1 No) No 1

Carried Forward

Section 3; Piling Works PL / 2


Proposed Development of a Nursing Home at Hougang Avenue 3, Singapore

Breakdown Cost of Works

SECTION 3 - PILING WORKS


Item Description Unit Quantity Rate Amount
$ ct

Brought Forward
$..........................

F PILE INSTRUMENTATION

The rates shall include the cost of fixing the


instruments to the piles, cost of manpower,
qualified personnel, plant, material and other
necessary equipment for measuring readings,
analyses, and interpretation of measured
readings by the P.E.

1 (a) To supply, install and monitor vibrating wire No 1


strain gauges for pile instrumentation works on
preliminary test piles

2 (b) To supply, install and monitor tell-tale rod No 1


extensometer assembly, consisting of a 8mm
diameter stainless steel rod attached to a fixed
anchor point in pile and placed within a
protective 20mm internal diameter galvanised
iron pipe.

3 Submission of pile penetration length, pile Sum 1


eccentricity survey plans and as-built drawings
complete with PE and surveyor endorsements.

4 Other works not listed above but as indicated in


the Drawings and/or Specifications, including all
obligations, matter and things necessary for the
proper construction and completion of the
Works (If no items are stated below, it shall be
deemed included in the items listed above).

(a) ________________________________ Sum

(b) ________________________________ Sum

(c) ________________________________ Sum

TOTAL CARRIED TO SUMMARY OF


TENDER, PAGE SOT/1

Section 3; Piling Works PL / 3


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

A SITE CLEARANCE

1 Site Clearance including disposal Sum $..............................

B EXCAVATION WORKS

1 Excavation including disposal of excavated earth Sum $..............................

C CONCRETOR

1 Sub-structure $..............................

(a) Pilecaps
(i) Lean concrete Sum $..........................

(ii) Concrete Sum $..........................

(iii) Formwork Sum $..........................

(iv) Reinforcement Sum $..........................

(b) Drop Panels


(i) Lean concrete Sum $..........................

(ii) Concrete Sum $..........................

(iii) Formwork Sum $..........................

(iv) Reinforcement Sum $..........................

(c) Ground slab


(i) Lean concrete Sum $..........................

(ii) Concrete Sum $..........................

(iii) Formwork Sum $..........................

(iv) Reinforcement Sum $..........................

(d) Waterproofing
(i) Waterproofing system to underside of Sum $..........................
ground slab

(e) Termite Control Barrier Sum $..........................

(f) RC Trench Sum $..........................

(g) RC plinths Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/1


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

2 Frame $..............................
(a) Columns / Precast Columns
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) R.C Staircase / Liftcore wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

3 Staircase $..............................
(a) Stair structure
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Stair finishes


(i) Floor finishes Sum $..........................

(ii) Wall finishes Sum $..........................

(iii) Ceiling finishes Sum $..........................

(c) Stair handrails and balustrades Sum $..........................

4 External wall and finishes $..............................


(a) External wall Sum $.........................

(b) External plastering Sum $.........................

(c) External painting Sum $.........................

(d) Groove lines Sum $.........................

(e) External façade Sum $.........................

5 Internal walls and partitions $..............................


(a) Internal walls Sum $.........................

(b) Glass Partitions Sum $.........................

(c) Operable walls Sum $.........................

(d) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/2


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

6 Windows and louvres Sum $..............................

7 Door and Ironmongeries Sum $..............................

8 Internal wall finishes $..............................


(a) Plastering / skim coat Sum $.........................

(b) Painting internally Sum $.........................

(c) Tiles finishes


(i) Cement and screed backing to receive wall Sum $.........................
tiles

(ii) Supply and install of wall tiles

Wastage
Allowance for wastage at _______% of

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(ii)-1 Homogeneous Tiles WT-01 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.
(Location; but not limited to the following :
Toilet with shower and Toilet)

(ii)-2 Homogeneous Tiles WT-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.
(Location; but not limited to the following :
Biohazard, Bin Centre and Refuse Chute
Area)

(d) Insulation Sum $.........................

(e) Laminate wall panel / Vinyl stickers Sum $.........................

(f) Waterproofing to wall Sum $.........................

(g) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/3


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

9 Floor finishes $..............................


(a) Cement sand pavior including trowelled smooth Sum $.........................

(b) Cement sand screed backing to receive floor tiles Sum $.........................

(c) Supply and install of vinyl flooring with skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(c)-1 Vinyl Sheet FV01-01 A , at P.C. Supply Sum $.........................


Rate of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
SCC Reception and Corridor)

(c)-2 Vinyl Sheet FV01-01 B , at P.C. Supply Sum $.........................


Rate of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Occupational Therapy Room, SCC Meeting
Room, SCC Office, Rehab/Gym and Nurse
Room)

(c)-3 Vinyl Sheet FV01-02 A , at P.C. Supply Sum $.........................


Rate of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
SCC Quiet Room 1)

(c)-4 Vinyl Sheet FV03-01 A , at P.C. Supply Sum $.........................


Rate of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Activity Area, Dining Area and Pantry)

(d) Waterproofing to wet areas Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/4


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

9 Floor finishes (cont'd) $..............................

(e) Supply and install of floor tiles

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(e)-1 Homogeneous Tiles FT-01-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.

(Location; but not limited to the following :


NH Reception)

(e)-2 Homogeneous Tiles FT-01-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Store Room, FCC, Visitor Lounge and
Service Corridor)

(e)-3 Homogeneous Tiles FT-01-02 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Holding Room)

(e)-4 Homogeneous Tiles FT-02-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.

(Location; but not limited to the following :


Lift Lobbies)

(e)-5 Homogeneous Tiles FT-02-01 C at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


SCC Laundry, Toilets, Bin Centre, Refuse
Chute Area and Bio Hazard Room)

(e)-6 Homogeneous Tiles FT-02-02 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.
(Location; but not limited to the following :
External Footpaths, Community Plaza and
Secured Garden)

Carried Forward

HGA3NH-Main Building Works BCW/5


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

9 Floor finishes (cont'd) $..............................

(f) Supply and install of 300mm high floor skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(f)-1 300mm high Homogeneous tiles at P.C. Sum $.........................


Supply Rate of $ 9.00 per m as specified.

(g) Others Sum $.........................

10 Ceiling finishes $..............................

(a) Fibre plaster ceiling with low VOC washable Sum $.........................
emulsion paint finish (water absorption not
exceeding 5%) to come w/ necessary access
panels
(b) Acoustic fibre plaster ceiling with low VOC Sum $.........................
washable emulsion paint finish (water absorption
not exceeding 5%) to come w/ necessary access
panels
(c) Fibre plaster ceiling with low VOC washable
emulsion paint finish with insulation to avoid
condensation (water absorption not exceeding 5%) Sum $.........................
to come w/ necessary access panels
(d) Fire rated fibre plaster ceiling with low VOC
washable emulsion paint finish with insulation to
avoid condensation (water absorption not
exceeding 5%) to come w/ necessary access Sum $.........................
panels
(e) Moisture resistant calcium silicate ceiling board
with low VOC washable emulsion paint finish to
come w/ necessary access panels Sum $.........................

(f) Fire rated moisture resistant calcium silicate ceiling


board with low VOC washable emulsion paint
finish to come w/ necessary access panels
Sum $.........................

(g) 600 x 600 Grid ceiling with fibre plaster ceiling


panels with concealed suspension system to come
w/ necessary access panels
Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/6


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

10 Ceiling finishes (cont'd) $..............................

(h) 600 x 600 Grid ceiling with heavy duty, washable,


moisture-resistant, anti-mould aluminum ceiling
panels with concealed suspension system to come
w/ necessary access panels Sum $.........................

(h) Skim coat on soffit with low washable emulsion


paint finish Sum $.........................

(i) Others Sum $.........................

11 Fittings and Furnishings / Furnitures $..............................


(a) Built-in cabinets Sum $.........................

(b) Others Sum $.........................

12 Sanitary wares and fittings $..............................


(a) Wall Hung Water Closet (WC) with Coloured Soft Sum $.........................
Close Seat & Cover & Chair Bracket

(b) WC Sensor Flush Valve Sum $.........................

(c) Handheld Bidet with Flexible Hose Sum $.........................

(d) Coloured WC Grab Bar (Accessible toilets type 1) Sum $.........................

(e) Coloured WC Grab Bar (Ambulant toilets type 2) Sum $.........................

(f) Paper Towel Dispenser (Wall Mount) Sum $.........................

(g) Urinal Sum $.........................

(h) Urinal Grab Bars Sum $.........................

(i) Jumbo Paper Roll Holder (Wall Mount) Sum $.........................

(j) Hand Dryer Sum $.........................

(k) Wall Hung Ceramic Sink Sum $.........................

(l) Deck Mounted Basin Tap with Long Lever Handle Sum $.........................

(m) Sensor Tap Sum $.........................

(n) Soap Dispenser Sum $.........................

(o) Wall Mounted Hose Coupling Bib Tap Sum $.........................

(p) Tilt Mirror Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/7


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

12 Sanitary wares and fittings (cont'd) $..............................


(q) Coloured Shower Grab Bar Sum $.........................

(r) Coloured Shower Seat Sum $.........................

(s) Shower Mixer Set Sum $.........................

(t) Shower Hose Sum $.........................

(u) Robe Hook Sum $.........................

(v) Pat Slide Hook Sum $.........................

(w) Sureface-mounted Soap Holder Sum $.........................

(x) Gooseneck Deck Mounted Lever Handle Sink Sum $.........................

(y) Sluice Room Sluice Sink Sum $.........................

(z) Sluice Room Mop Sink Sum $.........................

(aa) Sluice Room Lockable Bib Tap with Hose Sum $.........................
Coupling

(ab) Sluice Room Concealed Flushed Valve Sum $.........................

(ac) Kitchen Sink Sum $.........................

(ad) Semi-recessed Ceramic Sink Sum $.........................

(ac) Recessed Moulded Solid Surface Sink with Under- Sum $.........................
counter Leg Space

(ad) Wall-mounted Pan Rack Sum $.........................

(ae) Others Sum $.........................

13 Sundries $..............................
(a) Bumper railing / Wall protection guards Sum $.........................

(b) Planter Railing Sum $.........................

(c) Maintenance Railing Sum $.........................

(d) Surface Mounted Grab Rail Sum $.........................

(e) Lift hoisting hook Sum $.........................

(f) Hosereel cabinet Sum $.........................

(g) Fire extinguishers Sum $..........................

(h) R.C Apron


(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/8


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 1
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

13 Sundries (cont'd) $..............................


(i) Signages Sum $..........................

(j) Tactile Sum $..........................

(k) Perforated Mesh Sum $..........................

(l) FE cabinet Sum $..........................

(m) Kick Plate Sum $..........................

(o) Others Sum $..........................

14 Other works not listed above but are required or


indicated in the drawings so as to complete the
works as a whole (if not stated and allowed for
herein, shall be deemed to be included or
absorbed in the various breakdown items above). $..............................

(a) Sum $.........................

(b) Sum $.........................

(c) Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/9


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

Super-structure

1 Frame $..........................
(a) Columns / Precast Columns Sum $..........................

(b) Suspended beams / Precast Beams


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

2 Upper Floor $..........................


(a) Cast-in situ slab
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Precast Slab / Plank Sum $..........................

(c) R.C Staircase / Liftcore wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(d) R.C Wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(e) R.C Parapet / upstand


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(f) RC ledge Sum $..........................

(g) RC plinths

Carried Forward

HGA3NH-Main Building Works BCW/10


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

Super-structure (Cont'd)

3 Staircase $..........................
(a) Stair structure
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Stair finishes


(i) Floor finishes Sum $..........................

(ii) Wall finishes Sum $..........................

(iii) Ceiling finishes Sum $..........................

(c) Stair handrails and balustrades Sum $..........................

4 External wall and finishes $..............................


(a) External wall Sum $.........................

(b) External plastering Sum $.........................

(c) External painting Sum $.........................

(d) Groove lines Sum $.........................

(e) External façade Sum $.........................

(f) Precast fins Sum $.........................

(g) Others Sum $.........................

5 Internal walls and partitions $..........................


(a) Internal walls Sum $.........................

(b) Operable walls Sum $.........................

(c) Toilet cubicles Sum $.........................

(d) Internal partitions Sum $.........................

(e) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/11


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

6 Windows and louvres Sum $..........................

7 Doors and ironmongeries Sum $..........................

8 Internal wall finishes $..........................


(a) Plastering / skim coat Sum $.........................

(b) Painting internally Sum $.........................

(c) Tiles finishes


(i) Cement and screed backing to receive wall Sum $.........................
tiles

(ii) Supply and install of wall tiles

Wastage
Allowance for wastage at _______% of

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(ii)-1 Homogeneous Tiles WT-01 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Toilet, PT/OT Toilet w/ Shower and Toilet
for Staff/Visitor)

(d) Insulation Sum $.........................

(e) Laminate wall panel / Vinyl stickers Sum $.........................

(f) Waterproofing to wall Sum $.........................

(g) Others Sum $.........................

9 Floor finishes $..........................


(a) Cement sand pavior including trowelled smooth Sum $.........................

(b) Cement sand screed backing to receive floor tiles Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/12


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

9 Floor finishes (cont'd) $..........................

(c) Supply and install of vinyl flooring with skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for profit at _______% of supply
and delivery rate;

(c)-1 Vinyl Sheet FV01-01 B, at P.C. Supply Rate Sum $.........................


of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Medical Consult Room, MSW Office,
Volunteers Room, Admin Office, Directors's
Room, Meeting Room, Nurse Manager
Room, Finance and Pantry)

(c)-2 Vinyl Sheet FV02-01 A, at P.C. Supply Rate Sum $.........................


of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
PT/OT Room and IT Server Room)

(c)-3 Vinyl Sheet FV02-02 G/H, at P.C. Supply Sum $.........................


Rate of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
PT/OT)

(c)-2 Vinyl Sheet FV02-02 J, at P.C. Supply Rate Sum $.........................


of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
PT/OT, Meeting/ Training)

(c)-2 Vinyl Sheet FV02-02 K/L, at P.C. Supply Sum $.........................


Rate of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Meeting Training)

(c)-2 Vinyl Sheet FV03-01 A, at P.C. Supply Rate Sum $.........................


of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Multi Purpose Hall Main)

(d) Waterproofing to wet areas Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/13


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

9 Floor finishes (cont'd) $..............................

(e) Supply and install of floor tiles

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for profit at _______% of supply
and delivery rate;

(e)-1 Homogeneous Tiles FT-01-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.

(Location; but not limited to the following :


Corridors around Outdoor Garden)

(e)-2 Homogeneous Tiles FT-01-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Medical Supplies Room, Maintenance
Room, Medical Records Room)

(e)-3 Homogeneous Tiles FT-02-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.
(Location; but not limited to the following :
Lift Lobbies)

(e)-4 Homogeneous Tiles FT-02-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.

(Location; but not limited to the following :


Outdoor Gardens, Outdoor Terraces)

(e)-5 Homogeneous Tiles FT-02-01 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Toilets, Cleaner's Store)

Carried Forward

HGA3NH-Main Building Works BCW/14


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..............................

9 Floor finishes (cont'd) $..............................

(f) Supply and install of 300mm high floor skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(f)-1 300mm high Homogeneous tiles at P.C. Sum $.........................


Supply Rate of $ 9.00 per m as specified.

(g) Others Sum $.........................

10 Ceiling finishes $..............................

(a) Fibre plaster ceiling with low VOC washable Sum $.........................
emulsion paint finish (water absorption not
exceeding 5%) to come w/ necessary access
panels

(b) Acoustic fibre plaster ceiling with low VOC Sum $.........................
washable emulsion paint finish (water absorption
not exceeding 5%) to come w/ necessary access
panels

(c) Fibre plaster ceiling with low VOC washable


emulsion paint finish with insulation to avoid
condensation (water absorption not exceeding
5%) to come w/ necessary access panels
Sum $.........................

(d) Fire rated fibre plaster ceiling with low VOC


washable emulsion paint finish with insulation to
avoid condensation (water absorption not
exceeding 5%) to come w/ necessary access
Sum $.........................
panels
(e) Moisture resistant calcium silicate ceiling board
with low VOC washable emulsion paint finish to
come w/ necessary access panels Sum $.........................

(f) Fire rated moisture resistant calcium silicate


ceiling board with low VOC washable emulsion
paint finish to come w/ necessary access panels Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/15


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..............................

10 Ceiling finishes (cont'd) $..............................


(g) 600 x 600 Grid ceiling with fibre plaster ceiling Sum $.........................
panels with concealed suspension system to
come w/ necessary access panels

(h) 600 x 600 Grid ceiling with heavy duty, washable,


moisture-resistant, anti-mould aluminum ceiling
panels with concealed suspension system to
come w/ necessary access panels Sum $.........................

(h) Skim coat on soffit with low washable emulsion


paint finish Sum $.........................

(i) Others Sum $.........................

11 Fittings and Furnishings / Furnitures $..........................


(a) Built-in cabinets Sum $.........................

(b) Others Sum $.........................

12 Sanitary wares and fittings $..........................


(a) Wall Hung Water Closet (WC) with Coloured Soft Sum $.........................

(b) WC Sensor Flush Valve Sum $.........................

(c) Handheld Bidet with Flexible Hose Sum $.........................

(d) Coloured WC Grab Bar (Accessible toilets type 1) Sum $.........................

(e) Coloured WC Grab Bar (Ambulant toilets type 2) Sum $.........................

(f) Paper Towel Dispenser (Wall Mount) Sum $.........................

(g) Urinal Sum $.........................

(h) Urinal Grab Bars Sum $.........................

(i) Jumbo Paper Roll Holder (Wall Mount) Sum $.........................

(j) Hand Dryer Sum $.........................

(k) Wall Hung Ceramic Sink Sum $.........................

(l) Deck Mounted Basin Tap with Long Lever Handle Sum $.........................

(m) Sensor Tap Sum $.........................

(n) Soap Dispenser Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/16


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

12 Sanitary wares and fittings (cont'd) $..............................


(o) Wall Mounted Hose Coupling Bib Tap Sum $.........................

(p) Tilt Mirror Sum $.........................

(q) Coloured Shower Grab Bar Sum $.........................

(r) Coloured Shower Seat Sum $.........................

(s) Shower Mixer Set Sum $.........................

(t) Shower Hose Sum $.........................

(u) Robe Hook Sum $.........................

(v) Pat Slide Hook Sum $.........................

(w) Sureface-mounted Soap Holder Sum $.........................

(x) Gooseneck Deck Mounted Lever Handle Sink Sum $.........................

(y) Sluice Room Sluice Sink Sum $.........................

(z) Sluice Room Mop Sink Sum $.........................

(aa) Sluice Room Lockable Bib Tap with Hose Coupling Sum $.........................

(ab) Sluice Room Concealed Flushed Valve Sum $.........................

(ac) Kitchen Sink Sum $.........................

(ad) Semi-recessed Ceramic Sink Sum $.........................

(ac) Recessed Moulded Solid Surface Sink with Under- Sum $.........................
counter Leg Space

(ad) Wall-mounted Pan Rack Sum $.........................

(ae) Others Sum $.........................

13 Sundries $..........................
(a) Railing Sum $.........................

(b) Bumper railing / Wall protection guards Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/17


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

13 Sundries (cont'd) $..........................

(c) Planter Railing Sum $.........................

(d) Maintenance Railing Sum $.........................

(e) Surface Mounted Grab Rail Sum $..........................

(f) Hosereel cabinet Sum $.........................

(g) Fire extinguishers Sum $..........................

(h) Planter boxes


(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Drainage and waterproofing Sum $..........................

(iv) Plants & Planting Sum $..........................

(v) Auto Irrigation System Sum $..........................

(i) Outdoor Garden (Open to Sky)


(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Drainage and waterproofing Sum $..........................

(iv) Plants & Planting Sum $..........................

(v) Auto Irrigation System Sum $..........................

(j) Vertical fins Sum $..........................

(k) Scupper drains / drains Sum $..........................

(l) Signages Sum $.........................

(m) Tactile Sum $..........................

(n) FE cabinet Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/18


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 2

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

13 Sundries (cont'd) $..........................


(o) Kick Plate Sum $..........................

(p) Catwalk Sum $..........................

(q) Openable Firemen's Gate Sum $..........................

(r) Others Sum $..........................

14 Other works not listed above but are required or


indicated in the drawings so as to complete the
works as a whole (if not stated and allowed for
herein, shall be deemed to be included or
absorbed in the various breakdown items above).
$..........................

(a) Sum $.........................

(b) Sum $.........................

(c) Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/19


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

Super-structure

1 Frame $..........................
(a) Columns / Precast Columns Sum $..........................

(b) Suspended beams / Precast Beams


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

2 Upper Floor $..........................


(a) Cast-in situ slab
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Precast Slab / Plank Sum $..........................

(c) R.C Staircase / Liftcore wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(d) R.C Wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(e) R.C Parapet / upstand


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(f) RC ledge Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/20


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

Super-structure (Cont'd)
3 Staircase $..........................
(a) Stair structure
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Stair finishes


(i) Floor finishes Sum $..........................

(ii) Wall finishes Sum $..........................

(iii) Ceiling finishes Sum $..........................

(c) Stair handrails and balustrades Sum $..........................

4 External wall and finishes $..............................


(a) External wall Sum $.........................

(b) External plastering Sum $.........................

(c) External painting Sum $.........................

(d) Groove lines Sum $.........................

(e) External façade Sum $.........................

(f) Precast fins Sum $.........................

(g) Others Sum $.........................

5 Internal walls and partitions $..........................


(a) Internal walls Sum $.........................

(b) Internal partitions Sum $.........................

(c) Others Sum $.........................

6 Windows and louvres $..........................

7 Doors and ironmongeries $..........................

Carried Forward

HGA3NH-Main Building Works BCW/21


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

8 Internal wall finishes $..........................


(a) Plastering / skim coat Sum $.........................

(b) Painting internally Sum $.........................

(c) Tiles finishes


(i) Cement and screed backing to receive wall Sum $.........................
tiles

(ii) Supply and install of wall tiles

Wastage
Allowance for wastage at _______% of

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(ii)-1 Homogeneous Tiles WT-01 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Toilets, Showers, Assisted Bath and Large
Assisted Bath)

(ii)-2 Homogeneous Tiles WT-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Sluice Rooms)

(ii)-3 Homogeneous Tiles WT-02 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Toilets, Assisted Bath and Large Assisted
Bath (only behind WC))

(d) Insulation Sum $.........................

(e) Laminate wall panel / Vinyl stickers Sum $.........................

(f) Waterproofing to wall Sum $.........................

(g) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/22


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

9 Floor finishes $..........................


(a) Cement sand pavior including trowelled smooth Sum $.........................

(b) Cement sand screed backing to receive floor tiles Sum $.........................

(c) Supply and install of vinyl flooring with skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(c)-1 Vinyl Sheet FV01-01 A, at P.C. Supply Rate Sum $.........................


of
$ 40.00 per m2 as specified.
(Location; but not limited to the following :
Main Corridors and Gowning Area)

(c)-2 Vinyl Sheet FV01-01 B, at P.C. Supply Rate Sum $.........................


of
$ 40.00 per m2 as specified.
(Location; but not limited to the following :
Nurse Stations, Living Rooms, Bedrooms
Corridors, PT, ISO Rooms)

(c)-3 Vinyl Sheet FV01-02 A, at P.C. Supply Rate Sum $.........................


of
$ 40.00 per m2 as specified.
(Location; but not limited to the following :
Quiet Rooms)

(c)-4 Vinyl Sheet FV01-03 A, at P.C. Supply Rate Sum $.........................


of
$ 40.00 per m2 as specified.
(Location; but not limited to the following :
Staff Pantries, Part of Day Rooms)

(c)-1 Vinyl Sheet FV02-02 M, at P.C. Supply Sum $.........................


Rate of
$ 40.00 per m2 as specified.
(Location; but not limited to the following :
Day Rooms)

(d) Waterproofing to wet areas Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/23


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

9 Floor finishes (cont'd) $..........................


(e) Supply and install of floor tiles

Wastage
Allowance for wastage at _______% of

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(e)-1 Homogeneous Tiles FT01-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified

(Location; but not limited to the following :


Preparation Room, Ward Store, Protected
Lobbies, Part Corridor(next to airwell))

(e)-2 Homogeneous Tiles FT02-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.

(Location; but not limited to the following :


Lift Lobbies)

(e)-2 Homogeneous Tiles FT02-01 B at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.

(Location; but not limited to the following :


Outdoor Gardens, Outdoor Terraces, Sky
Terrace)

(e)-2 Homogeneous Tiles FT02-01 C at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Toilets, Shower, Toilet Corridor, Handwash
Basin Area, Sluice Rooms, Assisted Baths)

(f) Supply and install of 300mm high floor skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for profit at _______% of supply
and delivery rate;

(f)-1 300mm high Homogeneous tiles at P.C. Sum $.........................


Supply Rate of $ 9.00 per m as specified.

Carried Forward

HGA3NH-Main Building Works BCW/24


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

9 Floor finishes (cont'd) $.............................


(g) Others Sum $.........................

10 Ceiling finishes $..............................


(a) Fibre plaster ceiling with low VOC washable Sum $.........................
emulsion paint finish (water absorption not
exceeding 5%) to come w/ necessary access
panels

(b) Acoustic fibre plaster ceiling with low VOC Sum $.........................
washable emulsion paint finish (water absorption
not exceeding 5%) to come w/ necessary access
panels

(c) Fibre plaster ceiling with low VOC washable Sum $.........................
emulsion paint finish with insulation to avoid
condensation (water absorption not exceeding
5%) to come w/ necessary access panels

(d) Fire rated fibre plaster ceiling with low VOC Sum $.........................
washable emulsion paint finish with insulation to
avoid condensation (water absorption not
exceeding 5%) to come w/ necessary access
panels

(e) Moisture resistant calcium silicate ceiling board Sum $.........................


with low VOC washable emulsion paint finish to
come w/ necessary access panels

(f) Fire rated moisture resistant calcium silicate Sum $.........................


ceiling board with low VOC washable emulsion
paint finish to come w/ necessary access panels

(g) 600 x 600 Grid ceiling with fibre plaster ceiling Sum $.........................
panels with concealed suspension system to
come w/ necessary access panels

(h) 600 x 600 Grid ceiling with heavy duty, washable, Sum $.........................
moisture-resistant, anti-mould aluminum ceiling
panels with concealed suspension system to
come w/ necessary access panels

(h) Skim coat on soffit with low washable emulsion Sum $.........................
paint finish

(i) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/25


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..............................

11 Fittings and Furnishings / Furnitures $..............................


(a) Built-in cabinets Sum $.........................

(b) Curtain Tracks Sum $.........................

(c) Others Sum $.........................

12 Sanitary wares and fittings (cont'd) $..........................


(a) Wall Hung Water Closet (WC) with Coloured Soft Sum $.........................

(b) WC Sensor Flush Valve Sum $.........................

(c) Handheld Bidet with Flexible Hose Sum $.........................

(d) Coloured WC Grab Bar (Accessible toilets type 1) Sum $.........................

(e) Coloured WC Grab Bar (Ambulant toilets type 2) Sum $.........................

(f) Paper Towel Dispenser (Wall Mount) Sum $.........................

(g) Urinal Sum $.........................

(h) Urinal Grab Bars Sum $.........................

(i) Jumbo Paper Roll Holder (Wall Mount) Sum $.........................

(j) Hand Dryer Sum $.........................

(k) Wall Hung Ceramic Sink Sum $.........................

(l) Deck Mounted Basin Tap with Long Lever Handle Sum $.........................

(m) Sensor Tap Sum $.........................

(n) Soap Dispenser Sum $.........................

(o) Wall Mounted Hose Coupling Bib Tap Sum $.........................

(p) Tilt Mirror Sum $.........................

(q) Coloured Shower Grab Bar Sum $.........................

(r) Coloured Shower Seat Sum $.........................

(s) Shower Mixer Set Sum $.........................

(t) Shower Hose Sum $.........................

(u) Robe Hook Sum $.........................

(v) Pat Slide Hook Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/26


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

12 Sanitary wares and fittings (cont'd) $..........................


(w) Sureface-mounted Soap Holder Sum $.........................

(x) Gooseneck Deck Mounted Lever Handle Sink Sum $.........................

(y) Sluice Room Sluice Sink Sum $.........................

(z) Sluice Room Mop Sink Sum $.........................

(aa) Sluice Room Lockable Bib Tap with Hose Coupling Sum $.........................

(ab) Sluice Room Concealed Flushed Valve Sum $.........................

(ac) Kitchen Sink Sum $.........................

(ad) Semi-recessed Ceramic Sink Sum $.........................

(ac) Recessed Moulded Solid Surface Sink with Sum $.........................

(ad) Wall-mounted Pan Rack Sum $.........................

(ae) Others Sum $.........................

13 Sundries $..........................
(a) Railing Sum $.........................

(b) Bumper railing / Wall protection guards Sum $.........................

(c) Planter Railing Sum $.........................

(d) Maintenance Railing Sum $.........................

(e) Surface Mounted Grab Rail Sum $..........................

(f) Hosereel cabinet Sum $.........................

(g) Fire extinguishers Sum $..........................

(h) Planter boxes


(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Drainage and waterproofing Sum $..........................

(iv) Plants & Planting Sum $..........................

(v) Auto Irrigation System Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/27


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 3 TO 6
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

13 Sundries (cont'd) $..........................


(i) Lanscaped Deck
(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Drainage and waterproofing Sum $..........................

(iv) Plants & Planting Sum $..........................

(v) Auto Irrigation System Sum $..........................

(j) Outdoor Terrace and Garden


(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Drainage and waterproofing Sum $..........................

(iv) Plants & Planting Sum $..........................

(v) Auto Irrigation System Sum $..........................

(k) Vertical fins Sum $..........................

(l) Scupper drains / drains Sum $..........................

(m) Signages Sum $.........................

(n) Kick Plate Sum $.........................

(o) FE Cabinet Sum $.........................

(p) Catwalk Sum $..........................

(q) Openable Firemen's Gate Sum $..........................

(r) Others Sum $..........................

14 Other works not listed above but are required or $..........................


indicated in the drawings so as to complete the
works as a whole (if not stated and allowed for
herein, shall be deemed to be included or
absorbed in the various breakdown items above).

(a) Sum $.........................

(b) Sum $.........................

(c) Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/28


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

Super-structure

1 Frame $..........................
(a) Precast Columns / Columns Sum $..........................

(b) Suspended beams / Precast Beams


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

2 Upper Floor $..........................


(a) Cast-in situ slab
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Precast Slab / Plank Sum $..........................

(c) R.C Staircase / Liftcore wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(d) R.C Wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(e) R.C Parapet / upstand


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(f) RC ledge Sum $..........................

(g) RC plinths Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/29


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

Super-structure (Cont'd)

3 Staircase
(a) Stair structure $..........................
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Stair finishes


(i) Floor finishes Sum $..........................

(ii) Wall finishes Sum $..........................

(iii) Ceiling finishes Sum $..........................

(c) Stair handrails and balustrades Sum $..........................

4 External wall and finishes $..........................


(a) External wall Sum $.........................

(b) External plastering Sum $.........................

(c) External painting Sum $.........................

(d) Groove lines Sum $.........................

(e) External façade Sum $.........................

(f) Precast fins Sum $.........................

(g) Others Sum $.........................

5 Internal walls and partitions $..........................


(a) Internal walls Sum $.........................

(b) Others Sum $.........................

6 Windows and louvres $..........................

7 Doors and ironmongeries $..........................

Carried Forward

HGA3NH-Main Building Works BCW/30


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

8 Internal wall finishes $..........................


(a) Plastering / skim coat Sum $.........................

(b) Painting internally Sum $.........................

(c) Homogeneous wall tiles


(i) Cement and screed backing to receive wall Sum $.........................

(ii) Supply and install of wall tiles

Wastage
Allowance for wastage at _______% of

Profit
Allowance for overheads & profit at

(ii)-1 Homogeneous Tiles WT-01 A at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Staff Toilets, Staff Baths, Assisted Bath)

(ii)-2 Homogeneous Tiles WT-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Kitchen, Clean & Dirty Laundry, Staff
Laundry)

(d) Vinyl stickers Sum $.........................

(e) Insulation Sum $.........................

(f) Waterproofing to wall Sum $.........................

(g) Others Sum $.........................

9 Floor finishes $..........................


(a) Cement sand pavior including trowelled smooth Sum $.........................

(b) Cement sand screed backing to receive floor tiles Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/31


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

9 Floor finishes (cont'd) $..........................


(c) Supply and install of heavy-duty vinyl flooring with

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(c)-1 Vinyl Sheet FV01-01 A, at P.C. Supply Rate Sum $.........................


of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Main Corridors)

(c)-2 Vinyl Sheet FV01-01 B, at P.C. Supply Rate Sum $.........................


of $ 40.00 per m2 as specified.
(Location; but not limited to the following :
Staff Accomodation, Staff Living Rooms,
Sick bay)

(d) Waterproofing to wet areas Sum $.........................

(e) Supply and install of floor tiles

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit
Allowance for overheads & profit at
_______% of supply and delivery rate;

(e) Supply and install of floor tiles (cont'd) Sum $.........................

(e)-1 Homogeneous Tiles FT01-01 B at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Luggage Rooms, Protected Lobby, Smoke
Stop Lobby, Part Corridors, Part Corridor
(next to airwell), Corridor (outside Kitchen))

(e)-2 Homogeneous Tiles FT02-01 A at P.C. Sum $.........................


Supply Rate of $ 35.00 per m2 as specified.
(Location; but not limited to the following :
Lift Lobbies, Lobby 3)

Carried Forward

HGA3NH-Main Building Works BCW/32


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

9 Floor finishes (cont'd) $..............................


(e)-2 Homogeneous Tiles FT02-01 B at P.C. Sum $.........................
Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Maintenance walkway, Roof Terraces)

(e)-2 Homogeneous Tiles FT02-01 C at P.C. Sum $.........................


Supply Rate of $ 30.00 per m2 as specified.

(Location; but not limited to the following :


Kitchen, Dry Store, Clean & Dirty Laundry,
Clotes Drying Areas, Staff Toilets, Staff
Toilet Corridor, Staff Handwash Basin
Area,Sluice Room, Assisted Baths, Staff
Laundry)

(f) Supply and install of 100mm/300mm high floor skirting

Wastage
Allowance for wastage at _______% of
supply and delivery rate;

Profit

Allowance for overheads & profit at


_______% of supply and delivery rate;

(f)-1 100mm high Homogeneous tiles at P.C. Sum $.........................


Supply Rate of $ 3.00 per m as specified.

(f)-2 300mm high Homogeneous tiles at P.C. Sum $.........................


Supply Rate of $ 9.00 per m as specified.

(g) Others Sum $.........................

10 Ceiling finishes $..............................


(a) Fibre plaster ceiling with low VOC washable Sum $.........................
emulsion paint finish (water absorption not
exceeding 5%) to come w/ necessary access
panels

(b) Acoustic fibre plaster ceiling with low VOC Sum $.........................
washable emulsion paint finish (water absorption
not exceeding 5%) to come w/ necessary access
panels

Carried Forward

HGA3NH-Main Building Works BCW/33


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

10 Ceiling finishes (cont'd) $..............................


(c) Fibre plaster ceiling with low VOC washable Sum $.........................
emulsion paint finish with insulation to avoid
condensation (water absorption not exceeding
5%) to come w/ necessary access panels

(d) Fire rated fibre plaster ceiling with low VOC Sum $.........................
washable emulsion paint finish with insulation to
avoid condensation (water absorption not
exceeding 5%) to come w/ necessary access
panels
(e) Moisture resistant calcium silicate ceiling board Sum $.........................
with low VOC washable emulsion paint finish to
come w/ necessary access panels

(f) Fire rated moisture resistant calcium silicate Sum $.........................


ceiling board with low VOC washable emulsion
paint finish to come w/ necessary access panels

(g) 600 x 600 Grid ceiling with fibre plaster ceiling Sum $.........................
panels with concealed suspension system to
come w/ necessary access panels

(h) 600 x 600 Grid ceiling with heavy duty, washable, Sum $.........................
moisture-resistant, anti-mould aluminum ceiling
panels with concealed suspension system to
come w/ necessary access panels

(h) Skim coat on soffit with low washable emulsion Sum $.........................
paint finish

(i) Others Sum $.........................

11 Fittings and Furnishings / Furnitures $..............................


(a) Built-in cabinets Sum $.........................

(b) Curtain Tracks Sum $.........................

(c) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/34


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7

Item Description Unit Sum Amount


$ ct

Brought Forward $..............................

12 Sanitary wares and fittings $..............................


(a) Wall Hung Water Closet (WC) with Coloured Soft Sum $.........................

(b) WC Sensor Flush Valve Sum $.........................

(c) Handheld Bidet with Flexible Hose Sum $.........................

(d) Coloured WC Grab Bar (Accessible toilets type 1) Sum $.........................

(e) Coloured WC Grab Bar (Ambulant toilets type 2) Sum $.........................

(f) Paper Towel Dispenser (Wall Mount) Sum $.........................

(g) Urinal Sum $.........................

(h) Urinal Grab Bars Sum $.........................

(i) Jumbo Paper Roll Holder (Wall Mount) Sum $.........................

(j) Hand Dryer Sum $.........................

(k) Wall Hung Ceramic Sink Sum $.........................

(l) Deck Mounted Basin Tap with Long Lever Handle Sum $.........................

(m) Sensor Tap


Sum $.........................

(n) Soap Dispenser Sum $.........................

(o) Wall Mounted Hose Coupling Bib Tap Sum $.........................

(p) Tilt Mirror Sum $.........................

(q) Coloured Shower Grab Bar Sum $.........................

(r) Coloured Shower Seat Sum $.........................

(s) Shower Mixer Set Sum $.........................

(t) Shower Hose Sum $.........................

(u) Robe Hook Sum $.........................

(v) Pat Slide Hook Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/35


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

12 Sanitary wares and fittings (cont'd) $..........................


(w) Sureface-mounted Soap Holder Sum $.........................

(x) Gooseneck Deck Mounted Lever Handle Sink Sum $.........................

(y) Sluice Room Sluice Sink Sum $.........................

(z) Sluice Room Mop Sink Sum $.........................

(aa) Sluice Room Lockable Bib Tap with Hose Coupling Sum $.........................

(ab) Sluice Room Concealed Flushed Valve Sum $.........................

(ac) Kitchen Sink Sum $.........................

(ad) Semi-recessed Ceramic Sink Sum $.........................

(ac) Recessed Moulded Solid Surface Sink with Under- Sum $.........................

(ad) Wall-mounted Pan Rack Sum $.........................

(ae) Others Sum $.........................

13 Sundries $..........................
(a) Railing Sum $.........................

(b) Bumper railing / Wall protection guards Sum $.........................

(c) Planter Railing Sum $.........................

(d) Maintenance Railing Sum $.........................

(e) Surface Mounted Grab Rail Sum $..........................

(f) Hosereel cabinet Sum $.........................

(g) Fire extinguishers Sum $..........................

(h) Planter boxes


(i) Structural works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Drainage and waterproofing Sum $..........................

(iv) Plants & Planting Sum $..........................

(v) Auto Irrigation System Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/36


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_LEVEL 7
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

13 Sundries (cont'd) $..........................

(i) Signages Sum $.........................

(j) Rainwater down pipe Sum $.........................

(k) Vertical fins Sum $..........................

(l) Others Sum $.........................

14 Other works not listed above but are required or


indicated in the drawings so as to complete the
works as a whole (if not stated and allowed for
herein, shall be deemed to be included or
absorbed in the various breakdown items above). $..........................

(a) Sum $.........................

(b) Sum $.........................

(c) Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/37


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_ROOF
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

RC FLAT ROOF

1 Frame $..........................
(a) Precast Columns Sum $..........................

2 Upper Floor $..........................


(a) R.C Staircase / Liftcore wall
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

3 Roof $..........................
(a) Roof Slab
(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Roof Beam


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(c) R.C Wall


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(d) R.C Parapet / upstand


(i) Concrete Sum $..........................

(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(e) Waterproofing system to roof, gutter & upstand Sum $..........................

(f) Roof finishes Sum $..........................

(g) Roof drainage Sum $..........................

4 Staircase
(a) Stair structure $..........................
(i) Concrete Sum $..........................

Carried Forward

HGA3NH-Main Building Works BCW/38


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_ROOF
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

Super-structure (Cont'd)

4 Staircase (Cont'd) $..........................


(ii) Formwork Sum $..........................

(iii) Reinforcement Sum $..........................

(b) Stair finishes


(i) Floor finishes Sum $..........................

(ii) Wall finishes Sum $..........................

(iii) Ceiling finishes Sum $..........................

(c) Stair handrails and balustrades Sum $..........................

5 External wall and finishes $..........................


(a) External wall Sum $.........................

(b) External plastering Sum $.........................

(c) External painting Sum $.........................

(d) Groove lines Sum $.........................

(e) External façade Sum $.........................

(f) Others Sum $.........................

6 Doors and ironmongeries $..........................

7 Internal wall finishes $..........................


(a) Plastering internally Sum $.........................

(b) Painting internally Sum $.........................

(c) Others Sum $.........................

Carried Forward

HGA3NH-Main Building Works BCW/39


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 4 - MAIN BUILDING_ROOF
Item Description Unit Sum Amount
$ ct

Brought Forward $..........................

8 Floor finishes $..........................


(a) Cement sand pavior including trowelled smooth Sum $.........................

(b) Cement sand screed with floor hardener Sum $.........................

(c) Cement sand screed backing to receive floor tiles


including skirting. Sum $.........................

(d) Others Sum $.........................

9 Sundries $..........................
(a) Concrete plinth Sum $.........................

(b) Railing Sum $.........................

(c) Catladders Sum $.........................

(d) Lift hoisting hook Sum $.........................

(e) Fencing / Façade for the M&E spaces Sum $..........................

(f) Support to the tank Sum $..........................

(g) Structural support for PV System Sum $.........................

(h) Fire extinguishers Sum $.........................

(i) FE Cabinet Sum $.........................

(j) Aluminium fins Sum $.........................

(k) Signages Sum $.........................

(l) Davit Arm System Sum $..........................

(m) Mono-rial Track System Sum $..........................

(n) Hosereel with metal casing

(o) Others Sum $.........................

10 Other works not listed above but are required or


indicated in the drawings so as to complete the works
as a whole (if not stated and allowed for herein, shall
be deemed to be included or absorbed in the various
breakdown items above).
$..........................

(a) Sum $.........................

(b) Sum $.........................

(c) Sum $.........................

TOTAL CARRIED TO SUMMARY OF TENDER,


PAGE SOT/1

HGA3NH-Main Building Works BCW/40


Proposed Development of a Nursing Home at Hougang Avenue 3, Singapore

BREAKDOWN COST OF WORKS


SECTION 5 - EXTERNAL WORKS

Item Description Unit Sum Amount


$ ct

EXTERNAL WORKS

1 Service road / Driveway $..........................


(i) Structural Works Sum $..........................

(ii) Floor finishes Sum $..........................

(iii) Road kerb Sum $..........................

(iv) Road marking Sum $..........................

2 Switch Room / Transformer Room $..........................


(i) Structural Works Sum $..........................

(ii) Finishes Sum $..........................

3 External Corridor $..........................


(i) Structural Works Sum $..........................

(ii) Finishes Sum $..........................

(iii) Planting Sum $..........................

4 Secured Wandering Garden $..........................


(i) RC structure Sum $..........................

(ii) Finishes Sum $..........................

(iii) Planting Sum $..........................

(iv) 1.8m H Green Wall with Gate Sum $..........................

(v) Others Sum $..........................

5 Community Plaza $..........................


(i) RC structure Sum $..........................

(ii) Finishes Sum $..........................

(iii) Planting Sum $..........................

6 Refuse Chute / Bio Hazard Room / Bin Centre $..........................


(a) Structural works Sum $..........................

(b) Finishes Sum $..........................

7 Detention Tank / Stormwater Tank $..........................


(a) Structural works Sum $..........................

(b) Finishes Sum $..........................

Carried Forward

HGA3NH-External Works EXT/1


Proposed Development of a Nursing Home at Hougang Avenue 3, Singapore

BREAKDOWN COST OF WORKS


SECTION 5 - EXTERNAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

8 Planter boxes $..........................


(a) Structural works Sum $..........................

(b) Finishes Sum $..........................

(c) Drainage Sum $..........................

(d) Planting Sum $..........................

9 Covered Linkway $..........................


(a) Structural works Sum $..........................

(b) Finishes Sum $..........................

10 Drainage $..........................
(a) Drain construction Sum $..........................

(b) R.C sump Sum $..........................

(c) Grating Sum $..........................

11 Approach Road and Entrance Culvert $..........................


(a) Approach slab construction Sum $..........................

(b) Entrance culvert construction Sum $..........................

(c) Finishes Sum $..........................

12 Landscaping / Turfing Works $..........................


(a) Plant and Planting Sum $..........................

(b) Green Wall System and Plants Sum $..........................

(c) Planting Media Sum $..........................

(d) Staking and Supports Sum $..........................

(e) Subsoil Drainage Sum $..........................

(f) Planter Drainage Material Sum $..........................

(g) Project Nursery Sum $..........................

(h) Maintenance Sum $..........................

(i) Bib Tap Sum $..........................

(j) Others Sum $..........................

Carried Forward $

HGA3NH-External Works EXT/2


Proposed Development of a Nursing Home at Hougang Avenue 3, Singapore

BREAKDOWN COST OF WORKS


SECTION 5 - EXTERNAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

13 Bicycle rack / double tier bicycle rack $..........................

14 Bollards $..........................

15 Property studs $..........................

16 Carpark Barrier $..........................

17 BRC Fencing and Gate $..........................

18 Trellis

19 Other works not listed above but are required or


indicated in the drawings so as to complete the works
as a whole (if not stated and allowed for herein, shall
be deemed to be included or absorbed in the various
breakdown items above).
$..........................

(a) Sum $.........................

(b) Sum $.........................

(c) Sum $.........................

TOTAL CARRIED TO SUMMARY OF TENDER,


PAGE SOT/1 $

HGA3NH-External Works EXT/3


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

A ELECTRICAL WORKS

A1 ELECTRICAL INSTALLATION

1 Supply, install heavy duty uPVC pipes to be encased in concrete


other accessories for power supply incoming service feeder
cables as specified and shown in the drawings.
$..........................

2 Supply, deliver, install, test and commission complete Low


Voltage (LV) distribution system including circuit breakers,
meters, protection and all accessories. $..........................
(i) Main Switch Board (MSB) Sum $..........................

(ii) Emergency Main Switch Board (EMSB) Sum $..........................

(iii) Sub-boards, Distribution boards and OG boards

(iv) 1st Storey Sum $..........................

(v) 2nd Storey Sum $..........................

(vi) 3rd Storey Sum $..........................

(vii) 4th Storey Sum $..........................

(viii) 5th Storey Sum $..........................

(ix) 6th Storey Sum $..........................

(x) 7th Storey Sum $..........................

(xi) Roof Sum $..........................

3 Emergency main failure sensing devices and relays to Lift


Systems, Generator, Fire Pump System, and all other applicable
systems with Emergency Supply $..........................

Carried Forward

HGA3NH-MEl Works ME/1


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A1 ELECTRICAL INSTALLATION (cont'd)

4 Supply, deliver, install, test and commission complete sub-main $..........................


(i) Main Switch Board (MSB) Sum $..........................

(ii) Sub-main Distribution Cables Sum $..........................

(iii) Final Distribution Cables

(iv) 1st Storey (External) - Landscape Areas, Carpark, Service


Driveway, Drop-Off Area etc. Sum $..........................

(v) 1st Storey Sum $..........................

(vi) 3rd Storey Sum $..........................

(vii) 4th Storey Sum $..........................

(viii) 5th Storey Sum $..........................

(ix) 6th Storey Sum $..........................

(x) 7th Storey Sum $..........................

(xi) Roof Sum $..........................

5 Supply, deliver, install, test and commission all final circuiting


work and associated accessories. $..........................
(i) 1st Storey (External) - Landscape Areas, Carpark, Service
Driveway, Drop-Off Area etc. Sum $..........................

(ii) 1st Storey Sum $..........................

(iii) 1st Storey Sum $..........................

(iv) 3rd Storey Sum $..........................

(v) 4th Storey Sum $..........................

(vi) 5th Storey Sum $..........................

(vii) 6th Storey Sum $..........................

(viii) 7th Storey Sum $..........................

(ix) Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/2


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A1 ELECTRICAL INSTALLATION (cont'd)

6 Supply, deliver, install, test and commission complete all lighting


switches, dimming switches, motion sensors, fan switches and
regulators, heater switches switch socket outlets, contactors,
isolators, TV outlets and data outlets and other accessories for
the complete electrical system. $..........................

7 Supply, deliver, install, test and commission all necessary


sealing for openings with approved fire proof/ stop materials of
minimum 2 hrs for all opening penetration to fire compartment
area and risers. First aid chart, danger signs, rubber mat, fire
extinguisher, tool cabinets, key box with locks and keys, frame
up single-line diagrams shall be provided in the LT Switch room,
generator room as specified.
$..........................

8 Electrical Substation (SP), c/w necessary lighting & power


installation works, DB, light fittings, switches & etc.

$..........................

9 To allow for excavation for Electrical Substation (SP), including


PE certificate as required, and re-instatement works for
pavement/ turfing/ road & etc.
$..........................

10 Supply, install, test and commission Isolators for EV Chargers


including cabling, cable support system and all other associated
accessories for the complete installation as specified and shown
in the drawings.
$..........................

11 Supply, install, test and commission Grid-Tie Solar Photovolatic


(PV) system, complete with PV panels, invetors, structural
supports c/w PE endorsement, cabling works, cable supports,
other special mountings required to secure the system, and all
associated interfacing works with the electrical panels, grid-tied
inverters, energy consumption monitoring devices, combiners
and application to Authorities. It shall also include the
engagement of LEW or Qualified Personnel to carry out the
works and liaising with the relevant authorities for submission
and approval to carry out the works.
$..........................

Carried Forward

HGA3NH-MEl Works ME/3


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A1 ELECTRICAL INSTALLATION (cont'd)

12 Engage a Licensed Electrical Worker to coordinate with service


provider, endorse of all necessary documents and to turn on
power supply for the entire project.
$..........................

13 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

14 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

15 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/4


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A2 STANDBY EMERGENCY DIESEL GENERATOR

1 Supply, install, test and commission one set of 250 kVA @ 0.8
PF weatherproof outdoor emergency diesel generator system
(Prime rated) complete with attenuators and silencer, automatic
main failure panel, batteries, battery charger and other
accessories for the complete installation as specified.
$..........................

2 Supply, install, test and commission one number of day tank to


last for a period of up to 6 hours as specified.
$..........................

3 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

4 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

5 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/5


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A3 EARTHING SYSTEM

1 Supply, install, test and commission electrical earthing systems


and ELV earthing system as specified .
$..........................

2 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

3 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

4 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/6


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A4 LIGHTING AND FAN SYSTEM

1 Supply, install, test and commission of all general lighting fitting,


emergency lighting, exit light and signage light fitting for all
areas, except ward areas and staff accomodation, complete with
all accessories as specified.
$..........................
(i) 1st Storey Sum $..........................

(ii) 2nd Storey Sum $..........................

(iii) 3rd Storey Sum $..........................

(iv) 4th Storey Sum $..........................

(v) 5th Storey Sum $..........................

(vi) 6th Storey Sum $..........................

(vii) 7th Storey Sum $..........................

(ix) Roof Sum $..........................

2 Supply, install, test and commission of all fans for all common
areas, except ward areas and staff accomdation, complete with
all accessories as specified.
$..........................
(i) 1st Storey Sum $..........................

(ii) 2nd Storey Sum $..........................

(iii) 3rd Storey Sum $..........................

(iv) 4th Storey Sum $..........................

(v) 5th Storey Sum $..........................

(vi) 6th Storey Sum $..........................

(vii) 7th Storey Sum $..........................

(ix) Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/7


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A4 LIGHTING AND FAN SYSTEM (cont'd)

3 Supply, install, test and commission lightings at wards. Night


lights with timer control shall be provided at the entrance of the
patient wards, localized lighting control switch designed to be
“silent operation control” at wards area/Staff accomodation area
and bed head light at individual bed with dedicated switch control
located at the side of the bed and other accessories as specified.
$..........................
(i) 3rd Storey Sum $..........................

(ii) 4th Storey Sum $..........................

(iii) 5th Storey Sum $..........................

(iv) 6th Storey Sum $..........................

(v) 7th Storey Sum $..........................

4 Supply, install, test and commission ceiling fans integrated with


Tri-LED lights for each bed at wards, complete with switches
located at the side of the individual beds for control of the light
and fan individually as specified.
$..........................
(i) 3rd Storey Sum $..........................

(ii) 4th Storey Sum $..........................

(iii) 5th Storey Sum $..........................

(iv) 6th Storey Sum $..........................

(v) 7th Storey Sum $..........................

5 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

Carried Forward

HGA3NH-MEl Works ME/8


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A4 LIGHTING AND FAN SYSTEM (cont'd)

6 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

7 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/9


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A5 LIGHTNING PROTECTION SYSTEM

1 Supply, install, test and commission complete lightning


protection system comprising of horizontal aluminum / copper
tapes around the roof parapets, HVI cables, down conductors, air
terminal, test-link boxes and earth electrodes at ground level.
Bonding of all exposed metallic parts to the building lightning
protection system as specified.
$..........................

2 Engage a Qualified Person to complete, endorse and submit all


necessary documents on the LPS system.
$..........................

3 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

4 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

5 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/10


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A6 PUBLIC ADDRESS AND EMERGENCY VOICE COMMUNICATION SYSTEM

1 Supply, install, test and commission of digital Public Address/


Emergency Voice Communication/ Background Music system
complete with ceiling/ box/ horn speakers, power amplifier,
microphone, tuner, hard disc, compact disc and zone selection
relay unit located in the Fire Command Centre, complete with fire
rated cabling, cable support system and associated accessories
as specified.
$..........................

2 Supply and install cable support system for EVC system


installation including cable trays, cable ladders, trunkings,
conduits, hangers and other accessories for the complete
installation as specified and shown in the drawings.
$..........................

3 Supply, install, terminate, test and commission all the speaker


points including the cablings, interface terminal boxes and other
accessories for the complete installation as specified and shown
in the drawings.
$..........................

4 EVC interface terminal for AV systems (eg. Multipurpose Hall,


meeting room, training room, and etc.) as specified.
$..........................

5 Supply labour and material to create openings, riser penetration,


hole chasis, patching up, filling with approved fire-stop / fire proof
materials of 4 hours and making good to all the PA system
openings / installation as specified.
$..........................

6 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

7 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

8 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/11


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A7 TELECOMMUNICATION SYSTEM

1 Supply, install, test and commission of Telephone System


complete with PABX, telephone outlets, block terminals, CAT 6A
UTP cabling, cable support system and other associated
accessories for the complete installation as specified.
$..........................
(i) 1st Storey Sum $..........................

(ii) 2nd Storey Sum $..........................

(iii) 3rd Storey Sum $..........................

(iv) 4th Storey Sum $..........................

(v) 5th Storey Sum $..........................

(vi) 6th Storey Sum $..........................

(vii) 7th Storey Sum $..........................

(ix) Roof Sum $..........................

2 Supply, install heavy duty uPVC pipes to be encased in concrete,


manholes and other accessories for Telecom incoming service
feeder cables and linkage with server room as specified and
shown in the drawings.
$..........................

3 Supply, install, test and commission the telephone system


(PhoneNet) including block terminal, telephone distribution panel
and other needed accessories for the complete telephone
system installation as specified and shown in the drawings.
$..........................

4 Supply labour and material to create openings, riser penetration,


hole chasis, patching up, filling user approved fire-stop / fire
proof materials of 4 hours and making good to all the telecom
openings / installation as specified.
$..........................

5 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

Carried Forward

HGA3NH-MEl Works ME/12


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A7 TELECOMMUNICATION SYSTEM (cont'd)

6 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

7 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/13


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A8 STRUCTURED CABLING SYSTEM

1 Supply, install, test and commission Backbone IT Infrastructure


complete with fibre patch panel, server rack, network rack and
security rack, software, licensing, fibre optics cabling and other
necessary accessories as shown and stated in the drawing.
$..........................

2 Supply, install, terminate, test and commission all the data points
including the patch panels, Cat 6A UTP cablings, Fibre Optic
Cablings, RJ 45 outlets, wireless AP points, junction boxes and
other accessories for the complete installation as specified and
shown in the drawings.
$..........................
(i) 1st Storey Sum $..........................

(ii) 2nd Storey Sum $..........................

(iii) 3rd Storey Sum $..........................

(iv) 4th Storey Sum $..........................

(v) 5th Storey Sum $..........................

(vi) 6th Storey Sum $..........................

(vii) 7th Storey Sum $..........................

(ix) Roof Sum $..........................

3 Supply and install the cable ladders, cable trays, conduits,


hangers, trunking and other accessories for the complete
installation as specified and shown in the drawings.
$..........................

4 Supply labour and material to create openings, riser penetration,


hole chasis, patching up, filling user approved fire-stop / fire
proof materials of 4 hours and making good to all the openings /
installation as specified.
$..........................

5 Supply, install, test and commission rack mount uninterrupted


power supply unit complete with isolation transformer and all
related accessories for complete system operation for all server
and network racks as indicated in drawings.
$..........................

Carried Forward

HGA3NH-MEl Works ME/14


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A8 STRUCTURED CABLING SYSTEM (cont'd)

6 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

7 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

8 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/15


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A9 DIGITAL TV SYSTEM

1 Supply, install, test and commission of digital TV system and


cable support system complete with associated accessories as
specified.
$..........................

2 Supply, install, test and commission digital TV signal amplifier


and necessary accessories to boost the signal if the signal is low.
$..........................

3 Supply, install, terminate, test and commission all the TV points


including cablings, TV outlets and other accessories for the
complete installation as specified and shown in the drawings.
$..........................

4 Supply and install trunkings, trays, conduits and other needed


accessories for the complete installation as specified and shown
in the drawings.
$..........................

5 Supply labour and material to create opening, riser penetration,


hole chasis, patching up, filling with approved fire-stop / fire proof
materials of 4 hours and making good to all the electrical
openings / installation as specified.
$..........................

6 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

7 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

8 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/16


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A10 NURSE CALL SYSTEM AND EMERGENCY CALL SYSTEM

1 Supply, install, test and commission of Nurse Call System and


Emergency Call System and complete with nurse call display
panels at corridors, patient station come with call cord and staff
assist station, pull cords, controllers, call lights, dome lights
along corridor, communication cabling, nurse call system
workstation, cable support system and other associated
accessories for the complete installation as specified.
$..........................
(i) Senior Care Centre Sum $..........................

(ii) 1st Storey Sum $..........................

(iii) 2nd Storey Sum $..........................

(iv) 3rd Storey Sum $..........................

(v) 4th Storey Sum $..........................

(vi) 5th Storey Sum $..........................

(vii) 6th Storey Sum $..........................

(ix) 7th Storey Sum $..........................

2 Supply labour and material to create opening, riser penetration,


hole chasis, patching up, filling with approved fire-stop / fire proof
materials of 4 hours and making good to all the electrical
openings / installation as specified.
$..........................

3 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

4 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

5 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/17


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A11 CCTV SURVEILLANCE SYSTEM

1 Supply, install, test and commissioning of IP based CCTV


System complete with Internet Protocol (IP) type cameras, video
management system (VMS), VMS server, 2 nos. of client
workstation, 2 numbers of digital 40 inch LED FULL HD monitor,
video recording manager (VRM), software, licensing, cabling,
control cabling, cable support system and associated
accessories for the complete installation as specified and shown
in the drawings.
$..........................
(i) Senior Care Centre Sum $..........................

(ii) 1st Storey Sum $..........................

(iii) 2nd Storey Sum $..........................

(iv) 3rd Storey Sum $..........................

(v) 4th Storey Sum $..........................

(vi) 5th Storey Sum $..........................

(vii) 6th Storey Sum $..........................

(ix) 7th Storey Sum $..........................

(x) Roof Sum $..........................

2 Supply and install the cable support system including cable trays,
conduits, hangers and other accessories for the complete
installation as specified and shown in the drawings.
$..........................

3 Supply, install, test and commission one no. of localised


uninterrupted power supply unit that can supply minimum 30
minutes backup and all related accessories for complete system
operation as indicated in specification and drawings.
$..........................

Carried Forward

HGA3NH-MEl Works ME/18


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A11 CCTV SURVEILLANCE SYSTEM (cont'd)

4 Supply labour and materials to create openings, riser


penetration, hole chases, patching up, filling with approved fire-
stop / fire proof materials of 4 hours and making good of all the
openings. $..........................

5 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

6 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

7 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/19


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A12 SECURITY CARD ACCESS SYSTEM

1 Supply, install, test and commission all the main card access and
security alarm system including data server, workstations,
system monitoring software, card reader, controller, , door
contacts units, EM lock, exit push button units, break glass units,
cablings and all other needed accessories for the complete
installation as specified and shown in the drawings.
$..........................

2 Supply, installation, testing and commissioning of one lot of


intelligent access / locking system with facial recognition and
remote surveillance capabilities for room / enclosure of potable
water transfer tank and potable water roof storage tank, in
accordance with SS 636 Amendment No. 4 July 2021
requirements. The system shall c/w weatherproof type equipment
for outdoor area application, backend monitoring system c/w
recording and real-time alerts, associated Elec & ELV works, and
all necessary ancillaries and accessories as specified in the
tender documents and drawings. The system shall backup with
essential power supply from the generator and c/w 2-hours UPS.
$..........................

3 Supply and install of cable support system including cable trays,


trunkings, conduits, hangers support system and other needed
accessories for the complete installation as specified and shown
in the drawings.
$..........................

4 Supply, install, test and commission one no. of localised


uninterrupted power supply unit that can supply minimum 30
minutes backup and all related accessories for complete system
operation for all security system (inclusive of racks) as indicated
in specification and drawings.
$..........................

5 Supply, install, test and commission of 16 numbers Auto-door


interfacing with Autonomous Mobile Robot (AMR) and all related
power provision and accessories for complete system operation
for all auto-doors.
$..........................

Carried Forward

HGA3NH-MEl Works ME/20


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A12 SECURITY CARD ACCESS SYSTEM (cont'd)

6 Supply labour and materials to create openings, riser


penetration, hole chases, patching up, filling with approved fire-
stop / fire proof materials of 4 hours and making good of all the
openings. $..........................

7 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

8 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done
on a monthly period during the Defects Liability Period.
$..........................

9 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/21


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A13 CARPARK BARRIER SYSTEM

1 Supply, install, test and commission Carpark Barrier System


including workstation, software cabling, cable support system all
other needed accessories for the complete installation as
specified and shown in the drawings.
$..........................

2 Supply, install, test and commission interfacing with Card Access


System and Audio Intercom System, complete with carpark
release button and associated accessories at the FCC and main
nurse station at 3rd storey. The proximity for the card reader
operation shall be within 2m range.
$..........................

3 1 lot inclusive of 2 nos. of weatherproof barrier arms, heavy-duty


motor, adjusting clutch, emergency release, built-in limit
switches, separate keyswitch control in weatherproof unit to IP65
standard and all associated electrical and control cablings for the
carpark for the complete installation as specified in the
documents and drawings.
$..........................

4 Sensory loops including all necessary ancillaries and


accessories. $..........................

5 Electrical and control panels (including, field wiring and cabling)


including all necessary trunking, GI conduits and flexible conduits
$..........................

6 Testing and commissioning of Carpark Barrier System as


specified in the tender documents
$..........................

7 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

8 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

9 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/22


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A14 GUARD TOUR SYSTEM

1 Supply, install, test and commission Guard Tour System


including cabling, cable support system all other needed
accessories for the complete installation as specified and shown
in the drawings. $..........................

2 Electrical and control panels (including, field wiring and cabling)


including all necessary trunking, GI conduits and flexible conduits
$..........................

3 Testing and commissioning of Guard Tour System as specified in


the tender documents $..........................

4 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

5 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

6 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/23


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A15 HEARING ENHANCEMENT SYSTEM

1 Supply, install, test and commission Hearing Enhancement


System including counter loop detector, driver, cabling, cable
support system and all other associated accessories for the
complete installation as specified and shown in the drawings for
the following areas:
$..........................
(i) Reception Sum $..........................

(ii) Multi-Purpose Hall Sum $..........................

(iii) Meeting Room 1 Sum $..........................

(iii) Meeting Room 2 Sum $..........................

2 Testing and commissioning of Hearing Enhancement System as


specified in the tender documents
$..........................

3 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

4 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

5 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/24


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

A16 PWD (PERSON WITH DISABILITY) SYSTEM

1 Supply, install, test and commission PWD System including


cabling, cable support system and all other associated
accessories for the complete installation as specified and shown
in the drawings. $..........................

2 Testing and commissioning of PWD System as specified in the


tender documents
$..........................

3 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

4 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

5 Any Other Works


Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
(i) Sum $..........................

(ii) Sum $..........................

(iii) Sum $..........................

A17 PRELIMINARIES

1 Preliminaries for Electrical Works $..........................

Carried Forward

HGA3NH-MEl Works ME/25


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

MECHANICAL WORKS

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM

1 Complete supply, delivery, installation, testing and commissioning


of all the Variable Refrigerant Flow (VRF) and Direct Expansion
(DX) Single / Multi Split inverter controlled air-conditioner with
thermal insulation from outdoor condensing units to all the indoor
fan coil units. The work shall include all equipment, supporting
brackets, spring isolators, electrical works and all necessary
fittings and accessories to ensure a complete system etc.

(i) VRF / DX System


$..........................
a 1st Storey Fire Command Centre complete with 2N (1 Duty
& 1 Standby) air-con to obtain an operating cycle of 12
hour for each split unit alternately , daily. These systems
shall be back up by essential power supply and automatic
switch over for continuous operating of the air-con units in
the event of power failure.
Sum $..........................

b 1st Storey Visitor's lounges and Reception Sum $..........................

c 2nd Storey Medical Supplies Room complete with 2N (1


Duty & 1 Standby) air-con to obtain an operating cycle of
12 hour for each split unit alternately , daily. These systems
shall be back up by essential power supply and automatic
switch over for continuous operating of the air-con units in
the event of power failure.
Sum $..........................

d 7th Storey Dry Ration Store complete with 2N (1 Duty & 1


Standby) air-con to obtain an operating cycle of 12 hour for
each split unit alternately , daily. These systems shall be
back up by essential power supply and automatic switch
over for continuous operating of the air-con units in the
event of power failure.
Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/26


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

(ii) VRF System $..........................


a 1st Storey Senior Care Center Sum $..........................

b 1st Storey Holding Room complete with provision of 2N (1


Duty & 1 Standby) single-pass air-con unit/system and
emergency power supply for independent management
and control of environment. These systems shall be back
up by essential power supply and automatic switch over for
continuous operating of the air-con units in the event of
power failure.
Sum $..........................

c 2nd Storey Multi Purpose Hall, PT/OT, Admin Office, Nurse


Mgr, Meeting/ Training, Medical Consult, Volunteer Room,
MSW Office/ Interview/ Counselling, Medical Record Office
Sum $..........................

d 3rd to 6th Storey Gridline 5-E Isolation Rooms Sum $..........................

e 7th Storey Gridline 5-E Staff Lounge (VRF capacity


provision for future conversion of Staff Lounge into
Isolation Room) Sum $..........................

f 3rd to 6th Storey Quiet Rooms Sum $..........................

g 7th Storey Luggage Room (VRF capacity provision for


future conversion of Luggage Room into Quiet Room)
Sum $..........................

h 3rd to 6th Storey Prep Rooms, complete with 2N (Duty &


Standby) air-con to obtain an operating cycle of 12 hour for
each duty and standby unit alternately , daily. These
systems shall be back up by essential power supply and
automatic switch over for continuous operating of the air-
con units in the event of power failure.
Sum $..........................

i 7th Storey Staff Laundry (VRF capacity provision for future


conversion of Staff Laundry into Prep Room)
Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/27


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

j 1st-7th Storey pre-cooled outdoor air system with duty and


standby unit, outdoor weather-proof type. The outdoor unit
shall be weather-proof type and with automatic changeover
every 12 hours between the duty and standby units.

Sum $..........................

k 1st Storey pre-cooled outdoor air system with duty unit to


serve Senior Care Center. The outdoor unit shall be
weather-proof type.
Sum $..........................

l 1st Storey pre-cooled outdoor air system with duty and


standby unit to serve Holding Room. The outdoor unit shall
be weather-proof type and with automatic changeover
every 12 hours between the duty and standby units.
Sum $..........................

2 Complete supply, delivery, installation and testing of all the


condensate water pipes with thermal insulation from fan coil unit
(FCU)/ pre-cooled outdoor air unit to nearest floor trap of the
sanitary plumbing system including condensate pump sets if the
gradient is unable to be achieved. The work shall include all the
valves, joints, brackets, etc.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey (incl. future proofed provisions at 7th Storey for


future conversion) Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/28


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

3 Complete supply, delivery, installation, testing and commissioning


of FCU complete refrigerant piping with thermal insulation for
FCU. The work shall include all the brackets, spring isolators, etc.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey (incl. future proofed provisions at 7th Storey for


future conversion) Sum $..........................

h Roof Sum $..........................

4 Complete supply, delivery, installation, testing and commissioning


of electrical wiring and control systems including control panels,
temperature control devices, wiring works, electrical works,
brackets, mounting supports and other incidentals for efficient
operation of the systems.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey (incl. future proofed provisions at 7th Storey for


future conversion) Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/29


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

5 Complete supply, delivery, installation, testing and commissioning


of Environment Monitoring System (EMS) complete with Room
RH sensors, temperature sensors, condensate/ water leak
sensor, local control panel, remote monitoring panel, LCD
touchscreen display , isolators, control wiring, electrical works, all
necessary control devices, fittings and accessories for efficient
operation of systems.
$..........................
a 2nd Storey Server Room Sum $..........................

6 Complete supply, delivery, installation, testing and commissioning


of centralised control system for VRF system complete with
Central Remote Controller (CRC) with LCD touch screen display,
instrument for permanent measurement and verification for the
VRF System, UPS back-up battery for 48hrs, programming,
control, wiring, electricla works and all necessary fittings and
accessories to ensure a complete system etc.
$..........................
a Central Remote Controller for VRF System (serve 1st
Storey Senior Care Center) at 1st Storey Senior Care
Center Office Sum $..........................

b Central Remote Controller for VRF System at 2nd Storey


Admin Office Sum $..........................

7 Complete supply, delivery, installation and testing of ventilation


duct for air-conditioning system with fire-rating and/or acoustic
insulation, metal pre-insulated ducts for air-con supply and return
air ducts. The work shall also include plenum box, flexible ducts,
brackets,mounting supports etc.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey (incl. future proofed provisions at 7th Storey for


future conversion) Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/30


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

8 Complete supply, delivery, installation and testing of air diffusion


devices such as grilles, louvers, insect screen, fire dampers,
volume control dampers, non return dampers, motorised dampers
etc. The work shall also include brackets, mounting supports,
electrical power supply, control, wiring, electrical works etc.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey (incl. future proofed provisions at 7th Storey for


future conversion) Sum $..........................

h Roof Sum $..........................

9 Complete supply, delivery, installation, testing and commissioning


of mechanical ventilation fans (axial flow or centrifugal in-line or
box cabinet fans) with fire-rating and/or acoustic insulation
including attenuators & necessary sensors, ductwork, air diffusion
devices, volume control dampers, non-return dampers, fire
dampers, motorised dampers, control panels, isolators, electrical
control wiring, pressure differential sensors and all necessary
accessories etc. The work shall include all the brackets, spring
isolators, etc.

$..........................
a 1st Storey Public Thoroughfare (Fresh air system)
Sum $..........................

b 1st Storey Service Corridor (Fresh air system) Sum $..........................

c 1st Storey SCC Nurse Room (Exhaust air system) Sum $..........................

d 1st Storey SCC Toilets (Exhaust air system) Sum $..........................

e 1st Storey Toilet (Visitor Lounge) (Exhaust air system)


Sum $..........................

f 1st Storey Bio Hazard Room (Fresh air and exhaust air
systems)
Sum $..........................

g 1st Storey Bin Centre (Fresh air and exhaust air systems)
Sum $..........................

h 1st Storey Holding Room (Exhaust air system)


Sum $..........................

i 2nd Storey Toilets (Acc, Female, & Male toilets) (Exhaust


air system)
Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/31


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

j 2nd Storey Maintenance Room (Fresh air and exhaust air


systems) Sum $..........................

k 2nd Storey Cleaner Store (Fresh air and exhaust air


systems) Sum $..........................

l 2nd Storey Potable Water Tank And Transfer Pump Room


(Fresh air and exhaust air systems)
Sum $..........................

m 2nd Storey MDF Room (Fresh air and exhaust air systems)
Sum $..........................

n 2nd Storey Corridor (in front of Medical Supplies Room)


(Fresh air system) Sum $..........................

o 2nd Storey Corridor (in front of Server Room) (Fresh air


system) Sum $..........................

p 3rd to 7th Storey Toilets (Gridline 2/ B-C) (Exhaust air


system) Sum $..........................

q 3rd to 6th Storey Toilets (Gridline 7/ B) (Exhaust air


system) Sum $..........................

r 3rd to 7th Storey Toilets (Gridline 2/ E) (Exhaust air


system) Sum $..........................

s 3rd to 7th Storey Toilets (Gridline 6-8 / D-E) (Exhaust air


system) Sum $..........................

t 3rd to 7th Storey Toilets (Gridline 4/ D Large Assisted


Bath) (Exhaust air system) Sum $..........................

u 3rd to 7th Storey Toilets (Gridline 5-E Isolation Room's/


Staff Lounge's Assisted Bath and WC ) (Exhaust air
system) Sum $..........................

v 3rd to 7th Storey Gridline 5-E Isolation Room (including


provision for future conversion at 7th Storey) (Fresh air
system) Sum $..........................

w 3rd to 6th Storey Haze Shelter (Fresh air and exhaust air
systems) Sum $..........................

x 7th Storey Laundry (Fresh air and exhaust air systems)


Sum $..........................

y 7th Storey Laundry Equipment (Exhaust air system)


Sum $..........................

z 7th Storey Kitchen (Fresh air and exhaust air systems)


Sum $..........................

aa 7th Storey Luggage Rooms (Fresh air system) Sum $..........................

ab 7th Storey Lift Lobby 3 (Fresh air system) Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/32


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

ac Purging system for Senior Care Center (1st Storey) Sum $..........................

ad Purging system for Meeting/ Training, Medical Consult,


Volunteer Room, MSW Office/ Interview/ Counselling,
Medical Record Office (2nd Storey)
Sum $..........................

ae Purging system for Medical Supplies (2nd Storey)


Sum $..........................

af Purging system for Server Room (2nd Storey) Sum $..........................

ag Purging system for Admin Office (2nd Storey) Sum $..........................

ah Purging system for PTOT (2nd Storey) Sum $..........................

ai Purging system for MPH (2nd Storey) Sum $..........................

aj Purging system for Quiet Rooms, Prep Rooms (3rd to 7th


Storey including provision for future conversion at 7th
Storey) Sum $..........................

ak Purging system for Kitchen Dry Store (7th Storey) Sum $..........................

10 Complete supply, delivery, installation, testing and commissioning


of fire essential ventilation fans, fire rated ductwork, air diffusion
devices, various types of air dampers, fire dampers, fan control
panels, isolators for emergency power supply, acoustic treatment,
attenuators, electrical works and control wiring,brackets,
mounting supports and all necessary accessories. The work shall
include interfacing control to essential ACMV panels at FCC
room.
$..........................
a 1st Storey FCC room with duty and standby fresh air fan
system Sum $..........................

b 1st Storey to Roof Fire Lift Lobby 1 with duty and standby
fresh air fan system Sum $..........................

c 1st Storey to Roof Fire Lift Lobby 2 with duty and standby
fresh air fan system Sum $..........................

d 2st Storey Sprinkler Pump Room with duty and standby


fresh air and exhaust air systems
Sum $..........................

e 3rd to 7th Storey Corridors (gridline 3/ F, 6/ F) with fresh


air fan system Sum $..........................

11 Complete supply, delivery, installation, testing and commissioning


of kitchen bifurcated exhaust air and make up air fans, exhaust
and make up air duct, fire rated ductwork, air diffusion devices,
various types of air dampers, fan control panels, interfacing
control with gas solenoid valve, gas leak detection system, fire
alarm system, and kitchen fire suppression system, isolators,
acoustic treatment, attenuators, electrostatic air cleaner, active
carbon filter, electrical works and control wiring,brackets,
mounting supports and all necessary accessories.
$..........................
a 7th Storey Kitchen (Kitchen hoods exhaust)
Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/33


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

12 Complete supply, delivery, installation, testing and commissioning


of essential ACMV panel at FCC room with remote manual start-
stop switch, visual indication of the operational status for each
essential ACMV system and interface with building fire alarm
system. The works shall include bracket, mounting supports,
isolators, electrical wiring, control wiring and all necessary
accessorries etc.
$..........................

13 Complete supply, delivery, installation, testing and commissioning


of the mechanical ventilation (fresh air) system fitted with MERV
15 fan and filter unit/s (FFU) to the haze shelter in achieving 12
air-change per hour (ACH) set up by segregating partial of the
ward. This work shall include all the necessary duct work,
bracket, spring isolators, etc.
$..........................
a 3rd to 6th Storey Haze Shelter Sum $..........................

14 Complete supply, delivery, installation, testing and commissioning


of the pre-cooled outdoor air systems fitted with MERV 8 (normal
mode) and MERV 14 (pandemic mode) fan filter unit to achieve
required outdoor air requirement. This work shall include all the
necessary mounting supports, bracket, spring isolators, etc.

$..........................

15 Complete supply, delivery, installation, testing and commissioning


of MERV 8 air filter for all fan coil units and pre-filters for fresh air
fan systems. This work shall include all the necessary mounting
supports, bracket, spring isolators, etc.
$..........................

16 Complete supply, delivery, installation, testing and commissioning


of MERV 14 air filter c/w booster fan system for all ducted fan coil
units serve these areas. This work shall include all the necessary
mounting supports, bracket, spring isolators, etc.

$..........................
a 2nd Storey Multi Purpose Hall, PTOT Sum $..........................

b 3rd to 7th Storey Gridline 5-E Isolation Rooms Sum $..........................

17 Complete supply, delivery, installation, testing and commissioning


of the mechanical ventilation (fresh air) system fitted with MERV
15 fan and filter unit/s (FFU) to serve this area. This work shall
include all the necessary duct work, bracket, spring isolators, etc.

$..........................
a 3rd to 7th Storey Gridline 5-E Isolation Rooms Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/34


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

B AIR-CONDITIONING & MECHANICAL VENTILATION SYSTEM (cont'd)

18 Complete supply, delivery, installation, testing and commissioning


of the mechanical ventilated system fitted with HEPA fan and filter
unit/s (FFU) to serve this area. This work shall include all the
necessary duct work, bracket, spring isolators, etc.

$..........................
a 1st Storey Holding Room Sum $..........................

19 Complete supply, delivery, installation, testing and commissioning


of one (1) lot of booster air fan system c/w ductwork for routing
cold air discharge from heat pump system at roof to 7th storey.
The work shall also include insulation, air diffusion devices, non-
return dampers, volume control dampers, motorised dampers,
plenum box, fire damper, air dampers, brackets,mounting
supports, fan control panels, isolators for power supply, acoustic
treatment, attenuators, electrical works and control wiring,
interfacing with the heat pump system and all necessary
accessories.
$..........................

20 Complete supply, delivery, installation, testing and commissioning


One (1) lot of permanent measuring instruments to monitor the
energy performance of the VRF condensing units and air
distribution system as mentioned and described in the Tender
Documents.
$..........................

21 Complete Testing and commissioning of ACMV System, including


refrigerant pipe pressure test, condensate water pipe flow and
leakage test, duct leakage test, noise level and all other tests
deemed necessary by the S.O. The work shall include NEA
registered acoustic specialist engaged by contractor for authority
compliance.
$..........................

22 Submission of shop drawings, complete operation and


maintenance manuals including as-built drawings, equipment
catalogue and etc in hard and soft copy. $..........................

23 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.

$..........................

24 Preliminaries $..........................

25 Any ancillary or other works not specifically mentioned and


described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
a …....................................................... Sum $..........................

b …....................................................... Sum $..........................

c …....................................................... Sum $..........................

Carried Forward $..........................

HGA3NH-MEl Works ME/35


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

MECHANICAL WORKS

C FIRE PROTECTION SYSTEM

FIRE SPRINKLER SYSTEM


1 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of heavy duty ductile iron cement
lined pipes from and including water meter / valves chamber to
the sprinkler tank c/w supporting brackets, etc and all necessary
ancillaries and accessories as specified in the tender documents.
$..........................

2 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of accessories for the reinforced
concrete sprinkler/hose reel tank c/w float valves, cat ladder c/w
safety cage (internal & external), access panels, isolation valves,
drain pipes, balancing pipes, level indicators, water level alarm
system c/w signal cables to alarm panel, overflow pipes, vent
pipes, and all necessary ancillaries and accessories as specified
in the tender documents.
$..........................

3 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of UL/FM approved electrical
sprinkler pump set, jockey pump set, complete with valves,
strainers, pressure gauges, flow meter, test pipes, inertia block,
plinths, vibration isolators, motor controls, etc and all necessary
ancillaries and accessories as specified in the tender documents.
The work shall include sprinkler pump electrical control panel (IP
55 ,UL) ) c/w magnetic starters, relays, anti-condensation
heaters, control sensors, fire resistance cables, trunking,
emergency power supply, remote control and monitoring panel
and all necessary ancillaries and accessories as specified in the
tender documents. The fire pump sets set shall be fully pre-
assembled with control panels, and instruments mounted on
skids with lifting eyes for piping connection, valves cable
termination for power supply, and interfaces for fire alarm system.

$..........................

4 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of duty and standby control system
for fire pumping systems c/w all necessary ancillaries and
accessories as specified in the tender documents, such that the
system performance is not affected when one of the pumps
and/or the associated control system is out of operation due to
routine maintenance or break-down.
$..........................

Carried Forward

HGA3NH-MEl Works ME/36


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward

FIRE SPRINKLER SYSTEM (cont'd)

5 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of class “B” black steel pipes
(distribution pipes and range pipes) from sprinkler tank to
sprinkler points c/w fittings, brackets, orifice plates, flow switches,
automatic air vents, valves, drain pipes, access panels, fire rated
enclosures, etc and all necessary ancillaries and accessories as
specified in the tender documents.
$..........................

6 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of first layer sprinkler, c/w flexible
sprinkler hose assembly for area with false ceiling grids, alarm
valves, flow switch , drain point c/w gauges, fittings, valves, water
proving test and drain facilities and all necessary ancillaries and
accessories as specified in the tender documents.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/37


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

FIRE SPRINKLER SYSTEM (cont'd)

7 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of second layer sprinklers, sprinklers
under the beam/ ducts/ equipment/ PV platform, alarm valves,
flow switch , drain point c/w gauges, fittings, valves, water proving
test and drain facilities and all necessary ancillaries and
accessories as specified in the tender documents.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

8 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of sprinkler breeching inlet with
pipework to fire tank / alarm valve header c/w check valve,
pipework, brackets, earthing, fire rated enclosures, etc and all
necessary ancillaries and accessories as specified in the tender
documents.
$..........................

Carried Forward

HGA3NH-MEl Works ME/38


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

FIRE HOSEREEL SYSTEM


9 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of hosereel system compromising of
hosereel pump set, control panel, complete with valves, fittings,
brackets, hosereel pipes, hosereel drums and its associated
electrical and control wiring works and all necessary accessories
backup with essential power supply from the generator to effect a
complete installation. The fire hosereel pump sets set shall be
fully pre-assembled with control panels, and instruments mounted
on skids with lifting eyes for piping connection, valves cable
termination for power supply, and interfaces for fire alarm system.

$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/39


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

FIRE DETECTION AND FIRE ALARM SYSTEM


10 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of Addressable Main Fire Alarm
panel ( MAP ) in Fire Comand Centre ( FCC ) c/w master mimic
panel, associated control equipment, wirings, relays,
maintenance-free nickel cadmium batteries, battery charger,
meters, emergency power supply, etc and all necessary
ancillaries and accessories as specified in the tender documents.

$..........................

11 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of addressable sub-fire alarm panels
( SAP), repeater panel (RP), mimic panels c/w associated control
equipment, wirings, relays, maintenance-free nickel cadmium
batteries, battery charger, meters, associated electrical works,
emergency power supply, and all necessary ancillaries and
accessories as specified in the tender documents.

$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

12 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of approved type digital
communicator for the fire alarm communication with the approved
DECAMS including application of telephone leased line and direct
line, Telco's wireless/GPRS network of different services
providers (if means of wireless transmission is used for primary
and backup), arrangement with relevant Authorities for the
installation and all necessary ancillaries and accessories as
specified in the tender documents.
$..........................

Carried Forward

HGA3NH-MEl Works ME/40


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

FIRE DETECTION AND FIRE ALARM SYSTEM (cont'd)

13 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of addressable break glass, manual
call points and alarm bells, strobe lights , detectors c/w all
necessary ancillaries and accessories as specified in the tender
documents.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

14 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of lightning suppressors to guard
against lightning surge / inductive disturbance c/w all necessary
ancillaries and accessories as specified in the tender documents.
$..........................

15 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of fire resistant signal cables from
fire alarm panel to all lifts control panels, detectors, essential MV
fan panels, smoke control systems, all life safety support, access
gates, fire shutter, electromagnetic or electromechanical door-
holding/ locking device systems, etc including conduits,
trunkings, cable supports, fire stop and all necessary ancillaries
and accessories as specified in the tender documents.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/41


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

FIRE EXTINGUISHERS
16 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of portable fire extinguishers as
indicated in the architectural tender drawings. The works shall
also include brackets and all necessary accessories to effect a
complete installation.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

TWO-WAY EMERGENCY VOICE COMMUNICATION SYSTEM


17 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of two-way emergency voice
communication system including firemen intercom handsets,
main panel, fire resistant cables and all necessary builder’s work,
supports and accessories to effect a complete installation
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/42


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

DRY RISER SYSTEM


18 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of dry riser system, inclusive of
class “B” heavy-duty galvanized steel pipe for dry riser system,
automatic air vents, drains, fire rated enclosure, landing valves,
2-way / 4-way breeching inlets, 150/200 mm diameter distribution
pipe, fire-rated material, stainless steel hose cradle and
containment, and all necessary builder’s work to effect a
complete installation.
$..........................

19 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of standby fire hose for connection
to dry riser landing valves c/w all necessary ancillaries and
accessories as specified in the tender documents.
$..........................

CLEAN AGENT FIRE SUPPRESSION SYSTEM


20 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of clean agent (clean gas) fire
suppression system for the Server room inlcuding eletrical wiring
works, devices, control panel, valves, cylinders, pipeworks,
detectors, breathing apparatus, signages, visual & audible alarm,
interfacing to building fire alarm panel and all necessary
accessories to effect a complete installation and comply to NFPA
2001. The works shall included detailed design, calculation,
coordination, supervision, testing and commissioning,
endorsement & submission to authority for approval/ clearance
by Contractor's engaged Qualified Person (QP), and RI
inspection clearance by Contractor's engaged Registered
Inspector (RI).
$..........................

Carried Forward

HGA3NH-MEl Works ME/43


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

FIRE PROTECTION SYSTEMS


21 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of Pre-action Sprinkler system
complete with failed safe devices, air compressor, control valves
assembly, sprinkler head and sprinkler pipes, detectors, valves,
UL/FM approved control panel, cabling, and all necessary
ancillaries and accessories etc. to effect a complete installation
as specified in the tender documents.
$..........................

22 Complete testing and commissioning of all fire protection system


and all other tests deemed necessary by the S.O.
$..........................

23 Submission of shop drawings, complete operation and


maintenance manuals including as-built drawings in hard and soft
copy.
$..........................

24 Fire Alarm system provisions & interfacing with kitchen ventilation


fan system, gas solenoid valves, gas leak detection system,
clean agent fire suppression system and kitchen fire suppression
system.
$..........................

25 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.

$..........................

26 Contractor's engaged Qualified Person (QP) for design,


supervise, endorse and issue certification for special building
material (FSC 02) for authority compliance.
$..........................

ANY OTHER WORKS


27 Any ancillary or other works not specifically mentioned and
described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
a …....................................................... Sum $..........................

b …....................................................... Sum $..........................

c …....................................................... Sum $..........................

28 Preliminaries $..........................

Carried Forward

HGA3NH-MEl Works ME/44


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

MECHANICAL WORKS

D PLUMBING, SANITARY AND GAS SYSTEM

D1 PLUMBING & SANITARY SYSTEM

1 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of underground pipe (VCP) and
connection from last inspection chamber to existing sewer
manhole, complete with all necessary ancillaries and
accessories. The work shall include connection to public sewer
manhole via pipe-jacking, inclusive of Professional Engineer
design fee for deep ICs to S.O’s approval as specified in tender
document.
$..........................

2 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of heavy duty ductile iron cement
lined underground pipes/hubless cast iron c/w internal lining
and all necessary ancillaries and accessories as interconnection
(between inspection chambers, floor trap, gully sump, screen
chamber, or etc) c/w pipe fittings, vent pipes, concrete
haunching, etc and all necessary ancillaries and accessories as
specified in the tender documents.
$..........................

3 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of secondary drainage system c/w
inspection chambers, underground pipeworks, floor traps, gully
traps, frames, covers, underground pipe works etc and
connection to inspection chamber. $..........................
a 1st Storey from Sanitary discharge & vent stacks to
inspection chambers Sum $..........................

b 1st Storey other areas Sum $..........................

4 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of floor waste, waste sump , c/w
heavy duty covers, etc and all necessary ancillaries and
accessories as specified in the tender documents.
$..........................

Carried Forward

HGA3NH-MEl Works ME/45


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D1 PLUMBING & SANITARY SYSTEM (cont'd)

5 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of heavy duty ductile iron cement
lined underground pipes interconnection (between floor waste,
waste sump, gully trap or etc) c/w pipe fittings, vent pipes,
concrete haunching, etc and all necessary ancillaries and
accessories as specified in the tender documents.
$..........................

6 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of underground circular grease trap,
completed with heavy duty cover, stainless steel strainer bucket,
screen chamber and all necessary accessories to effect a
complete installation. The work shall include structural design &
endorsement of the grease trap for the vehicular loading and to
be carried out by Contractor's engaged Professional Engineer.
$..........................

7 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of aboveground soil, waste and vent
stacks, branch drainlines complete with floor wastes, floor and
urinal traps, sanitary and vent pipe works , waste outlets, gully
traps and inclusive of all connection to soil and waste fitments,
etc. The sanitary wares and fittings including wash basin, urinals,
S-trap water closet, auto sensors for flush valves, flush valves,
sink & etc. as specified in tender drawings.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/46


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D1 PLUMBING & SANITARY SYSTEM (cont'd)

8 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of waste pipe from equipment /
waste appliance (such as washing machine, etc.) to the nearest
floor trap shall be deem to be included as specified in tender
document. Adequate number of floor traps shall be provided for
laundry washing machine waste discharge outlet. The work shall
include one (1) lot of aboveground soil, waste and vent stacks,
branch drainlines complete with floor wastes, floor traps, sanitary
and vent pipe works , waste outlets and inclusive of all
connection to sanitary fitments, etc. The sanitary wares and
fittings including wash basin, sink etc. as specified in tender
drawings.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/47


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D1 PLUMBING & SANITARY SYSTEM (cont'd)

9 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of dedicated full ventilated sanitary
discharge system as specified in the tender drawing for Sluice
Rooms. The work shall include one (1) lot of aboveground soil,
waste and vent stacks, branch drainlines complete with floor
wastes, floor traps, sanitary and vent pipe works , waste outlets
and inclusive of all connection to sanitary fitments, etc. The
sanitary wares and fittings including wash basin, sink etc. as
specified in tender drawings.
$..........................
a 3rd to 6th Storey Sluice Rooms Sum $..........................

b 7th Storey sanitary provision for future conversion to


Sluice Room Sum $..........................

10 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of dedicated full ventilated sanitary
discharge system as specified in the tender drawing for each
Isolation Room's Assisted Bath and WC. The work shall include
aboveground soil, waste and vent stacks, branch drainlines
complete with floor wastes, shallow type floor and urinal traps,
sanitary and vent pipe works , waste outlets, gully traps and
inclusive of all connection to soil and waste fitments, etc. The
sanitary wares and fittings including wash basin, urinals, S-trap
water closet, auto sensors for flush valves, flush valves, sink ,
shower etc. as specified in tender drawings.
$..........................
a 3rd to 6th Storey Isolation Room's Assisted Bath and WC
Sum $..........................

b 7th Storey Staff Lounge's Assisted Bath and WC (serve as


Isolation Room's Assisted Bath and WC after future
conversion of 7th Storey)
Sum $..........................

11 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of dedicated full ventilated sanitary
system as specified in the tender drawing for kitchen. The work
shall include aboveground waste and vent stacks, branch
drainlines, pipe trenches complete with floor wastes, floor traps,
sanitary and vent pipe works , waste outlets and inclusive of all
connection to sanitary fitments, etc. The sanitary wares and
fittings including wash basins, sinks, equipment waste outlets
etc. as specified in tender drawings.
$..........................
a 7th Storey Kitchen Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/48


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D1 PLUMBING & SANITARY SYSTEM (cont'd)

12 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of dedicated waste drain discharge
system/ pipe as specified in the tender documents and drawings.
for hosereel risers The work shall include pipework to open
drains, haunching, and all necessary ancillaries and accessories
as specified in the tender documents and drawings.
$..........................
a 1st Storey to Roof Hosereel/ Dry Risers Sum $..........................

b 1st Storey to Roof Fire Sprinkler Pipe Riser Sum $..........................

c 1st Storey to Roof Plumbing Riser Sum $..........................

d 2nd Storey Potable Water Transfer Pump Room Sum $..........................

e 2nd Storey Fire Sprinkler Pump Room Sum $..........................

13 Complete design ,development, supply, delivery, installation,


testing and commissioning of one (1) lot of sump pumps (with
duty and standby pumps), pipe work to open drains and
associated electrical works, c/w fittings, supporting brackets,
check valves, gate valves, access panels, control panels, vertical
ladders, heavy duty covers, QP submission, etc and all
necessary ancillaries and accessories as specified in the tender
documents and drawings. The work shall include supply, delivery,
installation, testing and commissioning One (1) lot of water leak
detection system complete with condensate/ water leak sensor,
local control panel, remote monitoring panel, isolators, control
wiring, electrical works, all necessary control devices, fittings and
accessories for efficient operation of the systems.

$..........................
a Lift Pits for Fire Lift Lobby 1 Sum $..........................

b Lift Pits for Fire Lift Lobby 2 Sum $..........................

14 The excavation and backfilling of pipe trenches and valve


chambers. These works shall comply with the requirements as
specified in Specifications for the Civil /Builders Works which
formed part of the whole Specifications.
$..........................

15 Complete Testing and commissioning of plumbing and sanitary


system and all other tests deemed necessary by the S.O.. The
works shall include hydrostatic and leakage test for the systems,
all as specified. $..........................

16 Submission of shop drawings, complete operation and


maintenance manuals including as-built drawings, equipment
catalogue and etc in hard and soft copy.
$..........................

Carried Forward

HGA3NH-MEl Works ME/49


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D1 PLUMBING & SANITARY SYSTEM (cont'd)

17 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.
$..........................

18 Engagement of licensed plumber to undertake the supervision of


the connection works from the last inspection chamber to the
public manhole and the endorsing of all forms for sewarage
connections.
$..........................

19 Preliminaries $..........................

20 Any ancillary or other works not specifically mentioned and


described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
a …....................................................... Sum $..........................

b …....................................................... Sum $..........................

c …....................................................... Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/50


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM

` i COLD WATER DISTRIBUTION SYSTEM


1 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of heavy duty ductile iron cement
lined pipes from bulk meter to potable water transfer tank, c/w
supporting brackets, anti water hammer arrestor etc and all
necessary ancillaries and accessories as specified in the tender
documents.
$..........................

2 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of potable water FRP transfer tank,
transfer pumpset, c/w float valves, cat ladder with safety cage
(internal & external), isolation valves, drain pipes, balancing
pipes, level indicator, water level alarm system, overflow pipes,
vent pipes, strainer, variable vibration isolators, interconnecting
pipework and ancillaries c/w fittings, supporting brackets, access
panels, control panels, fittings, speed drive, base plate, plinth,
inertia blocks, vibration isolators, pressure gauges, pressure
switches, associated and accessories as specified in the tender
documents. The pump system shall backup with essential power
supply from the generator and fully pre-assembled with control
panels, and instruments mounted on skids with lifting eyes for
piping connection, valves cable termination for power supply, and
all necessary interfacing.

$..........................

3 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of potable domestic water FRP roof
tank, booster pumpset, pressure vessels, c/w float valves, cat
ladder with safety cage (internal & external), isolation valves,
drain pipes,balancing pipes, level indicator, water level alarm
system , overflow pipes, vent pipes, strainer, variable vibration
isolators, interconnecting pipework and ancillaries c/w fittings,
supporting brackets, access panels, control panels, fittings,
speed drive, base plate, plinth, inertia blocks, vibration isolators,
pressure gauges, pressure switches, associated and accessories
as specified in the tender documents. The pump system shall
backup with essential power supply from the generator and fully
pre-assembled with control panels, and instruments mounted on
skids with lifting eyes for piping connection, valves cable
termination for power supply, and all necessary interfacing.

$..........................

Carried Forward

HGA3NH-MEl Works ME/51


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

i COLD WATER DISTRIBUTION SYSTEM (cont'd)


4 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of potable water FRP break tank (for
Sluice Rooms' equipment sanitizers), booster pumpset, pressure
vessels, c/w float valves, cat ladder with safety cage (internal &
external), isolation valves, drain pipes,balancing pipes, level
indicator, water level alarm system, overflow pipes, vent pipes,
strainer, variable vibration isolators, interconnecting pipework and
ancillaries c/w fittings, supporting brackets, access panels,
control panels, fittings, speed drive, base plate, plinth, inertia
blocks, vibration isolators, pressure gauges, pressure switches,
associated and accessories as specified in the tender
documents. The pump system shall backup with essential power
supply from the generator and fully pre-assembled with control
panels, and instruments mounted on skids with lifting eyes for
piping connection, valves cable termination for power supply, and
all necessary interfacing.
$..........................

5 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of potable water FRP break tank (for
Auto-Irrigation system), c/w float valves, cat ladder with safety
cage (internal & external), isolation valves, drain pipes,balancing
pipes, level indicator, water level alarm system, overflow pipes,
vent pipes, strainer, variable vibration isolators, interconnecting
pipework and ancillaries c/w fittings, supporting brackets, access
panels, control panels, fittings, base plate, plinth, pressure
gauges, pressure switches, associated and accessories as
specified in the tender documents.
$..........................

Carried Forward

HGA3NH-MEl Works ME/52


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

i COLD WATER DISTRIBUTION SYSTEM (cont'd)


6 Complete design, supply, installation, testing and commissioning
of one (1) lot of Auto-Irrigation system, c/w booster pumpset,
pressure vessels, outgoing pipework and irrigation system
provisions, isolation valves, drain pipes,balancing pipes, strainer,
variable vibration isolators, and ancillaries c/w fittings, supporting
brackets, access panels, control panels, fittings, speed drive,
base plate, plinth, inertia blocks, vibration isolators, pressure
gauges, pressure switches, associated and accessories as
specified in the tender documents. The pump system shall fully
pre-assembled with control panels, and instruments mounted on
skids with lifting eyes for piping connection, valves cable
termination for power supply, and all necessary interfacing. The
works shall include detailed design, calculation, structural support
& design, coordination, supervision, testing and commissioning,
endorsement & drawing & document submission by Contractor's
engaged Auto-Irrigation System Specialist.
$..........................

7 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of potable domestic cold water
ductile iron / copper from bulk meter, roof potable domestic
water storage tank & from the booster system to header,
inclusive transfer water pipes, main distribution pipes risers,
private digital water meters, water points and cap-offs and etc
c/w fittings, supporting brackets, check valves, gate valves, anti
water hammer arrestor, etc and all necessary ancillaries and
accessories as specified in the tender documents. $..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/53


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

i COLD WATER DISTRIBUTION SYSTEM (cont'd)


8 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of cold water pipe work to water
points and etc c/w fittings, supporting brackets, check valves,
gate valves, anti water hammer arrestor, private digital water
meters, sub-meters, etc and all necessary ancillaries and
accessories as specified in the tender document.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

9 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of plumbing wares and fittings for
installation and final connection to the potable cold distribution
system c/w all necessary ancillaries and accessories as specified
in the tender documents. The plumbing & sanitary wares and
fittings are including the S-trap water closet, urinals, flush
valves, auto sensor, wash basin taps, cold and hot water
dispenser, water cooler, sinks and etc including all necessary
accessories to effect a complete installation.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/54


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

i COLD WATER DISTRIBUTION SYSTEM (cont'd)


10 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of cold water pipe works with bib
taps for landscape area/ M&E space and a set water supply to
the irrigation tank and all necessary ancillaries and accessories
as specified in the tender documents.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

11 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of wash and flush system to flush
the whole length of sluice chute, come with manual activation of
flushing and automatic & manual deactivation and all necessary
ancillaries and accessories as specified in the tender documents.
$..........................

12 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of suitably pipe sleeve or service
duct for PUB incoming water connecting pipe to over cross
existing external drain c/w fittings, supporting brackets, and all
necessary ancillaries and accessories as specified in the tender
documents and drawings. Contractor scope of work shall include
all necessary arrangement and coordination with related
authorities, authorities compliance and approval clearance,
hacking and make good of affected existing drain, and any other
compulsory authorities requirements.
$..........................

` ii HOT WATER DISTRIBUTION SYSTEM


13 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of centralized heat pump water
heating and storage system complete with hot water storage heat
exchanger tanks, air to water heat pumps, hot water circulation
pumps, vibration isolators, interconnecting pipe work and,
ancillaries c/w fittings, supporting brackets, isolation valves,
check valves, gate valves, IP 55 control panels, fittings, speed
drive, control panels, base plate, plinth, inertia blocks, vibration
isolators, pressure gauges, pressure switches, associated
electrical works, etc and all necessary ancillaries and accessories
as specified in the tender documents and drawings. The system
shall backup with essential power supply from the generator.

$..........................

Carried Forward

HGA3NH-MEl Works ME/55


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

ii HOT WATER DISTRIBUTION SYSTEM (cont'd)


14 Complete supply, delivery, installation, testing and
commissioning of one (1) lot of domestic hot water pipe work
from the heat pump system to header, private digital water
meters, and water fitments (e.g. showers) complete with fittings,
supporting brackets, check valves, gate valves, insulation, anti-
water hammer arrestor, etc and all necessary ancillaries and
accessories as specified in the tender document. The work shall
include interfacing for booster air fan system c/w ductwork for
routing cold air discharge from heat pump system at roof to 7th
storey.
$..........................
a 1st Storey Sum $..........................

b 2nd Storey Sum $..........................

c 3rd Storey Sum $..........................

d 4th Storey Sum $..........................

e 5th Storey Sum $..........................

f 6th Storey Sum $..........................

g 7th Storey Sum $..........................

h Roof Sum $..........................

15 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of electric instant water heater
system to serve shower heads in 1st Storey Senior Care Center,
complete with hot water heater, interconnecting pipe work and,
ancillaries c/w fittings, supporting brackets, isolation valves,
check valves, gate valves, control panels, fittings, speed drive,
control panels, base plate, pressure gauges, pressure switches,
associated electrical works, etc and all necessary ancillaries and
accessories as specified in the tender documents and drawings.
The system shall backup with essential power supply from the
generator.
$..........................

16 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of IP55 control panel and a remote
monitoring alarm panel at Fire Command Centre with connecting
cables to all tanks and pumps c/w all necessary ancillaries and
accessories as specified in the tender documents. The work shall
include BTU meter provision for the heat pump water heating and
storage system. It shall be linked to the system control panel
module for measure the system performance and efficiency. The
control panel shall also complete with power meter.

$..........................

Carried Forward

HGA3NH-MEl Works ME/56


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

ii HOT WATER DISTRIBUTION SYSTEM (cont'd)


17 Supply, delivery and installation of all showers in Toilet w/
Showers (1st Storey), Showers, Assisted Bath and WCs, Large
Assisted Baths, Toilets, & Staff Bath and WCs (3rd to 7th
Storeys) and showers in etc area with thermostatic mixing valve
as specified in the tender document complete with adjustable
temperature setting.
$..........................

18 Supply, delivery and installation of reinforced concrete plinths,


penetration works, hangers and brackets, etc supporting from the
building structure as specified in the tender document.
$..........................

19 Complete Testing and Commissioning of the water distribution


systems and all other tests deemed necessary by the S.O.. The
hydrostatic and leakage tests, water sampling test complete with
test reports for the complete water reticulation system as
specified. The cleaning and flushing for the systems as well as
the sterilization of the potable water system, all as specified. All
the necessary works, T&C shall be incldued for phase water turn-
on.
$..........................

Carried Forward

HGA3NH-MEl Works ME/57


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D2 POTABLE COLD AND HOT WATER DISTRIBUTION SYSTEM (cont'd)

20 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

21 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.

$..........................

22 Engagement of licensed plumber to liaise with PUB and all


relevant authorities on the submission, inspection, testing etc. of
the proposed works.
$..........................

23 Engagement of Licensed Cable Detection Worker for existing


underground services detection works as specified in the tender
documents.
$..........................

24 Preliminaries $..........................

25 Any ancillary or other works not specifically mentioned and


described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
a …....................................................... Sum $..........................

b …....................................................... Sum $..........................

c …....................................................... Sum $..........................

Carried Forward

HGA3NH-MEl Works ME/58


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D3 TOWN GAS SYSTEM

1 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of aboveground and underground
gas pipe work from authority's gas service isolation valve (GSIV)
c/w fittings, supporting brackets, flexible gas hose, pipe
protection, rooftop weatherproof louver, meters, ventilation ducts
and openings c/w weatherproof louver, service valves, spools,
gas cocks, gas solenoid valves, cap-off, etc and all necessary
ancillaries and accessories as specified in the tender documents.

$..........................

2 Complete supply, delivery, installation, testing and


commissioning of one (1) lot of API pipework complete with GI
jacketing from the stack to gas outlets c/w fittings and vendor cap
off with supporting brackets, pipe protection, service valves,
spools, gas cocks, gas solenoid valves, cap-off, etc and all
necessary ancillaries and accessories as specified in the tender
documents.
$..........................
a 1st Storey Sum $..........................

b 2nd to 6th Storey Sum $..........................

c 7th Storey Sum $..........................

d Roof Sum $..........................

3 Completesupply, delivery, installation, testing and


commissioning of one (1) lot of interfacing panel complete with all
necessary wiring works to interface with laundry and kitchen
ventilation fan systems, laundry and kitchen gas solenoid valves,
laundry and kitchen gas leak detection systems, kitchen fire
suppression system, and fire alarm system as specified in the
tender documents.
$..........................

Carried Forward $..........................

HGA3NH-MEl Works ME/59


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

D3 TOWN GAS SYSTEM (cont'd)

4 Engagement of licensed service gas worker to liaise with


Powergas and all relevant authorities on the submission,
inspection, testing etc. of the proposed works.
$..........................

5 Submission of complete operation and maintenance manuals


including as-built drawings, equipment catalogue and etc.
$..........................

6 Comprehensive maintenance and servicing of the whole works


against defects and the making good of any defects during the
Defects Liability Period. Servicing of the system shall be done on
a monthly period during the Defects Liability Period.

$..........................

7 Preliminaries $..........................

8 Any ancillary or other works not specifically mentioned and


described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
a …....................................................... Sum $..........................

b …....................................................... Sum $..........................

c …....................................................... Sum $..........................

Carried Forward $..........................

HGA3NH-MEl Works ME/60


PROPOSED DEVELOPMENT OF A NURSING HOME AT HOUGANG AVENUE 3, SINGAPORE

BREAKDOWN COST OF WORKS


SECTION 6 - MECHANICAL & ELECTRICAL WORKS

Item Description Unit Sum Amount


$ ct

Brought Forward $..........................

E LIFT INSTALLATION

1 Supply, install, test and commission two nos. of 33 Pax/2,500kg,


Machine Roomless, Service/Fire/Fire Escape Bed lifts
$..........................

2 Supply, install, test and commission two nos. of 33 Pax/2,500kg,


Machine Roomless, Passenger/Fire/Fire Escape Bed lifts
$..........................

3 Power and lighting in lift shafts and lift pits complete with all
necessary cabbling, cable containment, accessories, etc
$..........................

4 Computerized Lift Management System $..........................

5 Lift control panels and lift supervisory panels complete with all
necessary cabling, cable containment , accessories, etc
$..........................

6 Supply, install, test and commission of 2 numbers Service Lift


interfacing with Autonomous Mobile Robot (AMR) and all related
power provision and accessories for complete system operation
for all Service Lifts.
$..........................

7 Lift finishes, painting, identification and labelling to Architect


details.
$..........................

8 Testing and commissioning of Lift Installation as specified in the


tender documents
$..........................

9 To engage a lift Professional Engineer for certification,


commissioning and testing of the lift as to complete the whole
project $..........................

10 Preliminaries $..........................

11 Any ancillary or other works not specifically mentioned and


described in the Tender Documents but which are either
indispensably necessary to carry out and bring the works to
completion or which may contingently become necessary to
overcome difficulties before the completion. Please specify:-
$..........................
a …....................................................... Sum $..........................

b …....................................................... Sum $..........................

c …....................................................... Sum $..........................

TOTAL CARRIED TO SUMMARY OF TENDER, PAGE


SOT/1 $..........................

HGA3NH-MEl Works ME/61