Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 19

UNIQUE INDIA CONSTRUCTION PVT.

LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-5000
PLANNED VS ACHIEVED FOR THE MONTH OF JULY'2023
Doc. No.

S.NO DESCTRIPTION Unit July Planning Week -01

CONCRETE Grade of Concrete


1 M10 Cum 20.00 0.00
2 M25 Cum 10.00 0.00
3 M30 Cum 1624.00 411.50
4 M35 Cum 145.00 136.00

TOTAL QUANTITY OF CONCRETE 1799.00 547.50


FORMWORK 110th FLOOR
1 Block -B Sqm 2153.83 861.53
11th floor
2 Block -A Sqm 1270.68 1270.68
3 Block -B Sqm 2153.83 0.00
4 Block -C Sqm 778.23 778.23
12th floor
5 Block -A Sqm 1821.68 182.17
6 Block -B Sqm 2153.83 0.00
7 Block -C Sqm 1848.05 646.82
13th floor
8 Block -A Sqm 551.00 0.00
9 Block -C Sqm 1848.05 0.00
TOTAL QUANTITY OF SHUTTERING Sqm 14579.18 3739.43
REINFORCEMENT DIA OF STEEL
1 8MM Dia MT 80.75 29.86
2 10MM Dia MT 12.57 1.90
3 12MM Dia MT 29.48 9.59
4 16MM Dia MT 45.32 10.66
5 20MM Dia MT 18.91 2.30
6 25MM Dia MT 4.80 0.50
7 32MM Dia MT 0.25 0.00
TOTAL QUANTITY OF STEEL MT 192.08 54.81
BLOCK WORK 7th Floor
1 Block - A (6 flat) Sqm 1070.62 450.00
2 Block - B (7flat) Sqm 1343.00 102.00
B 8th Floor
1 Block - A (6 flat) Sqm 1070.62 0.00
2 Block - B (7flat) Sqm 1343.00 0.00
3 Block - C (6flat) Sqm 1121.33 0.00
C 9th Floor
3 Block - C (6flat) Sqm 1121.33 0.00
TOTAL QUANTITY OF BLOCK WORK Sqm 7069.90 552.00
INTERNAL PLASTER 4th floor
1 Block - A (6 flat) Sqm 2830.00 658.00
2 Block - B (7Flat) Sqm 2963.89 847.00
5th floor
1 Block - A (6 flat) Sqm 2830.00 0.00
2 Block - B (1Flat) Sqm 2963.89 0.00
3 Block - C (6flat) Sqm 2830.65 823.00
6th floor
3 Block - C (6flat) Sqm 2830.65 0.00
TOTAL QUANTITY OF INTERNAL PLASTER
WORK Sqm 17249.08 2328.00

EXTERNAL PLASTER Up to 5th floor


1 Block - A (6 flat) Sqm 1980.00 396.00
2 Block - B (7Flat) Sqm 2640.00 528.00
3 Block - C (6flat) Sqm 1980.00 396.00
TOTAL QUANTITY OF INTERNAL PLASTER
Sqm 6600.00 1320.00
WORK
UCTION PVT.LTD
GOLE HYDERABAD-500039
HE MONTH OF JULY'2023
Daet : Saturday, July 1, 2023

Week -02 Week -03 Week -04 July Achieved % REMARKS


Achieved

0.00 0%
0.00 0%
411.50 25%
136.00 94%

0.00 0.00 0.00 547.50 30%

861.53 40% Column+Slab


1839.00
1270.68 100% Slab
0.00 0% Column+Slab
778.23 100% Slab

182.17 10% Columns+Slab


0.00 0% Columns+Slab
646.82 35% Columns+Slab

0.00 0% Columns
0.00 0% Columns+Slab
0.00 0.00 0.00 3739.43 26%

29.86 37%
1.90 15%
9.59 33%
10.66 24%
2.30 12%
0.50 10%
0.00 0%
0.00 0.00 0.00 54.81 29%

450.00 42%
102.00 8%

0.00 0%
0.00 0%
0.00 0%

0.00 0%
0.00 0.00 0.00 552.00 8%

658.00 23%
847.00 29%

0.00 0%
0.00 0%
823.00 29%

0.00 0%

0.00 0.00 0.00 2328.00 13%

396.00 20%
528.00 20%
396.00 20%

0.00 0.00 0.00 1320.00 20%


5700.00

551.70
551.70
735.60

60.00
1137.20

1137.20
UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039
DOCUMENT NO:
THREE MONTH SCHEDULE OF JULY, AUG & SEPT-2023
Block - B
S.No Acitivity Block - A Block - C
B1 B2
Jul-23

1 10th floor slab 6/23/2023 6/26/2023 7/1/2023 6/13/2023

2 11th floor slab 7/6/2023 7/10/2023 7/15/2023 7/3/2023

3 11th to 12th column 7/16/2023 7/20/2023 7/25/2023 7/13/2023

4 12th floor slab 7/20/2023 7/24/2023 7/29/2023 7/18/2023

5 12th to 13th column 7/30/2023 8/2/2023 8/7/2023 7/28/2023

6 13th floor slab 8/4/2023 8/7/2023 8/11/2023 8/1/2023

Aug-23

7 13th to 14th column 8/14/2023 8/17/2023 8/21/2023 8/11/2023

8 14th floor slab 8/18/2023 8/20/2023 8/24/2023 8/16/2023

9 14th to 15th column 8/28/2023 8/30/2023 9/3/2023 8/26/2023

10 15th floor slab 9/1/2023 8/30/2023 9/3/2023 8/31/2023

Sep-23

11 14th to 16th column 9/11/2023 9/9/2023 9/13/2023 9/10/2023

12 16th floor slab 9/15/2023 9/12/2023 9/16/2023 9/15/2023

13 16th to 17th column 9/25/2023 9/22/2023 9/26/2023 9/25/2023

14 17th floor slab 9/29/2023 9/26/2023 9/29/2023 9/30/2023

15 16th to 17th column 10/9/2023 10/6/2023 10/9/2023 10/10/2023

16 18th floor slab 10/13/2023 10/10/2023 10/13/2023 10/15/2023

POUR 6 AREA

Acitivity Start date End date

17 Balance PCC 7/10/2023

18 Pour - 06 balance slab 7/1/2023 7/30/2023

19 B1 to stilt R.W. 8/2/2023 8/10/2023

STILT FLOOR (STP AREA )

20 STP Walls up to 7/5/2023


Stillt floor & Column

21 Stilt level slab Only stp area 7/20/2023


UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039
DOCUMENT NO:
THREE MONTH SCHEDULE OF JULY, AUG & SEPT-2023
Block - B
S.No Acitivity Block - A Block - C
B1 B2
Block work
Acitivity Block - A (6 flat) Block - B (7-Flat) Block - C (6 Flat)

6 7th floor (Block-A, B & C) 7/15/2023 7/16/2023 Done

7 8th floor (Block-A, B & C) 7/30/2023 7/31/2023 7/14/2023

8 9th floor (Block-A, B & C) 8/14/2023 8/15/2023 7/29/2023

9 10th floor (Block-A, B & C) 8/29/2023 8/30/2023 8/13/2023

10 11th floor (Block-A, B & C) 9/13/2023 9/14/2023 8/28/2023

11 12th floor (Block-A, B & C) 9/28/2023 9/29/2023 9/12/2023

Internal Plaster
Activity Block - A (6 flat) Block - B (FlatB1,B7) Block - C (6 Flat)

13 3rd floor(Block - C 6Flat) 7/3/2023 Done Done

14 4th floor 7/10/2023 7/16/2023 Done

15 5th floor 7/25/2023 7/31/2023 7/10/2023

16 6th floor 8/9/2023 8/15/2023 7/25/2023

17 7th floor 8/24/2023 8/30/2023 8/9/2023

18 8th floor 9/8/2023 9/14/2023 8/24/2023

19 9th floor 9/23/2023 9/29/2023 9/8/2023

20 10th floor 10/8/2023 10/14/2023 9/23/2023

Exteranal Plastering Up to 5th floor-----100%

1 External staging provided 5/23/2023 7/15/2023 9

2 External plaster 5/26/2023 8/11/2023 77


UNIQUE INDIA CONSTRUCTION PVT.LTD

PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039


DOCUMENT NO:
SCHEDULE MONTH OF JULY-2023
Block - B
S.No Acitivity Block - A Block - C
B1 B2
Jul-23

1 10th floor slab 6/23/2023 6/26/2023 7/1/2023 6/13/2023

2 10th to 11th columns Done 7/4/2023 7/9/2023 Done

3 11th floor slab 7/6/2023 7/10/2023 7/15/2023 7/3/2023

4 11th to 12th columns 7/16/2023 7/20/2023 7/25/2023 7/13/2023

5 12th floor slab 7/20/2023 7/24/2023 7/29/2023 7/18/2023

6 12th to 13th columns 7/30/2023 8/2/2023 8/7/2023 7/28/2023

7 13th floor slab 8/4/2023 8/7/2023 8/11/2023 8/1/2023

POUR 6 AREA

Acitivity Start date End date

2 Pour - 06 balance slab 7/1/2023 7/30/2023

STILT FLOOR (STP AREA )

STP Walls up to
1 Stillt floor & Column 7/5/2023

2 Stilt level slab Only stp area 7/20/2023

Block work
Block - B (Club Block - C (6
Acitivity Block - A (6 flat) House) Flat)

1 4th floor Block - A & B (12Flat) Done Done

2 5th floor(Block-A, B & C-19 Flat) Done Done

3 6th floor (Block-A, B & C) Done Done

4 7th floor (Block-A, B & C) 7/15/2023 7/16/2023 Done

5 8th floor (Block-A, B & C) 7/30/2023 7/31/2023 7/14/2023


6 9th floor (Block-A, B & C) 8/14/2023 8/15/2023 7/29/2023

Internal Plaster
Block - B Block - C (6
Activity Block - A (6 flat) (FlatB1,B7) Flat)

1 1st floor (Block -A&C 7flat) Done Done

2 2nd floor plaster Done Done

3 3rd floor(Block - C 6Flat) 7/3/2023 Done

4 4th floor 7/10/2023 7/16/2023 Done

5 5th floor 7/25/2023 7/31/2023 7/10/2023

6 6th floor 8/9/2023 8/15/2023 7/25/2023


UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039
DOCUMENT NO:
MONTH SCHEDULE OF JULY"2023

S.NO DESCRIPTION OF WORK SHORT ID Target Date

Block -A 7/6/2023
Block - B1 7/10/2023
1 11th floor slab
Block - B2 7/15/2023
Block -C 7/3/2023

Block -A 7/20/2023
Block - B1 7/24/2023
2 12th floor slab
Block - B2 7/29/2023
Block -C 7/18/2023

Block -A 8/4/2023
Block - B1 8/7/2023
3 13th floor slab
Block - B2 8/11/2023
Block -C 8/1/2023

4 Balance PCC-B1 lvl Pour-06 7/10/2023


5 Balance RW Wall B1 lvl Pour-06 7/15/2023
6 B1 Slab Pour-06 7/30/2023

7 Pour - 05 Stilt Lvl Pour-05 7/20/2023

Finishing Work
Block-A 7/15/2023
1 7th floor Block Work
Block-B 7/16/2023
Block-A 7/30/2023
2 8th floor Block work Block-B 7/31/2023
Block-C 7/14/2023
3 9th floor Block work Block-C 7/29/2023
Block-A 7/10/2023
4 4th floor Internal Plaster
Block-B 7/16/2023
Block-A 7/25/2023
5 5th floor Internal Plaster Block-B 7/31/2023
Block-C 7/10/2023
6 6th floor Internal Plaster Block-C 7/25/2023

TOTAL QTY
CTION PVT.LTD
LE HYDERABAD-500039

JULY"2023
Target Grade of Concrete Steel
Achived Date concrete Qty(CUM) Qty(MT)

M30 401.00
40.76
M35 115.00

M30 583.00 87.13

M30 240.00 36.72

M10 20.00
M25 10.00 6.97
M30 80.00

M30 230 20.50

Sqm 2413.62

Sqm 3534.95

Sqm 1121.33
Sqm 5793.89

Sqm 8624.54

Sqm 2830.65

M30 1534
192.082
M35 115
UNIQUE INDIA CONSTRUCTION PVT.LTD
OUR HOMES REALTORS LTD

Unskilled Carpenters Bar benders Block work Plastering


S.No Item Description Work Location Unit Qty NMR
(In Pairs) (In Pairs) (In Pairs) (In Pairs)
MAN POWER REQUIREMENT FOR EVERY TWO FLOOR WORK COMPLETAITION (STRUCTURE & BLOCK WORK /PLASTER
1 Shuttering (Form Work) Sqm 11,400.00 1,900
2 Barbenders MT 250.00 1,136
Concrete-M10, M25, M30 &
3 M50 Cum 1,700.00 1,200
4 Block work Sqm 7,064.00 706.40
5 Plastering work Sqm 17,274.00 1,549.24

Total Requirement in every


month 1,200 3,800 2,273 1,413 3,098

Requirement every 30 day 40 127 76 47 103


Available at Site 25 62 67 37 35
Balance Required 15 65 9 10 68
Remarks
UE INDIA CONSTRUCTION PVT.LTD
OUR HOMES REALTORS LTD

Remarks

O FLOOR WORK COMPLETAITION (STRUCTURE & BLOCK WORK /PLASTER


Considered 6 SQM/Pairs
Considered 0.25MT/Pairs

Considered 10-12 Sqm/Pairs


Considered 11-12 Sqm/Pairs

11,784

393
154
239
UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:OUR HOMES VASAVI METROPOLIS NAGOLE HYDERABAD-500039
Doc. No. Rev :
MICRO SCHEDULE (UP TO JULY 31) DATE:28-06-2023
SR.NO DESCRIPTION Block GRID DURATION START DATE FINISH DATE REMARK
(BLock - A)
1 10th to 11th floor column R-AD/3-16
2 Column marking & starter concrete A R-AD/3-16 5 6/24/2023 6/29/2023
3 Column Reinforcement A R-AD/3-16 4 6/25/2023 6/29/2023
4 Column Shuttering &concreting A R-AD/3-16 5 6/26/2023 7/1/2023
5 Core wall A R-AD/3-16 1 6/29/2023 6/30/2023
6 Staire case A R-AD/3-16 1 7/2/2023 7/3/2023
7 Slab shuttering A R-AD/3-16 7 6/27/2023 7/4/2023
8 Slab Reinforcemet A R-AD/3-16 7 6/29/2023 7/6/2023
9 MEP & Slab Checking A R-AD/3-16 0 7/6/2023 7/6/2023
10 Slab Casting A R-AD/3-16 0 7/6/2023 7/6/2023 11th Block - A
11 11th to 12th floor column R-AD/3-16
12 Column marking & starter concrete A R-AD/3-16 5 7/7/2023 7/12/2023
13 Column Reinforcement A R-AD/3-16 4 7/8/2023 7/12/2023
14 Column Shuttering &concreting A R-AD/3-16 5 7/9/2023 7/14/2023
15 Core wall A R-AD/3-16 1 7/12/2023 7/13/2023
16 Staire case A R-AD/3-16 1 7/15/2023 7/16/2023
17 Slab shuttering A R-AD/3-16 7 7/10/2023 7/17/2023
18 Slab Reinforcemet A R-AD/3-16 7 7/12/2023 7/19/2023
19 MEP & Slab Checking A R-AD/3-16 1 7/19/2023 7/20/2023
20 Slab Casting A R-AD/3-16 0 7/20/2023 7/20/2023 12th Block - A
8th Floor (Block - B1)
1 Column marking & starter concrete B1 N-AD/16-21 5 6/27/2023 7/2/2023
2 Column Reinforcement B1 N-AD/16-21 4 6/28/2023 7/2/2023
3 Column Shuttering &concreting B1 N-AD/16-21 5 6/29/2023 7/4/2023
4 Core wall B1 N-AD/16-21 1 7/2/2023 7/3/2023
5 Staire case B1 N-AD/16-21 1 7/5/2023 7/6/2023
6 Slab shuttering B1 N-AD/16-21 7 6/30/2023 7/7/2023
7 Slab Reinforcemet B1 N-AD/16-21 7 7/2/2023 7/9/2023
8 MEP & Slab Checking B1 N-AD/16-21 1 7/9/2023 7/10/2023
9 Slab Casting B1 N-AD/16-21 0 7/10/2023 7/10/2023 11th floor B1
11th Floor to 12th Floor column (pour - B1)
1 Column marking & starter concrete B1 N-AD/16-21 5 7/11/2023 7/16/2023
2 Column Reinforcement B1 N-AD/16-21 4 7/12/2023 7/16/2023
3 Column Shuttering &concreting B1 N-AD/16-21 5 7/13/2023 7/18/2023
4 Core wall B1 N-AD/16-21 1 7/16/2023 7/17/2023
5 Staire case B1 N-AD/16-21 1 7/19/2023 7/20/2023
6 Slab shuttering B1 N-AD/16-21 7 7/14/2023 7/21/2023
7 Slab Reinforcemet B1 N-AD/16-21 7 7/16/2023 7/23/2023
8 MEP & Slab Checking B1 N-AD/16-21 1 7/23/2023 7/24/2023
9 Slab Casting B1 N-AD/16-21 0 7/24/2023 7/24/2023 12th floor B1
8th Floor (Pour - B2)
10 Column marking & starter concrete B2 B-M/16-21 5 7/2/2023 7/7/2023
11 Column Reinforcement B2 B-M/16-21 4 7/3/2023 7/7/2023
12 Column Shuttering &concreting B2 B-M/16-21 5 7/4/2023 7/9/2023
13 Core wall B2 B-M/16-21 1 7/7/2023 7/8/2023
14 Staire case B2 B-M/16-21 1 7/10/2023 7/11/2023
15 Slab shuttering B2 B-M/16-21 7 7/5/2023 7/12/2023
16 Slab Reinforcemet B2 B-M/16-21 7 7/7/2023 7/14/2023
17 MEP & Slab Checking B2 B-M/16-21 1 7/14/2023 7/15/2023
18 Slab Casting B2 B-M/16-21 0 7/15/2023 7/15/2023 11th floor B2
6th Floor to 7th Floor column (pour - B2)
1 Column marking & starter concrete B2 B-M/16-21 5 7/16/2023 7/21/2023
2 Column Reinforcement B2 B-M/16-21 4 7/17/2023 7/21/2023
3 Column Shuttering &concreting B2 B-M/16-21 5 7/18/2023 7/23/2023
4 Core wall B2 B-M/16-21 1 7/21/2023 7/22/2023
5 Staire case B2 B-M/16-21 1 7/24/2023 7/25/2023
6 Slab shuttering B2 B-M/16-21 7 7/19/2023 7/26/2023
7 Slab Reinforcemet B2 B-M/16-21 7 7/21/2023 7/28/2023
8 MEP & Slab Checking B2 B-M/16-21 0 7/28/2023 7/28/2023
9 Slab Casting B2 B-M/16-21 0 7/28/2023 7/28/2023 12th floor B2
10th Floor (Pour - C)
1 11th to 12th column
2 Column marking & starter concrete C B-AD/16-21 5 7/4/2023 7/9/2023
3 Column Reinforcement C B-AD/16-21 4 7/5/2023 7/9/2023
4 Column Shuttering &concreting C B-AD/16-21 5 7/6/2023 7/11/2023
5 Core wall C B-AD/16-21 1 7/9/2023 7/10/2023
6 Staire case C B-AD/16-21 1 7/12/2023 7/13/2023
7 Slab shuttering C B-AD/16-21 7 7/7/2023 7/14/2023
8 Slab Reinforcemet C B-AD/16-21 7 7/9/2023 7/16/2023
9 MEP & Slab Checking C B-AD/16-21 1 7/16/2023 7/17/2023
10 Slab Casting C B-AD/16-21 1 7/17/2023 7/18/2023 12th floor slab C
1 12th to 13th column
2 Column marking & starter concrete C B-AD/16-21 5 7/19/2023 7/24/2023
3 Column Reinforcement C B-AD/16-21 4 7/20/2023 7/24/2023
4 Column Shuttering &concreting C B-AD/16-21 5 7/21/2023 7/26/2023
5 Core wall C B-AD/16-21 1 7/24/2023 7/25/2023
6 Staire case C B-AD/16-21 1 7/27/2023 7/28/2023
7 Slab shuttering C B-AD/16-21 7 7/22/2023 7/29/2023
8 Slab Reinforcemet C B-AD/16-21 7 7/24/2023 7/31/2023
9 MEP & Slab Checking C B-AD/16-21 1 7/31/2023 8/1/2023
10 Slab Casting C B-AD/16-21 0 8/1/2023 8/1/2023 13th floor slab C

D STP AREA
A Stilt floor Slab shuttering
2 Stilt floor Slab shuttering P - 05 J-N/4-13 10 7/1/2023 7/11/2023
3 Slab Reinforcemet P - 05 J-N/4-13 8 7/7/2023 7/15/2023
4 MEP & Slab Checking P - 05 J-N/4-13 1 7/15/2023 7/16/2023
5 Slab Casting C B-AD/16-21 5 7/15/2023 7/20/2023 Stilt slab
UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039
SCHEDULE FOR STRUCTURE
Block - B
S.No Acitivity Block - A Block - C
B1 B2
1 9th floor slab 6/2/2023 6/8/2023 6/10/2023 5/16/2023

2 9th to 10th column 6/12/2023 6/18/2023 6/20/2023 5/26/2023

3 10th floor slab 6/17/2023 6/23/2023 6/25/2023 6/7/2023

10 10th to 11th column 6/27/2023 7/3/2023 7/5/2023 6/17/2023

11 11th floor slab 7/1/2023 7/6/2023 7/8/2023 6/21/2023

14 11th to 12th column 7/11/2023 7/16/2023 7/18/2023 7/1/2023

15 12th floor slab 7/15/2023 7/19/2023 7/21/2023 7/5/2023

15 12th to 13th column 7/25/2023 7/28/2023 7/30/2023 7/15/2023

16 13th floor slab 7/29/2023 8/1/2023 8/3/2023 7/19/2023

17 13th to 14th column 8/8/2023 8/11/2023 8/13/2023 7/29/2023

18 14th floor slab 8/12/2023 8/14/2023 8/16/2023 8/2/2023

19 14th to 15th column 8/22/2023 8/24/2023 8/26/2023 8/12/2023

20 15th floor slab 8/26/2023 8/27/2023 8/29/2023 8/16/2023

19 14th to 16th column 9/5/2023 9/6/2023 9/8/2023 8/26/2023

16 16th floor slab 9/9/2023 9/9/2023 9/11/2023 8/30/2023

17 16th to 17th column 9/19/2023 9/19/2023 9/21/2023 9/9/2023

16 17th floor slab 9/23/2023 9/22/2023 9/24/2023 9/13/2023

17 17th to 18th column 10/3/2023 10/2/2023 10/4/2023 9/23/2023

16 18th floor slab 10/7/2023 10/5/2023 10/7/2023 9/27/2023

You might also like