Metropolis - July'23 Planning With Three Month Rolling Up To Aug'2023
Metropolis - July'23 Planning With Three Month Rolling Up To Aug'2023
LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-5000
PLANNED VS ACHIEVED FOR THE MONTH OF JULY'2023
Doc. No.
0.00 0%
0.00 0%
411.50 25%
136.00 94%
0.00 0% Columns
0.00 0% Columns+Slab
0.00 0.00 0.00 3739.43 26%
29.86 37%
1.90 15%
9.59 33%
10.66 24%
2.30 12%
0.50 10%
0.00 0%
0.00 0.00 0.00 54.81 29%
450.00 42%
102.00 8%
0.00 0%
0.00 0%
0.00 0%
0.00 0%
0.00 0.00 0.00 552.00 8%
658.00 23%
847.00 29%
0.00 0%
0.00 0%
823.00 29%
0.00 0%
396.00 20%
528.00 20%
396.00 20%
551.70
551.70
735.60
60.00
1137.20
1137.20
UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039
DOCUMENT NO:
THREE MONTH SCHEDULE OF JULY, AUG & SEPT-2023
Block - B
S.No Acitivity Block - A Block - C
B1 B2
Jul-23
Aug-23
Sep-23
POUR 6 AREA
Internal Plaster
Activity Block - A (6 flat) Block - B (FlatB1,B7) Block - C (6 Flat)
POUR 6 AREA
STP Walls up to
1 Stillt floor & Column 7/5/2023
Block work
Block - B (Club Block - C (6
Acitivity Block - A (6 flat) House) Flat)
Internal Plaster
Block - B Block - C (6
Activity Block - A (6 flat) (FlatB1,B7) Flat)
Block -A 7/6/2023
Block - B1 7/10/2023
1 11th floor slab
Block - B2 7/15/2023
Block -C 7/3/2023
Block -A 7/20/2023
Block - B1 7/24/2023
2 12th floor slab
Block - B2 7/29/2023
Block -C 7/18/2023
Block -A 8/4/2023
Block - B1 8/7/2023
3 13th floor slab
Block - B2 8/11/2023
Block -C 8/1/2023
Finishing Work
Block-A 7/15/2023
1 7th floor Block Work
Block-B 7/16/2023
Block-A 7/30/2023
2 8th floor Block work Block-B 7/31/2023
Block-C 7/14/2023
3 9th floor Block work Block-C 7/29/2023
Block-A 7/10/2023
4 4th floor Internal Plaster
Block-B 7/16/2023
Block-A 7/25/2023
5 5th floor Internal Plaster Block-B 7/31/2023
Block-C 7/10/2023
6 6th floor Internal Plaster Block-C 7/25/2023
TOTAL QTY
CTION PVT.LTD
LE HYDERABAD-500039
JULY"2023
Target Grade of Concrete Steel
Achived Date concrete Qty(CUM) Qty(MT)
M30 401.00
40.76
M35 115.00
M10 20.00
M25 10.00 6.97
M30 80.00
Sqm 2413.62
Sqm 3534.95
Sqm 1121.33
Sqm 5793.89
Sqm 8624.54
Sqm 2830.65
M30 1534
192.082
M35 115
UNIQUE INDIA CONSTRUCTION PVT.LTD
OUR HOMES REALTORS LTD
Remarks
11,784
393
154
239
UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:OUR HOMES VASAVI METROPOLIS NAGOLE HYDERABAD-500039
Doc. No. Rev :
MICRO SCHEDULE (UP TO JULY 31) DATE:28-06-2023
SR.NO DESCRIPTION Block GRID DURATION START DATE FINISH DATE REMARK
(BLock - A)
1 10th to 11th floor column R-AD/3-16
2 Column marking & starter concrete A R-AD/3-16 5 6/24/2023 6/29/2023
3 Column Reinforcement A R-AD/3-16 4 6/25/2023 6/29/2023
4 Column Shuttering &concreting A R-AD/3-16 5 6/26/2023 7/1/2023
5 Core wall A R-AD/3-16 1 6/29/2023 6/30/2023
6 Staire case A R-AD/3-16 1 7/2/2023 7/3/2023
7 Slab shuttering A R-AD/3-16 7 6/27/2023 7/4/2023
8 Slab Reinforcemet A R-AD/3-16 7 6/29/2023 7/6/2023
9 MEP & Slab Checking A R-AD/3-16 0 7/6/2023 7/6/2023
10 Slab Casting A R-AD/3-16 0 7/6/2023 7/6/2023 11th Block - A
11 11th to 12th floor column R-AD/3-16
12 Column marking & starter concrete A R-AD/3-16 5 7/7/2023 7/12/2023
13 Column Reinforcement A R-AD/3-16 4 7/8/2023 7/12/2023
14 Column Shuttering &concreting A R-AD/3-16 5 7/9/2023 7/14/2023
15 Core wall A R-AD/3-16 1 7/12/2023 7/13/2023
16 Staire case A R-AD/3-16 1 7/15/2023 7/16/2023
17 Slab shuttering A R-AD/3-16 7 7/10/2023 7/17/2023
18 Slab Reinforcemet A R-AD/3-16 7 7/12/2023 7/19/2023
19 MEP & Slab Checking A R-AD/3-16 1 7/19/2023 7/20/2023
20 Slab Casting A R-AD/3-16 0 7/20/2023 7/20/2023 12th Block - A
8th Floor (Block - B1)
1 Column marking & starter concrete B1 N-AD/16-21 5 6/27/2023 7/2/2023
2 Column Reinforcement B1 N-AD/16-21 4 6/28/2023 7/2/2023
3 Column Shuttering &concreting B1 N-AD/16-21 5 6/29/2023 7/4/2023
4 Core wall B1 N-AD/16-21 1 7/2/2023 7/3/2023
5 Staire case B1 N-AD/16-21 1 7/5/2023 7/6/2023
6 Slab shuttering B1 N-AD/16-21 7 6/30/2023 7/7/2023
7 Slab Reinforcemet B1 N-AD/16-21 7 7/2/2023 7/9/2023
8 MEP & Slab Checking B1 N-AD/16-21 1 7/9/2023 7/10/2023
9 Slab Casting B1 N-AD/16-21 0 7/10/2023 7/10/2023 11th floor B1
11th Floor to 12th Floor column (pour - B1)
1 Column marking & starter concrete B1 N-AD/16-21 5 7/11/2023 7/16/2023
2 Column Reinforcement B1 N-AD/16-21 4 7/12/2023 7/16/2023
3 Column Shuttering &concreting B1 N-AD/16-21 5 7/13/2023 7/18/2023
4 Core wall B1 N-AD/16-21 1 7/16/2023 7/17/2023
5 Staire case B1 N-AD/16-21 1 7/19/2023 7/20/2023
6 Slab shuttering B1 N-AD/16-21 7 7/14/2023 7/21/2023
7 Slab Reinforcemet B1 N-AD/16-21 7 7/16/2023 7/23/2023
8 MEP & Slab Checking B1 N-AD/16-21 1 7/23/2023 7/24/2023
9 Slab Casting B1 N-AD/16-21 0 7/24/2023 7/24/2023 12th floor B1
8th Floor (Pour - B2)
10 Column marking & starter concrete B2 B-M/16-21 5 7/2/2023 7/7/2023
11 Column Reinforcement B2 B-M/16-21 4 7/3/2023 7/7/2023
12 Column Shuttering &concreting B2 B-M/16-21 5 7/4/2023 7/9/2023
13 Core wall B2 B-M/16-21 1 7/7/2023 7/8/2023
14 Staire case B2 B-M/16-21 1 7/10/2023 7/11/2023
15 Slab shuttering B2 B-M/16-21 7 7/5/2023 7/12/2023
16 Slab Reinforcemet B2 B-M/16-21 7 7/7/2023 7/14/2023
17 MEP & Slab Checking B2 B-M/16-21 1 7/14/2023 7/15/2023
18 Slab Casting B2 B-M/16-21 0 7/15/2023 7/15/2023 11th floor B2
6th Floor to 7th Floor column (pour - B2)
1 Column marking & starter concrete B2 B-M/16-21 5 7/16/2023 7/21/2023
2 Column Reinforcement B2 B-M/16-21 4 7/17/2023 7/21/2023
3 Column Shuttering &concreting B2 B-M/16-21 5 7/18/2023 7/23/2023
4 Core wall B2 B-M/16-21 1 7/21/2023 7/22/2023
5 Staire case B2 B-M/16-21 1 7/24/2023 7/25/2023
6 Slab shuttering B2 B-M/16-21 7 7/19/2023 7/26/2023
7 Slab Reinforcemet B2 B-M/16-21 7 7/21/2023 7/28/2023
8 MEP & Slab Checking B2 B-M/16-21 0 7/28/2023 7/28/2023
9 Slab Casting B2 B-M/16-21 0 7/28/2023 7/28/2023 12th floor B2
10th Floor (Pour - C)
1 11th to 12th column
2 Column marking & starter concrete C B-AD/16-21 5 7/4/2023 7/9/2023
3 Column Reinforcement C B-AD/16-21 4 7/5/2023 7/9/2023
4 Column Shuttering &concreting C B-AD/16-21 5 7/6/2023 7/11/2023
5 Core wall C B-AD/16-21 1 7/9/2023 7/10/2023
6 Staire case C B-AD/16-21 1 7/12/2023 7/13/2023
7 Slab shuttering C B-AD/16-21 7 7/7/2023 7/14/2023
8 Slab Reinforcemet C B-AD/16-21 7 7/9/2023 7/16/2023
9 MEP & Slab Checking C B-AD/16-21 1 7/16/2023 7/17/2023
10 Slab Casting C B-AD/16-21 1 7/17/2023 7/18/2023 12th floor slab C
1 12th to 13th column
2 Column marking & starter concrete C B-AD/16-21 5 7/19/2023 7/24/2023
3 Column Reinforcement C B-AD/16-21 4 7/20/2023 7/24/2023
4 Column Shuttering &concreting C B-AD/16-21 5 7/21/2023 7/26/2023
5 Core wall C B-AD/16-21 1 7/24/2023 7/25/2023
6 Staire case C B-AD/16-21 1 7/27/2023 7/28/2023
7 Slab shuttering C B-AD/16-21 7 7/22/2023 7/29/2023
8 Slab Reinforcemet C B-AD/16-21 7 7/24/2023 7/31/2023
9 MEP & Slab Checking C B-AD/16-21 1 7/31/2023 8/1/2023
10 Slab Casting C B-AD/16-21 0 8/1/2023 8/1/2023 13th floor slab C
D STP AREA
A Stilt floor Slab shuttering
2 Stilt floor Slab shuttering P - 05 J-N/4-13 10 7/1/2023 7/11/2023
3 Slab Reinforcemet P - 05 J-N/4-13 8 7/7/2023 7/15/2023
4 MEP & Slab Checking P - 05 J-N/4-13 1 7/15/2023 7/16/2023
5 Slab Casting C B-AD/16-21 5 7/15/2023 7/20/2023 Stilt slab
UNIQUE INDIA CONSTRUCTION PVT.LTD
PROJECT:VASAVI METROPOLIS NAGOLE HYDERABAD-500039
SCHEDULE FOR STRUCTURE
Block - B
S.No Acitivity Block - A Block - C
B1 B2
1 9th floor slab 6/2/2023 6/8/2023 6/10/2023 5/16/2023