Project Report For Tendeseka (Old Mutua) Project

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

OLD MUTUAL: TENDESEKA REINSTATEMENT WORKS REPORT FROM 07/11/2022 TO

09/12/22

TO: Business Development Executive

FROM: Quantity Surveyor

DATE: 21 Dec. 22

RE: ASSESSMENT REPORT FOR OLD MUTUAL: TENDESEKA REINSTATEMENT


WORKS
Following is the request by the Business Development Executive (L. Chizikani), BSCC Mixers for an
assessment on renovations of tendeseka office park block 4 1st floor, the QS was on site from 08
November 2022 to 09 December 2022 and made the following observations; -

1. DESCRIPTION OF WORKS
 Remove supply and fix of ceiling tiles.
 Painting of internal walls.
 Demolition of partitioning walls.
 Construction of partitioning wall.
 Installation of new obscure window(glazing)
 Trunking for electrical cables
 Installation of 20x4x4ft LED lights
 Opening of “safe door” and key cutting.
 Tilling of kitchen and entrance area.
 Carpet cleaning (deep).
 Installation of geyser element and thermostat.
 Inspection of toilets to flush properly.
 Removing rubbles from the site
 Cleaning, sweeping after work done.

2. OBSERVATIONS
 Our work impressed the client.
 Whenever doing works always use skilled and qualified labour to maintain high level and
standards for the company.

3. PROBLEMS/CHALLENGES ENCOUNTED
 Working hours(0800hrs-1600hrs) was not enough
 Transport to come at work caused delays to start work
 Workers was complaining about bus fare allowance which forced them to wait for the
cheap transport.
 Electrician failed to complete the work as per our initial agreement because of materials
delay.
 Ceiling collapsed two (2) times because of shortage of hangers inside ceiling.
 Materials came in phases that caused delay on our working target.

4. RECOMMENDATIONS
 It’s better to take time buying all the required materials than mobilise early without
enough material.
 Client must be well notified to excuse the works in progress so that he will not interfere
with the work.
 Always have our internal inspection before client inspection to avoid failure.

Page 1 of 2
 We should try to minimise our costs, if possible to re-use the materials on site but only if
there are good enough to satisfy client.
 Qs Or project manager to implement as per instructions and where changes are done, Qs
to advice BDE.
 Safety talk to be done on daily basis before works have start.

5. CONCLUSION
 For future projects, we need to always mobilise all things considered to be necessary for
the project to show the level of being organised as a company as well as to maintain our
profit.
 Quantity surveyor or Project manager should always pay a visit to site with his skilled
labour just after the order has been issued and before mobilisation to allow the room of
buying necessary material, and it helps proper planning of the work.
 Agreed price with labour, transport and lunch should be approved by the BDE as per our
processes and procedure.

Compiled by:
......................... Date: 21/12/2022
T.CHIKANDIGWA
Quantity Surveyor

......................... Date. . . . . . . . . . . . . . . . . . .
L. CHIZIKANI
Business Development Executive

bsccmixers@gmail.com

Page 2 of 2

You might also like