PROGRESS MINGGUAN KONTRAKTOR

PT. KIDECO JAYA AGUNG


PROYEK : RELOCATION GENERATOR FORM MCCP TO SMCP No. Laporan : 02/CMC/I/2022
KONTRAKTOR : PT. CITRA MULIA CEMERLANG Tanggal : 6/13/2022
NO. KONTRAK : 112/KJA/SCM&AM/CON/V/2022
PERIODE : 30 MEI - 30 NOVEMBER 2022 (185 HARI)
LOKASI : MINE SITE MCCP TO SMCP - BATU KAJANG - PASER - KALTIM No. Document : SOP/MF-HSE/FM-026
g PREVIOUS PROGRESS 0.87%
g THIS PROGRESS 0.87%
g CUMMULATIVE PROGRESS 1.74%
g PLAN PROGRESS 0.71%
WEIGHT Prev (%) This (%) Com (%)
No. DESCRIPTION UNIT QTY
(%) Weight Prog. Weight Prog. Weight Prog.
I PREPARATION AND GENERAL WORK
1 Temporary Offife and Facilities
1.1 Site office and warehouse temporary Ls 1 3.60 0.13 0.13 0.13 0.13 0.27 0.27
1.2 Accomodation & Staff Catering Ls 1 3.20 0.12 0.12 0.12 0.12 0.24 0.24
2 Safety device
2.1 Personal safety include Insurance (BPJS) Ls 1 2.52 0.09 0.09 0.09 0.09 0.19 0.19
2.2 Safety sign equipment & Certificates Ls 1 1.44 0.05 0.05 0.05 0.05 0.11 0.11
2.3 Covid Cost Ls 1 0.36 0.01 0.01 0.01 0.01 0.03 0.03
3 General for Mob And Demob
3.1 Manpower mob and demob Ls 1 1.44 0.05 0.05 0.05 0.05 0.11 0.11
3.2 General mob and demob Ls 1 6.16 0.23 0.23 0.23 0.23 0.46 0.46
Sub Total I 18.73 0.69 0.69 0.69 0.69 1.39 1.39
II EQUIPMENT AND TOOLS
1 Truck Crane 10 Ton Ls 1 3.60 - - - - - -
2 Support Tools Ls 1 5.04 - 0.13 - 0.13 - 0.25
Sub Total II 8.65 - 0.13 - 0.13 - 0.25
III DESIGN AND ENGINERING
1 Review and revisi drawing + As Build draw Ls 1 0.54 0.02 0.02 0.02 0.02 0.04 0.04
2 Upgrade PLC System (software and hardware) Ls 1 11.21 - - - - - -
Sub Total III 11.75 0.02 0.02 0.02 0.02 0.04 0.04
IV DISMANTLING GENSET MCCP
1 Generator set no 3
3.1 Engine 5L28/32H / SANGYONG -MAN Unit 1 0.79 - - - - - -
3.2 Auxiliary Ls 1 0.09 - - - - - -
2 Generator set no 4
4.1 Engine 5L28/32H / SANGYONG -MAN Unit 1 0.79 - - - - - -
4.2 Auxiliary Ls 1 0.09 - - - - - -
3 Generator set no 6
6.1 Engine 6L28/32H / STX -MAN Unit 1 0.92 - - - - - -
6.2 Auxiliary Ls 1 0.10 - - - - - -
4 Common Equipment
7.4 Air Compressor (Motor & Air Receiver) Ls 1 0.01 - - - - - -
5 Electrical Equipment
8.1 Engine Control Panel PNL 2 0.03 - - - - - -
8.3 Generator Incoming Breaker Panel PNL 2 0.03 - - - - - -
8.4 NGR Panel PNL 1 0.01 - - - - - -
6 Dismantling Electrical Bulk Material (Cable, Cable Tray, Conduit, Etc)
9.1 Dismantling Cable, Connection and Accessories Lot 1 0.10 - - - - - -
9.2 Dismantling Cable Tray and Accessories Lot 1 0.12 - - - - - -
9.3 Dismantling Conduit & Accessories Lot 1 0.08 - - - - - -
Sub Total IV 3.16 - - - - - -
V CONTRUCTION WORK
1 Civil Work
1.1 Earth Work Ls 1 0.05 - - - - - -
1.2 Concrete Work
- Foundation Engine 1200 KW (Eng 05) Ls 1 0.95 - - - - - -
- Foundation Engine 1000KW (Eng 06) Ls 1 0.87 - - - - - -
- Foundation Generator (Existing SMCP) Ls 1 2.17 - - - - - -
- Foundation Jacket Water Ls 1 0.05 - - - - - -
- Foundation Oil Bath LP-40 Ls 1 0.04 - - - - - -
- Foundation Oil Bath LP-50 Ls 1 0.05 - - - - - -
- Foundation CW Pump Ls 1 0.11 - - - - - -
- Foundation Air Compressor Ls 1 0.03 - - - - - -
- Foundation Air Receiver Ls 1 0.04 - - - - - -
- Foundation Tower Jacket Expansion Tank Ls 1 0.04 - - - - - -
- Foundation Tower Silencer Ls 1 0.45 - 0.03 - 0.03 - 0.06
- Foundation Tower Maintenance Silencer Ls 1 0.19 - - - - - -
- Cooling Tower Pond Ls 1 4.93 - - - - - -
Sub Total V 9.96 - 0.03 - 0.03 - 0.06
2 Mech Part - Piping Work
2.1 Pipe exhaust gas Ls 1 6.82 - - - - - -
2.2 Pipe intake air inlet engine no.5 Ls 1 0.74 - - - - - -
2.3 Pipe intake air inlet engine no.6 & no.7 Ls 1 0.57 - - - - - -
2.4 Pipe J.W cooler Ls 1 1.65 - - - - - -
2.5 Pipe C.W pump Ls 1 2.56 - - - - - -
2.6 Pipe fuel Ls 1 0.46 - - - - - -
2.7 Pipe starting air tank Ls 1 0.25 - - - - - -
2.8 Pipe support Ls 1 0.91 - - - - - -
2.9 Tower maintenance silencer Ls 1 1.28 - - - - - -
2.10 Support silencer Ls 1 0.78 - - - - - -
2.11 Support jacket expantion tank Ls 1 0.23 - - - - - -
2.12 Pipe oil vapuor discharge Ls 1 0.15 - - - - - -
2.13 Pipe venting to expan. Tank Ls 1 0.63 - - - - - -
Sub Total VI 17.02 - - - - - -
3 Mech Part- Equipment Installation
3.1 Genset, unloading & grouting Unit 2 0.72 - - - - - -
3.1a Unloading Genset at genset room KM 35 Unit 1 0.22 - - - - - -
3.2 Oil bath air fillter Unit 2 0.04 - - - - - -
3.3 Jacket water cooler Unit 2 0.07 - - - - - -
3.4 Cooling water pump Unit 4 2.21 - - - - - -
3.5 Exhaust Gas Silencer Unit 2 1.11 - - - - - -
3.6 Air Compressors (Motor) Unit 1 0.04 - - - - - -
3.7 Compressed Air Tank Unit 1 0.04 - - - - - -
3.8 Cooling Tower, XT-150 Unit 2 9.03 - - - - - -
3.9 Lubrication oil cooler Eng 5 Unit 1 0.04 - - - - - -
3.9 Lubrication oil cooler Eng 6 Unit 1 0.10 - - - - - -
3.10 Deaerating tank Unit 2 0.27 - - - - - -
3.10 Jacket Expansion Tank Unit 1 0.19 - - - - - -
Sub Total VII 14.07 - - - - - -
4 Electrical Work
4.1 Cable And Connection (With Accessories)
- 6/10KV FCV 1C 185SQ Ls 1 3.17 - - - - - -
- 6/10KV FCV 3C 35SQ Ls 1 0.98 - - - - - -
- 0.6/1KV FCV 1C 185SQ Ls 1 2.31 - - - - - -
- 0.6/1KV FCV 2C 4SQ Ls 1 0.08 - - - - - -
- 0.6/1KV FCV 3C 2.5SQ Ls 1 0.16 - - - - - -
- 0.6/1KV FCV 3C 4SQ Ls 1 0.30 - - - - - -
- 0.6/1KV FCV 3C 6SQ Ls 1 0.14 - - - - - -
- 0.6/1KV FCV 3C 10SQ Ls 1 0.37 - - - - - -
- 0.6/1KV FCV 4C 4SQ Ls 1 0.27 - - - - - -
- 0.6/1KV FCVV 3C 2.5SQ Ls 1 0.12 - - - - - -
- 0.6/1KV FCVV 4C 2.5SQ Ls 1 0.17 - - - - - -
- 0.6/1KV FCVV 8C 2.5SQ Ls 1 0.16 - - - - - -
- 0.6/1KV FCVV 20C 2.5SQ Ls 1 0.10 - - - - - -
- 0.6/1KV FCVVS 12C 2.5SQ Ls 1 0.20 - - - - - -
- 0.6/1KV FCVVS 20C 2.5SQ Ls 1 0.43 - - - - - -
- 0.6/1KV FCVVS 30C 2.5SQ Ls 1 0.48 - - - - - -
- 0.6/1KV CABLE FGV 95SQ Ls 1 0.28 - - - - - -
- 0.6/1KV CABLE FGV 6 SQ Ls 1 1.03 - - - - - -
- 0.6/1KV CABLE FGV 2.5 SQ Ls 1 0.15 - - - - - -
Sub Total VIII 10.90 - - - - - -
4.2 Cable Tray And Conduit
- Cable tray engine side 200W x 100H x 3000L Ls 1 0.30 - - - - - -
- Cable tray engine side 300W x 100H x 3000L Ls 1 0.23 - - - - - -
- Cable Tray to Cooling Tower 300W x 100H x 3000L Ls 1 0.32 - - - - - -
- Support Tray Engine Side Ls 1 0.13 - - - - - -
- Support tray to Cooling Tower Ls 1 0.40 - - - - - -
- Conduit And Accessories Ls 1 0.33 - - - - - -
Sub Total IX 1.72 - - - - - -
4.3 Install Control Panel, Etc
- Engine Control Panel PNL 2 0.03 - - - - - -
- Generator Incoming Breaker Panel PNL 2 0.03 - - - - - -
- NGR Panel PNL 1 0.01 - - - - - -
- MCC Panel (600W x 600D x 2350H) PNL 2 0.46 - - - - - -
- Base frame panel & Auxiliary Trafo Kg 450 0.10 - - - - - -
- Change position terminal box generator Ea 2 0.03 - - - - - -
- Marking tube MS4020 WHITE – 4.0MM @200mtr Rol 1 0.02 - - - - - -
- Marking tube MS4520 WHITE – 4,5MM @200mtr Roll 1 0.02 - - - - - -
- Flat Cable Marker LS 1 0.02 - - - - - -
- Relocation Auxiliary Transformer PNL 2 0.03 - - - - - -
Sub Total X 0.74 - - - - - -
5 Painting Work
5.1 Steel Paint (International) Ls 1 0.59 - - - - - -
5.2 Concrete Paint (Jotun) Ls 1 0.06 - - - - - -
5.3 Waterproofing (No Drop) Ls 1 0.13 - - - - - -
Sub Total XI 0.78 - - - - - -
VI TEST & COMMISSIONING
1 Safety and Protection Test Ls 1 0.72 - - - - - -
2 Synchronization test Ls 1 0.36 - - - - - -
3 NDT 100 titik and Hydrotest Ls 1 1.44 - - - - - -
Sub Total XII 2.52 - - - - - -
TOTAL ( I + II + III + IV + V + VI + VII + VIII + IX + X + XI + XII ) 100.00 0.71 0.87 0.71 0.87 1.43 1.74
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
6/13/2022 6/13/2022 6/13/2022 6/13/2022 6/13/2022

Ade Dimas Johan A. I. Jefrianto S. A. Robby S. Herman H. Iman P.


Drafter Project Manager Engineer Ast. Manager Ast. Manager T. Manager
FOTO DOKUMENTASI
PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-025
PROYEK : RELOCATION GENERATOR FROM MCCP TO SMCP

KONTRAKTOR : PT. CITRA MULIA CEMERLANG

NO. KONTRAK : 112/KJA/SCM&AM/CON/V/2022

PERIODE : 30 MEI - 30 NOVEMBER 2022 (185 HARI)

LOKASI : MINE SITE MCCP TO SMCP - BATU KAJANG - PASER - KALTIM K


SENIN Tanggal : 06/06/2022 a
n
No. Foto Dokumentasi t Lokasi Keterangan
o
r

C
M
C
1
B
a
l
i
k
a
Pemotongan plat baja p
p
a
n

SELASA Tanggal : 07/06/2022

1
2

RABU Tanggal : 08/06/2022


No. Foto Dokumentasi Lokasi Keterangan

K
a
n
t
o
1 r

S
M
C
P

Meeting schedule proyek Review shopdrawing

KAMIS Tanggal : 09/06/2022

K
a
n
t
o
1 r

S
M
C
P

Meeting finalisasi schedule proyek Meeting finalisasi schedule proyek


2

JUMAT Tanggal : 10/06/2022


No. Foto Dokumentasi Lokasi Keterangan

SABTU Tanggal : 11/06/2022


W
o
r
k
s
h
1
o
p

B
p
n
2

MINGGU Tanggal : 12/06/2022


No. Foto Dokumentasi Lokasi Keterangan

PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG


Dibuat, Diperiksa, Diketahui, Disetujui,
6/13/2022 6/13/2022 6/13/2022 6/13/2022

Ade Dimas Johan A. I A. Robby S. Herman H. Iman P.


Drafter Project Manager Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN KONTRAKTOR
PT. KIDECO JAYA AGUNG No. Dokumen : SOP/MF-HSE/FM-027
PROYEK : RELOCATION GENERATOR FROM MCCP TO SMCP No. Laporan : 14/CMC/I/2022
KONTRAKTOR : PT. CITRA MULIA CEMERLANG Hari -Tanggal : Minggu -12/06/2022
NO. KONTRAK : 112/KJA/SCM&AM/CON/V/2022 Cuaca :
PERIODE : 30 MEI - 30 NOVEMBER 2022 (185 HARI) 07.00 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00

LOKASI : MINE SITE MCCP TO SMCP - BATU KAJANG - PASER - KALTIM 19.00 20.00 21.00 22.00 23.00 24.00 01.00 02.00 03.00 04.00 05.00 06.00

Waktu bekerja : 8 jam Total waktu sebelumnya : 104 Jam


Waktu bekerja (hari ini) : 8 jam Total waktu hingga hari ini : 112 Jam
PEKERJAAN PEKERJA
No Dekripsi Pekerjaan No Deskripsi Pekerja Unit Qty Prev
1 Penghitungan material elektrikal yang akan di order ke balikpapan 1 Project Manager orang 1
2 Mencari brosur material yang akan digunakan 2 Safety orang 1
3 Menunggu terbit RMK 3 Supervisor orang 0
4 Persiapan mobilisasi pekerja dan akomodasinya 4 Engineer orang 1
5 Drafter orang 0
6 Pekerja Baja orang 0
7 Pekerja Sipil orang 0
8 Driver orang 0
TOTAL orang 3
1 2
F
O
T
O

D
O
K
U
M
E
N
T
A
S
I

PENGUNAAN MATERIAL PENGGUNAAN PERALATAN


No Deskripsi Material Unit Qty Prev Cum No Deskripsi Alat-alat Unit Qty Prev
1 1
2 2
3 3
4 4
5 5
6 6
Rencana Pekerjaan besok
Membuat gambar denah direksi keet di area lokasi pekerjaan

Catatan:

NB : Cerah
Hujan
Kendala Lain
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
6/12/2022 6/12/2022 6/12/2022 6/12/2022 6/12/2022

Ade Dimas Johan A. I. Jefrianto S. A. Robby S. Herman H. Iman P.


Drafter Project Manager Engineer Ast. Manager Ast. Manager T. Manager
WEEKLY REPORT
PROJECT :

Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM


PT.KIDECO JAYA AGUNG

LOCATION :
Workshop HE TMCT - Tanah Merah - PASER - KALTIM
SAFETY REPORT

SUMMARY
NO REPORT : 01/CMC-KJA/SAFETY/VII/2023
WEEK : 1 st
WORKING DATE : 09 - 15 Juli 2023

CONTRACTOR :

PT. CITRA MULIA CEMERLANG


LAPORAN MINGGUAN HSE KONTRAKTOR
PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-029 SAFETY FIRST

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM

KONTRAKTOR : PT. CITRA MULIA CEMERLANG

NO. KONTRAK : 0

PERIODE : 09 - 15 Juli 2023

LOKASI : Workshop HE TMCT

JUMLAH JAM KERJA

Staff : 5 0rang Staff : 8 Jam

Worker : 10 0rang Worker : 8 Jam

PEKERJA Sub.cont : 0 0rang Sub.cont : 0 Jam

Total : 15 0rang Total : 56 Jam

TOTAL JAM KERJA Minggu Ini 56 TOTAL PEKERJA Minggu Ini 15

Pertolongan Rawat Rawat Meninggal


Hampir Kebakaran Keterangan
Pertama Jalan Inap Dunia
KECELAKAAN
- - - - - - -

Jumlah HSE Talk Minggu Ini :0


HSE TALK
Kehadiran HSE Talk :0

Jml Inspeksi / Minggu Jml Temuan / Minggu Jml Temuan Diselesaikan / Minggu
INSPEKSI HSE
0 0 0

PEKERJAAN TINDAKAN PENCEGAHAN

1. Melakukan Safety Talk / briefing pagi sebelum melakukan


1. Marking plat untuk dudukan purlin pekerjaan

2. Melakukan inspeksi area kerja dan inspeksi alat kerja


RENCANA PEKERJAAN 2. Pelubangan dan pemasangan stiffiner kuda kuda WF
MINGGU DEPAN
3. Cek kondisi kesehatan pekerja harus Fit & sehat
4. Pemotongan Plat untuk dudukan purlin WF

4. Mempersiapkan dan bekerja sesuai dengan prosedur & JSA


5. Pemasangan kupingan dudukan purlin kuda kuda

KEBERSIHAN / KERAPIHAN

1. Site Office Good 4. (Site area)


LINGKUNGAN
2. Site Gudang Good 5. (Site area)
3. (Site area) Good 6. (Site area)
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG

Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,


11/11/2022 11/11/2022 11/11/2022 11/11/2022 11/11/2022
Safety Officer Project Manager Spv HSE Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 01/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/9/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC
1 Workshop PT.CMC 08:00 P5M N/A N/A N/A N/A 11 Pengawas

2 Workshop PT.CMC 08:30 Marking plat untuk dudukan Hummer Tertimpa benda di workshop Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 5 Pengawas
purlin tempatnya

13:00 Fabrikasi kuda-kuda WF Bor duduk Tertimpa benda di workshop Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 4 Pengawas
tempatnya
3 Workshop PT.CMC 14:00 Pelubangan dan pemasangan Alat las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 4 Pengawas
stiffener kuda kuda WF alat las las memakai sarung tangan las

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 02/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/10/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC

1 Workshop PT.CMC 08:00 P5M N/A N/A N/A N/A 11 Pengawas

2 workshop PT.CMC 08:30 Marking plat untuk dudukan Hummer Tertimpa benda di workshop Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 4 Pengawas
purlin WF tempatnya

Penutupan tiang kuda kuda Alat las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 4 Pengawas
bagian atas alat las las memakai sarung tangan las

13:00 Pemasangan stiffiner kuda kuda Alat las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 5 Pengawas
alat las las memakai sarung tangan las

3 Mess Tanah Merah 14:00 IKABAR Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 3 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 03/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/11/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC

1 Workshop PT.CMC 08:00 P5M N/A N/A N/A N/A : 11 Pengawas

2 Workshop PT.CMC 08:30 Pemasangan stiffiner kuda kuda Alat las Terkena percikan api akibat Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 6 Pengawas
WF alat las tempatnya
2, Selalu menggunakan helm las dan sarung
tangan las
13:00 Pemotongan Plat untuk dudukan Gerinda laser Terkena percikan api akibat Tidak menggunakan APD 1. Memastikan penempatan barang sesuai 6 Pengawas
purlin WF gerinda laser menggunakan kaca mata dan sarung tangan
2. memasang penutup perapian gerinda

3 Mess Tanah Merah 16:00 Pengajuan ke Nembayu Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 10 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 04/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/12/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC
1 Workshop PT.CMC 08:00 P5M N/A N/A N/A N/A : 10 Pengawas

2 Workshop PT.CMC 08:00 Pelubangan untuk baut kuda kuda Mesin bor duduk Tertimpa benda di workshop Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 6 Pengawas
dan plat tempatnya

13:00 Pemotongan Plat setelah dimarking Mesin gerinda Terkena percikan api akibat Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 6 Pengawas
gerinda menggunakan kaca mata dan sarung tangan
2. memasang penutup perapian gerinda

3 Site TMCT 14:00 Virtual meeting kordinasi Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 4 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

4 Mess Tanah Merah 14:00 IKABAR Laptop Radiasi Layar Laptopv Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 4 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 05/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/13/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC

1 Workshop PT.CMC 08:00 P5M N/A N/A N/A N/A : 11 Pengawas

2 Workshop PT.CMC 08:30 Pengelasan Tiang sama Alat las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 6 Pengawas
dudukan overhead crane alat las las memakai sarung tangan las

13:00 Pemotongan plat buat dudukan Mesin gerinda Terkena percikan api akiba Tidak menggunakan APD 1. Memastikan penempatan barang sesuai pada 6 Pengawas
purlin mesin gerinda menggunakan kaca mata dan sarung tangan
2. memasang penutup perapian gerinda

3 Site Batu Kajang 08:00 Upacara Hari Lingkungan Hidup N/A Cuaca kurang kondusif N/A N/A 2 HSE

4 Mess Tanah Merah 14:00 Pembuatan Permit Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 1 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 06/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/14/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC

1 Workshop PT.CMC 8:00 P5M N/A N/A N/A N/A : 11 Pengurus

2 Workshop PT.CMC 08:30 Pengelasan stifner tiang kuda - Alat .las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 6 Pengawas
kuda dan dudukan overhead alat las las memakai sarung tangan las
crane

13:00 Pengelasan stifner tiang kuda - Alat .las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 6 Pengawas
kuda dan dudukan overhead alat las las memakai sarung tangan las
crane

3 Site TMCT 15:30 Tinjau lokasi untuk pengukuran Meteran Tertimpa benda di area site Tidak menggunakan APD 1. Memakai alat pelindung diri dan menggunakan 2 HSE
ulang fabrikasi kontraktor lama Debu tambang masker

4 Mess Tanah Merah 14:00 IKABAR Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 6 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

5 Mess Tanah Merah 16:00 Pengajuan ke Nembayu Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 2 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
LAPORAN HARIAN HSE KONTRAKTOR

PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-028 PT. CITRA MULIA CEMERLANG

PROYEK : Renovasi Workshop HE TMCT - Tanah Merah - PASER - KALTIM NO. LAPORAN : 07/CMC-KJA/HSE/VII/2023
KONTRAKTOR : PT. CITRA MULIA CEMERLANG TANGGAL : 7/15/2023
NO. KONTRAK : CUACA :
PERIODE : 09 - 15 Juli 2023 STAFF 5 orang
JML. PEKERJA
LOKASI : Workshop HE TMCT NON STAFF 10 orang

PERALATAN YANG KONDISI TINDAKAN PEKERJA


NO LOKASI JAM JENIS PEKERJAAN LANGKAH PERBAIKAN
DIGUNAKAN TIDAK AMAN TIDAK AMAN Jml.org PIC

1 Workshop PT.TMCT 08:00 P5M N/A N/A N/A N/A : 11 Pengawas

2 Workshop PT.TMCT 08:30 Pemasangan kupingan dudukan Alat las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 6 Pengawas
purlin kuda kuda alat las las memakai sarung tangan las

13:00 Pengelasan stiffiner tiang WF Alat las Terkena percikan api akibat Tidak menggunakan helm 1. Memakai helm las yang sesuai standar dan 6 Pengawas
alat las las memakai sarung tangan las

3 Mess Tanah Merah 15:00 Koordinasi pengajuan induksi Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 5 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

Koordinasi pengajuan IKABAR Laptop Radiasi Layar Laptop Cara kerja, posisi kerja 1. Melakukan penyetingan layar laptop 5 HSE
dan postur tubuh yang Ergonomi kerja
tidak sesuai

1 2 3

4 5 6

Dokumentasi
PT. CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG
Dibuat, Diperiksa, Diperiksa, Diketahui, Disetujui,
7/15/2023 7/15/2023 7/15/2023 7/15/2023 7/15/2023

Safety Officer Project Manager Spv HSE Ast. Manager Ast. Manager T. Manager
DAFTAR HADIR HARIAN
PT. KIDECO JAYA AGUNG No. Document : SOP/MF-HSE/FM-030 SAFETY FIRST
PROYEK : RELOCATION GENERATOR FROM MCCP TO SMCP
KONTRAKTOR : PT. CITRA MULIA CEMERLANG
NO. KONTRAK : 112/KJA/SCM&AM/CON/V/2022
PERIODE : WEEK 23th
LOKASI : Site Kideco Mane Facility SMCP Km 35 & MCCP Km 40
AGENDA : HSE Harian Pekerja
Tanggal :
No. NAMA JABATAN TANDA TANGAN KETERANGAN

PT CITRA MULIA CEMERLANG PT. KIDECO JAYA AGUNG


Dibuat, Diperiksa, Disetujui,

( Johan A.I ) Goifa K.R.


Safety Officer Project Manager Spv HSE