LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 1-Jun-20 s/d 7-Jun-20
Tanggal : 5-Jun-20

PROGRESS PEKERJAAN
NO DESKRIPSI Harga Satuan (IDR) Harga Total QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) Rp 9,300,000 Rp353,400,000 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work Rp 38,500,000 Rp1,463,000,000 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) Rp 27,500,000 Rp1,045,000,000 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting Rp 8,200,000 Rp311,600,000 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) Rp 16,500,000 Rp627,000,000 38 Platform 3.04% 35.53% 1.08% 0.00% 35.53% 1.081% 64.47% 1.96%
Lifting Rp 8,200,000 Rp311,600,000 38 Platform 1.51% 35.53% 0.54% 0.00% 35.53% 0.537% 64.47% 0.97%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan Rp 11,000,000 Rp418,000,000 38 Platform 2.03% 36.84% 0.75% 0.00% 36.84% 0.747% 63.16% 1.28%
Lifting Rp 8,200,000 Rp311,600,000 38 Platform 1.51% 36.84% 0.56% 0.00% 36.84% 0.557% 63.16% 0.95%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : Rp 39,600,000 Rp1,504,800,000 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation Rp 130,000 Rp370,500,000 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL
LVMDP to DB Rp 74,000 Rp82,954,000 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB Rp 48,000 Rp53,808,000 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP Rp 48,000 Rp136,800,000 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP Rp 122,000 Rp2,018,978,000 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP Rp 122,000 Rp2,060,702,000 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN Rp 74,000 Rp28,120,000 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN Rp 74,000 Rp28,120,000 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP Rp 48,000 Rp244,416,000 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP Rp 48,000 Rp277,248,000 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU Rp 48,000 Rp184,224,000 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU Rp 48,000 Rp425,904,000 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD Rp 48,000 Rp136,800,000 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI Rp 48,000 Rp136,800,000 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU Rp 48,000 Rp206,112,000 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU Rp 48,000 Rp513,456,000 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD Rp 48,000 Rp136,800,000 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI Rp 48,000 Rp136,800,000 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP Rp 5,500,000 Rp104,500,000 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Installation SCR-DCP Rp 3,850,000 Rp73,150,000 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP Rp 792,000 Rp15,048,000 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP Rp 792,000 Rp15,048,000 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) Rp 5,500,000 Rp209,000,000 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP Rp 792,000 Rp30,096,000 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme Rp 792,000 Rp541,728,000 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP Rp 2,750,000 Rp52,250,000 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP Rp 1,650,000 Rp31,350,000 19 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.032% 78.95% 0.12%
G.2 Installation and Termination PDP
Installation PDP Rp 5,500,000 Rp104,500,000 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Termination PDP Rp 792,000 Rp15,048,000 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Rp 190,000 Rp54,150,000 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Rp 190,000 Rp54,150,000 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding Rp 3,300,000 Rp125,400,000 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester Rp 16,500,000 Rp49,500,000 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester Rp 1,300,000 Rp5,200,000 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter Rp 4,620,000 Rp18,480,000 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 Rp 1,140,000 Rp4,560,000 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop Rp 19,800,000 Rp19,800,000 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer Rp 12,100,000 Rp36,300,000 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE Rp 1,345,368,421 Rp1,345,368,421 1 6.53% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 6.53%
K PROJECT MANAGEMENT Rp 4,180,231,579 Rp4,180,231,579 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL Rp20,609,400,000
TOTAL 100.00% 43.20% 0.00% 43.20% 56.80%

Menge
tahui Jakarta, 05 Juni Dibuat
2020 oleh
(Meny Menyetujui Memeriksa 22.859% KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an) 22.859%

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201%
Deviasi 0.000% 0.000%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 8-Jun-20 s/d 14-Jun-20
Tanggal : 12-Jun-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 35.53% 1.08% 0.00% 35.53% 1.081% 64.47% 1.96%
Lifting 38 Platform 1.51% 35.53% 0.54% 0.00% 35.53% 0.537% 64.47% 0.97%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 36.84% 0.75% 0.00% 36.84% 0.747% 63.16% 1.28%
Lifting 38 Platform 1.51% 36.84% 0.56% 0.00% 36.84% 0.557% 63.16% 0.95%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.032% 78.95% 0.12%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 6.53%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.20% 0.00% 43.20% 56.80%

Menge
tahui Jakarta, 08 Juni Dibuat
2020 oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201%
Deviasi 0.000% 0.000% 0.000%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 15-Jun-20 s/d 21-Jun-20
Tanggal : 19-Jun-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 35.53% 1.08% 0.00% 35.53% 1.081% 64.47% 1.96%
Lifting 38 Platform 1.51% 35.53% 0.54% 0.00% 35.53% 0.537% 64.47% 0.97%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 36.84% 0.75% 0.00% 36.84% 0.747% 63.16% 1.28%
Lifting 38 Platform 1.51% 36.84% 0.56% 0.00% 36.84% 0.557% 63.16% 0.95%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.032% 78.95% 0.12%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 6.53%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.20% 0.00% 43.20% 56.80%

Menge
tahui Jakarta, 19 Juni Dibuat
2020 oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201%
Deviasi 0.000% 0.000% 0.000% -0.119%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 22-Jun-20 s/d 28-Jun-20
Tanggal : 26-Jun-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 35.53% 1.08% 0.00% 35.53% 1.081% 64.47% 1.96%
Lifting 38 Platform 1.51% 35.53% 0.54% 0.00% 35.53% 0.537% 64.47% 0.97%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 36.84% 0.75% 0.00% 36.84% 0.747% 63.16% 1.28%
Lifting 38 Platform 1.51% 36.84% 0.56% 0.00% 36.84% 0.557% 63.16% 0.95%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.032% 78.95% 0.12%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 6.53%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.20% 0.00% 43.20% 56.80%

Menge
tahui Jakarta, 26 Juni Dibuat
2020 oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 29-Jun-20 s/d 5-Jul-20
Tanggal : 3-Jul-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 35.53% 1.08% 1.32% 0.04% 36.84% 1.121% 63.16% 1.92%
Lifting 38 Platform 1.51% 35.53% 0.54% 1.32% 0.02% 36.84% 0.557% 63.16% 0.95%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 36.84% 0.75% 5.26% 0.11% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 36.84% 0.56% 5.26% 0.08% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.032% 78.95% 0.12%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.00% 0.00% 0.50% 0.03% 0.50% 0.032% 99.50% 6.50%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.20% 0.28% 43.48% 56.52%

Menge
tahui Jakarta, 03 Juli 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 6-Jul-20 s/d 12-Jul-20
Tanggal : 10-Jul-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING 0.00%
B.1 Mobilisasi dan Lifting PSD Mechanical Structure 0.00%
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control 0.00%
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 36.84% 1.12% 0.00% 36.84% 1.121% 63.16% 1.92%
Lifting 38 Platform 1.51% 36.84% 0.56% 0.00% 36.84% 0.557% 63.16% 0.95%
B.3 Mobilisasi dan Lifting PDP 0.00%
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE 0.00%
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt ) 0.00%
- Measurement work after instaled 0.00%
- Adjustment work 0.00%
- Instalation of the Base Plate or LMB 0.00%
- Instalation work of the structure (Glass, Fix door, etc.) 0.00%
- Instalation for the drive Box 0.00%
- Instalation mortar work on the LMB/Base part. 0.00%
D INSTALATION CABLE TRAY 300 x 100 mm 0.00%
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL 0.00%
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL 0.00%
F.1 Installation in ER (Equipment Room) 0.00%
Installation MCP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform 0.00%
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL) 0.00%
G.1 Positioning and Mounting PDP 0.00%
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.032% 78.95% 0.12%
G.2 Installation and Termination PDP 0.00%
Installation PDP 19 Set 0.51% 21.05% 0.11% 0.00% 21.05% 0.107% 78.95% 0.40%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM 0.00%
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT 0.00%
I.1 Measurement Tools 0.00%
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment 0.00%
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.50% 0.03% 0.00% 0.00% 0.50% 0.032% 99.50% 6.50%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.48% 0.00% 43.48% 56.52%

Menge
tahui Jakarta, 10 Juli 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 13-Jul-20 s/d 19-Jul-20
Tanggal : 17-Jul-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 36.84% 1.12% 0.00% 36.84% 1.121% 63.16% 1.92%
Lifting 38 Platform 1.51% 36.84% 0.56% 0.00% 36.84% 0.557% 63.16% 0.95%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 0.00% 42.11% 0.757% 57.89% 1.04%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 21.05% 0.11% 10.53% 0.05% 31.58% 0.160% 68.42% 0.35%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 0.000% 27.63% 0.098% 72.37% 0.26%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 21.05% 0.03% 10.53% 0.02% 31.58% 0.048% 68.42% 0.10%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 21.05% 0.11% 10.53% 0.05% 31.58% 0.160% 68.42% 0.35%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.50% 0.03% 0.25% 0.02% 0.74% 0.048% 99.26% 6.48%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.48% 0.14% 43.62% 56.38%

Menge
tahui Jakarta, 17 Juli 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 20-Jul-20 s/d 26-Jul-20
Tanggal : 24-Jul-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 36.84% 1.12% 3.95% 0.12% 40.79% 1.241% 59.21% 1.80%
Lifting 38 Platform 1.51% 36.84% 0.56% 1.32% 0.02% 38.16% 0.577% 61.84% 0.94%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 42.11% 0.76% 2.63% 0.05% 44.74% 0.804% 55.26% 0.99%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 31.58% 0.16% 10.53% 0.05% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 27.63% 0.10% 7.89% 0.028% 35.53% 0.126% 64.47% 0.23%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 31.58% 0.05% 10.53% 0.02% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 31.58% 0.16% 10.53% 0.05% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 0.74% 0.05% 0.68% 0.04% 1.42% 0.093% 98.58% 6.44%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 43.62% 0.38% 44.00% 56.00%

Menge
tahui Jakarta, 24 Juli 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 27-Jul-20 s/d 2-Aug-20
Tanggal : 31-Jul-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 40.79% 1.24% 0.00% 40.79% 1.241% 59.21% 1.80%
Lifting 38 Platform 1.51% 38.16% 0.58% 0.00% 38.16% 0.577% 61.84% 0.94%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 44.74% 0.80% 2.63% 0.05% 47.37% 0.852% 52.63% 0.95%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 35.53% 0.13% 0.000% 35.53% 0.126% 64.47% 0.23%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 1.42% 0.09% 0.10% 0.01% 1.52% 0.099% 98.48% 6.43%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 44.00% 0.05% 44.05% 55.95%

Menge
tahui Jakarta, 31 Juli 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 3-Aug-20 s/d 9-Aug-20
Tanggal : 7-Aug-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 40.79% 1.24% 2.63% 0.08% 43.42% 1.321% 56.58% 1.72%
Lifting 38 Platform 1.51% 38.16% 0.58% 5.26% 0.08% 43.42% 0.656% 56.58% 0.86%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 47.37% 0.85% 10.53% 0.19% 57.89% 1.041% 42.11% 0.76%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 0.00% 42.11% 0.169% 57.89% 0.23%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 0.00% 42.11% 0.110% 57.89% 0.15%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 0.00% 42.11% 4.125% 57.89% 5.67%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 0.00% 42.11% 4.210% 57.89% 5.79%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 0.00% 42.11% 0.057% 57.89% 0.08%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 0.00% 42.11% 0.499% 57.89% 0.69%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 0.00% 42.11% 0.566% 57.89% 0.78%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 0.00% 42.11% 1.049% 57.89% 1.44%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 0.00% 42.11% 0.279% 57.89% 0.38%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 35.53% 0.13% 0.000% 35.53% 0.126% 64.47% 0.23%
Termination MCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 21.05% 0.02% 0.000% 21.05% 0.015% 78.95% 0.06%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 1.52% 0.10% 0.70% 0.05% 2.22% 0.145% 97.78% 6.38%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 44.05% 0.39% 44.45% 55.55%

Menge
tahui Jakarta, 07 Agustus 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 10-Aug-20 s/d 16-Aug-20
Tanggal : 14-Aug-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 43.42% 1.32% 5.26% 0.16% 48.68% 1.481% 51.32% 1.56%
Lifting 38 Platform 1.51% 43.42% 0.66% 2.63% 0.04% 46.05% 0.696% 53.95% 0.82%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 57.89% 1.04% 5.26% 0.09% 63.16% 1.135% 36.84% 0.66%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 42.11% 0.17% 5.26% 0.02% 47.37% 0.191% 52.63% 0.21%
UPS to DB 1121 Meter 0.26% 42.11% 0.11% 5.26% 0.01% 47.37% 0.124% 52.63% 0.14%
MCP to SCR DCP 2850 Meter 0.66% 42.11% 0.28% 5.26% 0.03% 47.37% 0.314% 52.63% 0.35%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 42.11% 4.12% 5.26% 0.52% 47.37% 4.640% 52.63% 5.16%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 42.11% 4.21% 5.26% 0.53% 47.37% 4.736% 52.63% 5.26%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 5.26% 0.01% 47.37% 0.065% 52.63% 0.07%
MCP to CBN 380 Meter 0.14% 42.11% 0.06% 5.26% 0.01% 47.37% 0.065% 52.63% 0.07%
MCP to DCP 5092 Meter 1.19% 42.11% 0.50% 5.26% 0.06% 47.37% 0.562% 52.63% 0.62%
MCP to DCP 5776 Meter 1.35% 42.11% 0.57% 5.26% 0.07% 47.37% 0.637% 52.63% 0.71%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 5.26% 0.03% 47.37% 0.314% 52.63% 0.35%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 5.26% 0.03% 47.37% 0.314% 52.63% 0.35%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 42.11% 1.05% 5.26% 0.13% 47.37% 1.180% 52.63% 1.31%
MCP to EWD 2850 Meter 0.66% 42.11% 0.28% 5.26% 0.03% 47.37% 0.314% 52.63% 0.35%
EWD to SLI 2850 Meter 0.66% 42.11% 0.28% 5.26% 0.03% 47.37% 0.314% 52.63% 0.35%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 35.53% 0.13% 7.89% 0.028% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 21.05% 0.02% 21.05% 0.015% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 21.05% 0.02% 21.05% 0.015% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 21.05% 0.02% 21.05% 0.015% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 2.22% 0.14% 3.82% 0.25% 6.04% 0.394% 93.96% 6.13%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 44.45% 2.15% 46.60% 53.40%

Menge
tahui Jakarta, 14 Agustus 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 17-Aug-20 s/d 23-Aug-20
Tanggal : 21-Aug-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 48.68% 1.48% 1.32% 0.04% 50.00% 1.521% 50.00% 1.52%
Lifting 38 Platform 1.51% 46.05% 0.70% 3.95% 0.06% 50.00% 0.756% 50.00% 0.76%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 63.16% 1.14% 5.26% 0.09% 68.42% 1.230% 31.58% 0.57%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 47.37% 0.19% 5.26% 0.02% 52.63% 0.212% 47.37% 0.19%
UPS to DB 1121 Meter 0.26% 47.37% 0.12% 5.26% 0.01% 52.63% 0.137% 47.37% 0.12%
MCP to SCR DCP 2850 Meter 0.66% 47.37% 0.31% 5.26% 0.03% 52.63% 0.349% 47.37% 0.31%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 47.37% 4.64% 5.26% 0.52% 52.63% 5.156% 47.37% 4.64%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 47.37% 4.74% 5.26% 0.53% 52.63% 5.263% 47.37% 4.74%
MCP to CBN 380 Meter 0.14% 47.37% 0.06% 5.26% 0.01% 52.63% 0.072% 47.37% 0.06%
MCP to CBN 380 Meter 0.14% 47.37% 0.06% 5.26% 0.01% 52.63% 0.072% 47.37% 0.06%
MCP to DCP 5092 Meter 1.19% 47.37% 0.56% 5.26% 0.06% 52.63% 0.624% 47.37% 0.56%
MCP to DCP 5776 Meter 1.35% 47.37% 0.64% 5.26% 0.07% 52.63% 0.708% 47.37% 0.64%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 47.37% 0.31% 5.26% 0.03% 52.63% 0.349% 47.37% 0.31%
EWD to SLI 2850 Meter 0.66% 47.37% 0.31% 5.26% 0.03% 52.63% 0.349% 47.37% 0.31%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 47.37% 1.18% 5.26% 0.13% 52.63% 1.311% 47.37% 1.18%
MCP to EWD 2850 Meter 0.66% 47.37% 0.31% 5.26% 0.03% 52.63% 0.349% 47.37% 0.31%
EWD to SLI 2850 Meter 0.66% 47.37% 0.31% 5.26% 0.03% 52.63% 0.349% 47.37% 0.31%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 0.000% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 6.04% 0.39% 3.47% 0.23% 9.51% 0.621% 90.49% 5.91%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 46.60% 1.95% 48.55% 51.45%

Menge
tahui Jakarta, 21 Agustus 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 24-Aug-20 s/d 30-Aug-20
Tanggal : 28-Aug-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 0.00% 21.05% 0.361% 78.95% 1.35%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 0.00% 21.05% 1.494% 78.95% 5.60%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 50.00% 1.52% 2.63% 0.08% 52.63% 1.601% 47.37% 1.44%
Lifting 38 Platform 1.51% 50.00% 0.76% 2.63% 0.04% 52.63% 0.796% 47.37% 0.72%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 68.42% 1.23% 5.26% 0.09% 73.68% 1.325% 26.32% 0.47%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 52.63% 0.21% 10.53% 0.04% 63.16% 0.254% 36.84% 0.15%
UPS to DB 1121 Meter 0.26% 52.63% 0.14% 10.53% 0.03% 63.16% 0.165% 36.84% 0.10%
MCP to SCR DCP 2850 Meter 0.66% 52.63% 0.35% 10.53% 0.07% 63.16% 0.419% 36.84% 0.24%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 52.63% 5.16% 10.53% 1.03% 63.16% 6.187% 36.84% 3.61%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 52.63% 5.26% 10.53% 1.05% 63.16% 6.315% 36.84% 3.68%
MCP to CBN 380 Meter 0.14% 52.63% 0.07% 10.53% 0.01% 63.16% 0.086% 36.84% 0.05%
MCP to CBN 380 Meter 0.14% 52.63% 0.07% 10.53% 0.01% 63.16% 0.086% 36.84% 0.05%
MCP to DCP 5092 Meter 1.19% 52.63% 0.62% 10.53% 0.12% 63.16% 0.749% 36.84% 0.44%
MCP to DCP 5776 Meter 1.35% 52.63% 0.71% 10.53% 0.14% 63.16% 0.850% 36.84% 0.50%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 52.63% 0.35% 10.53% 0.07% 63.16% 0.419% 36.84% 0.24%
EWD to SLI 2850 Meter 0.66% 52.63% 0.35% 10.53% 0.07% 63.16% 0.419% 36.84% 0.24%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 52.63% 1.31% 10.53% 0.26% 63.16% 1.573% 36.84% 0.92%
MCP to EWD 2850 Meter 0.66% 52.63% 0.35% 10.53% 0.07% 63.16% 0.419% 36.84% 0.24%
EWD to SLI 2850 Meter 0.66% 52.63% 0.35% 10.53% 0.07% 63.16% 0.419% 36.84% 0.24%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 0.000% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 9.51% 0.62% 6.59% 0.43% 16.11% 1.051% 83.89% 5.48%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 48.55% 3.71% 52.25% 47.75%

Menge
tahui Jakarta, 28 Agustus 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 31-Aug-20 s/d 6-Sep-20
Tanggal : 4-Sep-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 21.05% 0.36% 5.26% 0.09% 26.32% 0.451% 73.68% 1.26%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 21.05% 1.49% 5.26% 0.37% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 52.63% 1.60% 2.63% 0.08% 55.26% 1.681% 44.74% 1.36%
Lifting 38 Platform 1.51% 52.63% 0.80% 2.63% 0.04% 55.26% 0.836% 44.74% 0.68%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 73.68% 1.32% 0.00% 73.68% 1.325% 26.32% 0.47%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 63.16% 0.25% 10.53% 0.04% 73.68% 0.297% 26.32% 0.11%
UPS to DB 1121 Meter 0.26% 63.16% 0.16% 10.53% 0.03% 73.68% 0.192% 26.32% 0.07%
MCP to SCR DCP 2850 Meter 0.66% 63.16% 0.42% 10.53% 0.07% 73.68% 0.489% 26.32% 0.17%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 63.16% 6.19% 10.53% 1.03% 73.68% 7.218% 26.32% 2.58%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 63.16% 6.32% 10.53% 1.05% 73.68% 7.368% 26.32% 2.63%
MCP to CBN 380 Meter 0.14% 63.16% 0.09% 10.53% 0.01% 73.68% 0.101% 26.32% 0.04%
MCP to CBN 380 Meter 0.14% 63.16% 0.09% 10.53% 0.01% 73.68% 0.101% 26.32% 0.04%
MCP to DCP 5092 Meter 1.19% 63.16% 0.75% 10.53% 0.12% 73.68% 0.874% 26.32% 0.31%
MCP to DCP 5776 Meter 1.35% 63.16% 0.85% 10.53% 0.14% 73.68% 0.991% 26.32% 0.35%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 63.16% 0.42% 10.53% 0.07% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 63.16% 0.42% 10.53% 0.07% 73.68% 0.489% 26.32% 0.17%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 63.16% 1.57% 10.53% 0.26% 73.68% 1.836% 26.32% 0.66%
MCP to EWD 2850 Meter 0.66% 63.16% 0.42% 10.53% 0.07% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 63.16% 0.42% 10.53% 0.07% 73.68% 0.489% 26.32% 0.17%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 0.000% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 16.11% 1.05% 7.33% 0.48% 23.44% 1.530% 76.56% 5.00%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 52.25% 4.12% 56.38% 43.62%

Menge
tahui Jakarta, 04 September 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 7-Sep-20 s/d 13-Sep-20
Tanggal : 11-Sep-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 26.32% 0.45% 0.00% 26.32% 0.451% 73.68% 1.26%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 55.26% 1.68% 0.00% 55.26% 1.681% 44.74% 1.36%
Lifting 38 Platform 1.51% 55.26% 0.84% 0.00% 55.26% 0.836% 44.74% 0.68%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 73.68% 1.32% 0.00% 73.68% 1.325% 26.32% 0.47%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 73.68% 0.30% 0.00% 73.68% 0.297% 26.32% 0.11%
UPS to DB 1121 Meter 0.26% 73.68% 0.19% 0.00% 73.68% 0.192% 26.32% 0.07%
MCP to SCR DCP 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 73.68% 7.22% 0.00% 73.68% 7.218% 26.32% 2.58%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 73.68% 7.37% 0.00% 73.68% 7.368% 26.32% 2.63%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to DCP 5092 Meter 1.19% 73.68% 0.87% 0.00% 73.68% 0.874% 26.32% 0.31%
MCP to DCP 5776 Meter 1.35% 73.68% 0.99% 0.00% 73.68% 0.991% 26.32% 0.35%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 73.68% 1.84% 0.00% 73.68% 1.836% 26.32% 0.66%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 0.000% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 23.44% 1.53% 0.00% 0.00% 23.44% 1.530% 76.56% 5.00%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 56.38% 0.00% 56.38% 43.62%

Menge
tahui Jakarta, 11 September 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 14-Sep-20 s/d 20-Sep-20
Tanggal : 18-Sep-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 26.32% 0.45% 0.00% 26.32% 0.451% 73.68% 1.26%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 55.26% 1.68% 0.00% 55.26% 1.681% 44.74% 1.36%
Lifting 38 Platform 1.51% 55.26% 0.84% 0.00% 55.26% 0.836% 44.74% 0.68%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 73.68% 1.32% 0.00% 73.68% 1.325% 26.32% 0.47%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 73.68% 0.30% 0.00% 73.68% 0.297% 26.32% 0.11%
UPS to DB 1121 Meter 0.26% 73.68% 0.19% 0.00% 73.68% 0.192% 26.32% 0.07%
MCP to SCR DCP 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 73.68% 7.22% 0.00% 73.68% 7.218% 26.32% 2.58%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 73.68% 7.37% 0.00% 73.68% 7.368% 26.32% 2.63%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to DCP 5092 Meter 1.19% 73.68% 0.87% 0.00% 73.68% 0.874% 26.32% 0.31%
MCP to DCP 5776 Meter 1.35% 73.68% 0.99% 0.00% 73.68% 0.991% 26.32% 0.35%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 73.68% 1.84% 0.00% 73.68% 1.836% 26.32% 0.66%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 0.000% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 23.44% 1.53% 0.00% 0.00% 23.44% 1.530% 76.56% 5.00%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 56.38% 0.00% 56.38% 43.62%

Menge
tahui Jakarta, 18 September 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 21-Sep-20 s/d 27-Sep-20
Tanggal : 25-Sep-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 26.32% 0.45% 0.00% 26.32% 0.451% 73.68% 1.26%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 55.26% 1.68% 0.00% 55.26% 1.681% 44.74% 1.36%
Lifting 38 Platform 1.51% 55.26% 0.84% 0.00% 55.26% 0.836% 44.74% 0.68%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 73.68% 1.32% 0.00% 73.68% 1.325% 26.32% 0.47%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 73.68% 0.30% 0.00% 73.68% 0.297% 26.32% 0.11%
UPS to DB 1121 Meter 0.26% 73.68% 0.19% 0.00% 73.68% 0.192% 26.32% 0.07%
MCP to SCR DCP 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 73.68% 7.22% 0.00% 73.68% 7.218% 26.32% 2.58%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 73.68% 7.37% 0.00% 73.68% 7.368% 26.32% 2.63%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to DCP 5092 Meter 1.19% 73.68% 0.87% 0.00% 73.68% 0.874% 26.32% 0.31%
MCP to DCP 5776 Meter 1.35% 73.68% 0.99% 0.00% 73.68% 0.991% 26.32% 0.35%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 73.68% 1.84% 0.00% 73.68% 1.836% 26.32% 0.66%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 0.000% 43.42% 0.154% 56.58% 0.20%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 23.44% 1.53% 0.00% 0.00% 23.44% 1.530% 76.56% 5.00%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 56.38% 0.00% 56.38% 43.62%

Menge
tahui Jakarta, 25 September 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 28-Sep-20 s/d 4-Oct-20
Tanggal : 2-Oct-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 26.32% 0.45% 5.26% 0.09% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 55.26% 1.68% 0.00% 55.26% 1.681% 44.74% 1.36%
Lifting 38 Platform 1.51% 55.26% 0.84% 0.00% 55.26% 0.836% 44.74% 0.68%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 73.68% 1.32% 0.00% 73.68% 1.325% 26.32% 0.47%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 73.68% 0.30% 0.00% 73.68% 0.297% 26.32% 0.11%
UPS to DB 1121 Meter 0.26% 73.68% 0.19% 0.00% 73.68% 0.192% 26.32% 0.07%
MCP to SCR DCP 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 73.68% 7.22% 0.00% 73.68% 7.218% 26.32% 2.58%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 73.68% 7.37% 0.00% 73.68% 7.368% 26.32% 2.63%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to DCP 5092 Meter 1.19% 73.68% 0.87% 0.00% 73.68% 0.874% 26.32% 0.31%
MCP to DCP 5776 Meter 1.35% 73.68% 0.99% 0.00% 73.68% 0.991% 26.32% 0.35%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 73.68% 1.84% 0.00% 73.68% 1.836% 26.32% 0.66%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 43.42% 0.15% 6.58% 0.023% 50.00% 0.177% 50.00% 0.18%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 23.44% 1.53% 0.23% 0.01% 23.67% 1.545% 76.33% 4.98%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 56.38% 0.13% 56.51% 43.49%

Menge
tahui Jakarta, 04 Oktober 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 5-Oct-20 s/d 11-Oct-20
Tanggal : 9-Oct-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 55.26% 1.68% 2.63% 0.08% 57.89% 1.761% 42.11% 1.28%
Lifting 38 Platform 1.51% 55.26% 0.84% 2.63% 0.04% 57.89% 0.875% 42.11% 0.64%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 73.68% 1.32% 10.53% 0.19% 84.21% 1.514% 15.79% 0.28%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 73.68% 0.30% 0.00% 73.68% 0.297% 26.32% 0.11%
UPS to DB 1121 Meter 0.26% 73.68% 0.19% 0.00% 73.68% 0.192% 26.32% 0.07%
MCP to SCR DCP 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 73.68% 7.22% 0.00% 73.68% 7.218% 26.32% 2.58%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 73.68% 7.37% 0.00% 73.68% 7.368% 26.32% 2.63%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 0.00% 73.68% 0.101% 26.32% 0.04%
MCP to DCP 5092 Meter 1.19% 73.68% 0.87% 0.00% 73.68% 0.874% 26.32% 0.31%
MCP to DCP 5776 Meter 1.35% 73.68% 0.99% 0.00% 73.68% 0.991% 26.32% 0.35%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 73.68% 1.84% 0.00% 73.68% 1.836% 26.32% 0.66%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 0.00% 73.68% 0.489% 26.32% 0.17%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 50.00% 0.18% 2.63% 0.009% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 23.67% 1.55% 0.64% 0.04% 24.31% 1.587% 75.69% 4.94%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 56.51% 0.36% 56.87% 43.13%

Menge
tahui Jakarta, 09 Oktober 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 12-Oct-20 s/d 18-Oct-20
Tanggal : 16-Oct-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 57.89% 1.76% 0.00% 57.89% 1.761% 42.11% 1.28%
Lifting 38 Platform 1.51% 57.89% 0.88% 0.00% 57.89% 0.875% 42.11% 0.64%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 84.21% 1.51% 0.00% 84.21% 1.514% 15.79% 0.28%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 73.68% 0.30% 10.53% 0.04% 84.21% 0.339% 15.79% 0.06%
UPS to DB 1121 Meter 0.26% 73.68% 0.19% 10.53% 0.03% 84.21% 0.220% 15.79% 0.04%
MCP to SCR DCP 2850 Meter 0.66% 73.68% 0.49% 10.53% 0.07% 84.21% 0.559% 15.79% 0.10%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 73.68% 7.22% 10.53% 1.03% 84.21% 8.250% 15.79% 1.55%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 73.68% 7.37% 10.53% 1.05% 84.21% 8.420% 15.79% 1.58%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 10.53% 0.01% 84.21% 0.115% 15.79% 0.02%
MCP to CBN 380 Meter 0.14% 73.68% 0.10% 10.53% 0.01% 84.21% 0.115% 15.79% 0.02%
MCP to DCP 5092 Meter 1.19% 73.68% 0.87% 10.53% 0.12% 84.21% 0.999% 15.79% 0.19%
MCP to DCP 5776 Meter 1.35% 73.68% 0.99% 10.53% 0.14% 84.21% 1.133% 15.79% 0.21%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 10.53% 0.07% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 10.53% 0.07% 84.21% 0.559% 15.79% 0.10%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 73.68% 1.84% 10.53% 0.26% 84.21% 2.098% 15.79% 0.39%
MCP to EWD 2850 Meter 0.66% 73.68% 0.49% 10.53% 0.07% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 73.68% 0.49% 10.53% 0.07% 84.21% 0.559% 15.79% 0.10%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 24.31% 1.59% 6.16% 0.40% 30.47% 1.989% 69.53% 4.54%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 56.87% 3.46% 60.33% 39.67%

Menge
tahui Jakarta, 16 Oktober 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 19-Oct-20 s/d 25-Oct-20
Tanggal : 23-Oct-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 57.89% 1.76% 0.00% 57.89% 1.761% 42.11% 1.28%
Lifting 38 Platform 1.51% 57.89% 0.88% 0.00% 57.89% 0.875% 42.11% 0.64%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 84.21% 1.51% 0.00% 84.21% 1.514% 15.79% 0.28%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 84.21% 0.34% 0.00% 84.21% 0.339% 15.79% 0.06%
UPS to DB 1121 Meter 0.26% 84.21% 0.22% 0.00% 84.21% 0.220% 15.79% 0.04%
MCP to SCR DCP 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 84.21% 8.25% 0.00% 84.21% 8.250% 15.79% 1.55%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 84.21% 8.42% 0.00% 84.21% 8.420% 15.79% 1.58%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to DCP 5092 Meter 1.19% 84.21% 1.00% 0.00% 84.21% 0.999% 15.79% 0.19%
MCP to DCP 5776 Meter 1.35% 84.21% 1.13% 0.00% 84.21% 1.133% 15.79% 0.21%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 84.21% 2.10% 0.00% 84.21% 2.098% 15.79% 0.39%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 30.47% 1.99% 0.00% 0.00% 30.47% 1.989% 69.53% 4.54%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 60.33% 0.00% 60.33% 39.67%

Menge
tahui Jakarta, 23 Oktober 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328% 60.328%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803% 7.839%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 26-Oct-20 s/d 1-Nov-20
Tanggal : 30-Oct-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 57.89% 1.76% 0.00% 57.89% 1.761% 42.11% 1.28%
Lifting 38 Platform 1.51% 57.89% 0.88% 0.00% 57.89% 0.875% 42.11% 0.64%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 84.21% 1.51% 0.00% 84.21% 1.514% 15.79% 0.28%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 84.21% 0.34% 0.00% 84.21% 0.339% 15.79% 0.06%
UPS to DB 1121 Meter 0.26% 84.21% 0.22% 0.00% 84.21% 0.220% 15.79% 0.04%
MCP to SCR DCP 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 84.21% 8.25% 0.00% 84.21% 8.250% 15.79% 1.55%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 84.21% 8.42% 0.00% 84.21% 8.420% 15.79% 1.58%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to DCP 5092 Meter 1.19% 84.21% 1.00% 0.00% 84.21% 0.999% 15.79% 0.19%
MCP to DCP 5776 Meter 1.35% 84.21% 1.13% 0.00% 84.21% 1.133% 15.79% 0.21%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 84.21% 2.10% 0.00% 84.21% 2.098% 15.79% 0.39%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 30.47% 1.99% 0.00% 0.00% 30.47% 1.989% 69.53% 4.54%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 60.33% 0.00% 60.33% 39.67%

Menge
tahui Jakarta, 30 Oktober 2020
Dibuat oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328% 60.328% 60.328%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803% 7.839% 5.874%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 2-Nov-20 s/d 8-Nov-20
Tanggal : 6-Nov-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 57.89% 1.76% 0.00% 57.89% 1.761% 42.11% 1.28%
Lifting 38 Platform 1.51% 57.89% 0.88% 0.00% 57.89% 0.875% 42.11% 0.64%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 84.21% 1.51% 0.00% 84.21% 1.514% 15.79% 0.28%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 84.21% 0.34% 0.00% 84.21% 0.339% 15.79% 0.06%
UPS to DB 1121 Meter 0.26% 84.21% 0.22% 0.00% 84.21% 0.220% 15.79% 0.04%
MCP to SCR DCP 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 84.21% 8.25% 0.00% 84.21% 8.250% 15.79% 1.55%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 84.21% 8.42% 0.00% 84.21% 8.420% 15.79% 1.58%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to DCP 5092 Meter 1.19% 84.21% 1.00% 0.00% 84.21% 0.999% 15.79% 0.19%
MCP to DCP 5776 Meter 1.35% 84.21% 1.13% 0.00% 84.21% 1.133% 15.79% 0.21%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 84.21% 2.10% 0.00% 84.21% 2.098% 15.79% 0.39%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 30.47% 1.99% 0.00% 0.00% 30.47% 1.989% 69.53% 4.54%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 60.33% 0.00% 60.33% 39.67%

Menge
tahui Jakarta, 06 November
Dibuat2020
oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462% 0.000% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328% 60.328% 60.328% 60.328%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803% 7.839% 5.874% 5.274%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 9-Nov-20 s/d 15-Nov-20
Tanggal : 13-Nov-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 57.89% 1.76% 0.00% 57.89% 1.761% 42.11% 1.28%
Lifting 38 Platform 1.51% 57.89% 0.88% 0.00% 57.89% 0.875% 42.11% 0.64%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 84.21% 1.51% 0.00% 84.21% 1.514% 15.79% 0.28%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 84.21% 0.34% 0.00% 84.21% 0.339% 15.79% 0.06%
UPS to DB 1121 Meter 0.26% 84.21% 0.22% 0.00% 84.21% 0.220% 15.79% 0.04%
MCP to SCR DCP 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 84.21% 8.25% 0.00% 84.21% 8.250% 15.79% 1.55%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 84.21% 8.42% 0.00% 84.21% 8.420% 15.79% 1.58%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to DCP 5092 Meter 1.19% 84.21% 1.00% 0.00% 84.21% 0.999% 15.79% 0.19%
MCP to DCP 5776 Meter 1.35% 84.21% 1.13% 0.00% 84.21% 1.133% 15.79% 0.21%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 84.21% 2.10% 0.00% 84.21% 2.098% 15.79% 0.39%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 30.47% 1.99% 0.00% 0.00% 30.47% 1.989% 69.53% 4.54%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 60.33% 0.00% 60.33% 39.67%

Menge
tahui Jakarta, 13 November
Dibuat2020
oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328% 60.328% 60.328% 60.328% 60.328%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803% 7.839% 5.874% 5.274% 4.567%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 16-Nov-20 s/d 22-Nov-20
Tanggal : 20-Nov-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 57.89% 1.76% 1.32% 0.04% 59.21% 1.801% 40.79% 1.24%
Lifting 38 Platform 1.51% 57.89% 0.88% 1.32% 0.02% 59.21% 0.895% 40.79% 0.62%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 84.21% 1.51% 5.26% 0.09% 89.47% 1.608% 10.53% 0.19%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 84.21% 0.34% 0.00% 84.21% 0.339% 15.79% 0.06%
UPS to DB 1121 Meter 0.26% 84.21% 0.22% 0.00% 84.21% 0.220% 15.79% 0.04%
MCP to SCR DCP 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 84.21% 8.25% 0.00% 84.21% 8.250% 15.79% 1.55%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 84.21% 8.42% 0.00% 84.21% 8.420% 15.79% 1.58%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 0.00% 84.21% 0.115% 15.79% 0.02%
MCP to DCP 5092 Meter 1.19% 84.21% 1.00% 0.00% 84.21% 0.999% 15.79% 0.19%
MCP to DCP 5776 Meter 1.35% 84.21% 1.13% 0.00% 84.21% 1.133% 15.79% 0.21%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 84.21% 2.10% 0.00% 84.21% 2.098% 15.79% 0.39%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 0.00% 84.21% 0.559% 15.79% 0.10%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 30.47% 1.99% 0.31% 0.02% 30.78% 2.009% 69.22% 4.52%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 60.33% 0.17% 60.50% 39.50%

Menge
tahui Jakarta, 20 November
Dibuat2020
oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462% 0.000% 0.000% 0.000% 0.000% 0.175%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328% 60.328% 60.328% 60.328% 60.328% 60.503%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803% 7.839% 5.874% 5.274% 4.567% 4.111%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)


No Dok : FRM.MPR-003-03
LAPORAN KEMAJUAN PEKERJAAN
Revisi :0
Tanggal : 29-05-2019

Kontraktor Pelaksana : PT. ELTRAN INDONESIA Judul Pekerjaan : INSTALASI PLATFORM SCREEN DOOR
Nomor Kontrak : 0751/SPERJ/LRS/VII/2018 PROYEK LRT JABODEBEK
Tanggal Kontrak : 26 JULI 2018 Periode : 23-Nov-20 s/d 29-Nov-20
Tanggal : 27-Nov-20

PROGRESS PEKERJAAN
NO DESKRIPSI QTY SATUAN Bobot % Periode Lalu Periode ini s/d periode ini Sisa Pekerjaan
PROGRESS PROGRESS PROGRESS PROGRESS
BOBOT (%) BOBOT (%) BOBOT (%) BOBOT (%)
(VOL) (VOL) (VOL) (VOL)

A WORK PREPARATION
Working Preparation ( Marking and Measuring work) 38 Platform 1.71% 31.58% 0.54% 0.00% 31.58% 0.542% 68.42% 1.17%
Drilling work, Chemical Anchor and Bolt inserting work 38 Platform 7.10% 26.32% 1.87% 0.00% 26.32% 1.868% 73.68% 5.23%
B MOBILISASI AND LIFTING
B.1 Mobilisasi dan Lifting PSD Mechanical Structure
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 5.07% 21.05% 1.07% 0.00% 21.05% 1.067% 78.95% 4.00%
Lifting 38 Platform 1.51% 21.05% 0.32% 0.00% 21.05% 0.318% 78.95% 1.19%
B.2 Mobilisasi dan Lifting PSD Electrical-Control
Mobilisasi peralatan (Transport and Arrangement Work) 38 Platform 3.04% 59.21% 1.80% 1.32% 0.04% 60.53% 1.841% 39.47% 1.20%
Lifting 38 Platform 1.51% 59.21% 0.90% 1.32% 0.02% 60.53% 0.915% 39.47% 0.60%
B.3 Mobilisasi dan Lifting PDP
Mobilisasi peralatan 38 Platform 2.03% 42.11% 0.85% 0.00% 42.11% 0.854% 57.89% 1.17%
Lifting 38 Platform 1.51% 42.11% 0.64% 0.00% 42.11% 0.637% 57.89% 0.88%
C INSTALATION STRUCTURE
Installation Mechanical Structure, include : 38 Platform 7.30% 18.05% 1.32% 0.00% 18.05% 1.318% 81.95% 5.98%
- Instalation work of the main pole ( One Platform has 288 Bolt )
- Measurement work after instaled
- Adjustment work
- Instalation of the Base Plate or LMB
- Instalation work of the structure (Glass, Fix door, etc.)
- Instalation for the drive Box
- Instalation mortar work on the LMB/Base part.
D INSTALATION CABLE TRAY 300 x 100 mm
Cable Tray Instalation 2850 Meter 1.80% 89.47% 1.61% 0.00% 89.47% 1.608% 10.53% 0.19%
E INSTALATION CABLE EXTERNAL
LVMDP to DB 1121 Meter 0.40% 84.21% 0.34% 5.26% 0.02% 89.47% 0.360% 10.53% 0.04%
UPS to DB 1121 Meter 0.26% 84.21% 0.22% 5.26% 0.01% 89.47% 0.234% 10.53% 0.03%
MCP to SCR DCP 2850 Meter 0.66% 84.21% 0.56% 5.26% 0.03% 89.47% 0.594% 10.53% 0.07%
PDP1 to All BPSD - Slave FDP 16549 Meter 9.80% 84.21% 8.25% 5.26% 0.52% 89.47% 8.765% 10.53% 1.03%
PDP2 to All BPSD - Slave FDP 16891 Meter 10.00% 84.21% 8.42% 5.26% 0.53% 89.47% 8.946% 10.53% 1.05%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 5.26% 0.01% 89.47% 0.122% 10.53% 0.01%
MCP to CBN 380 Meter 0.14% 84.21% 0.11% 5.26% 0.01% 89.47% 0.122% 10.53% 0.01%
MCP to DCP 5092 Meter 1.19% 84.21% 1.00% 5.26% 0.06% 89.47% 1.061% 10.53% 0.12%
MCP to DCP 5776 Meter 1.35% 84.21% 1.13% 5.26% 0.07% 89.47% 1.204% 10.53% 0.14%
MCP to All BPSD - DCU 3838 Meter 0.89% 21.05% 0.19% 0.00% 21.05% 0.188% 78.95% 0.71%
MCP to All BPSD - DCU 8873 Meter 2.07% 21.05% 0.44% 0.00% 21.05% 0.435% 78.95% 1.63%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 5.26% 0.03% 89.47% 0.594% 10.53% 0.07%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 5.26% 0.03% 89.47% 0.594% 10.53% 0.07%
MCP (Screen shoield ) to All BPSD - DCU 4294 Meter 1.00% 21.05% 0.21% 0.00% 21.05% 0.211% 78.95% 0.79%
MCP to All BPSD - DCU 10697 Meter 2.49% 84.21% 2.10% 5.26% 0.13% 89.47% 2.229% 10.53% 0.26%
MCP to EWD 2850 Meter 0.66% 84.21% 0.56% 5.26% 0.03% 89.47% 0.594% 10.53% 0.07%
EWD to SLI 2850 Meter 0.66% 84.21% 0.56% 5.26% 0.03% 89.47% 0.594% 10.53% 0.07%
F INSTALATION PSD ELECTRICAL CONTROL
F.1 Installation in ER (Equipment Room)
Installation MCP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Installation SCR-DCP 19 Set 0.35% 52.63% 0.19% 0.000% 52.63% 0.187% 47.37% 0.17%
Termination MCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
Termination SCR-DCP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
F.2 Installation Electrical-Control on Platform
Installation Local-DCP (Platform) 38 Set 1.01% 21.05% 0.21% 0.00% 21.05% 0.213% 78.95% 0.80%
Termination Local-DCP 38 Set 0.15% 21.05% 0.03% 0.00% 21.05% 0.031% 78.95% 0.12%
Termination DCU & Drive Mechanisme 684 Set 2.63% 21.05% 0.55% 0.00% 21.05% 0.553% 78.95% 2.08%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)
G.1 Positioning and Mounting PDP
Positioning PDP 19 Set 0.25% 47.37% 0.12% 0.00% 47.37% 0.120% 52.63% 0.13%
Mounting PDP 19 Set 0.15% 42.11% 0.06% 0.00% 42.11% 0.064% 57.89% 0.09%
G.2 Installation and Termination PDP
Installation PDP 19 Set 0.51% 42.11% 0.21% 0.00% 42.11% 0.213% 57.89% 0.29%
Termination PDP 19 Set 0.07% 42.11% 0.03% 0.000% 42.11% 0.031% 57.89% 0.04%
H GROUNDING SYSTEM
Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) 285 Meter 0.26% 21.05% 0.06% 0.00% 21.05% 0.055% 78.95% 0.21%
Terminasi Grounding 38 Platform 0.61% 21.05% 0.13% 0.00% 21.05% 0.128% 78.95% 0.48%
I TOOLS & EQUIPMENT
I.1 Measurement Tools
Insulation Tester 3 Pcs 0.24% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.24%
LAN Tester 4 Pcs 0.03% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.03%
Digital Multimeter 4 Pcs 0.09% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.09%
Crimping Tools Cat-6 4 Pcs 0.02% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.02%
I.2 Office Equipment
Laptop 1 Pcs 0.10% 0.00% 0.00% 0.00% 0.00% 0.000% 100.00% 0.10%
Network Printer 3 Pcs 0.18% 33.33% 0.06% 0.00% 33.33% 0.059% 66.67% 0.12%
J MANAGEMENT INSTALLATION FEE 1 6.53% 30.78% 2.01% 3.20% 0.21% 33.98% 2.218% 66.02% 4.31%
K PROJECT MANAGEMENT 1 20.28% 100.00% 20.28% 0.00% 100.00% 20.283% 0.00% 0.00%
TOTAL 100.00% 60.50% 1.80% 62.30% 37.70%

Menge
tahui Jakarta, 27 November
Dibuat2020
oleh
(Meny Menyetujui Memeriksa KONTRAKTOR PELAKSANA
esuaik PT ELTRAN INDONESIA
an)

ILPAN APRILLIAN DENALI ANGGA K MUHAMMAD RIFQI SABARI


(PROJECT MANAGER) (PROJECT CONTROL) (PROJECT MANAGER)
No Dok : FRM.MPR-003-02
KURVA-S
Tanggal : 29-05-2019

Judul Pekerjaan: Instalasi Platform Screen Door Proyek LRT Jabodebek Lokasi : Jabodebek Tahun : 2018 Revisi :0

May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21
25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20 4-Jan-21 11-Jan-21 18-Jan-21 25-Jan-21 1-Feb-21 8-Feb-21 15-Feb-21 22-Feb-21 1-Mar-21 8-Mar-21 15-Mar-21 22-Mar-21 29-Mar-21 5-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 3-May-21 10-May-21 17-May-21 24-May-21 31-May-21 7-Jun-21 14-Jun-21 21-Jun-21 28-Jun-21
NO URAIAN SATUAN VOLUME BOBOT %
31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 3-Jan-21 10-Jan-21 17-Jan-21 24-Jan-21 31-Jan-21 7-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 7-Mar-21 14-Mar-21 21-Mar-21 28-Mar-21 4-Apr-21 11-Apr-21 18-Apr-21 25-Apr-21 2-May-21 9-May-21 16-May-21 23-May-21 30-May-21 6-Jun-21 13-Jun-21 20-Jun-21 27-Jun-21 4-Jul-21

W-97 W-98 W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117 W-118 W-119 W-120 W-121 W-122 W-123 W-124 W-125 W-126 W-127 W-128 W-129 W-130 W-131 W-132 W-133 W-134 W-135 W-136 W-137 W-138 W-139 W-140 W-141 W-142 W-143 W-144 W-145 W-146 W-147 W-148 W-149 W-150 W-151 W-152 W-153 W-154

A WORK PREPARATION

Working Preparation ( Marking and Measuring work) Platform 38 1.715% 0.361% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090% 0.090%
Drilling work, Chemical Anchor and Bolt inserting work Platform 38 7.099% 1.494% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374% 0.374%
B MOBILISASI AND LIFTING

B.1 Mobilisasi dan Lifting PSD Mechanical Structure

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 5.071% 1.067% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267% 0.267%
Lifting Platform 38 1.512% 0.318% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
B.2 Mobilisasi dan Lifting PSD Electrical-Control

Mobilisasi peralatan (Transport and Arrangement Work) Platform 38 3.042% 1.081% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.160% 0.040% 0.160%
Lifting Platform 38 1.512% 0.537% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.020% 0.080%
B.3 Mobilisasi dan Lifting PDP

Mobilisasi peralatan Platform 38 2.028% 0.747% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107% 0.107%
Lifting Platform 38 1.512% 0.557% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080% 0.080%
C INSTALATION STRUCTUREINSTALATION STRUCTURE

Installation Mechanical Structure, include : Platform 38 7.302% 1.318% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399% 0.399%
- Instalation work of the main pole ( One Platform has 288 Bolt ) `
- Measurement work after instaled

- Adjustment work

- Instalation of the Base Plate or LMB

- Instalation work of the structure (Glass, Fix door, etc.)

- Instalation for the drive Box

- Instalation mortar work on the LMB/Base part.

D INSTALATION CABLE TRAY 300 x 100 mm

Cable Tray Instalation Meter 2850 1.798% 0.757% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095% 0.095%
E INSTALATION CABLE EXTERNAL

LVMDP to DB Meter 1121 0.403% 0.169% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021% 0.021%
UPS to DB Meter 1121 0.261% 0.110% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
MCP to SCR DCP Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
PDP1 to All BPSD - Slave FDP Meter 16549 9.796% 4.125% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516% 0.516%
PDP2 to All BPSD - Slave FDP Meter 16891 9.999% 4.210% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526% 0.526%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to CBN Meter 380 0.136% 0.057% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007% 0.007%
MCP to DCP Meter 5092 1.186% 0.499% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062% 0.062%
MCP to DCP Meter 5776 1.345% 0.566% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071% 0.071%
MCP to All BPSD - DCU Meter 3838 0.894% 0.188% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047% 0.047%
MCP to All BPSD - DCU Meter 8873 2.067% 0.435% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109% 0.109%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
MCP (Screen shoield ) to All BPSD - DCU Meter 4294 1.000% 0.211% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
MCP to All BPSD - DCU Meter 10697 2.491% 1.049% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131% 0.131%
MCP to EWD Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
EWD to SLI Meter 2850 0.664% 0.279% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
F INSTALATION PSD ELECTRICAL CONTROL

F.1 Installation in ER (Equipment Room)

Installation MCP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Installation SCR-DCP Set 19 0.355% 0.098% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.014% 0.019%
Termination MCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
Termination SCR-DCP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
F.2 Installation Electrical-Control on Platform

Installation Local-DCP (Platform) Set 38 1.014% 0.213% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053% 0.053%
Termination Local-DCP Set 38 0.146% 0.031% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
Termination DCU & Drive Mechanisme Set 684 2.629% 0.553% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138% 0.138%
G INSTALATION PDP (POWER DISTRIBUTION PANEL)

G.1 Positioning and Mounting PDP

Positioning PDP Set 19 0.254% 0.120% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
Mounting PDP Set 19 0.152% 0.032% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008% 0.008%
G.2 Installation and Termination PDP

Installation PDP Set 19 0.507% 0.107% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027% 0.027%
Termination PDP Set 19 0.073% 0.015% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%
H GROUNDING SYSTEM

Tarikan Kabel dari Track to BPSD 01 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Tarikan Kabel dari Track to BPSD 02 (2 tarikan kabel Grounding) Meter 285 0.263% 0.055% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014% 0.014%
Terminasi Grounding Platform 38 0.608% 0.128% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032% 0.032%
I TOOLS & EQUIPMENT

I.1 Measurement Tools

Insulation Tester Pcs 3 0.240% 0.080% 0.080% 0.080%


LAN Tester Pcs 4 0.025% 0.006% 0.006% 0.006% 0.006%
Digital Multimeter Pcs 4 0.090% 0.022% 0.022% 0.022% 0.022%
Crimping Tools Cat-6 Pcs 4 0.022% 0.006% 0.006% 0.006% 0.006%
I.2 Office equipment

Laptop Pcs 1 0.096% 0.096%


Network Printer Pcs 3 0.176% 0.059% 0.059% 0.059%
J MANAGEMENT INSTALLATION FEE 6.528% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.014% 0.014% 0.060% 0.060% 0.045% 0.045% 0.085% 0.085% 0.012% 0.012% 0.226% 0.226% 0.069% 0.081% 0.073% 0.286% 0.271% 0.144% 0.185% 0.168% 0.290% 0.275% 0.118% 0.171% 0.158% 0.286% 0.271% 0.112% 0.165% 0.158% 0.286% 0.271% 0.112% 0.165% 0.371% 0.125% 0.077% 0.136% 0.113% 0.158% 0.113% 0.027%
K PROJECT MANAGEMENT 20.283% 20.283%
Total 100.000%
Rencana Mingguan 43.201% 0.000% 0.000% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.119% 0.119% 0.524% 0.524% 0.391% 0.391% 0.743% 0.743% 0.107% 0.107% 1.964% 1.964% 0.600% 0.707% 0.631% 2.488% 2.356% 1.257% 1.607% 1.465% 2.527% 2.395% 1.030% 1.489% 1.374% 2.488% 2.356% 0.976% 1.435% 1.374% 2.488% 2.356% 0.971% 1.435% 3.232% 1.088% 0.670% 1.186% 0.979% 1.370% 0.000% 0.979% 0.236% 0.000% 0.000% 0.000% 0.000%
Rekapitulasi Rencana Mingguan 43.201% 43.201% 43.201% 43.320% 43.438% 43.962% 44.486% 44.878% 45.269% 46.013% 46.756% 46.875% 46.993% 47.517% 48.041% 48.433% 48.824% 49.568% 50.311% 50.418% 50.525% 52.489% 54.454% 55.054% 55.761% 56.392% 58.880% 61.236% 62.493% 64.100% 65.564% 68.092% 70.486% 71.516% 73.005% 74.380% 76.868% 79.224% 80.200% 81.635% 83.010% 85.498% 87.854% 88.825% 90.260% 93.492% 94.580% 95.250% 96.436% 97.415% 98.786% 98.786% 99.764% 100.000% 100.000% 100.000% 100.000% 100.000%
Realisasi Mingguan 43.201% 0.000% 0.000% 0.000% 0.000% 0.279% 0.000% 0.139% 0.382% 0.054% 0.395% 2.148% 1.951% 3.705% 4.123% 0.000% 0.000% 0.000% 0.129% 0.360% 3.462% 0.000% 0.000% 0.000% 0.000% 1.799%
Rekapitulasi Realisai Mingguan
43.201% 43.201% 43.201% 43.201% 43.201% 43.480% 43.480% 43.619% 44.001% 44.055% 44.449% 46.598% 48.549% 52.254% 56.377% 56.377% 56.377% 56.377% 56.505% 56.866% 60.328% 60.328% 60.328% 60.328% 60.328% 62.127%
Deviasi 0.000% 0.000% 0.000% -0.119% -0.237% -0.483% -1.007% -1.259% -1.268% -1.958% -2.307% -0.277% 1.555% 4.736% 8.335% 7.944% 7.552% 6.809% 6.194% 6.447% 9.803% 7.839% 5.874% 5.274% 4.567% 5.735%

Garis biru Kurva S rencana


Garis merah kurva S realisasi

Menyetujui Memeriksa Dibuat oleh


PT. LEN RAILWAY SYSTEMS PT. LEN RAILWAY SYSTEMS PT. ELTRAN INDONESIA

(Project Manager) (Project Control) (Project Manager)