Petrolia Columbia
Petrolia Columbia
Seal
Assigned To Mechanic
Check the Lube manifold and
confirm proper offices in place
Page 1 of 6
BuW Guides
Assigned To Mechanic
Guide Teflon Need Replacing
Bolts Loose
Assigned To Just Remove
Removed
Page 2 of 6
Gauges Not Secure
Assigned To Mechanic
Put gouges back in panel and
secure
Tensioning Cylender
Fully Retracted
Assigned To Rig Crew /
Mechanic
Cable for tensioning needs to be
put in another pin hole to make
cable shorter
Page 3 of 6
Asb Comm Wiring
Assigned To Diagram
Page 4 of 6
Cable Added For TD
Comms
Assigned To Electrician
Part of comm issue
Page 5 of 6
Hydraulic Temp And
Lube Pressure
Assigned To Mechanic
Temp is high so oil should be
circulationing through cooler
and its not .suggested to bypass
till parts come in to replace
Page 6 of 6