Professional Documents
Culture Documents
5 F 3 C 099 Ad 4929
5 F 3 C 099 Ad 4929
What you do matters – your work can, and most likely will, save a life at
some point in your career.
• This is an easy to
use checklist for
possible areas of
leakage in a room
prior to conducting
the door fan test.
Room Integrity Sealing
Recommendations
• NFPA 2001 requires the enclosure to be tested for integrity
to verify the enclosure is capable of retaining the agent
enriched atmosphere for the required hold time. A door
fan test in accordance with Annex C of NFPA 2001 is the
typical means of performing the required test.
• Pressure venting may be required to prevent damage to
the enclosure due to pressure differential across walls,
floor, or ceilings during agent discharge. Always verify
that any venting operates properly to an atmosphere
capable of handling the volume of the vented gas.
Room Integrity Sealing Recommendations
• Sealing of the room is typically not the responsibility of the fire protection contractor. Our
role is to guide the responsible contractor in how to properly seal a hazard to contain the
clean agent gas.
• The information on the following slide should be sent to the company that we are working
for to be forwarded to the proper trade. Doing this early in the construction phase helps
eliminate any confusion regarding what is required to properly seal the hazard.
• It is also recommended that the number of door fan tests that will be conducted be
specified in the written contract. Often a general contractor will expect an endless
number of repeat tests when rooms do not pass the door fan test.
Room Integrity Sealing Recommendations
Items that need to be addressed when sealing a room for
containing Clean Agent Suppression Gas:
• Doors: All doors that exit a protected space, or lead into a different protected space
need to have the proper hardware installed to prevent the loss of clean agent gas.
Drop seals on the bottom of door, weather stripping around the jams, and
mechanical latching hardware will help prevent leakage after a discharge. Doors
that can not be kept normally closed should have self closing devices with
electromagnet door holders that release prior to a discharge.
• Windows: All windows inside of the hazard need to be caulked around the frame,
and at the gasket around the glass in the frame. Pay attention to sash, casing, and
any single pane grills if present.
• Ductwork: Ductwork that is no longer being used should be sealed off and made
airtight using metal plates screws and caulking. Building HVAC ductwork should have
butterfly type dampers with neoprene seals (smoke dampers). The dampers can be
spring loaded or closed by a motor (verify the discharge time delay is adequate for
the damper to close).
Room Integrity Sealing Recommendations
Continued:
• Conduit: Conduit leading into and out of the hazard area needs to be sealed with a fire-
rated sealing material. Electrical boxes, receptacles, etc. need also be sealed to prevent
leakage after discharge.
• Self-Contained Air Handling Units: CRAC (Computer Room Air Conditioning) units often
must be left in service after a discharge. Mission critical equipment that can not be
shutdown still requires cooling after a discharge. However unwanted subfloor
pressurization may accelerate leakage, or the air handler may be the source of the fire.
Therefore, when practical, shutting down the CRAC unit upon discharge is recommended.
• Perimeter Walls: All walls around the perimeter and between separate zones shall be
installed slab-to-slab. The wall shall be caulked inside at the top of the wall and at the
bottom of the wall. Walls that meet corrugated over head pan need to have the pockets
filled with a proper fire-rated material. Unrated canned spray foam is not an acceptable
rated wall sealant.
• Extended Raised Floors: Raised floors that extend outside of the protected hazard must
have a bulkhead installed under the raised floor where the protected area stops. The top
and bottom of the bulkhead needs to be sealed with caulk. Dampers located in walls
below the raised floor shall be installed following the duct work guidelines.
Room Integrity Sealing Recommendations
Continued:
• Floor Drains: All floor drains shall have traps that are designed to have water in them or a
non-evaporating approved liquid to keep the agent/air mixture from leaking through the
drain.
• Block Walls: All block walls are porous and need to be sealed. Walls should be painted
with two or three coats of paint from floor to the ceiling. Block walls covered by drywall
which extends above the ceiling must be painted and the joint between the drywall and
the block sealed.
• Cable Trays: Cable trays that pass through the perimeter wall must have proper rated
pillows or caulk to fill in the voids around the cables.
• Sealing Material: All caulk and material used for sealing must have a fire rating at least
equal to the rating of the wall assembly being sealed.
• Clean Agents: Clean Agents require calculation of required area of leakage so as not to
over pressurize the enclosure during a discharge. Refer to manufacturer’s guidelines to
determine the proper amount of pressure relief.
• Leakage: Many clean agents are heavier than air and settle after a discharge. Leakage
below the raised floor is more critical than above the suspended ceiling. The design
concentration must be maintained at the level of the highest combustibles in the
enclosure. Typical required hold time after a discharge is ten minutes.
NPFA Required Forms
• For sprinkler and alarm
systems, NFPA 13 Standard
for Installation of Sprinkler
Systems and NFPA 72
National Fire Alarm Code
forms must be filled out
prior to final acceptance.
The forms can be found in
each code.
NFPA 13 Standard for Installation of Sprinkler Systems
Contractor’s Material and Test Certificate for Above Ground Piping is a document that is
required when any work has been performed on any new or existing sprinkler system.
NFPA 72 National Fire Alarm Code
• Fire Alarm System
Record of Completion
needs to be
completed prior to
the Final Acceptance
testing of any of the
Fire Alarm Systems
including those with
Releasing Control
Panels.
Discharge Testing
• When required, a gaseous agent system may have to be discharged to verify the
agent is dispersed properly and the design concentration is achieved at the proper
height in the hazard.
• Prior to the advent of NFPA 2001 clean agent gases, the fire protection industry used
Halon 1301 and it was fairly common to discharge test systems in order to verify gas
dispersion and concentration. By the late 1980’s there was mounting evidence that
Halon 1301 was one of the refrigerant gases contributing to depletion of stratospheric
ozone. Discharge testing of systems became very rare.
• The Halon substitutes listed in NFPA 2001 have virtually no ozone depletion potential.
NFPA 2001 permits, but does not require, discharge tests of clean agent system to be
included as part of the final acceptance requirements. Discharge testing of clean
agent systems may be done to verify agent concentration and dispersion within a
protected hazard.
• NFPA 12 requires carbon dioxide systems to pass a full discharge test as part of final
acceptance.
Discharge Testing (continued)
• For total flooding systems, a concentration
meter is used to record the achieved
concentration over a period of time (hold
time).
• Many meters record concentrations on paper
tapes.
• Meters with digital outputs are available to
save data in digital file format.
Typical three-point
concentration meter with
paper strips to record
concentration
measurements.
Discharge Testing (continued)
• The meter typically is connected to sampling hoses which are located inside of the
hazard. One sample point is usually located at the elevation of highest piece of
equipment to be protected, then the next two are at the midway point and at the
bottom of the protected equipment. The meter itself is usually located outside of the
protected space.
Field calibration of the meter should be done after the meter has warmed up
and prior to the discharge test.
This is an example of a typical report as sent to an end
user documenting the test results. This report documented
that the end user did not want the system armed and the
required warning signs had not been installed.
CO2 Discharge
Safety Checklist for
Marine Systems
Sequence of Operation
• Verify occurrence of the
approved Sequence of
Operation when conducting
the Final Acceptance Test with
the AHJ.
Prior to conducting the Acceptance Test a form should be created
which can be used as a checklist during the test. This list is then
signed by the AHJ documenting the testing that was done.
An excellent reference document to use in developing checklists for
inspection and related testing of fire protection systems in the FSSA
Fire Protection Systems Inspection Form Guidelines. This guide lists the
procedures that should be done for many types of fire protection
systems.
Thank you!