PTB Report 47867
PTB Report 47867
User: Nirar
User Email: nirar1997@gmail.com
Total Score: 97/100
Duration Score: 31/34
Cost Score: 33/33
Scope Score: 33/33
Scenario: NPD-A
Created at: Tuesday, July 11, 2023 10:46:47 PM
Last simulation run result: Scenario finished
Simulation Time: 24
Target Date: 22
Target Cost: 36000
Simulation Cash: 3200
Total Cost: 32800
Value: 100
Estimated Cost: 32800
Estimated Duration: 24
Morale: Very Low
The PTB Simulation Report
Answer: We have learnt that the decision will depend on the expenses, as we can either
use our own team or outsource the work. The most important aspect is to learn how to
manage the quality, resources including cost and duration as those are the factors that
might effect the project.
The PTB Simulation Report
Question: In case you worked on this project in a team, how did you distribute the
management of the project between the team members?
Answer: We equally distributed our work so that no one gets to over work nor under work
and be fair on taking responsibilities. For instance overseeing schedule and resources
The PTB Simulation Report
Answer: This just makes our lives easy by getting to understand how to simulate and we
are enjoying doing this simulation.
The PTB Simulation Report
Answer: NA
The PTB Simulation Report
Scenario Information:
Project Name Number of Target Date Initial Cash Bonus per Day Penalty per Day
Tasks
Resource Information:
Name Availa Availa Cost/ Idle Firing Hiring Show Firing Hiring Minim Maxim
ble ble Day Cost/ Cost Cost Up Lead Lead um um
Units Units Day Proba Time Time Units Units
in bility
Lead (%)
Time
Quality Requirements:
The PTB Simulation Report
Task Information:
The PTB Simulation Report
Mode Name Optimistic Most Likely Pessimistic Fixed Cost Engineers Hardware
Duration Duration Duration Needed Design
Quality
[HDQ] (HDQ)
In-House 5 5 5 0 2 0.95
Subcontracto 6 6 6 0 0 0.9
r
The PTB Simulation Report
Mode Name Optimistic Most Likely Pessimistic Fixed Cost Engineers Software
Duration Duration Duration Needed Design
Quality
[SDQ] (SDQ)
In-House 2 2 2 0 3 0.98
Subcontracto 3 3 3 0 3 0.95
r
The PTB Simulation Report
In-House 6 6 6 0 2
The PTB Simulation Report
Mode Name Optimistic Most Likely Pessimistic Fixed Cost Engineers Hardware
Duration Duration Duration Needed Manufacturin
g Quality
[HMQ]
(HMQ)
In-House 7 7 7 0 1 0.99
Subcontracto 8 8 8 0 0 0.9
r
The PTB Simulation Report
Mode Name Optimistic Most Likely Pessimistic Fixed Cost Engineers Software
Duration Duration Duration Needed Coding
Quality
[SCQ] (SCQ)
In-House 6 6 6 0 2 0.99
Subcontracto 7 7 7 0 0 0.9
r
The PTB Simulation Report
Mode Name Optimistic Most Likely Pessimistic Fixed Cost Engineers Integration
Duration Duration Duration Needed Quality [IQ]
(IQ)
In-House 3 3 3 0 3 0.95
Subcontracto 4 4 4 0 0 0.8
r
The PTB Simulation Report
In-House 5 5 5 0 1