Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROJECT COMPLETION REPORT TRACKER

1 PROJECT OVERVIEW
A. PROJECT NAME
B. PROJECT LOCATION
C. OWNER OR CLIENT
D. CONSTRUCTION MANAGEMENT
E. ORIGINAL CONTRACT SUMMARY
F. REVISED CONTRACT SUMMARY CHANGE ORDER
G. TOTAL PROJECT COST
H. LIST OF CONSULTANTS
1 ARCHITECTURAL
2 STRUCTURAL
3 MECHANICAL
4 ELECTRICAL
5 PLUMBING
6 FIRE PROTECTION LEED

2 SCOPE OF WORKS
A. CLIENT
B. SCCI
C. NOMINATED SUBCONTRACTORS

3 FINAL APPROVED TABLE OF ORGANIZATION

4 MANPOWER LOADING (PLANTILLA) - PLANNED VS ACTUAL ON A MONTHLY BASIS


A. LIST OF MANPOWER COUNT (E.G. FOR STRUCTURAL, ARCHITECTURAL, MEPF MANPOWER)

5 EQUIPMENT LOADING - PLANNED VS ACTUAL


A. LIST OF KEY EQUIPMENT

6 SCHEDULE - PLANNED VS ACTUAL


A. MILESTONE DATES (TOPPING OFF, WATER TIGHTNESS, ENERGIZATION ETC..)
B. S-CURVE

7 MAJOR CHANGE ORDERS


A. SUBMITTED IN PHP
B. APPROVED IN PHP

8 EXTENSION OF TIME
A. SUBMITTED
B. APPROVED

9 PRODUCTIVITY REPORT
A. STRUCTURAL WORKS
1 REBAR INSTALLATION (MANDAY PER KILOGRAM)
2 CONCRETING (MANDAY PER CUBIC METER)
3 FORMWORKS (MAN-DAY PER SQM)
B. ARCHITECTURAL WORKS
1 TILE INSTALLATION
2 PAINTING WORKS
3 CHB / LIGHT WEIGHT BLOCKS / OTHER PARTITION
4 ETC.

10 SUBCONTRACTORS' EVALUATION REPORT (INCLUDE LISTING AND RATING)

11 SUBCONTRACTOR'S PAYABLES

12 SAFETY
A. SAFE MANHOURS
B. HSE STATISTICS

13 PROGRESS PHOTOS

14 LIST OF AS BUILT DRAWINGS HANDED OVER BY OPERATIONS


A. TYPE OF PLAN
B. DRAWING TYPE
C. DRAWING NO.
D. DESCRIPTION/CONTENT

15 LIST OF QUALITY DOCUMENTS


A. LIST OF WIR & APPROVED WIR COPY
B. LIST OF MIR & APPROVED MIR COPY

16 LIST OF HSE REPORTS


A. INCIDENT/ACCIDENT REPORT
B. DOLE REPORTS
C. DOLE INSPECTION CLOSE OUT REPORT (IF ANY)

17 COPIES OF INITIAL HANDLING OF CERTIFICATES (HAND-OVER) / COPA ( Certificate of Partial Acceptance)

18 COPIES OF VARIOUS PERMITS OR CERTIFICATES (E.G. OCCUPANCY PERMIT, PERMIT TO OPERATE, FIRE DEPARTMENTS' CERTIFICATE )

19 WARRANTY CERTIFICATES
A. GENERATOR SET
B. TRANSFORMER
C. ELEVATOR
D. FCU & ACCU, FANS & BLOWERS
E. BOOSTER PUMP & ELEVATOR PIT PUMP
F. FIRE PUMP AND JOCKEY PUMP
G. WATERPROOFING

20 CERTIFICATE OF COMPLETION AND ACCEPTANCE

21 RETENTION STATUS

You might also like