Professional Documents
Culture Documents
Assembly Report L&T Chennai XRE Week 10 - 2023
Assembly Report L&T Chennai XRE Week 10 - 2023
Assembly Report L&T Chennai XRE Week 10 - 2023
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
Remanufacturing location: KANCHIPURAM, INDIA
TRC Personnel:
John McNally – Team Leader. Richard Mauer ‐ Assembly Manager
Madhan P N – Project Manager. Ronny Hinkel – PLC
Nagarjuna Musikara Reddy – Site Manager Robbins Crew ‐ 25
Summary:
TBM 1 HBW manifold installed at front shield and connection given. HBW manifolds to
outer seals plumbing and hose installation done.
TBM 1 cavity B and C outer hose EC 210‐8 (8 ports) connected.
TBM 2 carrier roller bracket repairing work done.
TBM 1 bridge gantry hydraulic grease pipeline joint work under progress.
TBM 1 material lock mounting on front shield completed.
TBM 1 front shield inner ports connected to manifolds.
TBM 2 gantry 7 water hose reel fixed.
TBM 1 pinion lube, pinion bearing lube, main bearing all hoses connection done.
TBM 1 bridge gantry all hydraulic pipes inside cleaned, and all joint work done.
TBM 1 Thrust cylinders 13 No’s mounted on shield. New fasteners M30x100 socket
type installed.
TBM 1 main drive gear box sand blasting ongoing with covered plate.
TBM 1 cutterhead foam nozzle area rewelding under process.
TBM 2 articulation shield 04 No’s bentonite flange pipe welding done.
TBM 2 Erector accumulators fixed 02 No’s.
Page 1
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 2 front shield HBW, pinion lube hoses installed.
Received 02 No’s Main thrust cylinder received. Sand blasting completed.
TBM 2 cable tray laying work ongoing.
TBM 2 gantry lights installation completed in gantry 1, 2 and 3.
TBM 1 and TBM 2 APFC panel installed at Gantry 4.
Received New TBM cables 50%.
Main Tasks Carried Out.
Monday 06/3/2023
TBM 1 and TBM 2 Pending cable tray fixing work ongoing.
TBM 2 hose reel panel and TSG junction box buffing work done.
TBM 1 gantry lights 12 No’s fixed.
TBM 2 gantry lights 20 No’s fixed.
TBM 1 HBW manifolds, lube distributors inner and outer completed at front shield and hoses
connection given.
TBM 2 carrier roller brackets repairing work done.
TBM 1 man lock adaptor fixed.
Hose installation for Cavity B and C EC 210‐8 8 ports completed.
Page 2
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 2 Carrier roller frame repairing work ongoing.
Tuesday 07/3/2023
TBM 1 Material lock mounting on front shield completed.
TBM 1 inner lube ports connected to manifold. Hydraulic drain line manifold to tank connection
done.
TBM 2 water hose reel fixed in gantry 7.
TBM 1 bridge gantry hydraulic pipes fixed.
TBM 1 and TBM 2 APFC panel fixed at gantry 4.
TBM 2 TSG junction box and man lock junction box buffing done.
Page 3
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 1 gantry 7 Cable tray installed.
TBM 1 Cutterhead welding works ongoing for nozzles
Page 4
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 2 TSG junction box buffing work ongoing
Page 5
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 1 bridge gantry pipelines connection ongoing
Page 6
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 1 Snubber pulley sand blasting ongoing
Wednesday 08/3/2023
Day off. Holi Festival.
Thursday (09/3/2023)
TBM 1 pinion lube, pinion bearing lube, main bearing all hoses connection done at front shield
A.
TBM 1 bridge gantry all hydraulic pipes inside cleaned, and jointing done.
TBM 1 and TBM 2 tail pulley buffing done and applied grease.
TBM 1 and TBM 2 cable tray laying work ongoing.
TBM 1 main drive motor gear box sensors 6 No’s removed and kept aside in store.
New Cables for TBM received. 50 %
TBM 1 and 2 gantry 6 cable tray support angle fixed.
Page 7
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 1 Manifolds installation done and hoses connection given.
TBM 1 Manifolds and hoses connected for Front shield HBW, Pinion lube and B‐C cavity
Friday (10/3/2023)
TBM 1 Main thrust cylinders 13 No’s mounted on Middle shield.
TBM 1 main drive gear box pinion side protection covers fixed during sand blasting.
Page 8
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 2 EP2, HBW, pinion lube, pinion bearing lube, main bearing lube distributors installed on
front shield.
TBM 2 cutterhead foam nozzle area rewelding under process.
TBM 1 gantry 1 grease line pipes fixed.
TBM 2 articulation shield 04 No’s bentonite flange welding work done.
TBM 1 Material lock mounting fixed at front shield.
TBM 2 water hose reel fixed in gantry 7.
Page 9
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
Received Auxiliary cylinders for Erector, stabilizer, feeder etc., for TBM 1
Received 6 Gear boxed from Breivini.
Page 10
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
Saturday (11/3/2023)
TBM 1 thrust cylinder mounting bolts newly installed M30x100 socket type.
TBM 1 main drive gear box, gripper cylinders sand blasting completed. Painting ongoing.
TBM 2 front shield main bearing line hoses fixed 03 No’s.
TBM 2 erector accumulators fixed 02 No’s.
TBM 2 gantry 2 grease pipes fixed.
Received 2 more thrust cylinders and sand blasting ongoing.
TBM 2 Front shield Manifolds and hoses installation completed.
Page 11
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
TBM 1 Main thrust cylinders 13 No’s Installed in shield.
TBM 1 and TBM 2 gantry 6 cable tray installed.
Page 12
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
Received cable for TBM 1 and TBM 2 50%
Sunday (12/3/2023)
Pipe laying and hose laying works ongoing.
Page 13
Project: L&T Chennai Metro
TBM: XRE 2114 408‐1/ 409‐1
Chennai, India
Subject: Remanufacturing Robbins TBM
Customer: Larsen & Toubro
Date: Week10‐2023
VARINDER SINGH P P P P P P H
CHAMEL SINGH P P P P P P H
DHANANJAY P P P P P P H
ANTU CHOUDHARY P P P P P P H
RANJAN P P P P P P H
PAPPU KUMAR YADAV P P P P P P H
KAMLESH RAWAT P P P P P P H
NIGHT
GULAM MUSTAFA P P P P P P H
KULDEEP P P P P P P H
SUNENDER SINGH P P P P P P H
VELMURUGAN P P P P P P H
KOTESHWAR RAO P P P P P P H
PARASHURAM MALIK P P P P P P H
CK GUPTA P P P P P P H
PK GUPTA P P P P P P H
SANTOSH CHOUDHARY P P P P P P H
MAHESHWAR KUMAR P P P P P P H
ARASHADEEP SINGH P P P P P P H
GURPAL SINGH P P P P P P H
KIRAN METLAPALLI P P P P P P H
Unskilled Manpower Required for Week Unskilled Manpower Actual for Week
180 170
Report Prepared by Robbins Report Acknowledged by L&T
MADHAN P N AVINASH
PROJECT MANAGER Asst. Manager (TBM Electrical)
Page 14