Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 
Remanufacturing location:  KANCHIPURAM, INDIA 

TRC Personnel: 

John McNally – Team Leader.                             Richard Mauer ‐ Assembly Manager   

Madhan P N – Project Manager.               Ronny Hinkel – PLC    

Nagarjuna Musikara Reddy – Site Manager                 Robbins Crew ‐ 25         

Summary: 

 TBM 1 HBW manifold installed at front shield and connection given. HBW manifolds to 
outer seals plumbing and hose installation done. 

 TBM 1 cavity B and C outer hose EC 210‐8 (8 ports) connected. 

 TBM 2 carrier roller bracket repairing work done. 

 TBM 1 bridge gantry hydraulic grease pipeline joint work under progress. 

 TBM 1 material lock mounting on front shield completed. 

 TBM 1 front shield inner ports connected to manifolds. 

 TBM 2 gantry 7 water hose reel fixed. 

 TBM 1 pinion lube, pinion bearing lube, main bearing all hoses connection done. 

 TBM 1 bridge gantry all hydraulic pipes inside cleaned, and all joint work done. 

 TBM 1 Thrust cylinders 13 No’s mounted on shield. New fasteners M30x100 socket 
type installed. 

 TBM 1 main drive gear box sand blasting ongoing with covered plate. 

 TBM 1 cutterhead foam nozzle area rewelding under process. 

 TBM 2 articulation shield 04 No’s bentonite flange pipe welding done. 

 TBM 2 Erector accumulators fixed 02 No’s. 

 
Page 1

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 
 TBM 2 front shield HBW, pinion lube hoses installed. 

 Received 02 No’s Main thrust cylinder received. Sand blasting completed. 

 TBM 2 cable tray laying work ongoing. 

 TBM 2 gantry lights installation completed in gantry 1, 2 and 3. 

 TBM 1 and TBM 2 APFC panel installed at Gantry 4. 

 Received New TBM cables 50%. 

Main Tasks Carried Out. 
Monday 06/3/2023 

 TBM 1 and TBM 2 Pending cable tray fixing work ongoing. 

 TBM 2 hose reel panel and TSG junction box buffing work done. 

 TBM 1 gantry lights 12 No’s fixed. 

 TBM 2 gantry lights 20 No’s fixed. 

 TBM 1 HBW manifolds, lube distributors inner and outer completed at front shield and hoses 
connection given. 

 TBM 2 carrier roller brackets repairing work done. 

 TBM 1 man lock adaptor fixed. 

 Hose installation for Cavity B and C EC 210‐8 8 ports completed. 

 
Page 2

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 2 Carrier roller frame repairing work ongoing. 

Tuesday 07/3/2023 

 TBM 1 Material lock mounting on front shield completed. 

 TBM 1 inner lube ports connected to manifold. Hydraulic drain line manifold to tank connection 
done. 

 TBM 2 water hose reel fixed in gantry 7. 

 TBM 1 bridge gantry hydraulic pipes fixed. 

 TBM 1 and TBM 2 APFC panel fixed at gantry 4. 

 TBM 2 TSG junction box and man lock junction box buffing done. 

 
Page 3

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 1 gantry 7 Cable tray installed. 

TBM 1 Cutterhead welding works ongoing for nozzles 

 
Page 4

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 2 TSG junction box buffing work ongoing 

 
Page 5

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 1 bridge gantry pipelines connection ongoing 

 
Page 6

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 1 Snubber pulley sand blasting ongoing 

Wednesday 08/3/2023 

 Day off. Holi Festival. 

Thursday (09/3/2023) 

 TBM 1 pinion lube, pinion bearing lube, main bearing all hoses connection done at front shield 
A. 

 TBM 1 bridge gantry all hydraulic pipes inside cleaned, and jointing done. 

 TBM 1 and TBM 2 tail pulley buffing done and applied grease. 

 TBM 1 and TBM 2 cable tray laying work ongoing. 

 TBM 1 main drive motor gear box sensors 6 No’s removed and kept aside in store. 

 New Cables for TBM received. 50 % 

 TBM 1 and 2 gantry 6 cable tray support angle fixed. 

 
Page 7

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 1 Manifolds installation done and hoses connection given. 

TBM 1 Manifolds and hoses connected for Front shield HBW, Pinion lube and B‐C cavity 

Friday (10/3/2023) 

 TBM 1 Main thrust cylinders 13 No’s mounted on Middle shield. 

 TBM 1 main drive gear box pinion side protection covers fixed during sand blasting. 

 
Page 8

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 
 TBM 2 EP2, HBW, pinion lube, pinion bearing lube, main bearing lube distributors installed on 
front shield. 

 TBM 2 cutterhead foam nozzle area rewelding under process. 

 TBM 1 gantry 1 grease line pipes fixed. 

 TBM 2 articulation shield 04 No’s bentonite flange welding work done. 

TBM 1 Material lock mounting fixed at front shield. 

TBM 2 water hose reel fixed in gantry 7. 

 
Page 9

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

Received Auxiliary cylinders for Erector, stabilizer, feeder etc., for TBM 1 

Received 6 Gear boxed from Breivini. 

 
Page 10

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 
Saturday (11/3/2023) 

 TBM 1 thrust cylinder mounting bolts newly installed M30x100 socket type. 

 TBM 1 main drive gear box, gripper cylinders sand blasting completed. Painting ongoing. 

 TBM 2 front shield main bearing line hoses fixed 03 No’s. 

 TBM 2 erector accumulators fixed 02 No’s. 

 TBM 2 gantry 2 grease pipes fixed. 

 Received 2 more thrust cylinders and sand blasting ongoing. 

TBM 2 Front shield Manifolds and hoses installation completed. 

 
Page 11

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

TBM 1 Main thrust cylinders 13 No’s Installed in shield. 

TBM 1 and TBM 2 gantry 6 cable tray installed. 

 
Page 12

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 

Received cable for TBM 1 and TBM 2 50% 

Sunday (12/3/2023) 

 Pipe laying and hose laying works ongoing. 

MANPOWER (06th Mar – 12th March 2023)


Name: Designation: 06 07 08 09 10 11 12 Remark
MADHAN P N Project Manager P P P P P P H
RICHARD MAUER Assembly Manager P P P P P P H
NAGARJUNA MUSIKARA Site Manager P P P P P P H
RONNY HINKEL PLC Engineer L L L L L L L
OMAR ALVAREZ Assembly Manager T P P P P P H
- - - - - - -
DAY
VIVEK YADAV P P P P P P H
NARENDRA BABU P P P P P P H
RANJAN KR YADAV P P P P P P H
KOTI P P P P P P H

 
Page 13

 
Project: L&T Chennai Metro 
TBM: XRE 2114 408‐1/ 409‐1 
  Chennai, India 
 
Subject:  Remanufacturing Robbins TBM 
Customer:  Larsen & Toubro 
Date:   Week10‐2023 
 
VARINDER SINGH P P P P P P H
CHAMEL SINGH P P P P P P H
DHANANJAY P P P P P P H
ANTU CHOUDHARY P P P P P P H
RANJAN P P P P P P H
PAPPU KUMAR YADAV P P P P P P H
KAMLESH RAWAT P P P P P P H
NIGHT
GULAM MUSTAFA P P P P P P H
KULDEEP P P P P P P H
SUNENDER SINGH P P P P P P H
VELMURUGAN P P P P P P H
KOTESHWAR RAO P P P P P P H
PARASHURAM MALIK P P P P P P H  
CK GUPTA P P P P P P H

PK GUPTA P P P P P P H
SANTOSH CHOUDHARY P P P P P P H
MAHESHWAR KUMAR P P P P P P H
ARASHADEEP SINGH P P P P P P H
GURPAL SINGH P P P P P P H
KIRAN METLAPALLI P P P P P P H

Unskilled Manpower Required for Week  Unskilled Manpower Actual for Week 

180                                         170 

Report Prepared by Robbins  Report Acknowledged by L&T 

MADHAN P N  AVINASH 

PROJECT MANAGER  Asst. Manager (TBM Electrical) 

 
Page 14