Emergency Action Plan
1. Introduction-
The Emergency Action Plan (EAP) is to aid in handling site emergency in order to minimize injury and
losses. The EAP is only a general plan to follow in case emergencies and alterations can be made,
depending on circumstances of the emergency.
Mandatory Requirement:- Building & Other Construction Workers (regulation of Employment &
Condition of Service) an employer shall ensure at a construction site of building or other construction
work that in building worker are employed at such construction site emergency action plan to handle the
emergencies like –
a) Fire and explosion,
b) Collapse of lifting appliances and transport equipment
c) Collapse of building, sheds or structure, etc.
d) Gas leakage or spillage of dangerous goods or chemicals
e) Drowning of building workers ,sinking of vessels, and
f) Landslides getting building workers buried, floods ,storm and other natural calamities, is prepared
and submitted for the approval of the chief inspector
2. Objective-
In the event of an emergency this plan is designed to initiate a management control procedure to
enable key personnel to effectively manage emergencies and achieve the following objectives
Evacuation of non-essential personnel to a safe area
Account for all personnel on site at that time
Alert emergency services and provide subsequent support
Establish control centres and a communication network
Control the incidents
Liaise with the emergency services to ensure timely & appropriate initiation of the emergency plan
Establish training & update emergency preparedness
Emergency Controller-
2 of 9
Rescue Team Head-
He will reach immediately at affected site after getting the communication. On the basis of severity of
incident he will immediately,
Inform the correct picture of incident to the Emergency Controller & Security Officer at main gate by
telephone / Cell Phone.
Send the messenger about the fire, location & equipment involved immediately.
Cordon off affected area
Try to control the situation with ERT team.
After physical verification along with Site Control, send / communicate the information on “Emergency
under control”.
RESCUE TEAM
The team members shall reach to the incident location after getting the
information. The rescue team will ensure that:
Understand the location of the emergency & locations of emergency exits
The emergency doors are open & accessible to evacuate the Shop Floor Colleagues & guide
the shop floor colleagues to evacuate from the site by safe exits.
The head count is taken and if necessary start the search operation for missing person/s
Every member of team uses the required Personal Protective Equipment while operation is going
on.
Smooth rescue operation by either by the use of Man Lift, Two man lift method or by using the
foldable stretchers available at site Occupational Health Center (OHC) /First Aid Centre
3 of 9
2. Communication System
Communication Structure
Observer
4 of 9
G. Don’t jump from height
H. Don’t run but walk normally
I. Reach the Assembly point –Near Store Area
B) Fall of person
If a person falls from height, the supervisor of that area will immediately call emergency vehicle and
first aider at the same time he call to emergency controller.
After receiving the call, emergency controller communicate to rescue
Team head, team head will call to rescue team member and tell them for reach at location, Emergency
controller also operate the siren and communicate to higher authority
First aider will give first aid to victim
Then the rescue team members will
Move the victim into emergency vehicle.
And send to hospital for further treatment.
Other rescue team member will control the worker and send the worker at assembly point
Security person will look that no one is allowed to go out from site or
No outsider will come inside the site at time of emergency until &
Unless further instruction given to them by safety officer
After clearance from Project manager work will start normally
C) Electrical.
If electrical sock occurs due to electrical short circuit, nearby person/supervisor will Cut –Off the main
supply
Then call Emergency vehicle and first aider at the same time he will call to Emergency
controller .Emergency controller communicate to rescue team head, rescue team head will call to
rescue team member and tell them for reach at Location. Emergency controller also operates the siren
and communicates to higher authority.
First aider will give the CPR to victim & send to hospital
5 of 9
The rescue team will evacuate all persons and guide them to safe place Away from the danger of
electrical hazard.
Security person will look that no one is allowed to go out from site or no outsider will come inside
the site at time of emergency until & unless further instruction given to them by safety officer
Head count will be taken to see if any person is missing.
Work will be resumed after taking permission from senior management .
D) Earth quake
If there will be a earth quake on site any person shall contact to emergency vehicle and first aider and
emergency controller .emergency controller communicate to rescue team head ,team head will call to
rescue team member and tell them for reach at location , emergency controller also operate the siren
and communicate to higher authority
Always observe nearest escape point, staircase wherever you are inside any building and try to reach
nearest assembly point after hearing the sound of siren.
All people from rescue team will move immediately to site and help workers and other staff for safe
evacuation & guide them to move on safe path.
Security person will look that no one is allowed to go out from site or no outsider will come inside the
site at time of emergency until & unless further instruction given to them by safety officer.
Remaining people from rescue team will check the site for any person who is in situation of danger.
Electrician will do de energized all electrical connection as they heard the siren sound for emergency.
Headcount will be done by admin officer (rescue team member) at assembly point
Security person will look that no one is allowed to go out from site or no outsider will come inside the
site at time of emergency until & unless further instruction given to them by safety officer
As all situations are under control after earth quake stop rescue team member will observe the site
and Project Manager will give clearance for start the work
E) Collapse of wall/ structure
If a wall or heavy structure collapses the supervisor in that area will call emergency vehicle and first
aider and emergency controller. Emergency controller communicate to rescue team head, team head
will call to rescue team member and tell them for reach at location . Emergency controller also
operate the siren and communicate to higher authority
Emergency rescue teams will be activated in that area.
Rescue team will rescue the person who is caught in between the debris and assemble all.
First aider will give treatment to victim and send to hospital for further treatment.
Other rescue team member rescue the people at assembly point
Head count will be done at assembly point
After getting clearance of Project Manager, normal work will be start .
F) Snake bite.
If a snake bite occurs to a person, the nearby person /supervisor who will call emergency vehicle and
first aider at the same time he will call to emergency controller .Emergency controller will
communicate to rescue team head ,rescue team head will call to rescue team member and tell them
for reach at Location . Emergency controller also operate the siren and communicate to higher
authority
Emergency rescue team will be activated in that area.
They will assemble all the other persons in emergency assembly area.
First aider will give the first aid treatment & Victim will send to hospital for further treatment
immediately
Security person will look that no one is allowed to go out from site or no outsider will come inside the
site at time of emergency until & unless further instruction given to them by safety officer.
When the emergency is controlled and the situation is handled. Emergency over will be declared by
Project Manager.
All will resume duties as normal after getting clearance of emergency over.
G) Floods
6 of 9
If floods occurs due to heavy rains
All the emergency team in all areas will be activated.
The rescue teams will assemble all the persons in elevated area.
Persons caught in deep waters will be rescued by rescue team with help
Of rope and inflated rubber tubes.
Security person will look that no one is allowed to go out from site or
No outsider will come inside the site at time of emergency until &
Unless further instruction given to them by safety officer
Head count will be taken to see if any person is missing at elevated area
Work will be resumed with permission of senior management only after confirmation of safe
condition
H) Hurricane.
If hurricane occurs due to heavy wind flow emergency will be declared by siren.
The emergency team will be activated in all areas.
The rescue team will evacuate all persons and guide them to a safe place away from the danger of
hurricane & assembled at safe place.
Security person will look that no one is allowed to go out from site or no outsider will come inside the
site at time of emergency until & unless further instruction given to them by safety officer
Clearance will be taken from government agencies.
Work will be resumed after taking permission from senior management.
EMERGENCY VEHICLE:
An exclusive emergency vehicle is available at the site. During in emergency he is trained and
capable of handling the emergency crisis and management.
7 of 9
Emergency Contact Number-
8 of 9
On Site Trained Fire Fighter
Sr. No. Name Contact No.
1 Mr. Shamshad Ahamed (RBIPL) 7007055238
2 Mr. Manish Maurya 6393128478
3 Mr. Sushil Singh 9600566148
4 Mr. Ajay Bhujange 9686912127
5 Mr. Uvais khan 9639703004
Company is Tie-up With Nearest Hospital – Raising Hospital, Malanpur, Gwalior (MP)
Contact Details
_______________________________
_______________________________
_______________________________
9 of 9