Price ajustment per IPC - WORKS

USD/RSD
Base date November 2017 101.2868

Overall Price Total Bills Amount Difference due Difference due


Price adjustment
adjustment Middle Exchange Certified Value of Advance payment certified for which to late indices to late indices Price adjustment
IPC No. PN RSD PN USD amount per
multiplier Rate USD/RSD Works deduction (25% of adjustment index for salary per for salary cumulated
month
(PnUSD)_85% + Contract works applies month cumulated
Pn(RSD)_15% without Services)
IPC 1
Jan-20 1.0925 1.0524 1.0584 105.8184
Feb-20 1.0618 1.0073 1.0155 107.7470
Mar-20 1.0372 0.9967 1.0028 106.1940
Apr-20 1.0036 0.9500 0.9580 108.1625
may-20 0.9925 0.9413 0.9490 107.9096 533,881.00 -133,470.25 400,410.75 -1321.36
average 1.0375 0.9895 0.9967

IPC 2
Jun-20 1.0043 0.9792 0.9830 104.4158
Jul-20 1.0161 1.0030 1.0050 102.8466
aug-20 1.0105 1.0280 1.0254 99.3303 2,880,553.00 -720,138.25 2,160,414.75 9,649.85 8,328.49
average 1.0103 1.0034 1.0045

IPC 3
Sep-20 1.0041 1.0179 1.0158 99.6666
Oct-20 1.0111 1.0224 1.0207 99.9639 7,268,943.00 -1,817,235.75 5,451,707.25 99,493.66 107,822.15
average 1.0076 1.0202 1.0183

IPC 4
Nov-20 1.0059 1.0223 1.0198 99.3768 5,893,626.00 -1,473,406.50 4,420,219.50 87,520.35 195,342.50

IPC 5
Dec-20 1.0203 1.0636 1.0571 96.5635 5,638,005.00 -1,409,501.25 4,228,503.75 241,447.56 436,790.06

IPC 6
Jan-21 1.0245 1.0679 1.0614 96.4909 5,507,962.00 -1,376,990.50 4,130,971.50 253,641.65 690,431.71

IPC 7
Feb-21 1.0331 1.0707 1.0651 97.2091 6,293,213.00 -1,573,303.25 4,719,909.75 307,266.12 997,697.83

IPC 8
Mar-21 1.0587 1.0827 1.0791 98.7471 4,101,912.00 -1,025,478.00 3,076,434.00 243,345.93 1,241,043.76

IPC 9
Apr-21 1.0735 1.1006 1.0965 98.4205
may-21 1.1024 1.1468 1.1401 96.7877 12,525,442.00 -3,131,360.50 9,394,081.50 1,111,319.84 2,352,363.60
average 1.0880 1.1237 1.1183

IPC 10
Jun-21 1.1118 1.1488 1.1433 97.5793 12,872,382.00 -3,218,095.50 9,654,286.50 1,383,459.26 3,735,822.86

IPC 11
Jul-21 1.1260 1.1448 1.1420 99.4312 7,213,971.00 -1,803,492.75 5,410,478.25 768,287.91 4,504,110.77

For Contractor / Za Izvodjaca: Checked by Engeneer / Kontrrolisao: For Engeneer / Za Nadzora:

Shou Jicheng, Contractor's representative Vladimir Muric, Supervision Quantity Surveyor Vladimir M. Petrovic, Supervision Team Leader