a. SAND: in Brick work from Ravi, RCC work 100% Chanab, Plaster work 50 %Chanab and 50% Ravi.
b. Crush from Taxilla (Margalla)
c. Cement Maple leaf, DG Cement, Best Way (Which is easily available in the market).
2. PLINTH
Ground floor Finish level will be + 2’ from the road level porch and side passages level will be + 1’
from the road level.
3. SUPER STRUCTURE
a. 9” thick brick work in super structure of 1st class brick (Awal) masonry (Approximately
Rs.13,000/ 1000 bricks in cement sand mortar ratio (1:5) 4 ½ thick walls will be made with (1:5)
cement mortar.
b. ½” thick cement plaster (1:4) ratio on ceiling, shade, internal and external walls.
4. REINFORCMENT CEMENT CONCRETE (1:2:4)
a. All reinforced cement concrete in, lintels, column, beams, roof slabs, , parapet and shelves shell
be carried out in ratio (1:2:4)
b. Local deformed steel bar 60 grade (Bilal/Model Steel/Afco Steel) shall be used in RCC slab as
per structure drawing and design.
1.75Kg Steel/SQFT 5,000 SQFT Approx.8 Ton.
1
DESTINY BUILDERS
CCA3 First Floor Phase 5 DHA, Lahore Cantt.
0321-9900262
8. SEWERAGE
UPVC 6” Medium dia sewer pipes Popular/Turk Plast shall be used. It shall be connected to
Septic Tank and main Sewer line.
9. SUI GAS
Sui Gas connection shall be available in:
a. Kitchen
b. Drawing Room ( Fireplace)
c. T.V Lounge (Fireplace).
d. Geyser point and Servant Quarter as required.
e. 2 Extra gas point and sanitary point other than mentioned above will not be charged.
a. In case of addition / alteration during the construction in the approved and agreed plan by the
owner, it shall be charged separately according to the market rate. 9’’inch thick wall with
plaster Rs 300/SQ.FT, 4 ½ inch thick wall with plaster @200/SQ.FT and Front elevation
beam structure with steel @750 CFT Will is charged.
b. Actual measurements of covered area shall be measured from Roof at final stage.
2
DESTINY BUILDERS
CCA3 First Floor Phase 5 DHA, Lahore Cantt.
0321-9900262
Period for the completion of Gray Structure bungalow 5 month starting from ________________ and
ending on ______________________.
(a) If plot depth is more than 2 feet from the road level then extra feet in depth will be charged as :
1. For 1 Kanal Rs. 2,00,000 Sqft in depth
(b) Electricity Connection, Copper Piping, Gas Connection, Water connection, Molding and Boring
Expenses will be borne by the house owner.
(c) The owner will provide clean plot. If the plot is not clean then pay the cost of Plot clearance.