RFI 002 - Drainage Specific Drawings and Specification
RFI 002 - Drainage Specific Drawings and Specification
We request confirmation of acceptance for use of the following drawings and standards for the construction of
specific large drainage items including culverts and jacking pipes.
For the following, can you please confirm the drawings noted (which have been approved for a different project)
are acceptable for use for the Bororen to Tannum Sands project:
1. BCC1806x 2.4: Drawing 23250-BC-10 is to MRTS24 07/17 TMR Approved for Different project.
2. BCC2112 x 1.2: Drawing 23443-BC-04 is to MRTS24 07/17 TMR Approved for different project.
3. BCC2112 x 2.4: No Drawing available for MRTS24 07/17. Can you provide confirmation that our supplier
can extrapolate the 1.2L drawing for a 2.4L drawing and if TMR approval is required for this change.
4. BCC3030 x 1.2: Drafting and TMR approval will be required to proceed with construction to be submitted
at a later date.
5. 1800Dn Jacking Pipe: Drawing 23434PP01-0. Please confirm how many units require Bentonite ports
and if drawing is acceptable or if TMR approval is required. Drawing allows for 9,12 and 3 O'clock
positions. (TMR Requirement for pipes 1800Dn and larger is Saltwater cover (20/20))
Drawing 23250-BC-10
Drawing 23443-BC-04
Drawing 23434PP01-0.
Raised by:
Davendra Prasad
Name Signature
REQUEST for INFORMATION
Response to RFI from Administrator:
TECHNICAL SERVICES
BRISBANE, QUEENSLAND