Professional Documents
Culture Documents
05EEE - 2023 - Variable Load On Power System
05EEE - 2023 - Variable Load On Power System
Power
Renewable
Generation Conventional
Energy Based
Methods
1. Connected Load
The Sum of Continuous rating of all the equipments connected
to Electrical Supply System is known as Connected Load.
Load Item Number Wattage / unit Total Watts
lamps 6 60 360
tubes 4 40 160
fans 5 60 300
5A socket 10 100 1000
Power plug 3 1000 3000
CONNECTED LOAD = sum of total wattage 4820 W
TERMS COMMONLY USED IN SYSTEM OPERATION
2. Firm power
• Firm Factor is defined as, the theoretical (imaginary) value of power which
a power plant (Hydro, Thermal etc) is supposed to produce throughout a
year or at all time.
• For Example: In case of hydro power plant with reservoir, the firm power
is that power which a hydro electric plant supplies for 95% of the time.
3. Cold Reserve:
• Defined as the reserve generating capacity which is available for service but is not in operation.
• It is the total available capacity of generating sets in reserve for which the starting up may take
several hours
4. Hot Reserve:
• Defined as the reserve generating capacity which is available in operation but is not in service.
• If we have a hydroelectric generator of rating 100 MVA, but currently supplies only 70 MVA. In
this case we have 30 MVA hot reserve that can be loaded immediately by simply opening the
valve to hydro turbine
TERMS COMMONLY USED IN SYSTEM OPERATION
5. Spinning Reserve:
• Defined as the generating capacity which is connected to bus and is ready
to take load, but is at the moment unloaded
• In certain stations of the system some machines are kept on line but are
kept only partially loaded to meet almost instantaneously any contingency
of loss of a generator feeding the load.
• Load-curve
• load duration curve
• The curve which gives load of a whole day with respect to time (24 Hours) is
daily load curve.
• The monthly load curve can be obtained from the daily load curve of the
month. For this purpose, average values of power over a month at different
times of the day are calculated.
• The yearly load curve is obtained by considering the monthly load curve of
that particular year.
LOAD CURVE
• The area under the daily load curve gives the number
of unit generated in the day.
• When the load elements of a load curve are arranged in the order of
descending magnitudes, the curve thus obtained is called a load
duration curve.
• The load duration curve is obtained from the same data as load curve
but the ordinate representing the maximum load is represented to the
left and the decreasing loads are represented to the right in the
descending order.
LOAD DURATION CURVE
• The area under the load duration curve and the corresponding chronological load
curve is equal and represents total energy delivered by the generating station.
• The load duration curve readily shows the number of hours during which the
given load has prevailed.
TERMS/FACTORS AFFECTING THE COST OF GENERATION
lamps 6 60 360
tubes 4 40 160
fans 5 60 300
5A socket 10 100 1000
Power plug 3 1000 3000
CONNECTED LOAD = sum of total wattage 4820 W
AVERAGE DEMAND/LOAD
• The area under the load curve gives the total energy generated [kWh or units
generated]
• The area under the curve divided by the total numbers of hours gives the
Average load.
• The ratio of the area under the load curve to the total area of
the rectangle in which it is contained gives the load factor.
LOAD FACTOR FROM LOAD CURVE
DIVERSITY FACTOR
• The Ratio of the sum of individual maximum demands to the maximum demand on
power station is known as Diversity Factor
Diversity factor is more than 1 since all individual maximum demands may not
occur simultaneously
Higher the diversity factor, lower the station maximum demand, lower will be the
energy cost
PLANT CAPACITY FACTOR
PLANT CAPACITY FACTOR
• The plant capacity factor is an indication of the reserve capacity of the plant.
• The reserve capacity maintains the reliability of electricity system as it ensures that
there is more supply available than the demand.
• If the system has the capacity which is exactly equal to the demand, there can be
electricity shortage when just one power plant cannot operate as usual or there is a
sudden increasing demand.
PLANT USE FACTOR
• It is the ratio of kWh generated to the product of plant capacity and the
number of hours for which the plant was in operation.