METHOD OF STATEMENT
Marble installation
Table of contents
PURPOSE
SCOPE
RESPONSIBILITY
MANPOWER
METHODS / PROCEDURES
SAFETY PRECAUTION
ATTACHMENT
ELKHOMRA PROJECT
- PURPOSE
The aim of this method statement is to execute the scope of work, provide and maintain an
effective quality control in compliance with standards and good practices at all stages/
activities for Marble work for villa .
- SCOPE
- RESPONSIBILITY
A full and detailed description of roles and responsibilities of all staff is included within
the project quality plan . for the works as covered this method statement , the following
personnel have specific duties
- Shall refer to the QA/QC Department and the HSE Department for advice and
guidance when required.
- Shall ensure that operatives comply with the relevant method statements, Toolbox
Talks and general site briefings.
- MANPOWER
The Civil Supervisor shall control the overall activities at site and he will be directly
reporting to the Site Superintendent. The basic manpower under him shall consist
but not limited to the following:
Lead Pre-Commissioning Engineer
Testing Engineer
Civil Lead Man
Senior Technicians
Technician
Vendor Represented (if need)
QC Engineer / Inspector
Safety Engineer
Company Representative
- Materials :
- METHODS / PROCEDURES
Preparations
1-Sand beds under floor tiles spread and compact it manually to obtain
uniform depth and distribution. Remove stones and foreign materials.
Lightly rinse with water.
Installations:
Trades .3
.a.) Saturate with clean water several Times before placing setting bed
Remove surface water before placing setting bed
b.) Apply mortar setting bed over cement-paste slush coat immediately
after slush coat has been applied. Spread and screed setting bed to
uniform thickness at sub grade elevations required for accurate
.setting of stone to finish grade as indicated
c.) Place stone before initial set of cement occurs. Do not install one tread
until riser of the preceding step has been set and mortar bedding
.suitable hardened
d.) Tamp and beat stone with a wooden block or rubber mallet to obtain
full contact with setting bed and to bring finished surfaces within
.tolerances
f.) Set each unit in a single operation before initial set of mortar, do not
ELKHOMRA PROJECT
Risers .4
a.) Set risers to line proceeding tread, provide top level edge and 25 mm
.clearance between back of riser and face of concrete step riser
b.) Fix temporarily in place with gypsum dots and fill back clearance
with cement and sand grout mixed with sufficient water to obtain
.pourable consistency
Bases .5
a.) Bed marble bases in thick mortar approximately 20-30 mm thick and
. install directly to Concrete walls
.b.) Refer to the plans for the details on indicated drawings
.c.) The exterior and interior corners must be mitered at 45º
d.) Grout joints, including joints with flooring with the same pointing
.mortar used in floors
. f.) During the work , shall be carefully to make a level straight
ELKHOMRA PROJECT
Threshold .6
a.) At locations adjacent to stone flooring, install stone threshold in
.same type of setting bed as abutting stone flooring
b.) Set threshold in thin set, cement mortar at locations
where mortar bed would otherwise be exposed above other
.adjacent flooring
c.) At locations not adjacent to stone flooring, cut back and discard
any setting bed material from the other finish side and leave
.mortar surface uniform with surface of threshold
. d.) During the work , shall be carefully to make a level straight
- SAFETY PRECAUTION