Hela Bojuna - Comparative Statement
Hela Bojuna - Comparative Statement
Amount Amount
Savings
132,700.00
1,747,897.40
1,880,597.40
606,559.42
1.2 Allow Provisional sum for providing a Performance Bond Provisional Sum 33,200.00 - - - - 0% - - 100% 33,200.00
1.4 Allow Provisional sum for third party insurance. Provisional Sum 19,900.00 - - - - 0% - - 100% 19,900.00
1.6 Providing construction management services. Lum Sum 250,000.00 100% 250,000.00 0% - 100% 250,000.00 - - - -
Protecting and safeguarding the works, materials and plants 100% 300,000.00 0%
1.7
against damage, trespass or theft.
Lum Sum 300,000.00 - 100% 300,000.00 - - - -
0%
Earth excavation for wall foundation starting from ground level, to any depth 19.20 28,800.00 13.11
A.4
& disposal of excavated materials as directed. (including steps & ramp base)
m3 6.09 1,500.00 9,135.00 19.20 28,800.00 - - 19,665.00 - -
Filling earth around the foundation voids up to existing ground level with
A.5 gravel or other approved quality spread ,watered & well rammed in 75 mm thick m3 22.51 1,450.00 32,639.50 42.67 61,871.50 - - 42.67 61,871.50 20.16 29,232.00 - -
layers ( excavated earth use )
Filling under floors with imported gravel or other approved quality fill material
A.6 spread watered and well rammed in 75mm thick layers,(Rate to include m3 41.57 3,200.00 133,024.00 177.12 566,799.00 - - 177.12 566,799.00 135.55 433,775.00 - -
compaction with plate vibrator)
Supply & lay 1000 gauge polythene damp proof membrane on foundation &
A.7 filled earth including turning up between concrete floor & plinth wall with 200 m2 127.42 275.00 35,040.50 157.06 43,191.50 - - 157.06 43,191.50 29.64 8,151.00 - -
mm over laps.
Anti termite treatment on excavated foundation & compacted soil under floors
A.8 & 300 mm around the building (should be use approved chemicals in Pesticide m2 196.47 400.00 78,588.00 103.86 41,544.00 - - 103.86 41,544.00 92.61 37,044.00
dept. ) Warranty period 10 years. For food service & dining area building
Total amount of Excavation & earth works carried to summary 384,973.40 816,802.60 - 816,802.60 496,538.00 64,708.80
Total amount of Concrete work carried to summary 1,072,545.50 837,192.98 - 837,192.98 199,937.98 435,290.50
SECTION C - REINFORCEMENT
Note:
Rate shall include the following
a. Rolling margin & waste. Furnishing ,cutting, bending, placing in position,
holding & supporting including temporary fixing supports, space bars,
binding wires. Cleaning & wire brushing, All spacing laps ,tied with G.I
wire as directed
D.2 225mm(9") thick in cement sand 1:5 with wire cut brick m2 83.56 5,450.00 455,402.00 71.48 389,566.00 - - 71.48 389,566.00 12.08 65,836.00
D.3 150 mm thick block work in 1:5 cement mortar. m2 6.93 2,450.00 16,978.50 18.50 45,325.00 - - 18.50 45,325.00 11.57 28,346.50
Total amount of Brick work carried to summary 791,076.50 746,531.00 - 746,531.00 28,346.50 72,892.00
Doors
Supplying ,fabricating & installing of Wood finished Aluminium single slashed
100mm Door with 5mm thick glass pans. Rate inclusive of neccesary 4.86 148,230.00
E.1
pasteners,whool felt & hings(unioun or equvelent 102x76x2mm) etc(door
m2 4.86 30,500.00 148,230.00 4.86 148,230.00 - - - -
closers,door locks and door handles paid separetly )
Supply and fixing of 281 lock for steel door- ORIAN TERRA lak steel or 2.00 30,250.00
E.2
equvalant. (warranty period of 1 year.)
Nos 2.00 15,125.00 30,250.00 2.00 30,250.00 - - - -
Windows
Supply & fix W - 3575 x 1650 mm size, Aluminum sliding window with
Aluminum ampli mesh , rubber beading stick with Aluminum members & all 85.20 1,682,700.00 49.81
E.3
necessary accessories complete to the accepted standards. (Refer the detail
m2 35.39 19,750.00 698,952.50 85.20 1,682,700.00 - - 983,747.50
drawing)
Aluminium works carried to summary 877,432.50 1,861,180.00 - 1,861,180.00 983,747.50 -
Zn/Al sheet tile profile colour (thickness 0.47mm based metal thickness
G.1 0.4mm,strength 550Mpa ) Roof on existing frame work including necessary m2 174.62 2,200.00 384,164.00 218.79 481,338.00 - - 218.79 481,338.00 44.17 97,174.00
pasteners as per manufactures specifications
Supply and place in position steel roof truss (WEB) span 7.5-9.0Lm. Complete
with double member exterior and single member interior,10mm gusset plate , - -
G.2
16mm dia. Rag bolts , 10mm base plate welded and application of two coats of
Nos 6.00 125,000.00 750,000.00 - - - - 6.00 750,000.00
anticorrosive paint (Red) and enamal paint as per the drawing given by engineer.
Supply fix Zn/Al ridging (colour ) 0.47mm thick with ncessary bolt and nuts.(Tile 41.80 98,230.00 1.60
G.3
profile)
m 40.20 2,350.00 94,470.00 41.80 98,230.00 - - 3,760.00
Furnishing & fixing 150x65mm (base metal thickness 2mm galvanized C- Purlins 265.24 427,036.40 0.82
G.4
as per manufactures specifications.
m 264.42 1610.00 425,716.20 265.24 427,036.40 - - 1,320.20
G.5 Furnishing and laying 3mm thick double side Aluminium foil. m2 174.62 240.00 41,908.80 218.79 52,509.60 - - 218.79 52,509.60 44.17 10,600.80
Supply and fixing Zn/ Al valance board (colour) thickness 0.47mm with necessary 64.00 83,200.00
G.6
bolt and nut.
m 64.00 1,300.00 83,200.00 64.00 83,200.00 - - - -
Supply and fixing Zn/ Al eave gutter (colour) size 130x145mm ,thickness 64.00 128,000.00
G.7
0.47mm with necessary bolt and nut.
m 64.00 2,000.00 128,000.00 64.00 128,000.00 - - - -
Supply and fixing Zn/ Al down pipes (colour) size 100x100mm ,thickness 31.80 50,721.00 18.38
G.8
0.47mm to wall with necessary bracket clips.
m 13.42 1,595.00 21,404.90 31.80 50,721.00 - - 29,316.10
Supply and fixing 65x65x6mm Angle Iron purlin to roof work with 10mm dia.
G.9 Bolt and nuts weld including of two coat of anticorosive paint(Red) and enamal m 75.33 1,810.00 136,347.30 226.00 409,060.00 - - 226.00 409,060.00 150.67 272,712.70
paint as per the engineer instructions.
Roof work carried to summary 2,065,211.20 1,730,095.00 - 1,730,095.00 414,883.80 750,000.00
c. Solder, rivets, screws, nails, clips, brackets, running sockets, straps etc.
H.4.2 Furnish & install 100 mm dia. PVC vent pipe. nos 1.00 2,150.00 2,150.00 1.00 2,150.00 - - 1.00 2,150.00 - -
Construction of manhole with internal dimension 450x450x600 mm
deep ,150mm thick 1:3:6(40mm) concrete bed , 225 mm thick work in 1:5
ct.sand,12mm thick cement sand rendering in 1:2 with forming cannels and 75mm 3.00 49,500.00
H.4.3
thick thick removable concrete cover in 1:2:4 (20) concrete reinforced with R6 @
nos 3.00 16,500.00 49,500.00 3.00 49,500.00 - - - -
75 mm c/c both ways & plastered all exposed surfaces with 1:3 cement ,sand
mix.
H.5 Water supply system for connecting to the public main supply. Allow
Allow Provisional Sum 50,000.00 -
Total amount of Plumbing & Sanitary installation carried to summary 434,480.00 363,100.00 - 363,100.00 15,030.00 36,410.00
d. If the tendered finds that certain items are not included in the BOQ but
are required as per good engineering practices & for good performance of
the installation ,such item shall be clearly described & included in the BOQ
a. All temporary rules , screed grouts etc., for racking out joints of new
brick or concrete for key joints between different surface etc., & making
good around pipes, sanitary fittings and similar fixtures, forming arises &
stopping against joining work ,metal work etc., notching & other sundries ,
thickness of rendering bedding etc., All normal cutting arises ,rounded edges,
bedding & painting, given in the description of items are the optimum
thickness required , deduction for openings more than 0.5 m2 will be made
Floor finishes
Supply & lay 600x600mm Matt Homogenious porcelain floor tile, Engineer
approved size, quality & colour , paving on 1:2 ct,sand mortar screed & fill 124.52 927,674.00
K.1
groove with grout to match the tile including silver beading in floor of Stall ,
m2 126.42 7,450.00 941,829.00 124.52 927,674.00 - - 1.90 14,155.00
Food Service & Dining Area
Rendering cement 12mm, in 1:5 cement and sand on existing concrete, finished 9.39 7,605.90
K.2
rough in floor Ramp
m2 15.30 810.00 12,393.00 9.39 7,605.90 - - 5.91 4,787.10
Wall finishes -
16 mm thick cement plastering with 1:3 mix, finished semi rough in external & 32.72 24,540.00 23.18
K.3
internal walls.
m2 9.54 750.00 7,155.00 32.72 24,540.00 - - 17,385.00
Supply & lay tile glazed size 300x600 mm Sri lankan made of approved type and
K.4 colour with all specials supplied and fixed to wall including racking plaster and m2 27.71 6,550.00 181,500.50 26.00 170,300.00 - - 26.00 170,300.00 1.71 11,200.50
bedding in cement motor 1:2 with steel tile beading on top and edges ground floor.
20 mm thick plinth plaster in 1:3 cement sand mortar finished smooth with
K.5 m2 8.65 1,200.00 10,380.00 39.54 47,448.00 - - 39.54 47,448.00 30.89 37,068.00 -
neat cement to match the floor.
Terrazzo, wall lining with pre cast walling slabs 37.5mm thick supplying and - -
K.6
fixing to complete.
m 2
50.07 4,250.00 212,797.50 - - - - 50.07 212,797.50
Total amount of Floor & wall finishes carried to summary 1,366,055.00 1,177,567.90 - 1,177,567.90 54,453.00 242,940.10
225mm width surface drain joining to the existing ramp with 75mm thick 1:21/2:5
(25mm) concrete base,side wall of 112mm brick work in 1:5 cement sand 31.05 91,597.50 0.02
N.2
rendering in 1:5 match to existing floor/ramp complete with expansion joints and
m 31.03 2,950.00 91,538.50 31.05 91,597.50 - - 59.00
necessary excavation.
Total amount of Interlocking works carried to summary 839,012.50 839,071.50 - 839,071.50 59.00 -
Total Amount 8,416,194.30 9,020,203.72 85,250.00 9,105,453.72 2,487,156.82 1,747,897.40
Earth works
Excavate vegetable top soil for 1.0 m away from external walls
A.2 total area, Average 150 mm depth & disposal of excavated
materials as directed.
B.2 75 mm thick ct. concrete in floor including steps & ramp area .
SECTION C - REINFORCEMENT
C.1 Column foundation & shaft
(a). Tor steel
Qty as per bar schedule
Columns 610.65
Plinth Beam 294.73
Roof Beam 361.50
1266.88 kg
D.2 225mm(9") thick in cement sand 1:5 with wire cut brick
1/A-F 5 3.58 3.73 66.60
Window - W1 (5) 3.58 1.65 (29.49)
Lintel (5) 3.58 0.15 (2.68)
Roof beam (5) 3.58 0.23 (4.02)
2/A-F 5 3.58 0.90 16.09
A,F/1-2 2 2.78 3.73 20.68
Door -D1 (2) 0.90 2.70 (4.86)
Lintel (2) 2.78 0.15 (0.83)
Roof beam (2) 2.78 0.23 (1.25)
Gabel wall 2 1 6.82 1.65 11.25
Total Qty 71.48 m2
Supply and fixing of 281 lock for steel door- ORIAN TERRA lak
E.2
steel or equvalant. (warranty period of 1 year.)
2 2.00 Nos
Total Qty
2.00 Nos
Windows
Supply and place in position steel roof truss (WEB) span 7.5-
9.0Lm. Complete with double member exterior and single
member interior,10mm gusset plate , 16mm dia. Rag bolts ,
G.2 Nos
10mm base plate welded and application of two coats of
anticorrosive paint (Red) and enamal paint as per the drawing
given by engineer.
G.5 Furnishing and laying 3mm thick double side Aluminium foil.
Supply & laying UPVC pipe type 1000 with all necessary
H.1
bends, sockets & tees including excavation & backfilling
Furnish & install 20 mm dia type 1000 . PVC pipe line for
H.1.1 internal water service including all necessary bends, sockets &
tees
10.00 m
10.00 m
Total Qty
Furnish & install 25 mm dia type 1000 . PVC pipe line for
H.1.2 internal water service including all necessary bends, sockets & 50.00 m
tees
Furnish & install 63 mm dia. Type 400, PVC pipe line for waste
H.3.1
water including all necessary bends, sockets, tees
10.00 m
Furnish & install 110 mm dia. Type 400, PVC pipe line for waste
H.3.2
water including all necessary bends, sockets, tees
30.00 m
Total Qty
7.00 nos.
H.4.2 Furnish & install 100 mm dia. PVC vent pipe. 1.00 nos
3.00 nos
Total Qty
waste water pit with internal dia. 1200mm and depth 1500mm, all
complete including excavation, ring beam with 4 Nos. 10mm
H.4.4 bars & 6mm dia. Stirrups at 200mm spacing at bottom of wall, 1.00 nos
225mm brick work and 75mm thick cover slab with 12mm bars
in 150mm c/c both way. (Refer the detail drawing )
Total Qty
1.00 nos
Lights
Supply & install pendent lamp with LED , 9W bulb ,
( Osram ,Philips or equivalent type) lamp shade , including
J.2 housing ,prismatic diffuser with concealed /semi concealed type 13.00 nos.
wiring connection to main circuit with switches complete in
all respect with guarantee certificate.
Total Qty 13.00 nos.
J.7 Electrical service conecting charge from CEB to building 100% Allow
Wall finishes
16 mm thick cement plastering with 1:3 mix, finished semi
K.3 m2
rough in external & internal walls.
B/1-2 2 2.78 3.50 19.43
Support walls for vanity table 2/B-F 2 8 0.40 0.83 5.28
2 4 0.15 0.83 0.99
3 2 1.16 0.83 5.74
3 0.15 0.83 0.37
2/A-B 2 0.40 0.83 0.66
2 0.15 0.83 0.25
32.72 m2
Supply & lay tile glazed size 300x600 mm Sri lankan made of
approved type and colour with all specials supplied and fixed to
K.4 m2
wall including racking plaster and bedding in cement motor 1:2
with steel tile beading on top and edges ground floor.
Terrazzo, wall lining with pre cast walling slabs 37.5mm thick
K.6 m2
supplying and fixing to complete.
Column
A,F/1-3 T12 18 14 252 1.100 1.10 277.20 A
footings
Column Shaft
From Footing A,F/1-3 T12 18 4 72 5.251 0.450 5.70 410.47 A
to Roof Beam
A C
22
REINFORCEMENT BAR SCHEDULE
BAR SCHEDULE REF : 02 Construction of proposed Hela Bojun Hala at Thammannawa Tank, Thalawa, Anuradhapura
Member Location Type & Size No of No. of Bars in Total No Shape Code A B C D E/R Length of Total Length Bar Shape
Bar Mark Members each each bar
(m) (m) (m) (m) (m)
B
A C
Stirrups R6 3 153 459 0.175 0.175 0.120 0.82 376.38
B
A C
Stirrups R6 3 52 156 0.175 0.175 0.120 0.82 127.92
B
B
A C
Stirrups R6 1 32 32 0.175 0.175 0.120 0.82 26.24
B
DESCRIPTION PREPARED BY CHECKED BY APPROVED BY SUMMARY OF TOTAL USAGE
Siganature
Name B.A.S.C. Jayathilake Bar Type & Size R6 T8 T10 T12 T16 T20 T25
Designation TA(QS) Total Length (m) 530.54 - 331.90
Date Total Weight (Kg) 117.78 - - 294.73 - - -
Remarks Total Weight (MT)
23
REINFORCEMENT BAR SCHEDULE
BAR SCHEDULE REF : 03 Construction of proposed Hela Bojun Hala at Thammannawa Tank, Thalawa, Anuradhapura
Member Location Type & Size No of No. of Bars in Total No Shape Code A B C D E/R Length of Total Length Bar Shape
Bar Mark Members each each bar
(m) (m) (m) (m) (m)
B
A C
Stirrups R6 3 129 387 0.175 0.250 0.120 0.97 375.39
B
A C
Stirrups R6 6 47 282 0.175 0.250 0.120 0.97 273.54
B
DESCRIPTION PREPARED BY CHECKED BY APPROVED BY SUMMARY OF TOTAL USAGE
Siganature
Name B.A.S.C. Jayathilake Bar Type & Size R6 T8 T10 T12 T16 T20 T25
Designation TA(QS) Total Length (m) 648.93 - 407.10
Date Total Weight (Kg) 144.06 - - 361.50 - - -
Remarks Total Weight (MT)
24
RC
ape
T30
25
RC
ape
T30
26
RC
ape
T30
27