Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 40

RENCANA ANGGARAN PELAKSANAAN (RAP)

PT. PERMATA TIMUR LESTARI 2


DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH

CIVIL WORKS
SUMMARY
HARGA SUBKON
NO. DESCRIPTION QTY UNIT AMOUNT
(Rp.)
A MILL BUILDING - Civil & Steel Structure
- Foundations 59.00 ttk 30,190,000.00
- Steel Structure 160,667.16 Kg -
- Roofing 6,035.15 m2 -
- Cladding 3,456.00 m2 -
- Wall power house and clarification station 168.00 m2 38,998,000.00
- Floor Ceramic power house and clarification station 636.54 m2 38,192,000.00
- Jalur Tamu 426.00 m 6,390,000.00
- Wall boier station 105.40 m2 19,545,000.00
- Floor 3,907.50 m2 252,229,000.00
- Perimeter Drain --> Include Washing Process Drain 326.00 m 65,631,000.00
- Roofing Over Loading Ramp Platform → full cover 1,188.00 m2 22,119,000.00

B MACHINERY FOUNDATIONS
- FOUNDATIONS - EMPTY BUNCH CONVEYOR → Include bak sampah 1.00 ls 9,018,000.00
- FOUNDATIONS - FFB CONV AT LOADING RAMP → Include bak sampah 1.00 ls 10,269,000.00
- FOUNDATIONS - STERILISER STATION 1.00 ls 28,658,000.00
- FOUNDATIONS - TRESSHING , PRESSING , AND CLARIFICATION STATIONS 1.00 ls 109,581,000.00
- FOUNDATION EFB PRESS 1.00 ls 8,032,000.00
- FOUNDATIONS - POWER HOUSE FDT 1.00 ls 44,083,000.00
- FOUNDATIONS - DEPERICARFER AND KERNEL RECOVERY STATION 1.00 ls 40,977,000.00
- SHELL DISPOSAL YARD ( 23 M X 24 M ) 552.00 m2 110,306,000.00
- FIBER AREA (15 M x 24 M) 360.00 ls 44,422,000.00
- FOUNDATIONS - PIT FOR BOILER FUEL RYCYCLING ELEVATOR AT BOILER STATION 1.00 ls 7,798,000.00
- FOUNDATIONS - BOILER FEED WATER TREATMENT PLANT FDT AT BOILER STATION 1.00 ls 23,346,000.00
- FOUNDATIONS - BAK ABU BOILER AT BOILER AREA 1.00 ls 9,525,000.00
- FOUNDATIONS - RAW WATER TREATMENT PLANT → Include domestic tank housing 1.00 ls 61,587,000.00
- FOUNDATIONS - BLOWDOWN SILENCER , CONDENSAT PIT , HEAVY DAN WASHING PIT 1.00 ls 89,846,000.00
- FOUNDATIONS - OIL STORAGE TANK FDT 1500 T ( 2 UNIT ) 1.00 ls 194,919,000.00
- FOUNDATIONS - TECHNICAL OIL TANK 500 TON ( 1 UNIT ) 1.00 ls 52,396,000.00
- FOUNDATIONS - WEIGHBRIDGE FDT ( 2 UNIT ) Hercules ls 13,560,000.00
- FOUNDATIONS - BUNKER KERNEL SILO FDT ( 1 UNIT ) 1.00 ls 15,149,000.00
- CABLE TRENCH 1.00 ls 77,550,000.00
- SUPPORT FOR PUMP , PIPE AND CONVEYOR → Inc. pondasi mesin workshop 1.00 ls 23,054,000.00
- BOILER FOUNDATION ( DESAIN MECH ) 1.00 ls 66,915,000.00
- PERKUATAN PONDASI DENGAN STRAUSS PILE Dia 25cm 1.00 ls 34,440,000.00

C ANCILLARY BUILDINGS
- Mill Workshop & Store (Uk. 14.00 M x 26.00 M) + INCLUDE Rak Baja Siku 1.00 unit 159,745,000.00
- Weighbridge House - Roof 12 M x 13 M (Uk. 3.00 M x 4.00 M) 1.00 unit 16,170,000.00
- Oil Loading Shed (Uk. 4.0 M x 9.0 M) 1.00 unit 1,276,000.00
- Bicycle Shed (Uk. 3.0 M x 10.0 M) 1.00 unit 2,232,000.00
- Shelter SPSI ( Uk 3.0 M x 5.0 M ) 1.00 unit 1,320,000.00

D OTHER CIVIL WORKS


1 INTERNAL CONCRETE ROAD 8,822.00 m² 1,947,522,000.00
2 INTERNAL DRAINAGE & OUTLET 1,620.28 m 240,524,000.00
3 IPAL DOMESTIC ( INCLUDE PIPA IPAL ) 1.00 ls 163,792,000.00
4 GATE AND FENCING 907.20 m' 300,892,000.00
5 FRUIT LOADING RAMP CONCRETE FOUNDATION & PLATFORM 1,217.00 m2 655,555,000.00
7 SLOPE PROTECTION AREA LOADING RAMP (concrete) 625.00 m2 44,752,000.00
8 FOUNDATION FOR CLARIFIER STORAGE TANK (CAP 250 M3 FILTERED) 1.00 nos 24,861,000.00
TOTAL I 5,107,366,000.00

HARGA SUBKON
NO. DESCRIPTION QTY UNIT AMOUNT
(Rp.)
II OUTSIDE FENCE
- Lining effluent Pond 1.00 ls 528,213,000.00
- Drain & overflow for effluent Ponds 621.00 m 101,140,000.00
- Main Drain to Discharge out 1.00 ls 60,000.00

TOTAL II 629,413,000.00
GRAND TOTAL ( I + II ) 5,736,779,000.00
NB :
1. Total Bahan Estimate 5,736,779,000.00
2. Upah Kerja All In (borongan Lumpsump) 1,400,000,000.00
3. Sewa Alat Berat 5 Bulan (all in Include Operator) 525,000,000.00
4. Mobil Mixer 3 Bulan, INCLUDE BBM 180,000,000.00
5. Overhead 5% 610,000,000.00

ESTIMATE CAPITAL EXPENSE 8,451,779,000.00

SPK VALUE 12,200,000,000.00

OVERALL MARGIN 3,748,221,000.00


Note :
- Untuk Estimate Capital Expense (RAP), adalah Fix cost dan tanggung jawab dari pelaksana Lapangan
- Apabila ternyata ada kelebihan dari kalkulasi RAP, akan ditanggung dan dipotongkan dari bagi hasil pelaksana
- Bagi hasil 60 pemodal : 40 Pelaksana
- Waktu pelaksanaan terhitung 7 bulan maksimal dari Perjanjian Pendanaan Awal
- Estimasi Modal tertahan adalah estimasi waktu lama pelaksanaan
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - FOUNDATIONS

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 326.47 m' 1,000.00 326,466.67
2 Excavation 95.38 m³ - -
3 Bakcfill+ compacted 82.60 m³ - -
4 Removal surplus soil 12.78 m³ - -
5 Lean concrete 1:3:5 3.84 m³ 650,000.00 2,492,750.00
6 Construct concrete 1:2:3 (batu pecah) 36.88 m³ 579,200.00 21,358,000.00
7 Fabrication & install steel bar Ø12 mm 2,959.83 kg - -
8 Fabrication & install steel bar D16 mm 1,155.42 kg - -
9 Fabrication & install steel bar Ø8 mm 351.05 kg - -
10 Supply and install formwork 168.15 m² 35,000.00 5,885,250.00
11 Install anchor bolt 25 - 600 247.00 nos -
12 Grouting flat, ±2cm thk, "SIKA" 59.00 nos - -
13 Plastering concrete works 8.56 m² 15,000.00 128,325.00
SUB TOTAL 30,190,791.67
ROUNDED 30,190,000.00

Page 2
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - STEEL STRUCTURE INCLUDE WORKSHOP

NO DESCRIPTION QTY UNIT RATE AMOUNT


WORKSHOP
- WF 300 Rafter 2,642.40 kg BY OTHERS
- WF 300 tiang 3,710.37 kg BY OTHERS
- WF 300 Bendera 440.40 kg BY OTHERS
- WF 300 over hang 275.25 kg BY OTHERS
- WF 300 canopy 2,5 m 458.75 kg BY OTHERS
- CNP 125 atap utama 2,095.73 kg BY OTHERS
- CNP 125 jack roof 785.90 kg BY OTHERS
- CNP 125 canopy 2,5m 609.75 kg BY OTHERS
- CNP 125 cladding 641.37 kg BY OTHERS

MILL BUILDING
- WF 300 Rafter 23,396.25 kg BY OTHERS
- WF 300 tiang 37,793.66 kg BY OTHERS
- WF 300 perkuatan rafter dan tiang 5,725.20 kg BY OTHERS
- WF 300 Bendera 1,548.74 kg BY OTHERS
- WF 300 over hang 1,156.05 kg BY OTHERS
- WF 300 canopy 1,5 m 1,266.15 kg BY OTHERS
- WF 300 canopy 2,5 m 2,064.38 kg BY OTHERS

- WF 150 tie beam 4,759.00 kg BY OTHERS


- CNP 125 atap utama 18,071.18 kg BY OTHERS
- CNP 125 jack roof 2,471.52 kg BY OTHERS
- CNP 125 canopy 4m & 5m 842.36 kg BY OTHERS
- CNP 125 canopy 1,5m 2,240.27 kg BY OTHERS
- CNP 125 canopy 2,5m 3,794.00 kg BY OTHERS
- CNP 125 cladding 13,622.27 kg BY OTHERS
- PIPA 2" untuk bracing 5,212.16 kg BY OTHERS
- UNP 180 untuk cremona 1,092.86 kg BY OTHERS
- UNP 100 jack roof 1,011.60 kg BY OTHERS
- L 80 canopy 4m & 5m 1,083.80 kg BY OTHERS
- L 75 angle clit pada cladding 858.20 kg BY OTHERS
- L 75 cremona 1,033.62 kg BY OTHERS
- L 40 untuk talang 252.55 kg BY OTHERS
- PLAT 20MM base plate 754.19 kg BY OTHERS
- PLAT 12MM sambungan rafter ke rafter 396.49 kg BY OTHERS
- PLAT 12MM sambungan kolom ke rafter 224.10 kg BY OTHERS
- PLAT 12MM sambungan tiang tengah ke rafter 97.50 kg BY OTHERS
- PLAT 12MM sambungan perkuatan rafter & kolom 252.39 kg BY OTHERS
- PLAT 12MM sambungan canopy 342.51 kg BY OTHERS
- PLAT 12MM sambungan over hang 142.43 kg BY OTHERS
- PLAT 12MM sambungan pada tie beam WF150 237.95 kg BY OTHERS
- PLAT 12MM sambungan pada pipa bracing 2" 2,058.80 kg BY OTHERS
- PLAT 12MM sambungan pada cremona 1,145.47 kg BY OTHERS
- PLAT 10MM tapak jack roof 78.90 kg BY OTHERS
- PLAT 10MM gusset plate pada tali angin 282.60 kg BY OTHERS
- PLAT 10MM stiffner rafter 1,723.67 kg BY OTHERS
- PLAT 10MM stiffner tiang 2,040.86 kg BY OTHERS
- PLAT 10MM sambungan tiang > 12m 2,035.50 kg BY OTHERS
- PLAT 10MM sambungan Rafter > 12m 552.00 kg BY OTHERS
- PLAT 10MM segitiga pada base plate 54.30 kg BY OTHERS
- PLAT 8MM stiffner jack roof 91.04 kg BY OTHERS
- PLAT 8MM segitiga pada sambungan 475.27 kg BY OTHERS
- PLAT 8MM pada perkuatan rafter & kolom 1,096.77 kg BY OTHERS
- PLAT 6MM tupai tupai 1,843.26 kg BY OTHERS
- Sagrot 12mm atap utama 1,498.45 kg BY OTHERS
- Sagrot 12mm cladding 210.08 kg BY OTHERS
- Sagrot 12mm atap jack roof 398.26 kg BY OTHERS
- Sagrot 12mm canopy 1,5 dan 2,5m 84.24 kg BY OTHERS
- Sagrot 12mm canopy 4m & 5m 1,360.80 kg BY OTHERS
- Tali angin 16mm 233.58 kg BY OTHERS
-
- T Buckle 16mm 72.00 set - include
- Talang horizontal seng plate 0,4 mm 36.00 m BY OTHERS
- Talang vertical PVC 6"/8" + accessories 102.00 m BY OTHERS

Page 3
SUB TOTAL -
ROUNDED -

Page 4
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - ROOFING

NO DESCRIPTION QTY UNIT RATE AMOUNT


TOTAL 6,035.15 m²
1 Roofing Sheets AluZinc 0.45 mm atap utama 4,181.57 m² BY OTHERS
2 Roofing Sheets AluZinc 0.45 mm jack roof 572.08 m² BY OTHERS
3 Roofing Sheets AluZinc 0.45 mm canopy 1,5m 378.80 m² BY OTHERS
4 Roofing Sheets AluZinc 0.45 mm canopy 2,5m 696.90 m² BY OTHERS
5 Roofing Sheets AluZinc 0.45 mm canopy 4m & 5m 205.80 m² BY OTHERS
6 Ridge Capping Aluzinc 0.45 mm atap utama 58.00 m' BY OTHERS
7 Ridge Capping Aluzinc 0.45 mm jack roof 91.20 m' BY OTHERS
8 Ridge Capping Aluzinc 0.45 mm canopy 1,5m 20.00 m' BY OTHERS
9 Ridge Capping Aluzinc 0.45 mm canopy 2,5m 36.00 m' BY OTHERS

SUB TOTAL -
ROUNDED -

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - CLADDING

NO DESCRIPTION QTY UNIT RATE AMOUNT


3,456.00 m²
BANGUNAN STERILISIER & TRESSING STATION
1 Cladding Sheets Aluzinc 0.35 mm thick 3,094.00 m² BY OTHERS
2 Cladding Sheets Fiber /transparant 362.00 m² BY OTHERS
3 Flashing Aluzinc 0.35 mm sudut bangunan 132.40 m' BY OTHERS
4 Flashing Aluzinc 0.35 mm sudut canopy 1,5m 232.00 m' BY OTHERS
5 Flashing Aluzinc 0.35 mm sudut canopy 2,5m 252.00 m' BY OTHERS
6 Flashing Aluzinc 0.35 mm sudut canopy 5m 34.00 m' BY OTHERS
SUB TOTAL -
ROUNDED -
Power House & Clarification Station
1 Wall
- Excavation for ground beam (25/40) 10.58 m³ - -
- Removal surplus soil 10.58 m³ - -
- Formwork 90.84 m² 35,000.00 3,179,400.00
- Lean concrete 1.18 m² 650,000.00 763,750.00
- Concrete 1:2:3 K 175 (batu pecah) 9.81 m³ 579,200.00 5,679,403.52
- Fabrication & install steel bar ø 12 mm 596.30 kg - -
- Fabrication & install steel bar ø 8 mm 326.40 kg - -
- Brickwall 1.5 m & 2,5 m high, 115 mm 159.00 m² 60,000.00 9,540,000.00
- Ceramic tiles for wall , 40 x 40 cm ex. Ikad/equiv 318.00 m² 60,000.00 19,080,000.00
- Brick louvre (area turbine, power house) 9.00 m² 60,000.00 540,000.00
- Wall Painting - emulsion paint (brick louvre) ex. Nippon paint /equip. Ivory 18.00 m² 12,000.00 216,000.00

SUB TOTAL 38,998,553.52


ROUNDED 38,998,000.00

2 Supply & install ceramic tiles, for flooring , 40x40 cm ex. Ikad/equiv 636.54 m² 60,000.00 38,192,292.00
SUB TOTAL 38,192,292.00
ROUNDED 38,192,000.00

4 Jalur tamu warna kuning keramik 10x40 cm 426.00 m 15,000.00 6,390,000.00


SUB TOTAL 6,390,000.00
ROUNDED 6,390,000.00

Wall in Boiler Station


- Excavation for ground beam (30/40) 4.08 m³ - -
- Removal surplus soil 4.08 m³ - -
- Formwork 69.28 m² 35,000.00 2,424,800.00
- Lean concrete 0.56 m² 650,000.00 367,017.86
- Concrete 1:2:3 K 175 (batu pecah) 8.18 m³ 579,200.00 4,737,856.00
- Fabrication & install steel bar ø 12 mm 703.55 kg - -
- Fabrication & install steel bar ø 8 mm 353.85 kg - -
- Brickwall 3 m high , t 230 mm 105.40 m² 60,000.00 6,324,000.00
- Plastering brickwall 210.80 m² 15,000.00 3,162,000.00
- Wall Painting - emulsion paint for brickwall ex. Nippon paint /equip. Ivory 210.80 m² 12,000.00 2,529,600.00
SUB TOTAL 19,545,273.86
ROUNDED 19,545,000.00

SUB TOTAL 103,125,000.00


ROUNDED 103,125,000.00

Page 5
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - FLOOR

NO DESCRIPTION QTY UNIT RATE AMOUNT


TOTAL 3,907.50 m²
BANGUNAN STERILISIER & TRESSING STATION
BANGUNAN OIL ROOM, POWER STATION, BOILER STATION & FIBRE STORAGE STATION
BANGUNAN STERILISIER & TRESSING STATION
1 Sandfill (50 mm thick) 195.38 m³ 120,000.00 23,445,000.00
2 Formwork 70.34 m² 35,000.00 2,461,725.00
3 Concrete 1 : 2 : 3 , K - 175 - batu pecah t. 10 cm+acian 390.75 m³ 579,200.00 226,322,400.00
4 Wiremesh M-6, 1 Layer 3,907.50 m² - -
SUB TOTAL 252,229,125.00
ROUNDED 252,229,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - PERIMETER DRAIN & WASHING DRAIN

NO DESCRIPTION QTY UNIT RATE AMOUNT


DRAIN TYPE B
1 Staking & Pegging 326.00 m' 1,000.00 326,000.00
2 Excavation 92.19 m³ - -
3 Removal surplus soil 92.19 m³ - -
4 Cor 1:3:5 43.65 m³ 650,000.00 28,373,410.00
5 Formwork 358.60 m² 35,000.00 12,551,000.00

WASHING PROCESS DRAIN


1 Staking & Pegging 290.00 m' 1,000.00 290,000.00
2 Excavation 54.72 m³ - -
3 Removal surplus soil 54.72 m³ - -
4 Cor 1:2:3 + acian 31.08 m³ 579,200.00 18,001,536.00
5 Formwork 174.00 m² 35,000.00 6,090,000.00
SUB TOTAL 65,631,946.00
ROUNDED 65,631,000.00

Page 6
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - ROOFING OVER PLATFORM LOADING RAMP

NO DESCRIPTION QTY UNIT RATE AMOUNT


I PEKERJAAN PENDAHULUAN
1 Pemasangan Bouwplank 108.67 m' 1,000.00 108,666.67
2 Galian Tanah 35.00 m³ - -
3 Removal Surplus Soil 15.00 m³ - -
4 Timbunan + Pemadatan 20.00 m³ - -

II PEKERJAAN PONDASI
1 Lean concrete 1:3:5 0.90 m³ 650,000.00 585,000.00
2 Cor K175 13.20 m³ 579,200.00 7,645,440.00
3 Besi Dia 12 mm 593.73 kg - -
4 Besi Dia 16 mm 325.00 kg - -
5 Besi Dia 8 mm 152.77 kg - -
6 Bekisting 54.30 m² 35,000.00 1,900,500.00
7 Pabrikasi Cover Tiang 4 mm, MS Plate 1,000.00 kg BY OTHERS
8 Cover Tiang 4 mm, MS Plate upah rol 1,000.00 kg BY OTHERS

III PEKERJAAN STRUKTUR BAJA


A KOLOM
1 HB350x350x12x19 6,576.00 kg BY OTHERS
2 Base plate, t = 20mm, (4" x 8") 203.33 kg BY OTHERS
3 Plat stiffner base plate, t = 10mm (4" x 8") 32.50 kg BY OTHERS
4 Install Anchor Bolts, Ø25 mm - 600 mm 48.00 nos -
5 Plat stiffner kolom, t = 10mm (4" x 8") 386.67 kg BY OTHERS

B Tie Biem WF
1 WF 150 x 75 x 5 x 7 672.00 kg BY OTHERS
2 Plat Join, t = 12 mm (4" x 8") 41.93 kg BY OTHERS

E RAFTER
1 WF 400 x 200 x8 x 13 12,672.00 kg BY OTHERS
2 Plat Stiffner Span, t = 10mm (4" x 8") 603.33 kg BY OTHERS
3 Plat 12 mm Join Span - Tiang 160.00 kg BY OTHERS
4 Plat 8 mm untuk Pengaku Span - Tiang 70.00 kg BY OTHERS
5 Plat 12 mm Join Tiang - Over Stek 63.33 kg BY OTHERS
6 Plat 12 mm Join Span - Span 160.00 kg BY OTHERS
7 Plat 10 mm untuk Pengaku Span - Span dan kolom 26.67 kg BY OTHERS
8 Plat 8 mm untuk honeycomb dan pengaku kolom over stek 1,093.33 kg BY OTHERS
9 Plat 10 mm, untuk sambungan rafter 713.33 kg BY OTHERS
10 Plat 6 mm, 170.00 kg BY OTHERS

IV PEKERJAAN ATAP
1 CNP 150 x 50 x 20 x 2.3 5,506.20 kg BY OTHERS
2 Sagrod Ø12 mm - + mur 541.38 kg BY OTHERS
3 Ikatan Angin Ø20 mm 616.15 kg BY OTHERS
4 Plat 10 mm thk Ms Gusset, (4" x 8") 159.23 kg BY OTHERS
5 Atap Zincalumn, t = 0.45mm 1,188.00 m² BY OTHERS
6 Rabung, t = 0.45mm 27.00 m' BY OTHERS
7 Baja Siku L 40 x 40 x 4 263.08 kg BY OTHERS
8 Talang Horizontal (Seng Plat 0.4mm, Soft) 54.00 m' 50,000.00 2,700,000.00
9 Talang Vertikal (Pipa PVC 6") 108.00 m' 85,000.00 9,180,000.00
10 Ikatan Angin Ø20mm - 3200mm, untuk pengikat kolom - kolom 346.15 kg BY OTHERS
11 Besi Beton dia 12, untuk sokong pipa 150.00 kg BY OTHERS

SUB TOTAL 22,119,606.67


ROUNDED 22,119,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - EMPTY BUNCH CONVEYOR FDT

NO DESCRIPTION QTY UNIT RATE AMOUNT


EMPTY BUNCH CONVEYOR (EB1, EB2, EB3, EB4, EB8 dan EB10)
1 Staking & pegging 34.00 m' 1,000.00 34,000.00
2 Excavation 4.42 m³ - -
3 Removal surplus soil 4.42 m³ - -
4 Lean concrete- kerikil 0.56 m³ 650,000.00 364,000.00
5 Formwork 43.23 m² 35,000.00 1,513,050.00
6 Concrete 1:2:3 K 175- batu pecah 8.99 m³ 579,200.00 5,207,008.00
7 MS bar 10mm 701.50 kg - -
8 Pocket hole 30.00 nos - -
9 Plaster for concrete work 1.02 m² 15,000.00 15,300.00

BAK SAMPAH
1 Excavation 1.35 m³ - -
2 Removal surplus soil 1.35 m³ - -
3 Formwork 10.00 m² 35,000.00 350,000.00
4 Concrete 1:2:3 K 175- batu pecah 2.65 m³ 579,200.00 1,534,880.00
5 Wiremesh M6 36.80 m² - -
SUB TOTAL 9,018,238.00
ROUNDED 9,018,000.00

Page 7
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - FFB CONV AT LOADING RAMP

NO DESCRIPTION QTY UNIT RATE AMOUNT


CONVEYOR FOUNDATION ( FR1, FR 2, FR3, FR4, FR 5, FR 6)
1 Staking & pegging 56.13 m' 1,000.00 56,127.27
2 Excavation 7.68 m³ - -
3 Backfill 2.95 m³ - -
4 Removal surplus soil 4.73 m³ - -
5 Lean concrete 0.61 m³ 650,000.00 395,761.36
6 Formwork 48.08 m² 35,000.00 1,682,959.09
7 Concrete 1:2:3 K 175- batu pecah 8.29 m³ 579,200.00 4,802,725.71
8 MS bar 10mm 611.75 kg - -
9 MS bar 12mm 49.67 kg - -
10 Ms bar 8mm 20.19 kg - -
11 Pocket hole 28.00 nos - -
12 Plaster for concrete work 5.61 m² 15,000.00 84,190.91

BAK SAMPAH ( 3M x 3 M)
1 Excavation 0.54 m³ - -
2 Removal surplus soil 0.54 m³ - -
3 Formwork 13.73 m² 35,000.00 480,375.00
4 Concrete 1:2:3 K 175- batu pecah 3.10 m³ 579,200.00 1,795,158.00
5 Besi 8mm 90.00 kg - -
6 Besi 6mm 67.50 kg - -
7 Pas Bata 1/2 batu camp 1:4 10.80 m2 60,000.00 648,000.00
8 Plesteran camp 1:4 21.60 m2 15,000.00 324,000.00
9 Wiremesh M6 2 layer 9.00 m² - -
SUB TOTAL 10,269,297.35
ROUNDED 10,269,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - STERILISER FOUNDATION

NO DESCRIPTION QTY UNIT RATE AMOUNT


STERILISIER STATION FOR VERTICAL STERILISER 4.00 unit
1 Staking & pegging 80.00 m' 1,000.00 80,000.00
2 Excavation 41.07 m³ - -
3 Backfill 4.72 m³ - -
4 Removal surplus soil 36.35 m³ - -
5 Lean concrete 2.56 m³ 650,000.00 1,664,000.00
6 Formwork 97.03 m² 35,000.00 3,395,924.53
7 Concrete 1:2:3 K 175- batu pecah 20.00 m³ 579,200.00 11,584,000.00
8 Fabrication & install steel bar ø 10 mm 932.87 kg - -
9 Fabrication & install steel bar ø 8 mm 155.17 Kg - -

Page 8
10 Pocket hole 60.00 nos - -
11 Plastering for concrete works 5.92 m² 15,000.00 88,754.72

CONCRETE TRENCH FOR PIPING


1 Staking & pegging 60.00 m' 1,000.00 60,000.00
2 Excavation 37.60 m³ - -
3 Removal surplus soil 37.60 m³ - -
4 Sandfill 17.20 m³ 120,000.00 2,064,000.00
5 Formwork 47.80 m² 35,000.00 1,673,000.00
6 Concrete 1:2:3 K 175- batu pecah 9.74 m³ 579,200.00 5,643,724.80
7 Concrete 1:3:5 3.70 m³ 650,000.00 2,405,000.00
8 Wiremesh M6 - 1 layer 121.80 m² - -
SUB TOTAL 28,658,404.05
ROUNDED 28,658,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - PRESSING, TRESHING AND CLARIFICATION STATION FDT

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking and pegging 250.00 m 1,000.00 250,000.00
-
THRESSING STATION -
TS1&TS5 16.00 UNIT -
- Excavation 11.20 m³ - -
- Backfill 7.28 m³ - -
- Removal surplus soil 3.92 m³ - -
- Lean concrete 0.80 m³ 650,000.00 520,000.00
- Formwork 30.72 m² 35,000.00 1,075,200.00
- Concrete 1:2:3 K 175- batu pecah 4.99 m³ 579,200.00 2,891,366.40
- Fabrication & install steel bar 10mm 270.93 kg - -
- Fabrication & install steel bar 8mm 60.60 kg - -
- Pocket hole 16.00 nos - -
- Plastering for concrete works 2.56 m² 15,000.00 38,400.00

TS2 1.00 UNIT


- Excavation 0.72 m³ - -
- Removal surplus soil 0.72 m³ - -
- Lean concrete 0.18 m³ 650,000.00 117,000.00
- Formwork 3.36 m² 35,000.00 117,600.00
- Concrete 1:2:3 K 175- batu pecah 1.44 m³ 579,200.00 834,048.00
- Fabrication & install steel bar 10mm 69.84 kg - -
- Plastering for concrete works 0.84 m² 15,000.00 12,600.00
-
TS3 2.00 UNIT -
- Excavation 1.01 m³ - -
- Removal surplus soil 1.01 m³ - -
- Lean concrete 0.11 m³ 650,000.00 72,800.00
- Formwork 5.66 m² 35,000.00 198,100.00
- Concrete 1:2:3 K 175- batu pecah 1.20 m³ 579,200.00 695,040.00
- Fabrication & install steel bar 10mm 57.21 kg - -
- Fabrication & install steel bar 6mm 8.08 kg - -
- Pocket hole 4.00 nos - -
- Plastering for concrete works 0.84 m² 15,000.00 12,600.00
-
TS4 3.00 UNIT -
- Excavation 0.71 m³ - -
- Removal surplus soil 0.71 m³ - -
- Lean concrete 0.08 m³ 650,000.00 51,187.50
- Formwork 5.33 m² 35,000.00 186,375.00
- Concrete 1:2:3 K 175- batu pecah 0.65 m³ 579,200.00 374,018.40
- Fabrication & install steel bar 10mm 40.97 kg - -
- Fabrication & install steel bar 6mm 8.32 kg - -
- Pocket hole 6.00 nos - -
- Plastering for concrete works 0.75 m² 15,000.00 11,250.00
-
P5 7.00 UNIT -
- Excavation 3.09 m³ - -
- Removal surplus soil 3.09 m³ - -
- Lean concrete 0.34 m³ 650,000.00 222,950.00
- Formwork 17.99 m² 35,000.00 629,650.00
- Concrete 1:2:3 K 175- batu pecah 3.68 m³ 579,200.00 2,128,560.00
- Fabrication & install steel bar 10mm 159.96 kg - -
- Fabrication & install steel bar 6mm 23.61 kg - -
- Pocket hole 14.00 nos - -
- Plastering for concrete works 2.66 m² 15,000.00 39,900.00
Page 9
-
PRESSING STATION -
P1&P1a 22.00 UNIT -
- Excavation 25.34 m³ - -
- Backfill 12.67 m³ - -
- Removal surplus soil 12.67 m³ - -
- Lean concrete 1.58 m³ 650,000.00 1,029,600.00
- Formwork 56.32 m² 35,000.00 1,971,200.00
- Concrete 1:2:3 K 175- batu pecah 11.98 m³ 579,200.00 6,936,084.94
- Fabrication & install steel bar 10mm 509.97 kg - -
- Fabrication & install steel bar 8mm 92.59 kg - -
- Pocket hole 22.00 nos - -
- Plastering for concrete works 3.52 m² 15,000.00 52,800.00
-
P2A&B 12.00 UNIT -
- Excavation 5.86 m³ - -
- Removal surplus soil 5.86 m³ - -
- Lean concrete 0.45 m³ 650,000.00 293,085.00
- Formwork 47.28 m² 35,000.00 1,654,800.00
- Concrete 1:2:3 K 175- batu pecah 6.01 m³ 579,200.00 3,482,150.40
- Fabrication & install steel bar 10mm 268.49 kg - -
- Fabrication & install steel bar 6mm 68.18 kg - -
- Plastering for concrete works 11.52 m² 15,000.00 172,800.00
-
P3 22.00 UNIT -
- Excavation 2.99 m³ - -
- Removal surplus soil 2.99 m³ - -
- Lean concrete 0.33 m³ 650,000.00 216,287.50
- Formwork 33.88 m² 35,000.00 1,185,800.00
- Concrete 1:2:3 K 175- batu pecah 4.11 m³ 579,200.00 2,382,828.80
- Fabrication & install steel bar 10mm 226.50 kg - -
- Fabrication & install steel bar 6mm 46.87 kg - -
- Pocket hole 22.00 nos - -
- Plastering for concrete works 9.90 m² 15,000.00 148,500.00
-
P4 - UNIT -
- Excavation - m³ - -
- Backfill - m³ - -
- Removal surplus soil - m³ - -
- Lean concrete - m³ 650,000.00 -
- Formwork - m² 35,000.00 -
- Concrete 1:2:3 K 175- batu pecah - m³ 579,200.00 -
- Fabrication & install steel bar 10mm - kg - -
- Fabrication & install steel bar 8mm - kg - -
- Pocket hole - nos - -
- Plastering for concrete works - m² 15,000.00 -
-
P5 - UNIT -
- Excavation - m³ - -
- Removal surplus soil - m³ - -
- Lean concrete - m³ 650,000.00 -
- Formwork - m² 35,000.00 -
- Concrete 1:2:3 K 175- batu pecah - m³ 579,200.00 -
- Fabrication & install steel bar 10mm - kg - -
- Fabrication & install steel bar 6mm - kg - -
- Plastering for concrete works - m² 15,000.00 -

P6 1.00 UNIT -
- Excavation 3.12 m³ - -
- Removal surplus soil 3.12 m³ - -
- Lean concrete 0.20 m³ 650,000.00 126,750.00
- Formwork 9.31 m² 35,000.00 325,850.00
- Concrete 1:2:3 K 175- batu pecah 3.71 m³ 579,200.00 2,145,936.00
- Fabrication & install steel bar 10mm 70.32 kg - -
- Fabrication & install steel bar 6mm 13.05 kg - -
- Pocket hole - nos - -
- Plastering for concrete works 1.96 m² 15,000.00 29,400.00
-
CLARIFICATION STATION -
C1 1.00 UNIT -
- Excavation 26.97 m³ - -
- Backfill 10.79 m³ - -
- Removal surplus soil 16.18 m³ - -
- Lean concrete 1.42 m³ 650,000.00 922,736.10
- Formwork 33.27 m² 35,000.00 1,164,452.80
- Concrete 1:2:3 K 175- batu pecah 11.62 m³ 579,200.00 6,731,148.47
- Fabrication & install steel bar 16mm 343.50 kg - -
- Fabrication & install steel bar 12mm 118.97 kg - -
Page 10
- Fabrication & install steel bar 10mm 642.11 kg - -
- Fabrication & install steel bar 8mm 45.02 kg - -
- Pocket hole 6.00 nos - -
- Plastering for concrete works 3.82 m² 15,000.00 57,318.30
-
C2 8.00 UNIT -
- Excavation 17.02 m³ - -
- Backfill 8.51 m³ - -
- Removal surplus soil 8.51 m³ - -
- Lean concrete 1.22 m³ 650,000.00 790,400.00
- Formwork 40.08 m² 35,000.00 1,402,800.00
- Concrete 1:2:3 K 175- batu pecah 9.56 m³ 579,200.00 5,539,468.80
- Fabrication & install steel bar 16mm 242.42 kg - -
- Fabrication & install steel bar 10mm 722.54 kg - -
- Fabrication & install steel bar 8mm 113.63 kg - -
- Pocket hole 16.00 nos - -
- Plastering for concrete works 2.88 m² 15,000.00 43,200.00
-
-
C3 4.00 UNIT -
- Excavation 2.11 m³ - -
- Removal surplus soil 2.11 m³ - -
- Lean concrete 0.26 m³ 650,000.00 171,600.00
- Formwork 12.80 m² 35,000.00 448,000.00
- Concrete 1:2:3 K 175- batu pecah 2.46 m³ 579,200.00 1,427,148.80
- Fabrication & install steel bar 10mm 95.68 kg - -
- Fabrication & install steel bar 6mm 18.47 kg - -
- Plastering for concrete works 2.08 m² 15,000.00 31,200.00
-
C4 4.00 UNIT -
- Excavation 4.48 m³ - -
- Backfill 1.34 m³ - -
- Removal surplus soil 3.14 m³ - -
- Lean concrete 0.32 m³ 650,000.00 208,000.00
- Formwork 10.08 m² 35,000.00 352,800.00
- Concrete 1:2:3 K 175- batu pecah 2.30 m³ 579,200.00 1,334,476.80
- Fabrication & install steel bar 10mm 99.96 kg - -
- Fabrication & install steel bar 8mm 12.63 kg - -
- Pocket hole 4.00 nos - -
- Plastering for concrete works 0.64 m² 15,000.00 9,600.00
-
C5 1.00 UNIT -
- Excavation 0.36 m³ - -
- Removal surplus soil 0.36 m³ - -
- Lean concrete 0.09 m³ 650,000.00 59,231.25
- Formwork 2.97 m² 35,000.00 103,950.00
- Concrete 1:2:3 K 175- batu pecah 1.00 m³ 579,200.00 580,575.60
- Fabrication & install steel bar 10mm 42.17 kg - -
- Plastering for concrete works 1.35 m² 15,000.00 20,250.00
-
C6 7.00 UNIT -
- Excavation 34.19 m³ - -
- Removal surplus soil 6.19 m³ - -
- Lean concrete 1.55 m³ 650,000.00 1,010,100.00
- Formwork 117.60 m² 35,000.00 4,116,000.00
- Concrete 1:2:3 K 175- batu pecah 59.67 m³ 579,200.00 34,562,949.12
- Fabrication & install steel bar 10mm 1,398.41 kg - -
- Pocket hole 70.00 nos - -
- Plastering for concrete works 42.00 m² 15,000.00 630,000.00
- Pas 1/2 bata 45.93 m2 60,000.00 2,755,800.00
- Cor 1:2:3 bt pecah + acian 2.40 m3 579,200.00 1,387,321.56
- Earthfill ( ambil dari Excavation C6 ) 28.00 m3 - -
- Sika grouting 42.00 nos - -

C7 (CLARIFICATION TANK) 1.00 UNIT


- Excavation 25.25 m³ - -
- Backfill 9.85 m³ - -
- Removal surplus soil 15.40 m³ - -
- Lean concrete 1.12 m³ 650,000.00 728,000.00
- Formwork 33.27 m² 35,000.00 1,164,450.00
- Concrete 1:2:3 K 175- batu pecah 11.21 m³ 579,200.00 6,492,832.00
- Fabrication & install steel bar 16mm 340.20 kg - -
- Fabrication & install steel bar 12mm 112.60 kg - -
- Fabrication & install steel bar 10mm 638.00 kg - -
- Fabrication & install steel bar 8mm 42.10 kg - -
- Pocket hole 6.00 nos - -
- Plastering for concrete works 3.82 m² 15,000.00 57,318.30

Page 11
TO1 1.00 Unit
- Excavation 2.28 m³ - -
- Removal surplus soil 2.28 m³ - -
- Lean concrete 0.17 m³ 650,000.00 112,510.13
- Formwork 4.29 m² 35,000.00 150,013.50
- Concrete 1:2:3 K 175- batu pecah 2.08 m³ 579,200.00 1,203,062.11
- Fabrication & install steel bar 54.10 kg - -
- Plastering for concrete works 0.66 m² 15,000.00 9,891.00

TO2 1.00 Unit


- Excavation 1.75 m³ - -
- Removal surplus soil 1.75 m³ - -
- Lean concrete 0.15 m³ 650,000.00 96,687.50
- Formwork 4.08 m² 35,000.00 142,800.00
- Concrete 1:2:3 K 175- batu pecah 1.59 m³ 579,200.00 920,638.40
- Fabrication & install steel bar 72.54 kg - -
- Plastering for concrete works 0.68 m² 15,000.00 10,200.00

SUB TOTAL 109,581,448.48


ROUNDED 109,581,000.00

SCOPE : MACHINERY FOUNDATIONS -EFB PRESSING STATION FDT

NO DESCRIPTION QTY UNIT RATE AMOUNT


EMPTY BUNCH PRESS (EP1)
1 Staking & pegging 27.47 m' 1,000.00 27,468.53
2 Excavation 19.94 m³ - -
3 Removal surplus soil 19.94 m³ - -
4 Lean concrete/concrete 1 : 3 : 5 0.99 m³ 650,000.00 644,718.75
5 Supply and install formwork 46.82 m² 35,000.00 1,638,836.96
6 Concrete 1 : 2 : 3 K175 (batu pecah) 7.24 m³ 579,200.00 4,194,493.25
7 MS bar 10mm 466.55 kg - -
8 MS bar 8mm 65.58 kg - -
9 Plastering for concrete 3.54 m² 15,000.00 53,119.57
10 Pocket hole 30.00 nos - -

EMPTY BUNCH CONVEYORS (EB9)


1 Staking & pegging 11.00 m' 1,000.00 11,000.00
2 Excavation 4.18 m³ - -
3 Removal surplus soil 4.18 m³ - -
4 Lean concrete/concrete 1 : 3 : 5 0.22 m³ 650,000.00 143,000.00
6 Supply and install formwork 12.35 m² 35,000.00 432,250.00
7 Concrete 1 : 2 : 3 K175 (batu pecah) 1.51 m³ 579,200.00 874,592.00
8 MS bar 10mm 120.00 kg - -
9 MS bar 8mm 25.00 kg - -
9 Plastering for concrete 0.90 m² 15,000.00 13,500.00
10 Pocket hole 10.00 nos - -

SUB TOTAL 8,032,979.05


ROUNDED 8,032,000.00

Page 12
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - POWER HOUSE FDT

NO DESCRIPTION QTY UNIT RATE AMOUNT


FOUNDATION OF TURBINE KE 1

1 Staking & pegging 22.26 m' 1,000.00 22,260.10


2 Excavation 14.19 m³ - -
3 Removal surplus soil 14.19 m³ - -
4 Sand fill 3.35 m³ 120,000.00 401,918.45
5 lean concrete 0.40 m³ 650,000.00 256,824.75
5 Formwork 18.03 m2 35,000.00 631,218.07
6 Concrete 1:2:3 K 175- batu pecah 11.85 m³ 579,200.00 6,864,354.83
7 MS bar 13mm 484.36 kg - -
8 Pocket Hole 10.00 nos - -
9 Asphalt 0.06 m3 800,000.00 48,000.00
10 Plastering for concrete works 3.20 m2 15,000.00 48,044.71

FOUNDATION OF TURBINE KE 2
1 Staking & pegging 22.26 m' 1,000.00 22,260.10
2 Excavation 14.19 m³ - -
3 Removal surplus soil 14.19 m³ - -
4 Sand fill 3.35 m³ 120,000.00 401,918.45
5 lean concrete 0.40 m³ 650,000.00 256,824.75
5 Formwork 18.03 m2 35,000.00 631,218.07
6 Concrete 1:2:3 K 175- batu pecah 11.85 m³ 579,200.00 6,864,354.83
7 MS bar 13mm 484.36 kg - -
8 Pocket Hole 10.00 nos - -
9 Asphalt 0.06 m3 800,000.00 48,000.00
10 Plastering for concrete works 3.20 m2 15,000.00 48,044.71

FOUNDATION OF GENERATOR 3 UNIT


1 Staking & pegging 28.80 m' 1,000.00 28,800.00
2 Excavation 12.25 m³ - -
3 Removal surplus soil 12.25 m³ - -
4 Sand fill 5.60 m³ 120,000.00 672,000.00
5 lean concrete 0.74 m³ 650,000.00 481,000.00
5 Formwork 30.00 m³ 35,000.00 1,050,000.00
6 Concrete 1:2:3 K 175- batu pecah 16.50 m³ 579,200.00 9,556,800.00
7 MS bar 12mm 600.00 kg - -
8 Pocket Hole 18.00 nos - -
9 Asphalt 0.15 kg 800,000.00 120,000.00
10 Plastering for concrete works 6.00 m2 15,000.00 90,000.00

BVP & BLOWDOWN SILENCER ( PH1, PH2, PH6)


1 Staking & pegging 31.60 m' 1,000.00 31,600.00
2 Excavation 8.79 m³ - -
3 Backfill 0.58 m³ - -
4 Removal surplus soil 8.21 m³ - -
5 lean concrete 0.58 m³ 650,000.00 377,000.00
6 Formwork 38.30 m2 35,000.00 1,340,500.00
7 Concrete 1:2:3 K 175- batu pecah 7.32 m3 579,200.00 4,241,771.20
8 MS bar 16mm 32.20 kg - -
9 MS bar 12mm 173.00 kg - -
10 MS bar 10mm 99.30 kg - -
11 MS bar 8mm 81.00 kg - -
12 Pocket Hole 22.00 nos - -
13 Plastering for concrete works 5.25 m2 15,000.00 78,750.00

DIESEL STORAGE TANK + INCLUDE SKAT DAN DRAIN 1 UNIT


1 Staking & pegging 20.00 m 1,000.00 20,000.00
2 Excavation 6.36 m3 - -
3 Backfill 6.36 m3 - -
4 lean concrete 1.10 m³ 650,000.00 715,000.00
5 Formwork 18.00 m2 35,000.00 630,000.00
6 Concrete 1:2:3 K 175- batu pecah 8.87 m3 579,200.00 5,135,467.53
7 MS bar 6mm 8.00 kg - -
8 MS bar 8mm 53.00 kg - -
9 MS bar 10mm 63.00 kg - -
10 MS bar 12mm 160.00 kg - -

Page 13
11 Brickwall 33.00 m2 60,000.00 1,980,000.00
12 Plastering 66.00 m2 15,000.00 990,000.00
13 Wiremesh M6 - 1 layer 14.92 m2 - -
14 Tangga
Besi Dia 16mm 7.58 kg BY OTHERS
Plat Strip 50 x 6mm 34.15 kg BY OTHERS

TOTAL 44,083,930.54
ROUNDED 44,083,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - DEFERICARFER AND KERNEL RECOVERY STATION

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 118.00 m' 1,000.00 118,000.00
2 Excavation 88.89 m³ - -
3 Backfill 62.23 m³ - -
4 Removal surplus soil 26.67 m³ - -
5 Lean concrete 5.02 m³ 650,000.00 3,263,162.50
6 Formwork 225.86 m² 35,000.00 7,905,023.00
7 Concrete 1:2:3 K 175- batu pecah 50.54 m³ 579,200.00 29,273,710.01
8 MS bar 16MM 545.44 kg - -
9 MS bar 12mm 332.38 kg - -
10 MS bar 10mm 2,068.75 kg - -
11 MS bar 8mm 327.45 kg - -
12 Pocket hole 149.00 nos - -
13 Plastering for concrete works 27.85 m² 15,000.00 417,750.00
14 Fabrikasi Plate t. 6 mm utk cover kolom FB 1,251.00 kg BY OTHERS
15 Upah Roll plat 6mm utk cover kolom FB 1,251.00 kg BY OTHERS

SUB TOTAL 40,977,645.51


ROUNDED 40,977,000.00

SCOPE : MACHINERY FOUNDATIONS - SHELL DISPOSAL YARD 23 M x 24 M

NO DESCRIPTION QTY UNIT RATE AMOUNT


SHELL DISPOSAL YARD
1 Concrete 1 : 2 : 3 K175 (batu pecah-) floor 15 cm 82.80 m³ 579,200.00 47,957,760.00
2 Supply and install formwork 15.00 m² 35,000.00 525,057.14
3 Laterit/Sirtu fill t. 20 cm 110.40 m³ 560,000.00 61,824,000.00
4 Wiremesh M6 552.00 m² - -
SUB TOTAL 110,306,817.14
ROUNDED 110,306,000.00

Page 14
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - FIBER AREA (15 M x 24 M)

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Sand fill 5 cm 18.00 m³ 120,000.00 2,160,000.00
2 Concrete 1 : 2 : 3 K175 (batu pecah) 20 cm 72.00 m³ 579,200.00 41,702,400.00
3 Wiremesh M6 - 2 layer 360.00 m² - -
4 Formwork 16.00 m² 35,000.00 560,000.00

SUB TOTAL 44,422,400.00


ROUNDED 44,422,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - PIT FOR BOILER FUEL RYCYCLING ELEVATOR AT BOILER STATION

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 57.83 m' 1,000.00 57,830.00
2 Excavation 29.39 m³ - -
3 Removal surplus soil 29.39 m³ - -
4 Lean concrete 1.27 m³ 650,000.00 824,346.25
5 Formwork 70.19 m² 35,000.00 2,456,650.00
6 Concrete 1:2:3 K 175- batu pecah 7.70 m³ 579,200.00 4,459,840.00
7 MS bar 12mm 330.24 kg - -
8 Install wiremesh M6 - 1 layer 42.42 m² - -

SUB TOTAL 7,798,666.25


ROUNDED 7,798,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BOILER FEED WATER TREATMENT PLANT FDT AT BOILER AREA

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 69.28 m' 1,000.00 69,280.00
2 Excavation 29.38 m³ - -
3 Backfill 8.60 m³ - -
4 Removal surplus soil 20.78 m³ - -
5 Lean concrete 3.16 m³ 650,000.00 2,056,236.00
6 Formwork 34.80 m² 35,000.00 1,218,140.00
7 Concrete 1:2:3 K 175- batu pecah 34.26 m³ 579,200.00 19,843,160.32
8 Install wiremesh M6 141.34 m² - -
9 Ms Bar 12mm 245.47 kg - -
10 Ms Bar 8mm 20.00 kg - -
11 Pocket Hole 16.00 nos - -
12 Plastering for concrete work 10.67 m² 15,000.00 160,020.00

SUB TOTAL 23,346,836.32


ROUNDED 23,346,000.00

Page 15
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BAK ABU BOILER AT BOILER AREA INCLUDE FLOOR AREA BOILER

NO DESCRIPTION QTY UNIT RATE AMOUNT


BAK ABU BOILER
1 Staking & pegging 19.60 m' 1,000.00 19,600.00
2 Excavation 6.75 m³ - -
3 Backfill 2.46 m³ - -
4 Removal surplus soil 4.29 m³ - -
5 Sand fill 1.11 m³ 120,000.00 133,062.00
6 Lean concrete 1.14 m³ 650,000.00 740,350.00
7 Formwork 28.09 m² 35,000.00 983,132.50
8 Concrete 1:2:3 K 175- batu pecah 7.74 m³ 579,200.00 4,483,876.80
9 MS bar 8mm 392.01 kg - -
10 Plastering concrete works 28.30 m² 15,000.00 424,500.00

DRAIN SAMPING BAK ABU BOILER


1 Staking & pegging 23.00 m 1,000.00 23,000.00
2 Excavation 4.14 m3 - -
3 Removal surplus soil 4.14 m3 - -
4 Lean concrete 2.20 m3 650,000.00 1,430,000.00
5 Formwork 36.80 m2 35,000.00 1,288,000.00

SUB TOTAL 9,525,521.30


ROUNDED 9,525,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - RAW WATER TREATMENT PLANT

NO DESCRIPTION QTY UNIT RATE AMOUNT


FOUNDATIONS FOR :
- Water Clarifier Stump Foundation
- Domestic Water Tank, Untreated Water Tank
- Clarifier Water Storage Tank
- Mill Process Water Storage Tank

1 Staking & pegging 78.00 m' 1,000.00 78,000.00


2 Excavation 98.01 m³ - -
3 Lean Concrete 4.73 m³ 650,000.00 3,074,500.00
4 Removal surplus soil 98.01 m³ - -
5 Sand fill 9.88 m³ 120,000.00 1,185,600.00
6 Formwork 167.60 m² 35,000.00 5,866,000.00
7 Concrete 1:2:3 K 175- batu pecah 44.69 m³ 579,200.00 25,884,448.00
8 MS bar 16mm 540.39 kg - -
9 MS bar 12mm 2,877.00 kg - -
10 MS bar 8mm 304.96 kg - -
11 Pocket Hole 16.00 nos - -
12 Concrete 1:2:3 K 175, for slab batu pecah)+acian 22.63 m³ 579,200.00 13,107,296.00
13 Plaster for concrete work 9.52 m² 15,000.00 142,800.00
14 Wiremesh M6- 1 layer 312.30 m² - -

DRAINAGE
1 Excavation 14.11 m³ - -
2 Removal surplus soil 14.11 m³ - -
3 Sand fill - m³ 120,000.00 -
4 Concrete 1:3:5 2.02 m³ 650,000.00 1,313,000.00
5 Brickwall partition 1:4, 115 mm (ordinary) 43.80 m² 60,000.00 2,628,000.00
6 Plastering for brickwall t.15 mm (1:4) 65.70 m² 15,000.00 985,500.00
7 Concrete 1:2:3 for cover and sump pit- batu pecah 0.56 m³ 579,200.00 325,800.00

PONDASI TANGKI PERUMAHAN


a. Pondasi Domestic water Storage Tank Perum Staff
b. Pondasi Domestic water Storage Tank Perum Karyawan
1 Staking & pegging 39.60 m' 1,000.00 39,600.00
2 Excavation 17.82 m³ - -
3 Lean Concrete 0.80 m³ 650,000.00 520,000.00
4 Removal surplus soil 17.82 m³ - -
5 Sand fill 0.80 m³ 120,000.00 96,000.00
6 Formwork 47.04 m² 35,000.00 1,646,400.00
7 Concrete 1:2:3 K 175- batu pecah 4.72 m³ 579,200.00 2,733,824.00
8 MS bar 12mm 696.68 kg - -
Page 16
9 Pocket Hole 16.00 nos - -
10 Concrete 1:2:3 K 175 (for floor batu pecah+acian) 3.36 m³ 579,200.00 1,946,112.00
11 Plaster for concrete work 0.96 m² 15,000.00 14,400.00

SUB TOTAL 61,587,280.00


ROUNDED 61,587,000.00

Page 17
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BLOWDOWN SILENCER , CONDENSAT PIT , HEAVY DAN WASHING PIT

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 86.70 m' 1,000.00 86,700.00
2 Excavation 257.50 m³ - -
3 Removal surplus soil 257.50 m³ - -
4 Lean concrete 5.49 m³ 650,000.00 3,571,425.00
5 Formwork 448.00 m² 35,000.00 15,680,000.00
6 Concrete 1:2:3 K 175- batu pecah 101.00 m³ 579,200.00 58,499,200.00
7 MS bar 10mm 400.00 kg - -
8 Install wiremesh M-6 533.00 m² - -
9 Pocket Hole 16.00 nos - -
10 Pas 1/2 bata camp 1:4 2.25 m2 60,000.00 135,000.00
11 Plaster bata 4.50 m2 15,000.00 67,500.00
12 Plastering for concrete works 38.00 m² 15,000.00 570,000.00
13 Railing (pipe dia 1 1/2" & 1 1/4") + painting 45.00 m BY OTHERS
14 Pipa NB 300 Sch 40 170.12 kg BY OTHERS
15 Pipa NB 100 Sch 40 127.50 kg BY OTHERS
16 Plate 8 mm untuk ring plate 75.00 kg BY OTHERS

1 Roofing for Pumh:


- Anchor bolt dia 16mm- 150 mm 64.00 nos BY OTHERS
- Column & Rafter : Pipa BSP dia 2" 350.00 Kg BY OTHERS
- Purlin CNP 125 x 50 x 2,3 350.00 Kg BY OTHERS
- Sagrod MS Bar dia 12 mm 30.00 Kg BY OTHERS
- Plate 8 mm for joint, base and connection 35.00 Kg BY OTHERS
- Plate 6 mm for connection purlin 35.00 Kg BY OTHERS
- Galvalume roofing t. 0,45 mm 77.00 M2 BY OTHERS

DRAINAGE
1 Staking & pegging 54.80 m' 1,000.00 54,800.00
2 Excavation 13.40 m³ - -
3 Removal surplus soil 13.40 m³ - -
4 sand fill 1.55 m3 120,000.00 186,000.00
5 Concrete 1:2:3 K 175- batu pecah 2.00 m³ 579,200.00 1,158,400.00
6 Concrete 1:3:5 1.00 m3 650,000.00 650,000.00
7 Pas 1/2 bata camp 1:4 39.50 m2 60,000.00 2,370,000.00
8 Plesteran camp 1:4 39.50 m2 15,000.00 592,500.00
9 Wiremesh M6 - 1 layer 16.50 m2 - -
10 Formwork 7.50 m² 35,000.00 262,500.00

COLLECTION PIT
1 Staking & pegging 33.60 m 1,000.00 33,600.00
2 Excavation 16.52 m³ - -
3 Removal surplus soil 16.52 m³ - -
4 Sand fill 0.62 m³ 120,000.00 74,520.00
5 Formwork 61.44 m² 35,000.00 2,150,400.00
6 Concrete 1:2:3 K 175 - batu pecah 6.40 m³ 579,200.00 3,704,346.00
7 Wiremesh M6 - 1 layer untuk pit 40.84 m2 - -
8 Wiremesh M6 - 1 layer untuk selasar 2.70 m2 - -

SUB TOTAL 89,846,891.00


ROUNDED 89,846,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - OIL STORAGE TANK FDT 1500 T ( 2 UNIT ) - STANDARD

NO DESCRIPTION QTY UNIT RATE AMOUNT


- Staking & pegging 168.00 m 1,000.00 168,000.00
- Excavation 15.85 m³ - -
- Removal surplus soil 15.85 m³ - -
- Lean concrete - m³ 650,000.00 -
- Sandfill 152.46 m³ 120,000.00 18,295,507.99
- Compacted sirtu 172.43 m³ 560,000.00 96,558,984.03
- Formwork 217.06 m² 35,000.00 7,597,167.20
- Concrete 1:2:3 K 175- batu pecah 32.17 m³ 579,200.00 18,633,549.77
- Concrete 1:2:3/ K175 for floor+ acian , batu pecah 40.00 m³ 579,200.00 23,168,000.00
- Plastering concrete 79.46 m² 15,000.00 1,191,865.50
- MS bar 13mm 3,559.98 kg - -
- Drain dia 50 PVC - 20 cm+ falm fibre 36.00 unit 20,000.00 720,000.00
- Aspalt sand mix 32.33 m³ 800,000.00 25,864,013.58

Page 18
- Wiremesh M6- 1 layer 400.00 m² - -
- Sandfill bawah lantai 20.00 m³ 120,000.00 2,400,000.00
- Formwork floor 9.20 m² 35,000.00 322,000.00

SUB TOTAL 194,919,088.07


ROUNDED 194,919,000.00

Perkuatan dengan sirtu


NO DESCRIPTION QTY UNIT RATE AMOUNT
Tangki 1500 No.1
1 Gali , Buang tanah, dan merapikan tanah buangan - m³ - -
2 Campuran Sirtu 60% dengan Tanah bagus 40% ( diblending )
- Sirtu fill 60% + pemadatan - m³ 560,000.00 -
- timbunan tanah BAGUS 40% + pemadatan - m³ - -

Tangki 1500 No.2


1 Excavation - m³ - -
2 Campuran Sirtu 60% dengan Tanah bagus 40% ( diblending )
- Sirtu fill 60% + pemadatan - m³ 560,000.00 -
- timbunan tanah BAGUS 40% + pemadatan - m³ - -

SUB TOTAL -
ROUNDED -

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - TECHNICAL OIL TANK FDT 500 T ( 1 UNIT ) - STANDARD

NO DESCRIPTION QTY UNIT RATE AMOUNT


- Staking & pegging 48.00 m' 1,000.00 48,000.00
- Excavation 2.83 m³ - -
- Removal surplus soil 2.83 m³ - -
- Sand fill + compacted 11.55 m³ 120,000.00 1,386,011.70
- Compacted sirtu 53.92 m3 560,000.00 30,194,233.72
- Lean concrete - m3 650,000.00 -
- Formwork 65.31 m² 35,000.00 2,285,920.00
- Concrete 1:2:3 K 175- batu pecah 9.61 m³ 579,200.00 5,565,185.28
- Concrete 1:2:3/ K175 for floor+ acian , batu pecah 12.03 m³ 579,200.00 6,970,114.43
- Plastering concrete 28.26 m² 15,000.00 423,900.00
- MS bar 13mm 1,140.67 kg - -
- Drain dia 50 PVC - 20 cm+ falm fibre 11.00 nos 20,000.00 220,000.00
- Aspalt sand mix 5.54 m3 800,000.00 4,431,639.00
- Wiremesh M6- 1 layer 120.34 m2 - -
- Sandfill bawah lantai 6.02 m² 120,000.00 722,042.24
- Formwork floor 4.27 m² 35,000.00 149,415.00

SUB TOTAL 52,396,461.37


ROUNDED 52,396,000.00

Perkuatan dengan sirtu


NO DESCRIPTION QTY UNIT RATE AMOUNT
Tangki TECHNICAL OIL
1 Gali , Buang tanah, dan merapikan tanah buangan - m³ - -
2 Campuran Sirtu 60% dengan Tanah bagus 40% ( diblending )
- Sirtu fill 60% + pemadatan - m³ 560,000.00 -
- timbunan tanah BAGUS 40% + pemadatan - m³ - -

SUB TOTAL -
ROUNDED -

Page 19
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - WEIGHT BRIDGE FDT ( 2 UNIT )

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 104.00 m' 1,000.00 104,000.00
2 Excavation 6.30 m³ - -
3 Bakcfill+ compacted - m³ - -
4 Removal surplus soil 6.30 m³ - -
5 Compacted sand t=5 cm - m³ 120,000.00 -
6 Earthfill + compacted 4.44 m³ - -
7 Lean concrete 1.27 m³ 650,000.00 825,500.00
8 Concrete 1:2:3 K 175- batu pecah (include floor di bawah jembatan) - m³ 579,200.00 -
9 Concrete K 225 17.88 m³ 579,200.00 10,356,096.00
10 Ms bar 13mm 1,175.00 kg - -
11 Ms bar 8mm 97.31 kg - -
12 Wiremesh M6 - 2 layer 24.96 m² - -
13 Install L. 100x100X10 181.44 kg BY OTHERS
14 Supply and install formwork 65.00 m² 35,000.00 2,275,000.00
15 Anchor bolt 12.00 nos - -

SUB TOTAL 13,560,596.00


ROUNDED 13,560,000.00

60 TONNES FFB / HR PALM OIL MILL


PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BUNKER KERNEL SILO FDT ( 1 UNIT )

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 48.00 m' 1,000.00 48,000.00
2 Excavation 45.02 m³ - -
3 Bakcfill+ compacted 31.52 m³ - -
4 Removal surplus soil 13.51 m³ - -
5 Lean concrete 1.84 m³ 650,000.00 1,194,297.00
6 Concrete 1:2:3 K 175- batu pecah include cover column 18.68 m³ 579,200.00 10,820,255.30
7 Concrete 1:2:3 for slab + acian , batu pecah 3.25 m³ 579,200.00 1,882,400.00
8 Fabrications and install steel bar 16mm 986.84 kg - -
9 Fabrications and install steel bar 12mm 674.55 kg - -
10 Fabrications and install steel bar 8mm 40.06 kg - -
9 Supply and install formwork 32.68 m² 35,000.00 1,143,933.00
10 Pocket hole 4.00 nos - -
11 Plastering for concrete works 4.01 m² 15,000.00 60,150.00
12 Cover column with + Plate 6 mm 1,083.00 kg BY OTHERS
13 Upah Roll plat 6mm 1,083.00 kg BY OTHERS

SUB TOTAL 15,149,035.30


ROUNDED 15,149,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - CABLE TRENCH

NO DESCRIPTION QTY UNIT RATE AMOUNT


KABEL TRENCH + SWITCH BOARD
1 Staking & pegging 514.00 m' 1,000.00 514,000.00
2 Excavation 164.00 m³ - -
3 Removal surplus soil 164.00 m³ - -
4 Sand fill 89.00 m³ 120,000.00 10,680,000.00
5 Lean concrete (incld cover) 15.00 m³ 650,000.00 9,750,000.00
6 Formwork 44.50 m² 35,000.00 1,557,500.00
7 Concrete 1:2:3 K 175- batu pecah 38.50 m³ 579,200.00 22,299,200.00
8 Pipa PVC cross jalan 4" 35.00 m 85,000.00 2,975,000.00
9 Bata 1/2 Batu camp 1:4 397.00 m2 60,000.00 23,820,000.00
10 Plesteran camp 1:4 397.00 m2 15,000.00 5,955,000.00
11 Rebar 8MM 380.00 kg - -
SUB TOTAL 77,550,700.00
ROUNDED 77,550,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH

Page 20
SCOPE : MACHINERY FOUNDATIONS - SUPPORT FOR PUMP , PIPE AND CONVEYOR

NO DESCRIPTION QTY UNIT RATE AMOUNT


PIPE SUPPORT, CONVEYOR SUPPORT
1 Staking & pegging 78.10 m' 1,000.00 78,100.00
2 Excavation 23.97 m³ - -
3 Removal surplus soil 23.97 m³ - -
4 Formwork 109.24 m² 35,000.00 3,823,400.00
5 Concrete 1:2:3 K 175- batu pecah 15.71 m³ 579,200.00 9,099,232.00
6 MS bar 10MM 557.14 kg - -

PUMP FOUNDATION
1 Staking & pegging 42.86 m' 1,000.00 42,860.00
2 Excavation 22.10 m³ - -
3 Removal surplus soil 21.05 m³ - -
4 Formwork 52.50 m² 35,000.00 1,837,500.00
5 Concrete 1:2:3 K 175- batu pecah 10.68 m³ 579,200.00 6,186,435.20
6 MS bar 8MM 300.00 kg - -
7 Pocket Hole 12.00 nos - -

PONDASI DI WORKSHOP
a. Pondasi Mesin Bubut
b. Pondasi Mesin Bor
c. Pondasi mesin Press
d. Pondasi mesin Scrap
1 Staking & pegging 19.38 m' 1,000.00 19,382.00
2 Excavation 3.63 m³ - -
3 Removal surplus soil 3.45 m³ - -
4 Formwork 9.44 m² 35,000.00 330,330.00

Page 21
5 Concrete 1:2:3 K 175- batu pecah 2.83 m³ 579,200.00 1,637,398.40
6 MS bar 10MM 268.14 kg - -
7 Pocket Hole 25.00 nos - -
SUB TOTAL 23,054,637.60
ROUNDED 23,054,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BOILER FOUNDATIONS - BOILERMECH

NO DESCRIPTION QTY UNIT RATE AMOUNT


BOILER FDT
- Staking and pegging 46.94 m 1,000.00 46,940.24
- Excavation 44.60 m3 - -
- Removal Surplus soil 44.60 m3 - -
- Lean concrete 2.70 m3 650,000.00 1,755,000.00
- Cor K225 - batu pecah 45.63 m3 579,200.00 26,428,896.00
- MS Bar 16mm 3,455.56 kg - -
- Formwork 36.62 m2 35,000.00 1,281,700.00
- Pocket hole 14.00 nos - -
- Grouting pocket 14.00 nos - -

CHIMNEY
- Staking & pegging 27.20 m' 1,000.00 27,200.00
- Excavation 61.00 m³ - -
- Back Fill 15.26 m³ - -
- Removal surplus soil 45.79 m³ - -
- Lean concrete/concrete 1 : 3 : 5 1.15 m³ 650,000.00 748,800.00
- Supply and install formwork 36.47 m² 35,000.00 1,276,303.46
- Concrete K225- batu pecah 37.59 m³ 579,200.00 21,772,128.00
- MS barD16- ulir 1,537.37 kg - -
- Install Anchor Bolt Ø 1 1/4 x 1500 mm 20.00 nos - -
- Grouting 20.00 nos - -

FOUNDATION OF FEED WATER PUMP 2 UNITS


- Staking & pegging 20.00 m' 1,000.00 20,000.00
- Excavation 1.30 m³ - -
- Removal surplus soil 1.30 m³ - -
- Lean concrete 0.20 m³ 650,000.00 130,000.00
- Formwork 5.60 m² 35,000.00 196,000.00
- Concrete K225- batu pecah 1.70 m³ 579,200.00 984,640.00
- MS bar 12MM 110.00 kg - -
- Pocket hole 6.00 nos - -
- Grouting pocket 6.00 nos - -

ID FAN
- Staking & pegging 12.64 m' 1,000.00 12,640.00
- Excavation 12.50 m³ - -
- Removal surplus soil 12.50 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.68 m³ 650,000.00 442,000.00
- Supply and install formwork 13.50 m² 35,000.00 472,500.00
- Concrete K225- batu pecah 12.24 m³ 579,200.00 7,089,408.00
- MS bar Ø 16 mm - Ulir 650.00 kg - -
- Pocket hole 13.00 nos - -
- Grouting pocket 14.00 nos - -

FUEL FEEDER FAN BASE


- Staking & pegging 6.68 m' 1,000.00
- Excavation 1.07 m³ - -
- Removal surplus soil 1.07 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.09 m³ 650,000.00 57,720.00
- Supply and install formwork 3.33 m² 35,000.00 116,550.00
- Concrete K225- batu pecah 1.07 m³ 579,200.00 617,195.52
- MS bar Ø 16 MM 166.50 kg - -
- Pocket hole 8.00 nos - -
- Grouting pocket 14.00 nos - -

PONDASI FD FAN
- Staking & pegging 7.48 m' 1,000.00 7,479.00
- Excavation 0.75 m³ - -
- Removal surplus soil 0.75 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.07 m³ 650,000.00 45,500.00
- Supply and install formwork 2.88 m² 35,000.00 100,800.00
- Concrete K225- batu pecah 0.84 m³ 579,200.00 486,528.00
- MS bar Ø 16 mm 120.00 kg - -
Pocket hole 4.00 nos - -
- Grouting pocket 4.00 nos - -

PONDASI SECONDARY AIR FAN BASE


- Staking & pegging 6.68 m' 1,000.00 6,682.20
- Excavation 1.07 m³ - -
- Removal surplus soil 1.07 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.09 m³ 650,000.00 57,720.00
- Supply and install formwork 3.33 m² 35,000.00 116,550.00
- Concrete K225- batu pecah 1.07 m³ 579,200.00 617,195.52
- MS bar Ø 16 mm 166.50 kg - -
- Pocket hole 8.00 nos - -
- Grouting pocket 8.00 nos - -

BLOWDOWN PIT
- Staking & pegging 6.00 m' 1,000.00 6,000.00
- Excavation 1.70 m³ - -
- Removal surplus soil 1.70 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.10 m³ 650,000.00 65,000.00
- Supply and install formwork 10.50 m² 35,000.00 367,500.00
- Concrete K225- batu pecah 0.90 m³ 579,200.00 521,280.00
- MS bar Ø 10 mm - Polos 130.00 kg - -

TYPE BS1 FOOTING

Page 22
- Staking & pegging 15.00 m' 1,000.00 15,000.00
- Excavation 1.35 m³ - -
- Back Fill 0.40 m³ - -
- Removal surplus soil 0.95 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.13 m³ 650,000.00 83,200.00
- Supply and install formwork 7.90 m² 35,000.00 276,500.00
- Concrete K225- batu pecah 1.15 m³ 579,200.00 667,238.40
- MS bar Ø 10 mm - Polos 35.00 kg - -
- MS bar Ø 6 mm - Polos 20.00 kg - -
-

SUB TOTAL 66,915,794.34


ROUNDED 66,915,000.00

Page 23
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - PERKUATAN DENGAN STROUSS PILE

NO DESCRIPTION QTY UNIT RATE AMOUNT

1 BUILDING FOUNDATION
- Strauss pile f 25 cm -5 M 7.00 Nos 70,000.00 490,000.00
- Strauss pile f 25 cm -3 M 52.00 Nos 70,000.00 3,640,000.00

2 MACHINARY FOUNDATION
FOUNDATIONS - EMPTY BUNCH CONVEYOR
- Strauss pile f 25 cm -2 M (EP1) 15.00 Nos 70,000.00 1,050,000.00

3 FOUNDATIONS - STERILISER STATION


- Strauss pile f 25 cm -2 M, for S1 16.00 Nos 70,000.00 1,120,000.00
- Strauss pile f 25 cm -2 M, for S2 12.00 Nos 70,000.00 840,000.00

4 FOUNDATIONS - TRESSHING , PRESSING, AND CLARIFICATION STATIONS


- Strauss pile f 25 cm -2 M, For TS1 & TS5 16.00 Nos 70,000.00 1,120,000.00
- Strauss pile f 25 cm -2 M, For P1 18.00 Nos 70,000.00 1,260,000.00
- Strauss pile f 25 cm -2 M, For C7 12.00 Nos 70,000.00 840,000.00
- Strauss pile f 25 cm -2 M, For C1 12.00 Nos 70,000.00 840,000.00
5 FOUNDATIONS - DEPERICARFER AND KERNEL RECOVERY STATION
- Strauss pile f 25 cm -3 M (K3) 9.00 Nos 70,000.00 630,000.00
- Strauss pile f 25 cm -3 M (K1, K1A) 8.00 Nos 70,000.00 560,000.00

6 FOUNDATIONS - RAW WATER TREATMENT PLANT


- Strauss pile f 25 cm -3 M (K3) 24.00 Nos 70,000.00 1,680,000.00

7 FOUNDATIONS - WEIGHBRIDGE FDT ( 2 UNIT )


- Strauss pile f 25 cm -3 M 24.00 Nos 70,000.00 1,680,000.00

8 FOUNDATIONS - BUNKER KERNEL SILO FDT ( 1 UNIT )


- Strauss pile f 25 cm -5 M 18.00 Nos 70,000.00 1,260,000.00

9 FOUNDATIONS - BOILER STATION


- Strauss pile f 25 cm -3 M 70.00 Nos 70,000.00 4,900,000.00
- Strauss pile f 25 cm -2 M- BH1A 1.00 Nos 70,000.00 70,000.00
- Strauss pile f 25 cm -3 M- BH1 4.00 Nos 70,000.00 280,000.00
- Strauss pile f 25 cm -2 M- Boiler Feed Water treatment 15.00 Nos 70,000.00 1,050,000.00
10 LOADING RAMP
- Strauss pile f 25 cm -3 M, for Type -2 62.00 Nos 70,000.00 4,340,000.00
- Strauss pile f 25 cm -3 M, for retaining Wall column 31.00 Nos 70,000.00 2,170,000.00
- Strauss pile f 25 cm -5 M, for balok stopper 31.00 Nos 70,000.00 2,170,000.00
- Strauss pile f 25 cm -5 M, for atap loading ramp 8.00 Nos 70,000.00 560,000.00

12 ANCILLARY BUILDING
a. Workshop
- Strauss pile f 25 cm -3 M 19.00 Nos 70,000.00 1,330,000.00
b. Loading Shed
- Strauss pile f 25 cm -2 M 4.00 Nos 70,000.00 280,000.00
c. Rumah Jembatan Timbang
- Strauss pile f 25 cm -2 M 4.00 Nos 70,000.00 280,000.00

SUB TOTAL 34,440,000.00


ROUNDED 34,440,000.00

Page 24
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - MILL WORKSHOP AND STORE

NO DESCRIPTION QTY UNIT RATE AMOUNT


A CIVIL & FINISHING WORKS
1 Staking & pegging 110.00 m' 1,000.00 110,000.00
2 Excavation 30.15 m³ - -
3 Backfill 10.13 m³ - -
4 Removal surplus soil 20.03 m³ - -
5 Lean concrete 1.71 m³ 650,000.00 1,111,500.00
6 Compacted sand 25.47 m³ 120,000.00 3,056,280.00
7 Formwork 269.82 m² 35,000.00 9,443,708.75
8 Concrete 1:2:3 K 175 ( batu pecah ) 28.00 m³ 579,200.00 16,217,600.00
9 Concretet 1:2:3 + acian ( batu pecah ) 54.10 m3 579,200.00 31,334,720.00
9 MS bar 16mm 255.00 kg - -
10 MS bar 12mm 1,835.00 kg - -
10 MS bar 10mm 1,015.00 kg - -
11 MS bar 8mm 65.00 kg - -
11 MS bar 6mm 420.00 kg - -
10 Install wiremesh M6 -1 layer 541.00 m² - -
11 Brickwall 1:4 608.00 m² 60,000.00 36,480,000.00
12 Plastering for brickwall 1:4 1,216.00 m² 15,000.00 18,240,000.00
Pintu panel kayu Uk 92x201 cm + Jalusi kayu Uk 90x40 cm + kosen kayu + accessories
13 3.00 nos 2,500,000.00 7,500,000.00
complete
Jendela nako 2 lobang @ Uk 60x113 cm + jalusi kayu 2 lobang @ Uk 60x40 cm + kosen
14 3.00 nos 850,000.00 2,550,000.00
kayu J2

Jendela nako 1 lobang @ Uk 60x113 cm + jalusi kayu 1 lobang @ Uk 60x40 cm + kosen


15 4.00 nos 1,200,000.00 4,800,000.00
kayun J1

16 Ceiling triplex /gypsum + frame furing 51.00 m² 75,000.00 3,825,000.00


17 Trim for ceiling (wood) 64.00 m' 7,000.00 448,000.00
18 Anchor bolt 25- 600 52.00 nos -
19 Painting works for brickwall & ceiling ( cat air ) 1,267.00 m² 12,000.00 15,204,000.00
20 Painting works for door & frames ( cat minyak ) 36.25 m² 12,000.00 435,000.00
21 Cable installation 31.00 nos 120,000.00 3,720,000.00
22 Supply & install lamp LED 18 W 17.00 nos 50,000.00 850,000.00
23 Supply & install switch and outlet 18.00 nos 30,000.00 540,000.00
24 Supply & install ceramic tiles for flooring, 40x 40 ex.Ikad/ equiv 51.00 m² 60,000.00 3,060,000.00
25 Supply & install ceramic tiles tempat wudhu 6.75 m² 60,000.00 405,000.00

B. WATER INSTALLATION & SANITASI


- Air bersih pipa PVC 1/2" 3 Titik 1.00 Lot 300,000.00 300,000.00

- Kran air dia 1/2" 3.00 nos 30,000.00 90,000.00


Floor drain stainless steel 1.00 nos 25,000.00 25,000.00

C STEEL WORKS INCLUDE IN MILD BUILDING


1 IWF 300.150.6,5.9 , include in mill building
2 CNP.125.50.20.2,3, include in mill building
2 IWF 150 336.00 kg BY OTHERS
3 UNP.100.50.5 337.20 kg BY OTHERS
4 L.60.60.6 262.60 kg BY OTHERS
5 L75.75.7 31.24 kg BY OTHERS
5 L.50.50.5 1,419.94 kg BY OTHERS
5 Plat strip 5x50 356.82 kg BY OTHERS
6 Plat Ms t. 20 mm base plate 160.73 kg BY OTHERS
7 Plat T=10mm , Ms 558.43 kg BY OTHERS
8 Plat T=12mm , Ms 239.64 kg BY OTHERS
9 Plat T=6mm , Ms 145.19 kg BY OTHERS
10 Besi Beton dia.12mm for sagrod 241.29 kg BY OTHERS
11 Besi Beton dia.16mm utk tali angin 303.02 kg BY OTHERS
12 L40 Rak workshop 435.46 kg BY OTHERS
13 Triplek 9mm Rak workshop 11.71 m2 85,000.00
14 Wiremesh M8 ventilasi 67.00 m² -
15 Expanded mesh 34.08 m2 -
16 Install & Supply roof 758.00 m² BY OTHERS
17 Install & supply cladding 230.00 m² BY OTHERS
18 Install & supply ridge capping 28.00 m' BY OTHERS
19 Install & supply flashing 58.00 m' BY OTHERS
20 Pintu besi + cat minyak
( Ukuran 3,0 M x 3,0 M ) 2.00 set BY OTHERS
SUB TOTAL 159,745,808.75
ROUNDED 159,745,000.00

Page 25
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - WEIGHBRIDGE HOUSE Ukuran 3 x 4 M (bangunan) / 13,2 M x 14,2 M (Atap)

NO DESCRIPTION QTY UNIT RATE AMOUNT


- Staking & pegging 18.00 m 1,000.00 18,000.00
- Excavation 4.84 m³ - -
- Backfill 3.63 m³ - -
- Removal surplus soil 1.21 m³ - -
- Sand fill 0.60 m³ 120,000.00 72,000.00
- Formwork 19.36 m² 35,000.00 677,600.00
- Concrete 1:2:3 K 175 - batu kerikil 1.90 m³ 579,200.00 1,100,480.00
- Concrete 1:2:3 + acian untuk lantai 1.20 m³ 579,200.00 695,040.00
- MS bar 10MM DAN 6MM 164.29 kg - -
- 115 mm thick brickwall partition 54.60 m² 60,000.00 3,275,850.00
- 15 mm plastering for brickwall 109.20 m² 15,000.00 1,637,925.00
- Ceiling Gypsum+ frame furing 12.00 m² 75,000.00 900,000.00
- List plafond 16.00 m 7,000.00 112,000.00
- Fascia (wood) + cat minyak 54.80 m 12,000.00 657,600.00
Pintu Uk 90x210 cm kaca bening 8 mm +ventilasi Uk 90x40 cm + kosen Alm ex. Damai
- abadi/Alexindo, jendela 2 daun@80x105+ventilasi 2@80x40 cm (sesuai gamabar) + 1.00 unit 750,000.00 750,000.00
accessoies PJ1
Jendela kaca mati 3 lobang aluminium ex. Alexindo/Damai Abadi ukuran sesuai gambar
- 2@80x150+ ventilasi 2 @80x40 cm + 1@90x105 cm ventilasi kaca mati 40x90 cm 1.00 unit 750,000.00 750,000.00
+accessories (lihat gambar) J1

Jendela kaca mati 3 lobang aluminium ex. Alexindo/Damai Abadi ukuran sesuai gambar
- 2@115x105+ ventilasi 2 @115x40 cm + 1@120x105 cm ventilasi kaca mati 40x115 cm 2.00 unit 750,000.00 1,500,000.00
+accessories (lihat gambar) J2

- Painting for wall + ceiling: emulsion paint 121.20 m² 12,000.00 1,454,400.00


- Cable installation 8.00 nos 120,000.00 960,000.00
- Supply & install lamp LED 12 W 2.00 nos 50,000.00 100,000.00
- Supply & install lamp LED 9 W 4.00 nos 50,000.00 200,000.00
- Supply & install switch and outlet 3.00 nos 30,000.00 90,000.00
- Fabrication & erection for steel structure :
-.Plat 12mm ,Ms 33.91 kg BY OTHERS -
-.Plat 10mm ,Ms 7.07 kg BY OTHERS -
-.Plat 8mm ,Ms 345.40 kg BY OTHERS -
-.Plat 6mm ,Ms 72.06 kg BY OTHERS -
-.Pipa Hitam dia.8" , Ms 1,020.72 kg BY OTHERS -
-.WF.150.75.5.7 196.00 kg BY OTHERS -
-.L.70.70.6 2,020.08 kg BY OTHERS -
-.L.50.50.5 1,449.78 kg BY OTHERS -
-.CNP.125.50.20.2,3 808.48 kg BY OTHERS -
-.Besi Beton dia.12mm for sagrod 51.13 kg BY OTHERS -
- Anchor bolt dia 19 mm - 400 mm 16.00 nos - -
- Roofing installation (aluzinc sheet t.0,45 mm) 216.10 m² BY OTHERS -
- Ridge capping (aluzinc t.0,45 mm) 42.44 m BY OTHERS -
- Keramik lantai ukuran 40x40 cm ex. Ikad/setara 12.00 m² 60,000.00 720,000.00
- Meja cor , beton 1:2:3 + Wiremesh 1.00 ls 500,000.00 500,000.00

SUB TOTAL 16,170,895.00


ROUNDED 16,170,000.00

Page 26
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - OIL LOADING SHED Ukuran 4M x 9 M

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 28.00 m 1,000.00 28,000.00
2 Excavation 4.75 m³ - -
3 Backfill 3.18 m³ - -
4 Removal surplus soil 1.58 m³ - -
5 Lean concrete 0.22 m³ 650,000.00 140,400.00
6 Formwork 8.50 m² 35,000.00 297,500.00
7 Concrete 1:2:3 K 175 , batu pecah 1.40 m³ 579,200.00 810,880.00
8 MS bar 12mm dan 6mm 115.00 kg - -
9 Fabrication & erection for steel structure
WF250 710.40 kg BY OTHERS
WF200 766.80 kg BY OTHERS
WF150 281.40 kg BY OTHERS
CNP125 298.10 kg BY OTHERS
UNP100 298.80 kg BY OTHERS
UNP125 150.08 kg BY OTHERS
L60 374.83 kg BY OTHERS
L50 362.30 kg BY OTHERS
Besi 12mm cremona 22.60 kg BY OTHERS
Sagrot 12mm 24.86 kg BY OTHERS
Plat bordes 4.5mm 440.00 kg BY OTHERS
Plat 8mm 123.38 kg BY OTHERS
Plat 6mm 19.08 kg BY OTHERS
Plat 12mm 47.77 kg BY OTHERS
Plat 10mm 31.40 kg BY OTHERS
-.Pipa Hitam dia.1 1/4" 144.77 kg BY OTHERS
-.Pipa Hitam dia.1 " 56.87 kg BY OTHERS
10 Anchor bolt dia 19 mm - 400 mm 8.00 nos -
11 Roofing installation (aluzinc sheet t.0,45 mm) 73.04 m2 BY OTHERS
12 Ridge capping (aluzinc t.0,45 mm) 12.00 m BY OTHERS

SUB TOTAL 1,276,780.00


ROUNDED 1,276,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - BYCYCLE SHED

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 21.60 m' 1,000.00 21,600.00
2 Excavation 5.00 m³ - -
3 Bakcfill+ compacted 1.95 m³ - -
4 Removal surplus soil 3.05 m³ - -
5 Compacted sand t=5 cm 1.50 m³ 120,000.00 180,000.00
6 Construct concrete 1:2:3 ( kerikil + acian ) 1.50 m³ 579,200.00 868,800.00
7 Concrete 1:2:3 K 175 1.10 m³ 579,200.00 637,120.00
8 Bekisting 15.00 m2 35,000.00 525,000.00
9 Fabrications and install steel bar 8 , 10 , 6 mm 34.67 kg - -
10 Fabrication & erection for steel structure kg -
Pipa 4" 158.94 kg BY OTHERS
Pipa 3" 75.72 kg BY OTHERS
Plat 12mm 25.43 kg BY OTHERS
Plat 6mm 12.72 kg BY OTHERS
Plat 8mm 5.00 kg BY OTHERS
CNP125 180.67 kg BY OTHERS
Sagrot 12mm 14.91 kg BY OTHERS
Tali anging 16mm 28.41 kg BY OTHERS
11 Anchor bolt D16 - 600 12.00 nos -
12 Roofing installation 43.86 m² BY OTHERS

SUB TOTAL 2,232,520.00


ROUNDED 2,232,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - SHELTER SPSI ( 3 x 5 m )

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 10.00 m' 1,000.00 10,000.00
2 Excavation 2.50 m³ - -
3 Bakcfill+ compacted 0.98 m³ - -
4 Removal surplus soil 1.53 m³ - -
5 Compacted sand t=5 cm 0.75 m³ 120,000.00 90,000.00
6 Construct concrete 1:2:3 ( kerikil + acian ) 0.75 m³ 579,200.00 434,400.00
7 Concrete 1:2:3 K 175 0.55 m³ 579,200.00 318,560.00
8 Bekisting 5.40 m2 35,000.00 189,000.00
9 Fabrications and install steel bar 8 , 10 , 6 mm 23.12 kg - -
10 Fabrication & erection for steel structure - -
Pipa 4" 105.96 kg BY OTHERS

Page 27
Pipa 3" 37.86 kg BY OTHERS
Plat 12mm 12.72 kg BY OTHERS
Plat 6mm 6.36 kg BY OTHERS
Plat 8mm 2.50 kg BY OTHERS
CNP125 108.00 kg BY OTHERS
Sagrot 12mm 7.46 kg BY OTHERS
Tali anging 16mm 14.21 kg BY OTHERS
11 Anchor bolt D16 - 600 8.00 nos -
12 Roofing installation 21.93 m² BY OTHERS

TEMPAT DUDUK
1 Pas 1/2 batu camp 1:4 1.08 m2 60,000.00 64,800.00
2 Plesteran bata/ batako camp 1:4 2.16 m2 15,000.00 32,400.00
3 Cor 1:2:3 ( kerikil ) 7cm 0.14 m3 650,000.00 91,455.00
4 Wiremesh M6 - 1 layer 2.01 m2 - -
5 Formwork 2.56 m2 35,000.00 89,705.00

SUB TOTAL 1,320,320.00


ROUNDED 1,320,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE- OTHER CIVIL WORKS - INTERNAL CONCRETE ROAD

NO DESCRIPTION QTY UNIT RATE AMOUNT


ROADS 8,822.00 m²
CONCRETE ROAD
- From +30 M Gate to Loading Ramp (Type A) 5,949.00 m²
- Others (Type B) 2,873.00 m²

1 Hardcore/ Laterit/Sirtufill (200 mm thick) 1,764.40 m³ 560,000.00 988,064,000.00


2 Formwork 592.00 m² 35,000.00 20,720,000.00
3 Concrete K-175 t.200 mm thick + 30 M gate- LR- batu pecah 1,189.80 m³ 579,200.00 689,132,160.00
4 Concrete K-175 t.150 mm thick other road - batu pecah 430.95 m³ 579,200.00 249,606,240.00
5 Wiremesh M6, 2 layer (+30 M Gate - to L.ramp) 5,949.00 m² - -
6 Wiremesh M6, 1 layer (Others) 2,873.00 m² - -
SUB TOTAL 1,947,522,400.00
ROUNDED 1,947,522,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS - INTERNAL CONCRETE DRAIN & OUTLET

NO DESCRIPTION QTY UNIT RATE AMOUNT


DRAINS
TYPE A
- Staking & pegging 323.00 m' 1,000.00 323,000.00
- Excavation 81.40 m³ - -
- Removal surplus soil 81.40 m³ - -
- Cor 1:3:5 40.12 m³ 650,000.00 26,075,469.47
- Formwork 371.45 m² 35,000.00 13,000,750.00

TYPE A1
- Staking & pegging 6.00 m' 1,000.00 6,000.00
- Excavation 1.44 m³ - -
- Removal surplus soil 1.44 m³ - -
- Cor 1:3:5 0.58 m³ 650,000.00 374,400.00
- Formwork 4.32 m² 35,000.00 151,200.00

- TYPE B
- Staking & pegging 151.00 m' 1,000.00 151,000.00
- Excavation 52.85 m³ - -
- Removal surplus soil 52.85 m³ - -
- Cor 1:3:5 19.93 m³ 650,000.00 12,955,800.00
- Formwork 169.12 m² 35,000.00 5,919,200.00

TYPE B1
- Staking & pegging 48.00 m' 1,000.00 48,000.00
- Excavation 16.80 m³ - -
- Removal surplus soil 16.80 m³ - -
- Cor 1:3:5 5.18 m³ 650,000.00 3,369,600.00
- Formwork 39.36 m² 35,000.00 1,377,600.00

TYPE D
- Staking & pegging 812.28 m' 1,000.00 812,278.49
- Excavation 365.53 m³ - -
- Removal surplus soil 365.53 m³ - -
- Cor 1:3:5 100.17 m³ 650,000.00 65,111,250.67
Beton K175 batu pecah 4.81 m³ 579,200.00 2,786,653.78
- Formwork 998.73 m² 35,000.00 34,955,709.30
- Rebar 8mm dan 6 mm 419.66 kg - -

TYPE E
- Staking & pegging 198.00 m' 1,000.00 198,000.00
- Excavation 170.28 m³ - -
- Removal surplus soil 170.28 m³ - -
- Beton K175 batu pecah 42.73 m³ 579,200.00 24,748,289.28
- Formwork 429.00 m² 35,000.00 15,015,000.00
- Rebar 8mm dan 6 mm 190.08 kg - -
- Wiremesh 534.60 m² - -

TYPE F
- Staking & pegging 30.00 m' 1,000.00 30,000.00
- Excavation 30.00 m³ - -
- Removal surplus soil 30.00 m³ - -
- Beton K175 batu pecah 8.37 m³ 579,200.00 4,847,904.00

Page 28
- Formwork 77.50 m² 35,000.00 2,712,500.00
- Rebar 8mm dan 6 mm 36.00 kg - -
- Wiremesh 87.00 m² - -

TYPE G DAN G1
- Staking & pegging 52.00 m' 1,000.00 52,000.00
- Excavation 42.12 m³ - -
- Removal surplus soil 42.12 m³ - -
- Concrete 1:2:3- batu pecah 13.06 m³ 579,200.00 7,565,742.08
- Formwork 261.25 m² 35,000.00 9,143,680.00
- Rebar 8MM 687.19 kg - -

DRAIN SUMP (S1, S2, S3)


- Staking & pegging 95.20 m' 1,000.00 95,200.00
- Excavation 37.12 m³ - -
- Removal surplus soil 37.12 m³ - -
- Cor 1:3:5 10.83 m³ 650,000.00 7,041,762.00
- Formwork 47.32 m² 35,000.00 1,656,200.00
SUB TOTAL 240,524,189.07
ROUNDED 240,524,000.00
1,620.28

Page 29
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS - IPAL DOMESTIC

NO DESCRIPTION QTY UNIT RATE AMOUNT


AREA MILL ( 3 LOBANG) TERDAPAT 2 UNIT
- Staking & pegging 48.00 m' 1,000.00 48,000.00
- Excavation 120.58 m³ - -
- Removal surplus soil 120.58 m³ - -
- Concrete 1:3:5- 2.08 m³ 650,000.00 1,352,000.00
- Concrete 1:2:3 for beam- batu pecah 20.52 m³ 579,200.00 11,885,184.00
- Wiremesh M6 - 1 layer 173.12 m² - -
- Pipa PVC 6" 16.00 m 120,000.00 1,920,000.00
- Formwork 258.00 m² 35,000.00 9,030,000.00
-
AREA PERUMAHAN ( 5 LOBANG) TERDAPAT 1 UNIT -
- Staking & pegging 21.68 m 1,000.00 21,680.00
- Excavation 56.51 m3 - -
- Removal surplus soil 56.51 m3 - -
- Concrete 1:3:5- 1.44 m3 650,000.00 937,716.00
- Concrete 1:2:3 for beam- batu pecah 15.70 m3 579,200.00 9,093,440.00
- Wiremesh M6 - 1 layer 128.00 m2 - -
- Pipa PVC dia 4" inlet & outlet 11.00 m - -
- Formwork 170.00 m2 35,000.00 5,950,000.00
- Tutup bak kontrol ukuran 70x70 cm -
- Frame siku 50x50.5 65.00 kg BY OTHERS
- plate borders 4 mm 62.00 kg BY OTHERS
- Tutup bak kontrol ukuran 70x120 cm -
- Frame siku 50x50.5 28.00 kg BY OTHERS
- plate borders 4 mm 27.00 kg BY OTHERS
- Pasangan bata 1.26 m2 60,000.00 75,660.00
- Plastering 2.52 m2 15,000.00 37,830.00
-
AREA WORKERS TOILET, B3, WORKSHOP, OFFICE (4 Units) -
- Staking & pegging 14.00 m' 1,000.00 14,000.00
- Excavation 2.03 m³ - -
- Removal surplus soil 2.03 m³ - -
- Concrete 1:3:5- 0.13 m³ 650,000.00 84,500.00
- Pasangan bata 7.00 m2 60,000.00 420,000.00
- Plastering 14.00 m2 15,000.00 210,000.00
- Pipa PVC dia 4" inlet & outlet 8.00 m - -
-
PEKERJAAN PEMIPAAN -
1 Pipa PVC AW 3" include Elbow dan T 350.00 M' 75,000.00 26,250,000.00
2 Pipa PVC AW 4" include Elbow dan T 750.00 M' 85,000.00 63,750,000.00
3 Pipa PVC AW 5" include Elbow dan T 200.00 M' 10,000.00 2,000,000.00
4 Pipa PVC AW 6" include Elbow dan T 30.00 M' 120,000.00 3,600,000.00
5 Galian pipa 117.30 m3 - -
6 Timbun kembali pipa dan buang sisa galian 117.30 m3 - -
7 Pipa HDPE 6" 50.00 M' 300,000.00 15,000,000.00
8 Kabel - M' BY OWNER -
9 Bak Kontrol Ukuran (50 x 50 x 50) cm - UNIT -
- Galian Tanah - M3 - -
- Buang Sisa Galian - M3 - -
- Cor Beton 1:3:5 tebal 5 cm - M3 650,000.00 -
- Pasangan Bata , 1/2 batu camp 1:4 - M2 60,000.00 -
- Plesteran camp 1:4 - M2 15,000.00 -
-
11 Bak Kontrol Ukuran (50 x 50 x 75) cm 40.00 UNIT -
- Galian Tanah 15.68 M3 - -
- Buang Sisa Galian 15.68 M3 - -
- Cor Beton 1:3:5 tebal 5 cm 0.98 M3 650,000.00 637,000.00
- Pasangan Bata , 1/2 batu camp 1:4 60.00 M2 60,000.00 3,600,000.00
- Plesteran camp 1:4 68.00 M2 15,000.00 1,020,000.00
-
12 Bak Transfer Ukuran (150 x 100 x 75) cm - UNIT -
- Galian Tanah - M3 - -
- Buang Sisa Galian - M3 - -
- Cor Beton 1:3:5 tebal 5 cm - M3 650,000.00 -
- Pasangan Bata , 1/2 batu camp 1:4 - M2 60,000.00 -
- Plesteran camp 1:4 - M2 15,000.00 -
- Pompa - unit BY OWNER -
-
13 Bak Kontrol Ukuran (75 x 100 x 100) cm 4.00 UNIT -
- Galian Tanah 5.20 M3 - -
- Buang Sisa Galian 5.20 M3 - -
- Cor Beton 1:3:5 tebal 5 cm 0.29 M3 650,000.00 187,200.00
- Pasangan Bata , 1/2 batu camp 1:4 13.20 M2 60,000.00 792,000.00
- Plesteran camp 1:4 14.40 M2 15,000.00 216,000.00
-
12 Bak Sedimen ukuran 1580x830x830 mm -
- Excavation 1.07 M3 - -
- Removal suplus soil 1.07 M3 - -
- Lean concreete 1:3:5 t. 5 cm 0.07 M3 650,000.00 45,500.00
- Concrete K 225 0.48 M3 579,200.00 280,397.67
- Fomwork 9.36 M2 35,000.00 327,600.00
- Wiremesh M6 - 1 layer 6.05 M2 - -
-
13 Bak penyaringan/ Penjernihan/ Indikator 4480x2240x1350 mm -
- Excavation 12.04 M3 - -
- Removal suplus soil 12.04 M3 - -
- Lean concreete 1:3:5 t. 5 cm 0.50 M3 650,000.00 326,144.00
- Concrete K 225 4.02 M3 579,200.00 2,326,437.89
- Fomwork 50.11 M2 35,000.00 1,753,920.00
- Wiremesh M6 - 1 layer 50.21 M2 - -
- Ijuk untuk bak ukuran 1 m x 2 M 1.00 ls 300,000.00 300,000.00
- Arang cangkang + pasir kerikil untuk bak 1 m x 2 m 1.00 ls 300,000.00 300,000.00
-

-
SUB TOTAL ( 1 UNIT) 163,792,209.56
ROUNDED 163,792,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)

Page 30
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS -GATE AND FENCING

NO DESCRIPTION QTY UNIT RATE AMOUNT


- Excavation 60.48 m³ - -
- Removal surplus soil 60.48 m³ - -
- Formwork 241.92 m² 35,000.00 8,467,200.00
- Sand fill 3.02 m² 120,000.00 362,880.00
- Concrete 1 : 3 : 5 13.61 m³ 650,000.00 8,845,200.00

COLUMN (GATE STATION)


- Concrete 1:2:3 K 175- batu pecah 4.00 m³ 579,200.00 2,316,800.00
- Formwork 21.00 m² 35,000.00 735,000.00
- MS Bar 10MM 388.00 kg - -
Lean concrete 1:3:5 0.70 m3 650,000.00 455,000.00
- Fencing
- Pagar Prima / BRC 907.20 m
- Pagar type 175 A3 dan tiang 378.00 unit 500,000.00 189,000,000.00
GATE
1. Main Gate (Excl. Motor Mch)
- Rail 12.80 m' 150,000.00 1,920,000.00
- MS Pipe 2" 260.10 kg BY OTHERS
- Plate 2mm 114.16 kg BY OTHERS
- L 40.40.4 253.62 kg BY OTHERS
- Wheel 6.00 set 100,000.00 600,000.00

2. Personal Gate
- MS Pipe 2" 38.76 kg BY OTHERS
- Plate 2mm 10.70 kg BY OTHERS
- L 40.40.4 26.14 kg BY OTHERS
- Gerendel/kunci 1.00 bh 150,000.00 150,000.00
- Barbed wire 2,721.60 m' 25,000.00 68,040,000.00
- Sign board/name board 1.00 ls 20,000,000.00 20,000,000.00
SUB TOTAL 300,892,080.00
ROUNDED 300,892,000.00

Page 31
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS -FRUIT LOADING RAMP

NO DESCRIPTION QTY UNIT RATE AMOUNT


A FOUNDATION TYPE A 31 UNITS
1 Staking & pegging 248.00 m' 1,000.00 248,000.00
2 Excavation 187.40 m³ - -
3 Bakcfill+ compacted 119.23 m³ - -
4 Removal surplus soil 68.16 m³ - -
5 Lean concrete 1:3:5 6.05 m3 650,000.00 3,929,250.00
6 Concrete 1:2:3 K 175- batu pecah 55.43 m³ 579,200.00 32,103,897.60
7 Fabrications and install steel bar 16mm 6,648.97 kg - -
8 Fabrications and install steel bar 12mm 572.43 kg - -
9 Fabrications and install steel bar 8mm 309.86 kg - -
10 Supply and install formwork 191.27 m² 35,000.00 6,694,450.00
11 Plastering for concrete work 29.45 m² 15,000.00 441,750.00
12 Install anchor pocket hole 62.00 nos - -

B FOUNDATION TYPE B 31 UNITS


1 Staking & pegging 124.00 m' 1,000.00 124,000.00
2 Excavation 26.35 m³ - -
3 Backfill+ compacted 17.13 m³ - -
4 Removal surplus soil 9.22 m³ - -
5 Lean concrete 1:3:5 1.55 m3 650,000.00 1,007,500.00
6 Construct concrete 1:2:3 -batu pecah 10.19 m³ 579,200.00 5,902,772.00
7 Fabrications and install steel bar 12mm 798.10 kg - -
8 Fabrications and install steel bar 6mm 65.59 kg - -
9 Supply and install formwork 66.81 m² 35,000.00 2,338,175.00
10 Install pocket hole 31.00 nos - -
11 Plastering for concrete work 3.41 m² 15,000.00 51,150.00

C DETAIL-1 --> 100 M


1 Staking & pegging 100.00 m' 1,000.00 100,000.00
2 Excavation 291.50 m³ - -
3 Bakcfill+ compacted 38.20 m³ - -
4 Removal surplus soil 246.00 m³ - -
5 Lean concrete 1:3:5 5.50 m3 650,000.00 3,575,000.00
6 Concrete 1:2:3 K 175- batu pecah 180.00 m³ 579,200.00 104,256,000.00
7 Fabrications and install steel bar 12mm 9,410.26 kg - -
8 Supply and install formwork 530.00 m² 35,000.00 18,550,000.00
9 Install anchor bolt 7/8" - 400 600.00 nos - -
11 Cover plate 8 mm utk curb- (Fabrikasi)+tekuk 5,526.40 kg BY OTHERS

D DETAIL 2- RETAINING WALL + SLOPE


1 Staking & pegging 115.00 m' 1,000.00 115,000.00
2 Excavation 291.53 m³ - -
3 Bakcfill+ compacted 125.36 m³ - -
4 Removal surplus soil 166.17 m³ - -
5 Sand fill 23.17 m³ 120,000.00 2,779,860.00
Lean concrete 1:3:5 7.48 m³ 650,000.00 4,858,750.00
6 Concrete 1:2:3 K 175- batu pecah 107.21 m³ 579,200.00 62,096,900.80
7 Concrete 1:2:3 K 175- batu pecah+ acian 55.60 m³ 579,200.00 32,201,898.24
7 Fabrications and install steel bar 12mm 8,178.64 kg - -
8 Fabrications and install steel bar 10mm 1,985.13 kg - -
8 Supply and install formwork 540.50 m² 35,000.00 18,917,500.00
9 Plastering for concrete work 184.00 m² 15,000.00 2,760,000.00
10 Wiremesn M6- 1 layer 463.31 m2 - -

E SLAB / FLOOR
1 Staking & pegging 144.00 m' 1,000.00 144,000.00
2 Laterit/Sirtu fill t. 20 cm + compacted 243.40 m³ 560,000.00 136,304,000.00
3 Construct concrete K-225 for floor t. 20 cm 243.40 m³ 579,200.00 140,977,280.00
4 Supply and install formwork 18.99 m² 35,000.00 664,482.00
5 Install wiremesh m-6 (2 layers) 1,217.00 m² - -
6 Pipa PVC 6" AW 72.00 m 120,000.00 8,640,000.00
7 Curb menuju loading ramp
- Construct concrete 1:2:3 -batu pecah 34.00 m³ 579,200.00 19,692,800.00
- Fabrications and install steel bar 10mm 1,726.20 kg - -
- Supply and install formwork 110.00 m² 35,000.00 3,850,000.00

F LANTAI DAN ATAP CONVEYOR


Luas lantai 816.00 m2
1 Sand fill 5 cm 40.80 m³ 120,000.00 4,896,000.00
2 Concrete 1:2:3 for slab/floor+acian t. 7 cm 57.12 m³ 579,200.00 33,083,904.00
3 formwork 10.28 m2 35,000.00 359,856.00
4 Roofing 477.00 m2 BY OTHERS

G TANGGA
1 Wiremesh 60.00 m2 - -
2 Supply and install formwork 45.00 m² 35,000.00 1,575,000.00
3 Construct concrete 1:2:3 for stair & foundation- batu pecah 4.00 m3 579,200.00 2,316,800.00
4 Railing, pipa dia 2" 35.00 m BY OTHERS
5 Tanah timbun dipadatkan 12.00 m3 - -

SUB TOTAL 655,555,975.64


ROUNDED 655,555,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS - RETAINING WALL / SLOPE PROTECTION AT LOADING RAMP

NO DESCRIPTION QTY UNIT RATE AMOUNT


AREA SEKITAR LOADING RAMP
1 Excavation 15.52 m³ - -
2 Removal surplus soil 15.52 m³ - -

Page 32
3 Concrete 1:2:3 K 175- batu pecah t. 12 cm + ACIAN 75.00 m³ 579,200.00 43,440,000.00
4 Install Wiremesh M6 ( 1 layer) 625.00 m² - -

Page 33
5 Formwork 37.50 m² 35,000.00 1,312,500.00
SUB TOTAL 44,752,500.00
ROUNDED 44,752,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS- FOUNDATION FOR CLARIFIER STORAGE TANK (CAP 250 M3 FILTERED)

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 31.27 m' 1,000.00 31,274.40
2 Excavation 11.65 m³ - -
3 Removal surplus soil 11.65 m³ - -
4 Formwork 26.00 m² 35,000.00 910,000.00
5 Concrete 1:2:3 K 175 , batu pecah 25.64 m³ 579,200.00 14,850,688.00
6 Concrete 1:2:3 K 175 + acian , batu pecah 6.69 m³ 579,200.00 3,874,848.00
7 Wiremesh m6 - 1 layer 67.00 m² - -
8 Asphalt Sand mix, t = 75 mm 4.06 m3 800,000.00 3,248,000.00
9 Ms Bar 12mm 1,816.00 Kg - -
10 Ms Bar 8mm 60.00 Kg - -
11 Lean concrete 2.70 m3 650,000.00 1,755,000.00
12 Sand fill 1.60 m3 120,000.00 192,000.00
SUB TOTAL 24,861,810.40
ROUNDED 24,861,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : EARTHWORKS - LINING COOLING POND
NO DESCRIPTION QTY UNIT RATE AMOUNT
1 Staking, pegging and marking 296.00 M' 1,000.00 296,000.00
2 Trimming 2,697.00 M2 1,000.00 2,697,000.00
3 Supply and install stone pitching -/+ 15 cm-20cm 2,697.00 M2 185,000.00 498,945,000.00
4 Excavation for open drainage 29.60 M3 - -
5 Removal surplus soil 29.60 M3 - -
6 Formwork 78.00 M2 35,000.00 2,730,000.00
7 Concrete 1:3:5 for drainage 26.00 M3 650,000.00 16,900,000.00
8 Plastering 443.00 M2 15,000.00 6,645,000.00
SUB TOTAL 528,213,000.00
ROUNDED 528,213,000.00

RENCANA ANGGARAN PELAKSANAAN (RAP)


60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : OUTSIDE FENCE-EFFLUENT TREATMENT PLANT -OVERFLOW FOR EFFLUENT POND

NO DESCRIPTION QTY UNIT RATE AMOUNT


A DARI FAT PIT KE COOLING POND 1
Memakai Pipa ( Pipa By Mechanical )

B SLUDGE PIT ANTARA COOLING POND 1 & COOLING POND-2


1 Staking & pegging 18.80 m' 1,000.00 18,800.00
2 Excavation 15.33 m³ - -
3 Removal surplus soil 15.33 m³ - -
4 Concrete 1:2:3 K 175 -kerikil 5.01 m³ 579,200.00 2,901,792.00
5 Formwork 54.03 m² 35,000.00 1,890,875.00
6 Install Wiremesh M6 - 1 layer 33.40 m² - -

C DARI COOLING POND 2 SD POLISHING


1 Staking & pegging 621.00 m' 1,000.00 621,000.00
2 Excavation 217.35 m³ - -
3 Removal surplus soil 217.35 m³ - -
4 Concrete 1:2:3 K 175 - kerikil 109.14 m³ 579,200.00 63,214,322.40
5 Formwork 928.40 m² 35,000.00 32,493,825.00
6 Ms Bar 8mm dan 6mm 302.74 kg - -
7 Install Wiremesh M6 - 1 layer 1,055.70 m² - -

SUB TOTAL 101,140,614.40


ROUNDED 101,140,000.00

Page 34
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : OUTSIDE FENCE - -EFFLUENT TREATMENT PLANT -MAIN DRAIN TO DISCHARGE OUT

NO DESCRIPTION QTY UNIT RATE AMOUNT


1 Staking & pegging 60.00 m' 1,000.00 60,000.00
2 Excavation 60.00 m³ - -
3 Removal surplus soil 60.00 m³ - -

SUB TOTAL 60,000.00


ROUNDED 60,000.00

Page 35
HARGA SATUAN BAHAN
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
5,736,779,000.00
RATE BAHAN YANG DISUPPLY OLEH PT THB
No DESCRIPTION Volume Unit
Rp.
A BANGUNAN MILL DAN PONDASI MESIN
- Staking & pegging 1.00 m 1,000.00
- Trimming 1.00 m² 1,000.00
- Excavation 1.00 m³ Include Sewa alat berat
- Bakcfill+ compacted 1.00 m³ Include Sewa alat berat
- Removal surplus soil 1.00 m³ Include Sewa alat berat
- Compacted sand /sand fill 1.00 m³ 120,000.00 Include Borong Mandor
- Laterit / Sirtu fill + compacted 1.00 m³ 560,000.00
- Grouting flat, ±2cm thk, "SIKA" 1.00 lot Sika Grout, Include Borong Mandor
- Inctall anchor bolt 1.00 nos Anchor,Include Borong Mandor
- Install anchor bolt 7/8" - 400 atau untuk pondasi mesin lainnya 1.00 nos Anchor,Include Borong Mandor
- Lean concrete/concrete 1:3:5 1.00 m³ 650,000.00 Semen,Include Borong Mandor
- Concrete K175 Foundations & Road (Batu Kerikil) 1.00 m³ 579,200.00 Semen
- Concrete K175 Foundations & Road (Batu Pecah) 1.00 m³ 579,200.00 Semen
- Concrete K175 for slab & floor + acian (Batu Kerikil) 1.00 m³ 579,200.00 Semen
- Concrete K175 for slab & floor + acian (Batu Pecah) 1.00 m³ 579,200.00 Semen
- Concrete K225 batu pecah (untuk L. ramp & Boiler) 1.00 m³ 579,200.00 Semen
- Fabrications and install steel bar 1.00 kg Besi beton dan kawat beton
- Supply and install formwork for foundation 1.00 m² 35,000.00
- Supply and install formwork for drainage 1.00 m² 35,000.00
- Supply and install formwork for road 1.00 m² 35,000.00
- Install pocket hole 1.00 nos
- Strauss pile dia 250 mm x 1000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 2000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 3000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 4000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 5000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Pecah kepala MINI pile 1.00 nos
- Install & supply wiremesh 1 layer M6 1.00 m² Wiremesh dan kawat beton
- Install wiremesh m-6 (2 layers) 1.00 m² Wiremesh dan kawat beton
- Wiremesh M8 + Frame 1.00 m² Wiremesh dan cat baja
- Expanded mesh 1.2x2.4m 1.00 m² Expanded mesh dan cat baja
- Brickwall partition 1:4, 115 mm for ordinary works 1.00 m² 60,000.00 Semen
- Brickwall partition 1:4, 115 mm for ordinary works 1.00 m² 60,000.00 Semen

- Brickwall 3 m high 230 mm, fibre storage include cover column WF 1.00 m² 60,000.00
Semen
- Plastering for brickwall t.15 mm (1:4) 1.00 m² 15,000.00 Semen
- Plastering for concrete work 1.00 m² 15,000.00 Semen
- Aspalt sand mix 1.00 m³ 800,000.00
- Ventilation Block/Hollow block (batu kerawang) 1.00 m² 60,000.00 Semen
- Painting for door & fascia: enamel paint, Bee Brand 1.00 m² 12,000.00
- Painting for wall : emulsion paint, ex Vinilex 1.00 m² 12,000.00
- Ceiling triplex t. 6 mm + frame / Gypsum 9mm 1.00 m² 75,000.00
- Cable installation 1.00 nos 120,000.00
- Supply & install lamp LED 18 W Ex Hannocs/Philips 1.00 nos 50,000.00
- Supply & install lamp LED 12 W Ex. Hannocs/Philips 1.00 nos 50,000.00
- Supply & install lamp LED 9 W 1.00 nos 50,000.00
- Supply & install switch and outlet 1.00 nos 30,000.00
- Fabrications and install steel structure
- WF 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- WF 400 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- H. Beam 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- UNP 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Besi CNP 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Besi Siku 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Plate 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Plate Strip 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Pipa Besi Hitam 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Besi Round Bar 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Instal Plat + tekuk 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
Upah Roll Plate 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Railing (pipe dia 1 1/2" & 1 1/4") + painting 1.00 m BY OTHERS Baja , Cat baja , Tbuckledan baut
- Railing stair 1.00 m BY OTHERS Baja , Cat baja , Tbuckledan baut
- Drain dia 50mm PVC+ plam fibre 1.00 unit 20,000.00
- Install roofing ( aluzinc t.0,45 mm) ( incld biaya potong seng ) 1.00 m² BY OTHERS Seng dan paku seng
- Install cladding (aluzinc t.0,35 mm) ( incld biaya potong seng ) 1.00 m² BY OTHERS Seng dan paku seng
- Install cladding TRANSPARANT 2MM ( incld biaya potong seng ) 1.00 M2 BY OTHERS Seng dan paku seng
- Install Ridge capping 0.45mm ( incld biaya potong seng ) 1.00 m BY OTHERS Seng dan paku seng
- Install Ridge capping 0.3mm ( incld biaya potong seng ) 1.00 m BY OTHERS Seng dan paku seng
- Install flashing ( incld biaya potong seng ) 1.00 m BY OTHERS Seng dan paku seng
- Install gutter horizontal 1.00 m BY OTHERS Seng plat
- Pekerjaan talang- PVC pipe for gutter vertical, pipa 8" AW 1.00 m BY OTHERS
Pekerjaan talang- PVC pipe for gutter vertical, pipa 4" AW 1.00 m BY OTHERS
- Pasangan batu kali lining cooling pond 1.00 m² 185,000.00 Semen
- Pipa PVC AW -cross jalan dia 4" 1.00 m 85,000.00
Pipa PVC AW -Slba l. ramp dia 6" 1.00 m 120,000.00
B ANCHILLARY
Pekerjaan Umum

- Supply & install ceramic tiles for flooring ex. Ikad/ Mulia ukuran 40x40 cm 1.00 m² 60,000.00
semen
- Supply & install ceramic tiles for wall ex. Ikad/ Mulia 1.00 m² 60,000.00 semen
- Supply & install ceramic plinth for flooring ex. Ikad/ Mulia 1.00 m 60,000.00 semen
- Supply & install ceramic tiles for bath room ex. Ikad/ Mulia 1.00 m² 60,000.00 semen
- Supply & install ceramic tiles for kitchen 1.00 m² 60,000.00 semen
- Supply & install ceramic tiles for laboratorium's table 1.00 m² 60,000.00 semen
- Supply & install fix wood trim K3 1.00 m 7,000.00
- Fascia /listplank kayu+cat minyak 1.00 m 12,000.00
- Rangka baja ringan untuk office 1.00 m² 75,000.00

Pintu & Jendela


1 Workshop & Store
Pintu panel kayu Uk 92x201 cm + Jalusi kayu Uk 90x40 cm + kosen kayu +
- 1.00 unit 2,500,000.00
accessories complete
Jendela nako 2 lobang @ Uk 60x113 cm + jalusi kayu 2 lobang @ Uk 60x40
- 1.00 unit 850,000.00
cm + kosen kayu

Jendela nako 1 lobang @ Uk 60x113 cm + jalusi kayu 1 lobang @ Uk 60x40


1.00 unit 1,200,000.00
cm + kosen kayun J1
- Pintu besi ukuran 3x 3 M 1.00 unit BY OTHERS Baja, cat baja , dan baut

2 Weighbridge House

Pintu Alm Uk 90x210 cm kaca being 8 mm +ventilasi Uk 90x40 cm + kosen


- Alm ex. Damai abadi/Alexindo, 2 daun@80x105+ventilasi (sesuai gambar) + 1.00 unit 750,000.00
accessoies PJ1

Jendela kaca mati 3 lobang aluminium ex. Alexindo/Damai Abadi ukuran


- sesuai gambar 2@80x150+ ventilasi 2 @80x40 cm + 1@90x105 cm ventilasi 1.00 unit 750,000.00
kaca mati 40x90 cm +accessories (lihat gambar) J1

Jendela kaca mati 3 lobang aluminium ex. Alexindo/Damai Abadi ukuran


- sesuai gambar 2@115x105+ ventilasi 2 @115x40 cm + 1@120x105 cm 1.00 unit 750,000.00
ventilasi kaca mati 40x115 cm +accessories (lihat gambar) J2

Instalasi air & Sanitair


- Kran air merk ONDA SS 1.00 unit 30,000.00
- Floor drain Lokal 1.00 unit 25,000.00
- Septiktank 1.00 unit 350,000.00 Semen

Gate & Fencing


- Barbed wire 1.00 m 25,000.00
- Papan nama 1.00 ls 20,000,000.00
- Rel 1.00 m 150,000.00
- Pagar :
a. Pagar type 175 A3 1.00 unit 500,000.00 Pagar , tiang dan u Clip
- Grendel / kunci 1.00 unit 150,000.00
- Wheel 4" 1.00 unit 100,000.00
- Roda 1.5" 1.00 unit 50,000.00

Lain-lain
- Talang horizontal seng plate 0,4 mm 1.00 m 50,000.00 Seng plat
- Talang vertical PVC 6"/8" + accessories 1.00 m 85,000.00
- Jalur tamu 1.00 m 15,000.00 Semen
- earthfill + compacted 1.00 m3
- Gali , Buang tanah, dan merapikan tanah buangan 1.00 m3
- Air bersih pipa PVC 1/2" (3 Titik) 1.00 LOT 300,000.00
- Triplek 9mm Rak workshop 1.00 m2 85,000.00
- Meja cor , beton 1:2:3 + Wiremesh 1.00 ls 500,000.00
- MCB 1.00 unit 75,000.00
- AC 2 PK 1.00 nos 6,500,000.00

Pekerjaan Pemipaan IPAL


Pipa PVC AW 3" 1.00 m 75,000.00
Pipa PVC AW 4" 1.00 m 85,000.00
Pipa PVC AW 5" 1.00 m 10,000.00
Pipa PVC AW 6" 1.00 m 120,000.00
Pipa HDPE 6" 1.00 m 300,000.00
Ijuk untuk bak ukuran 1 m x 2 M 1.00 ls 300,000.00
Arang cangkang + pasir kerikil untuk bak 1 m x 2 m 1.00 ls 300,000.00
Mobil Mixer 50000000 100,000,000.00 100,000.00
Excavator 275,000.00 55,000,000.00 55,000.00
Fuel 8000 140,000,000.00 140,000.00
Jasa 50000 50,000,000.00 50,000.00
Total 345,000.00
TOTAL (A) 345,000.00

formula Unit Price Rp/m3 vol


K-175 A B C D AXD
Pasir 900,000.00 175000 0.56 98,000.00
Split 3,750,000.00 750000 0.8 600,000.00
Semen 0.00 0 0 0.00
Air 120.00 120.00 215 25,800.00
Total 723,800.00
TOTAL (B) 723,800.00

Jasa Pengecoran 150,000.00


Over Head 10% 15,000.00
TOTAL (C) 165,000.00

K-175 TOTAL (A+B+C) 1,233,800.00

VOLUME BASE
Kg Unit Price Rp/m3 Rp/Kg/Ltr
K-175 A B C D AXD
Pasir 692 875,000.00 175000 125 86,500.00
Split 1039 3,750,000.00 750000 535.7143 556,607.14
Semen 384 0.00 0 0.00
Air 215 1,200,000.00 150 32,250.00
Total 675,357.14
TOTAL (B) 675,357.14

K-175 TOTAL (A+B+C) 1,185,357.14

TONASE BASE
beton 1700000
semen 720000

Selisih 980000

Split 700000
Pasir 175000
875000

Beton
K175

Split 1029 0.762222


Pasir 760 0.542857
Semen 326 6.52
Air 215 215

You might also like