Professional Documents
Culture Documents
Bedessa 33kv Final 2
Bedessa 33kv Final 2
Bedessa 33kv Final 2
Contents
Contents .......................................................................................................................................... 1
1. Introduction ................................................................................................................................. 4
2. Objectives ................................................................................................................................... 4
3. Scope of the project .................................................................................................................... 5
4. Main activities performed during this work................................................................................ 5
4.2. Dismantling the old 33kv Switchgear .................................................................................. 6
4.2.1 Removing wirings .......................................................................................................... 6
4.2.2 Dismantling the Panel ..................................................................................................... 7
4.3. Erection of the New 33kv Switchgears ................................................................................ 8
5. Bus bar Connecting ................................................................................................................... 11
6. Earthing and System Ground connection ................................................................................. 12
7. Wiring Works............................................................................................................................ 13
8. Pre commissioning and Tests.................................................................................................... 13
8.1 Mechanical Checks and Visual Inspection.......................................................................... 14
9. 33kv Incoming line feeder ........................................................................................................ 17
9.1. Specification ....................................................................................................................... 17
9.2 General Inspection............................................................................................................... 17
9.3. Insulation Resistance Test .................................................................................................. 17
9.4 Current Transformer inspection and testing ........................................................................ 18
9.4.1Visual inspection ........................................................................................................... 19
9.4.2 CT Insulation Resistance Test ...................................................................................... 19
9.5 Relay configuration and testing........................................................................................... 19
9.6. CT primary Injection Test Report ...................................................................................... 20
9.7. Secondary Current Injection Test Report ........................................................................... 21
9.8. Surge Arrester Testing ....................................................................................................... 23
9.9. PT Check list ...................................................................................................................... 23
9.10. 33kv Incoming Power cable Insulation Resistance (IR) Test .......................................... 24
10. 33kv outgoing Line 1 .............................................................................................................. 24
10.1 Specification ...................................................................................................................... 24
10.2 General Inspection............................................................................................................. 24
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 1
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 2
66/33/15Kv Bedessa Substation Rehabilitation Work Report
List of Figures
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 3
66/33/15Kv Bedessa Substation Rehabilitation Work Report
1. Introduction
Now a day, the demand for electrical energy is growing at a very fast rate. To cover this demand,
the existing power system network should be upgraded and rehabilitated to meet the need of the
customers. Bedessa 66/33/15kv substation is on of the power supplying substation which is
administered under Ethiopian Electric utility Oromiya region Chiro district and supplies power to
the town of Bedessa and around the area. This substation is too old and needs rehabilitation and
upgrading. Mostly, the available 33kv switchgear panels in this substation are too old. There
were two 33kv outgoing, 1 incoming and two spare panels. One of the outgoing panels is on the
incoming and the other is getting directed without circuit breaker. All lines are controlled and
protected by incoming feeder line. Most of circuit breakers are not functional and direct. The
protective relays are analogue and old model which don’t clear faults happening on the
distribution network. In addition to this, the fault happened on the 33kv panel trips the 66kv
circuit breaker and de-energizes the transformer through out a day which also interrupts the 15kv
side of the transformer as 66kv side interrupts. This problem needs a solution which solves the
above listed problem; the one is a rehabilitation and upgrading work on these 33kv switchgears.
2. Objectives
The main objective of this work is to rehabilitate the existing33kv switchgear panel and improve
control and protection system and reducing power interruption by replacing the old switchgear
with a new one. The specific objectives of this work include:
To dismantle the old 33kv switchgear to have free space for the new panel
To remove the old dismantled switchgear from its dismantled position
To erect the new 33kv switchgear on its appropriate place
To inspect the new 33kv switchgear components and request the unavailable accessories
for fitting
To configure and test the available switchgear protection devices (protective and
measuring devices)
To test the available switchgear components and confirming the test results
To shift the 33kv power cable from the old panels to the new panel and energize
incoming and outgoing panels.
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 4
66/33/15Kv Bedessa Substation Rehabilitation Work Report
We have made inspection to confirm that the components of the switchgear available or not. We
have found that some switchgear accessories are not brought with the pane. We have request the
following accessories to be brought for erection and energizing the panels. These are
Until these accessories are fulfilled we have performed 33kv old panel dismantling work.
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 5
66/33/15Kv Bedessa Substation Rehabilitation Work Report
There were two old panels which were idle and not delivering power. So our work was started by
dismantling these panels and free up the space for erection of the new panel.
The wires inside the panels were dismantled carefully to make isolate the panel to dismantle and
lift it to the appropriate place for transportation.
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 6
66/33/15Kv Bedessa Substation Rehabilitation Work Report
The erected panel is dismantled from the basement to make it ready for transportation by forklift.
This includes:-
Disconnecting the bus bar line connecting these panel to other panel
Disconnecting the power cable from the panels
Removing nuts and bolts which fixes the panel with the basement and panel to panel
Removing the Body grounds and any interlocks
Lifting the panels from their dismantled position to the appropriate place using both
human power and forklift machine
While make ready the panel for forklift machine for removing from the room
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 7
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Figure 2: Dismantling and lifting the panels to appropriate place using forklift machine
After the panels were dismantled and the area is cleared the next task was erecting the new 33kv
switchgear panels on these places. First the 33kv incoming switchgear was going to be erected
while the two old panels were serving electricity. This is done to minimize the duration of
interruption time for restoring the service with the new panels. Under this the following task
were performed:-
Lifting the new 33kv Switchgear from outside to control room using crane and
forklift
Lifting the new 33kv switchgear to its erection place inside control room using
both crane and forklift
Erecting the new panel when it is placed at its stand place
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 8
66/33/15Kv Bedessa Substation Rehabilitation Work Report
This photo shows when the crane lifts from outside to control room during evening time
Figure 4: Shows when the panels were lifted from outside to control room
Figure 5: After the panels entered into the control room using crane and forklift
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 9
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Figure 6: The above Photos show activities to erect the panel on its required place
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 10
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Figure 7: The above photos show after the three panels have been erected
Note: - The new 33kv panel erection work was carried out step by step to minimize the
interruption time.
First the new 33kv panel was erected, wired and tested and commissioned while the old
incoming 33kv panel was supplying power
After the panel tested and functional, the incoming and outgoing power cables were shifted from
the old 33kv panels to the new 33kv incoming panel and the line get energized. For the time
being, this panel was used as both incoming and outgoing panel until the two panels have been
erected.
According to our request, the required standard and number of copper bus bars were brought and
We have used copper bus bars to distribute power from incoming panels to outgoing feeders
Bus bar insulators were installed between each panels to insulate from metal sheet
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 11
66/33/15Kv Bedessa Substation Rehabilitation Work Report
In addition to this,
were grounded to provide a return path for the leakage current and hence protect the equipment
from damage.
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 12
66/33/15Kv Bedessa Substation Rehabilitation Work Report
7. Wiring Works
The wiring work for each panels have been done according to the schematic drawing of the
switchgear. The wiring work includes
DC Supply distribution for controlling and protection for each switchgear panels
AC Supply distribution for lighting, heating and Socket for each switchgear panels
VT Circuit Wiring for each Switchgear panels
Note: - The existing DC and AC distribution wires from the old panels were used to supply the
new incoming panels and distributed to each outgoing panels.
Figure 9: The photos show while performing wiring works for each switchgear panels
After the wiring work has been done, the panels were ready for pre commissioning and testing.
8. Pre commissioning and Tests
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 13
66/33/15Kv Bedessa Substation Rehabilitation Work Report
SWITCHGEAR-GENERAL
Equipment Type 33kv Switchgear panel
Make CHINA
Type Air Insulated Metal –Clad Switchgear
Feeder Name 33KV Incoming Feeder
Rated voltage 33kv
Rated current 200-400A
Serial Number 20220415-01
Model Number KYN61-33-1G
8.1 Mechanical Checks and Visual Inspection
S. Description Status Remarks if any
No Yes No
1 Switchgear is cleaned and free from dust/dirt, foreign
materials etc.
2 Switchgear is free from all visible defects on physical
inspection
3 Switchgear panel has been provided with and grounding
4 Check that all nuts and bolts are tightened correctly as per
specified torque
5 Leveling and alignment of switchgear and base frame
checked
6 Tightness of nuts and bolts of bus bar and supports are
checked
7 Auxiliary contacts and relays have been cleaned and free
from dust /damage
8 All spare wires terminated at terminal blocks
CT spare wires should be closed at terminal block
9 Erection completion certificate along with list of
outstanding activities reviewed
10 Check control knobs and switches for freedom of movement
and contact condition.
11 Inspect door handles, locking bars, and mechanism.
12 Check door interlocks for positive operation.
13 Check in and out circuit breaker mechanism for freedom of
movement.
14 Check rails, guides, rollers, and shutter mechanism.
15 Check Lubrication of draw out assembly parts as required.
16 Inspect breaker and cell primary and secondary contacts and
alignment.
17 Close and trip breakers manually in the connected, test and
disconnected positions
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 14
66/33/15Kv Bedessa Substation Rehabilitation Work Report
SWITCHGEAR-GENERAL
Equipment Type 33kv Switchgear panel
Make CHINA
Type Air Insulated Metal –Clad Switchgear
Feeder Name 33KV Outgoing Line 1
Rated voltage 33kv
Rated current 100-200A
Serial Number 20220301-09
Model Number KYN61-33-5G
Mechanical Checks and Visual Inspection
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 15
66/33/15Kv Bedessa Substation Rehabilitation Work Report
SWITCHGEAR-GENERAL
Equipment Type 33kv Switchgear panel
Make CHINA
Type Air Insulated Metal –Clad Switchgear
Feeder Name 33KV Outgoing Line 2
Rated voltage 33kv
Rated current 100-200A
Serial Number 20220301-07
Model Number KYN61-33-3G
Visual Inspection
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 16
66/33/15Kv Bedessa Substation Rehabilitation Work Report
9.1. Specification
Sr.No Model Voltage Rated Making Breaking
Make/Type
Rating current capacity capacity
China 22080619 ZN85-40.5/T1250-31.5 40.5KV 1250A - 31.5kA
Aim: To get the insulation resistance of the Circuit breaker and to insure the performance and
functionality.
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 17
66/33/15Kv Bedessa Substation Rehabilitation Work Report
@1Min, 5kv
Phase Measured Between Insulation Resistance in GΩ
R R-R’ 16.4GΩ
S S-S’ 41.6GΩ
T T-T’ 491GΩ
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 18
66/33/15Kv Bedessa Substation Rehabilitation Work Report
9.4.1Visual inspection
Table 6:- CT visual inspection Checklist
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 19
66/33/15Kv Bedessa Substation Rehabilitation Work Report
S-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 20
66/33/15Kv Bedessa Substation Rehabilitation Work Report
T-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR.No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120
Secondary Injection Testing is carried out to determine the correct operation of circuits
connected to the secondary side of current transformer circuits. This testing relates to Protection
relay testing and Circuit Breaker trip tests. This test is performed to ensure that the trip functions
of a relay under various fault conditions are maintained within the setting values.
The testing relay includes:
Start-Value 0.58
Pick-up 0.6 0.49 Sec
S
Start-Value 0.58
Pick-up 0.6 0.51 Sec
T
Start-Value 0.59
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 21
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Time setting
Current setting
Phase Operation
(I>=(67P3)=0.85) Relay and CB Status
(t67P3=0.03sec )
The Relay as well as the CB trips
Pick-up 0.85 0..028 Sec
R according to the protection setting Values
Start-Value 0.83
Pick-up 0.85 0.027 Sec
S
Start-Value 0.84
Pick-up 0.85 0.031 Sec
T
Start-Value 0.84
Start-Value 0.029
Pick-up 0.03 0.069 Sec
S
Start-Value 0.028
Pick-up 0.03 0.071 Sec
T
Start-Value 0.028
Second Stage Earth fault protection (67N-2)
Time setting
Current setting
Phase Operation
(Io>=(67N-2)=0.06) (t67N-2=0.03sec) Relay and CB Status
Start-Value 0.05
Pick-up 0.06 0.027Sec
S
Start-Value 0.05
Pick-up 0.06 0.031 Sec
T
Start-Value 0.05
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 22
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 23
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 24
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Aim: To get the insulation resistance of the Circuit breaker and to insure the performance and
functionality.
@1Min, 5kv
Phase Measured Between Insulation Resistance in GΩ
R R-R’ 4.52TΩ
S S-S’ >10ΩΩ
T T-T’ 1TΩ
Contact Resistance
Phase Measured Between Insulation Resistance in milliohms
R R-R’ 0.4Ω
S S-S’ 0.4Ω
T T-T’ 0.4Ω
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 25
66/33/15Kv Bedessa Substation Rehabilitation Work Report
10.4.1Visual inspection
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 26
66/33/15Kv Bedessa Substation Rehabilitation Work Report
S-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 27
66/33/15Kv Bedessa Substation Rehabilitation Work Report
T-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR.No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120
Secondary Injection Testing is carried out to determine the correct operation of circuits
connected to the secondary side of current transformer circuits. This testing relates to Protection
relay testing and Circuit Breaker trip tests. This test is performed to ensure that the trip functions
of a relay under various fault conditions are maintained within the setting values.
The testing relay includes:
Start-Value 0.58
Pick-up 0.6 0.049 Sec
S
Start-Value 0.58
Pick-up 0.6 0.049 Sec
T
Start-Value 0.59
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 28
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Time setting
Current setting
Phase Operation
(I>=(67P3)=1.2) Relay and CB Status
(t67P3=0.01sec )
The Relay as well as the CB trips
Pick-up 1.2 0.009 Sec
R according to the protection setting Values
Start-Value 1.19
Pick-up 1.2 0.008 Sec
S
Start-Value 1.19
Pick-up 1.2 0.02 Sec
T
Start-Value 1.19
Start-Value 0.06
Pick-up 0.07 0.02 Sec
S
Start-Value 0.06
Pick-up 0.07 0.021 Sec
T
Start-Value 0.06
Start-Value 0.05
Pick-up 0.06 0.01Sec
S
Start-Value 0.05
Pick-up 0.06 0.009 Sec
T
Start-Value 0.05
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 29
66/33/15Kv Bedessa Substation Rehabilitation Work Report
10.9. 33kv Outgoing line 1 Power cable Insulation Resistance (IR) Test
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 30
66/33/15Kv Bedessa Substation Rehabilitation Work Report
11.1 Specification
Sr.No Model Voltage Rated Making Breaking
Make/Type
Rating current capacity capacity
China 22080616 ZN85-40.5/T1250-31.5 40.5KV 1250A - 31.5kA
Aim: To get the insulation resistance of the Circuit breaker and to insure the performance and
functionality.
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 31
66/33/15Kv Bedessa Substation Rehabilitation Work Report
@1Min, 5kv
Phase Measured Between Insulation Resistance in GΩ
R R-R’ 74.4GΩ
S S-S’ 95.6GΩ
T T-T’ 137GΩ
Contact Resistance
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 32
66/33/15Kv Bedessa Substation Rehabilitation Work Report
11.4.1Visual inspection
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 33
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 34
66/33/15Kv Bedessa Substation Rehabilitation Work Report
S-Phase
Sr. Injected Current Meter Reading Relay Reading Relay and CB Status
No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120
T-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR.No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120
Secondary Injection Testing is carried out to determine the correct operation of circuits
connected to the secondary side of current transformer circuits. This testing relates to Protection
relay testing and Circuit Breaker trip tests. This test is performed to ensure that the trip functions
of a relay under various fault conditions are maintained within the setting values.
The testing relay includes:
Trip Timing checks as per settings
Correct operation of Auxiliary contacts
Alarm functions
Polarity checks
Physical conditions
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 35
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Specifications
Relay Type: - PMC-851X multifunctional relay
CT ratio: - 100/1A
Sr.No:- PMC-851X-E11115ACA
Feeder: - 33Kv Outgoing Line 1
Test Instrument Used:-SCITS 100 secondary current Injection Test set
Directional over Current and Earth Fault Relay
Start-Value 0.58
Pick-up 0.6 0.049 Sec
S
Start-Value 0.58
Pick-up 0.59 0.049 Sec
T
Start-Value 0.58
Second Stage direction overcurrent (67P3)
Time setting
Current setting
Phase Operation
(I>=(67P3)=1.2) Relay and CB Status
(t67P3=0.01sec )
The Relay as well as the CB trips
Pick-up 1.2 0.009 Sec
R according to the protection setting Values
Start-Value 1.19
Pick-up 1.2 0.008 Sec
S
Start-Value 1.19
Pick-up 1.2 0.02 Sec
T
Start-Value 1.19
Start-Value 0.06
Pick-up 0.07 0.02 Sec
S
Start-Value 0.06
Pick-up 0.07 0.021 Sec
T
Start-Value 0.06
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 36
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Start-Value 0.09
Pick-up 0.1 0.01Sec
S
Start-Value 0.08
Pick-up 0.1 0.009 Sec
T
Start-Value 0.09
11.9. 33kv outgoing line 2 Power cable Insulation Resistance (IR) Test
Megger Type:-Meggrer MIT525
Applied Test voltage: - 5kv
Test Time duration: - 1min
33kv incoming Power Cable Insulation Resistance(IR) test results(@ 5kv, 60sec)
R-G S-G T-G
>10TΩ >10TΩ >10TΩ
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 37
66/33/15Kv Bedessa Substation Rehabilitation Work Report
3 Energization OK
Commissioning Team
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 38
66/33/15Kv Bedessa Substation Rehabilitation Work Report
3 Energization OK
Commissioning Team
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 39
66/33/15Kv Bedessa Substation Rehabilitation Work Report
3 Energization OK
Commissioning Team
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 40
66/33/15Kv Bedessa Substation Rehabilitation Work Report
Conclusion
The aim of this project was to made rehabilitation and upgrading work on 33kv switchgear
panels. The work includes:
Dismantling
Erecting
Testing and Commissioning
Energization
Each switchgear panel has been tested and commissioned and the results were analyzed to
confirm each panels were ready for energization.All the test results were good and according to
the standards. After all, the lines were energized successfully without any problems.
Challenge
Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 41