66/33/15Kv Bedessa Substation Rehabilitation Work Report

Contents

Contents .......................................................................................................................................... 1
1. Introduction ................................................................................................................................. 4
2. Objectives ................................................................................................................................... 4
3. Scope of the project .................................................................................................................... 5
4. Main activities performed during this work................................................................................ 5
4.2. Dismantling the old 33kv Switchgear .................................................................................. 6
4.2.1 Removing wirings .......................................................................................................... 6
4.2.2 Dismantling the Panel ..................................................................................................... 7
4.3. Erection of the New 33kv Switchgears ................................................................................ 8
5. Bus bar Connecting ................................................................................................................... 11
6. Earthing and System Ground connection ................................................................................. 12
7. Wiring Works............................................................................................................................ 13
8. Pre commissioning and Tests.................................................................................................... 13
8.1 Mechanical Checks and Visual Inspection.......................................................................... 14
9. 33kv Incoming line feeder ........................................................................................................ 17
9.1. Specification ....................................................................................................................... 17
9.2 General Inspection............................................................................................................... 17
9.3. Insulation Resistance Test .................................................................................................. 17
9.4 Current Transformer inspection and testing ........................................................................ 18
9.4.1Visual inspection ........................................................................................................... 19
9.4.2 CT Insulation Resistance Test ...................................................................................... 19
9.5 Relay configuration and testing........................................................................................... 19
9.6. CT primary Injection Test Report ...................................................................................... 20
9.7. Secondary Current Injection Test Report ........................................................................... 21
9.8. Surge Arrester Testing ....................................................................................................... 23
9.9. PT Check list ...................................................................................................................... 23
9.10. 33kv Incoming Power cable Insulation Resistance (IR) Test .......................................... 24
10. 33kv outgoing Line 1 .............................................................................................................. 24
10.1 Specification ...................................................................................................................... 24
10.2 General Inspection............................................................................................................. 24

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 1
66/33/15Kv Bedessa Substation Rehabilitation Work Report

10.3 Insulation Resistance Test ................................................................................................. 25


10.4 Current Transformer inspection and testing ...................................................................... 25
10.4.1Visual inspection ......................................................................................................... 26
10.4.2 CT Insulation Resistance Test .................................................................................... 26
10.5. Relay configuration and testing ........................................................................................... 26
10.6. CT primary Injection Test Report .................................................................................... 27
10.7. Secondary Current Injection Test Report ......................................................................... 28
10.8. Surge Arrester Testing ..................................................................................................... 30
10.9. 33kv Outgoing line 1 Power cable Insulation Resistance (IR) Test ................................ 30
11. 33kv outgoing Line 2 .............................................................................................................. 31
11.1 Specification ...................................................................................................................... 31
11.2 General Inspection............................................................................................................. 31
11.3 Insulation Resistance Test ................................................................................................. 31
11.4 Current Transformer inspection and testing ...................................................................... 32
11.4.1Visual inspection ......................................................................................................... 33
11.4.2 CT Insulation Resistance Test .................................................................................... 33
11.5 .Relay configuration and testing ........................................................................................... 33
11.6. CT primary Injection Test Report ........................................................................................ 34
11.7. Secondary Current Injection Test Report ............................................................................ 35
11.8. Surge Arrester Testing ......................................................................................................... 37
11.9. 33kv outgoing line 2 Power cable Insulation Resistance (IR) Test ..................................... 37
12. Final commissioning Between EEP and EEU ........................................................................ 38
Conclusion .................................................................................................................................... 41
Challenge ...................................................................................................................................... 41

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 2
66/33/15Kv Bedessa Substation Rehabilitation Work Report

List of Figures

Figure 1 :The available wiring on the panel ................................................................................... 6


Figure 2: Dismantling and lifting the panels to appropriate place using forklift machine ............. 8
Figure 3: After cleared the area of erection .................................................................................... 8
Figure 4: Shows when the panels were lifted from outside to control room .................................. 9
Figure 5: after the panels entered into the control room using crane and forklift .......................... 9
Figure 6: the Photos show activities to erect the panel on its required place ............................... 10
Figure 7: the photos show after the three panels have been erected ............................................. 11
Figure 8: Busbar connecting from incoming feeder to outgoing line ........................................... 12
Figure 9: the photos show while performing wiring works for each switchgear panels .............. 13

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 3
66/33/15Kv Bedessa Substation Rehabilitation Work Report

1. Introduction
Now a day, the demand for electrical energy is growing at a very fast rate. To cover this demand,
the existing power system network should be upgraded and rehabilitated to meet the need of the
customers. Bedessa 66/33/15kv substation is on of the power supplying substation which is
administered under Ethiopian Electric utility Oromiya region Chiro district and supplies power to
the town of Bedessa and around the area. This substation is too old and needs rehabilitation and
upgrading. Mostly, the available 33kv switchgear panels in this substation are too old. There
were two 33kv outgoing, 1 incoming and two spare panels. One of the outgoing panels is on the
incoming and the other is getting directed without circuit breaker. All lines are controlled and
protected by incoming feeder line. Most of circuit breakers are not functional and direct. The
protective relays are analogue and old model which don’t clear faults happening on the
distribution network. In addition to this, the fault happened on the 33kv panel trips the 66kv
circuit breaker and de-energizes the transformer through out a day which also interrupts the 15kv
side of the transformer as 66kv side interrupts. This problem needs a solution which solves the
above listed problem; the one is a rehabilitation and upgrading work on these 33kv switchgears.

2. Objectives
The main objective of this work is to rehabilitate the existing33kv switchgear panel and improve
control and protection system and reducing power interruption by replacing the old switchgear
with a new one. The specific objectives of this work include:

 To dismantle the old 33kv switchgear to have free space for the new panel
 To remove the old dismantled switchgear from its dismantled position
 To erect the new 33kv switchgear on its appropriate place
 To inspect the new 33kv switchgear components and request the unavailable accessories
for fitting
 To configure and test the available switchgear protection devices (protective and
measuring devices)
 To test the available switchgear components and confirming the test results
 To shift the 33kv power cable from the old panels to the new panel and energize
incoming and outgoing panels.

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 4
66/33/15Kv Bedessa Substation Rehabilitation Work Report

3. Scope of the project

The scope of this work


 Dismantling and lifting the old 33kv switchgear panels
 Erecting new 33kv Switchgear panels
 33KV switchgear panel wiring (for each panels)
 Testing and Commissioning of each switchgear components
 Testing and configuration of all protective relays
 Power cable shifting
 Energization of the lines

4. Main activities performed during this work

4.1 Inspection on The new 33kv Switchgear

We have made inspection to confirm that the components of the switchgear available or not. We
have found that some switchgear accessories are not brought with the pane. We have request the
following accessories to be brought for erection and energizing the panels. These are

 Connecting bus bar for each panel


 Circuit breaker charging handle
 Circuit breaker in and out handle
 Bakelite for each bus bar
 Switchgear lock keys
 Panel to Panel AC and DC supply connecting insulated
copper rods
 Bolts and nuts
 Schematic Drawings

Until these accessories are fulfilled we have performed 33kv old panel dismantling work.

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 5
66/33/15Kv Bedessa Substation Rehabilitation Work Report

4.2. Dismantling the old 33kv Switchgear

There were two old panels which were idle and not delivering power. So our work was started by
dismantling these panels and free up the space for erection of the new panel.

4.2.1 Removing wirings

The wires inside the panels were dismantled carefully to make isolate the panel to dismantle and
lift it to the appropriate place for transportation.

 AC and DC Supply wiring connecting panel to panel and


from 380v ac and125kv dc Panel
 VT wires coming from the incoming
 CT wiring for 66kv differential relay
 Ground Wires

Figure 1:-The available wiring on the panel

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 6
66/33/15Kv Bedessa Substation Rehabilitation Work Report

4.2.2 Dismantling the Panel

The erected panel is dismantled from the basement to make it ready for transportation by forklift.
This includes:-

 Disconnecting the bus bar line connecting these panel to other panel
 Disconnecting the power cable from the panels
 Removing nuts and bolts which fixes the panel with the basement and panel to panel
 Removing the Body grounds and any interlocks
 Lifting the panels from their dismantled position to the appropriate place using both
human power and forklift machine

While dismantling the panel

While make ready the panel for forklift machine for removing from the room

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 7
66/33/15Kv Bedessa Substation Rehabilitation Work Report

While the dismantled panel is lifted by forklift to outside

Figure 2: Dismantling and lifting the panels to appropriate place using forklift machine

Figure 3: After cleared the area of erection

4.3. Erection of the New 33kv Switchgears

After the panels were dismantled and the area is cleared the next task was erecting the new 33kv
switchgear panels on these places. First the 33kv incoming switchgear was going to be erected
while the two old panels were serving electricity. This is done to minimize the duration of
interruption time for restoring the service with the new panels. Under this the following task
were performed:-
 Lifting the new 33kv Switchgear from outside to control room using crane and
forklift
 Lifting the new 33kv switchgear to its erection place inside control room using
both crane and forklift
 Erecting the new panel when it is placed at its stand place

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 8
66/33/15Kv Bedessa Substation Rehabilitation Work Report

This photo shows when the crane lifts from outside to control room during evening time

Figure 4: Shows when the panels were lifted from outside to control room

Figure 5: After the panels entered into the control room using crane and forklift

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 9
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Figure 6: The above Photos show activities to erect the panel on its required place

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 10
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Figure 7: The above photos show after the three panels have been erected

Note: - The new 33kv panel erection work was carried out step by step to minimize the
interruption time.
First the new 33kv panel was erected, wired and tested and commissioned while the old
incoming 33kv panel was supplying power
After the panel tested and functional, the incoming and outgoing power cables were shifted from
the old 33kv panels to the new 33kv incoming panel and the line get energized. For the time
being, this panel was used as both incoming and outgoing panel until the two panels have been
erected.

5. Bus bar Connecting

According to our request, the required standard and number of copper bus bars were brought and

 We have used copper bus bars to distribute power from incoming panels to outgoing feeders
 Bus bar insulators were installed between each panels to insulate from metal sheet

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 11
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Figure 8: Bus bar connecting from incoming feeder to outgoing line

6. Earthing and System Ground connection

The non current carrying parts of the switchgears such as

Switchgear Components( CT,VT, Surge arrester, Switchgear body)


Power Cable (on both incoming and outgoing lines)
Ground rods (in case of outgoing line switchgears) were earthed to
avoid electric shock to personal and equipment protection.

In addition to this,

Star point of CT in secondary wiring


Star point of VT secondary wiring

were grounded to provide a return path for the leakage current and hence protect the equipment
from damage.

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 12
66/33/15Kv Bedessa Substation Rehabilitation Work Report

7. Wiring Works

The wiring work for each panels have been done according to the schematic drawing of the
switchgear. The wiring work includes

 DC Supply distribution for controlling and protection for each switchgear panels
 AC Supply distribution for lighting, heating and Socket for each switchgear panels
 VT Circuit Wiring for each Switchgear panels
Note: - The existing DC and AC distribution wires from the old panels were used to supply the
new incoming panels and distributed to each outgoing panels.

Figure 9: The photos show while performing wiring works for each switchgear panels

After the wiring work has been done, the panels were ready for pre commissioning and testing.
8. Pre commissioning and Tests

Pre commissioning test for switchgear components


 Circuit breakers
 CT
 VT
 Surge arrester
 Protective and measuring equipment ( relays, Voltmeters and Ammeters)
 Displays
 Power Cable
 Earthing Switch

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 13
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Table 1:- Incoming, Outgoing Line 1 and 2 Switchgear panels Pre-commissioning


PRE-COMMISSIONING CHECK LIST FORM

SWITCHGEAR-GENERAL
Equipment Type 33kv Switchgear panel
Make CHINA
Type Air Insulated Metal –Clad Switchgear
Feeder Name 33KV Incoming Feeder
Rated voltage 33kv
Rated current 200-400A
Serial Number 20220415-01
Model Number KYN61-33-1G
8.1 Mechanical Checks and Visual Inspection
S. Description Status Remarks if any
No Yes No
1 Switchgear is cleaned and free from dust/dirt, foreign 
materials etc.
2 Switchgear is free from all visible defects on physical 
inspection
3 Switchgear panel has been provided with and grounding 
4 Check that all nuts and bolts are tightened correctly as per 
specified torque
5 Leveling and alignment of switchgear and base frame 
checked
6 Tightness of nuts and bolts of bus bar and supports are 
checked
7 Auxiliary contacts and relays have been cleaned and free 
from dust /damage
8 All spare wires terminated at terminal blocks 
CT spare wires should be closed at terminal block
9 Erection completion certificate along with list of 
outstanding activities reviewed
10 Check control knobs and switches for freedom of movement 
and contact condition.
11 Inspect door handles, locking bars, and mechanism. 
12 Check door interlocks for positive operation. 
13 Check in and out circuit breaker mechanism for freedom of 
movement.
14 Check rails, guides, rollers, and shutter mechanism. 
15 Check Lubrication of draw out assembly parts as required. 
16 Inspect breaker and cell primary and secondary contacts and 
alignment.
17 Close and trip breakers manually in the connected, test and 
disconnected positions

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 14
66/33/15Kv Bedessa Substation Rehabilitation Work Report

PRE-COMMISSIONING CHECK LIST FORM

SWITCHGEAR-GENERAL
Equipment Type 33kv Switchgear panel
Make CHINA
Type Air Insulated Metal –Clad Switchgear
Feeder Name 33KV Outgoing Line 1
Rated voltage 33kv
Rated current 100-200A
Serial Number 20220301-09
Model Number KYN61-33-5G
Mechanical Checks and Visual Inspection

S. Description Status Remarks if any


No Yes No
1 Switchgear is cleaned and free from dust/dirt, foreign 
materials etc.
2 Switchgear is free from all visible defects on physical 
inspection
3 Switchgear panel has been provided with grounding 
4 Check that all nuts and bolts are tightened correctly as per 
specified torque
5 Leveling and alignment of switchgear and base frame 
checked
6 Tightness of nuts and bolts of bus bar and supports are 
checked
7 Auxiliary contacts and relays have been cleaned and free 
from dust /damage
8 All spare wires terminated at terminal blocks 
CT spare wires should be closed at terminal block
9 Erection completion certificate along with list of 
outstanding activities reviewed
10 Check control knobs and switches for freedom of movement 
and contact condition.
11 Inspect door handles, locking bars, and mechanism. 
12 Check door interlocks for positive operation. 
13 Check in and out circuit breaker mechanism for freedom of 
movement.
14 Check rails, guides, rollers, and shutter mechanism. 
15 Check Lubrication of draw out assembly parts as required. 
16 Inspect breaker and cell primary and secondary contacts and 
alignment.
17 Close and trip breakers manually in the connected, test and 
disconnected positions
18 Check mechanical and interlock operation of earth switch 

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 15
66/33/15Kv Bedessa Substation Rehabilitation Work Report

PRE-COMMISSIONING CHECK LIST FORM

SWITCHGEAR-GENERAL
Equipment Type 33kv Switchgear panel
Make CHINA
Type Air Insulated Metal –Clad Switchgear
Feeder Name 33KV Outgoing Line 2
Rated voltage 33kv
Rated current 100-200A
Serial Number 20220301-07
Model Number KYN61-33-3G
Visual Inspection

S. Description Status Remarks if any


No Yes No
1 Switchgear is cleaned and free from dust/dirt, foreign 
materials etc.
2 Switchgear is free from all visible defects on physical 
inspection
3 Switchgear panel has been provided with grounding 
4 Check that all nuts and bolts are tightened correctly as per 
specified torque
5 Leveling and alignment of switchgear and base frame 
checked
6 Tightness of nuts and bolts of bus bar and supports are 
checked
7 Auxiliary contacts and relays have been cleaned and free 
from dust /damage
8 All spare wires terminated at terminal blocks 
CT spare wires should be closed at terminal block
9 Erection completion certificate along with list of 
outstanding activities reviewed
10 Check control knobs and switches for freedom of movement 
and contact condition.
11 Inspect door handles, locking bars, and mechanism. 
12 Check door interlocks for positive operation. 
13 Check in and out circuit breaker mechanism for freedom of 
movement.
14 Check rails, guides, rollers, and shutter mechanism. 

15 Check Lubrication of draw out assembly parts as required. 


16 Inspect breaker and cell primary and secondary contacts and 
alignment.
17 Close and trip breakers manually in the connected, test and 
disconnected positions
18 Check mechanical and interlock operation of earth switch 

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 16
66/33/15Kv Bedessa Substation Rehabilitation Work Report

9. 33kv Incoming line feeder

Table 2:- Circuit Breaker data


Indoor vacuum Circuit Breaker
Equipment Name
Bedessa substation Date of Test Feb 12,2023
Site Location
System 33kv Incoming feeder

9.1. Specification
Sr.No Model Voltage Rated Making Breaking
Make/Type
Rating current capacity capacity
China 22080619 ZN85-40.5/T1250-31.5 40.5KV 1250A - 31.5kA

9.2 General Inspection

Table 3:-Mechanical And Electrical checking list of CB


Mechanical Check description Status Remarks Electrical Check Status Remarks
Description
Yes No Yes No
CB rack in/out operation  Spring charging 
operation
CB rack in/out indications  Test/service position 
switch
Manual spring charging operation  ON/OFF operation in 
Local/Remote
Spring charge indication  Spring Charge 
Indication
CB Manual ON/OFF operation  CB ON/OFF indication 

CB ON/OFF indication  Lamp Indication 


Emergency Trip Operation 
Power contact Alignment with 
panel contacts

9.3. Insulation Resistance Test

Aim: To get the insulation resistance of the Circuit breaker and to insure the performance and
functionality.

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 17
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Circuit Breaker Close Condition


Table 4:- Circuit Breaker Insulation resistance test @1Min, 5kv
R-S S-T R-T R-E S-E T-E

>1TΩ >1TΩ >1TΩ 56.9GΩ 59.6GΩ 62GΩ

Circuit Breaker Open Condition

@1Min, 5kv
Phase Measured Between Insulation Resistance in GΩ
R R-R’ 16.4GΩ
S S-S’ 41.6GΩ
T T-T’ 491GΩ

Note R – upper CB R pole S-upper CB S pole T- upper CB T pole

R’ - Lower CB R pole S’- Lower CB S pole T’- lower CB T pole


Contact Resistance

Phase Measured Between Insulation Resistance in milliohms


R R-R’ 0.4Ω
S S-S’ 0.4Ω
T T-T’ 0.4Ω

9.4 Current Transformer inspection and testing


Table 5:- Current Transformer nameplate data
CT location 33kv Incoming Feeder
1s1-1s2 1s1-1s3 2s1-2s2 2s1-2s3 3s1-3s2 3s1-3s3
Rated current Ratio 200A 400A 200A 400A 200A 400A
Core 1 Core 2 Core 3
Burden 50VA 50VA 50VA
Core 1 Core 2 Core 3
Accuracy class 0.1 5P20 5P20
R S T
Serial Number 2203372 2203371 2203370

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 18
66/33/15Kv Bedessa Substation Rehabilitation Work Report

9.4.1Visual inspection
Table 6:- CT visual inspection Checklist

S.No Description of Items Status Remarks


1 No physical damage on The CT ok
2 Prove that the wiring from CT to panel terminal block is as per ok
the approved drawing
3 Check the CT star point is properly earthed ok
4 Check all the CT connections properly tightened ok
5 Check the CT body is grounded ok
6 Check polarities of primary and secondary connection is as per ok
schematic drawing
7 Check the desired ratio is correctly selected as per the ok
schematic diagram and nameplate data
9.4.2 CT Insulation Resistance Test

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min
Table 6:-CT insulation Resistance Test
Primary-Ground IR test Results
R-G S-G T-G
63.9G 60.8G 68.7G
9.5 Relay configuration and testing

Relay Setting Record


Company 66/33/15KV Substation Date 7/06/2015E.C

Substation Bedessa Substation Equipment PMC-851X Relay


Table 7:- Relay setting value record
Configured Relay Setting Values
Substation Name Bedessa Substation
Voltage Level 33KV
Feeder 33kv Incoming Feeder
Relay Type PMC-851Multi functional Relay
Manufacturer China
Serial Number PMC-851X-E11115ACA
CT Ratio 200/1A

Configured Relay Setting Values

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 19
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Current Current Delay time


Existing setting value setting value Setting value
Protection in Secondary in Primary
Existing 67P2 0.6 120A 0.02 sec
Protection Relay 67P3 0.75 150A 0.00 sec
50P6 0.6 120A 0.02 sec
67N1 0.03 6A 0.02 sec
67N2 0.06 12A 0.00sec
9.6. CT primary Injection Test Report

This test was conducted to

 Check the correct installation from CT to relay and metering devices


 Check the functionality of CT primary and secondary windings, relay coils, trip
and alarm circuit
 Compare the relay and meter reading with the injected current value and observe
the error
Table 8:- CT primary current Injection Value
R-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

S-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 20
66/33/15Kv Bedessa Substation Rehabilitation Work Report

T-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR.No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

9.7. Secondary Current Injection Test Report

Secondary Injection Testing is carried out to determine the correct operation of circuits
connected to the secondary side of current transformer circuits. This testing relates to Protection
relay testing and Circuit Breaker trip tests. This test is performed to ensure that the trip functions
of a relay under various fault conditions are maintained within the setting values.
The testing relay includes:

 Trip Timing checks as per settings


 Correct operation of Auxiliary contacts
 Alarm functions
 Polarity checks
 Physical conditions

Relay Type: - PMC-851X multifunctional relay


CT ratio: - 200/1A
Sr.No:- PMC-851X-E11115ACA
Directional over Current and Earth Fault Relay
First Stage direction overcurrent (67P2)
Table 9:- Secondary current injection test results at each protection settings
Time setting
Current setting
Phase Operation
(I>=(67P2)=0.6) Relay and CB Status
(t67P2=0.5sec)
The Relay as well as the CB trips
Pick-up 0.6 0.48 Sec
R according to the protection setting Values

Start-Value 0.58
Pick-up 0.6 0.49 Sec
S
Start-Value 0.58
Pick-up 0.6 0.51 Sec
T
Start-Value 0.59

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 21
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Second Stage direction overcurrent (67P3)

Time setting
Current setting
Phase Operation
(I>=(67P3)=0.85) Relay and CB Status
(t67P3=0.03sec )
The Relay as well as the CB trips
Pick-up 0.85 0..028 Sec
R according to the protection setting Values
Start-Value 0.83
Pick-up 0.85 0.027 Sec
S
Start-Value 0.84
Pick-up 0.85 0.031 Sec
T
Start-Value 0.84

First Stage Earth fault protection (67N-1)


Time setting
Current setting
Phase Operation
(Io>=(67N-1)=0.03) (t67N-1=0.07sec) Relay and CB Status

The Relay as well as the CB trips according


Pick-up 0.03 0.068 Sec
R to the protection setting Values

Start-Value 0.029
Pick-up 0.03 0.069 Sec
S
Start-Value 0.028
Pick-up 0.03 0.071 Sec
T
Start-Value 0.028
Second Stage Earth fault protection (67N-2)
Time setting
Current setting
Phase Operation
(Io>=(67N-2)=0.06) (t67N-2=0.03sec) Relay and CB Status

The Relay as well as the CB trips


Pick-up 0.06 0.028 Sec
R according to the protection setting Values

Start-Value 0.05
Pick-up 0.06 0.027Sec
S
Start-Value 0.05
Pick-up 0.06 0.031 Sec
T
Start-Value 0.05

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 22
66/33/15Kv Bedessa Substation Rehabilitation Work Report

9.8. Surge Arrester Testing

Type: - Metal Oxide Surge Arrester


Feeder: - 33kv Incoming Feeder
Continuous Rated Voltage (Uc): - 41kv
Maximum Residual Voltage (Ur):- 51Kv
Sr.No:-001(R), 002(S), 082(T)
Table 10:- Surge Arrester IR test results
Surge Arrester IR test Results
R-G(top-bottom) S-G(top-bottom) T-G(top-bottom)
78.2GΩ 65.2GΩ 60GΩ

9.9. PT Check list

Type: - Indoor dry Type Voltage Transformer


Rated Insulation level: - 40.5/95/185kv
Primary Voltage: - 33kv
Secondary Voltage: - 100v
Accuracy Class: - 0.2 0.5 3P
Rated load: - 15 20 100 VA
Sr.No:- 2203311

Table 11:- PT inspection checklist


Sr.no Description of Items Status Remarks
1 No physical damage on the PT Ok
2 Prove that the wiring from PT to panel terminal block is as Ok
per the approved drawing
3 Check the PT primary Neutral point is properly earthed Ok
4 Check all the PT connections properly tightened Ok
5 Check the PT body is grounded Ok
6 Check that Primary fuse rating is as per the drawing and Ok
fuses are healthy
7 Check correct PT primary and secondary voltage reading on Ok
relay and meters

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 23
66/33/15Kv Bedessa Substation Rehabilitation Work Report

9.10. 33kv Incoming Power cable Insulation Resistance (IR) Test

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min
33kv incoming Power Cable Insulation Resistance(IR) test results
R-G S-G T-G
6.14TΩ >10TΩ >10TΩ

10. 33kv outgoing Line 1


Indoor vacuum Circuit Breaker
Equipment Name
Bedessa substation Date of Test Feb 20,2023
Site Location
33kv Outgoing Line 1
System
10.1 Specification

Sr.No Model Voltage Rated Making Breaking


Make/Type
Rating current capacity capacity
China 22080613 ZN85-40.5/T1250-31.5 40.5KV 1250A - 31.5kA

10.2 General Inspection

Status Remarks Electrical Check Status Remarks


Mechanical Check description Description
CB rack in/out operation Ok Spring charging operation Ok
CB rack in/out indications Ok Test/service position switch Ok
Manual spring charging Ok ON/OFF operation in Ok
operation Local/Remote
Spring charge indication Ok Spring Charge Indication Ok
CB Manual ON/OFF operation Ok CB ON/OFF indication Ok
CB ON/OFF indication Ok Lamp Indication Ok
Emergency Trip Operation Ok Ok

Power contact Alignment with Ok Ok


panel contacts

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 24
66/33/15Kv Bedessa Substation Rehabilitation Work Report

10.3 Insulation Resistance Test

Aim: To get the insulation resistance of the Circuit breaker and to insure the performance and
functionality.

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min

Circuit Breaker Close Condition


@1Min, 5kv
R-S S-T R-T R-E S-E T-E

>1TΩ >1TΩ >1TΩ 56.9GΩ 59.6GΩ 62GΩ

Circuit Breaker Open Condition

@1Min, 5kv
Phase Measured Between Insulation Resistance in GΩ
R R-R’ 4.52TΩ
S S-S’ >10ΩΩ
T T-T’ 1TΩ

Note R – upper CB R pole S-upper CB S pole T- upper CB T pole

R’ - Lower CB R pole S’- Lower CB S pole T’- lower CB T pole

Contact Resistance
Phase Measured Between Insulation Resistance in milliohms
R R-R’ 0.4Ω
S S-S’ 0.4Ω
T T-T’ 0.4Ω

10.4 Current Transformer inspection and testing


CT location 33kv Outgoing line 1
1s1-1s2 1s1-1s3 2s1-2s2 2s1-2s3 3s1-3s2 3s1-3s3
Rated current Ratio 100/1A 200/1A 100/1A 200/1A 100/1A 200/1A
Core 1 Core 2 Core 3
Burden 50VA 50VA 50VA
Core 1 Core 2 Core 3
Accuracy class 0.2 5P20 5P20
R S T
Serial Number 2202176 2202173 2202175

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 25
66/33/15Kv Bedessa Substation Rehabilitation Work Report

10.4.1Visual inspection

S. Description of Items Status Remarks


No
1 No physical damage on The CT Ok
2 Prove that the wiring from CT to panel terminal block is as per Ok
the approved drawing
3 Check the CT star point is properly earthed Ok
4 Check all the CT connections properly tightened Ok
5 Check the CT body is grounded Ok
6 Check polarities of primary and secondary connection is as per Ok
schematic drawing
7 Check the desired ratio is correctly selected as per the schematic Ok
diagram and nameplate data

10.4.2 CT Insulation Resistance Test

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min
Primary-Ground IR test Results
R-G S-G T-G
122GΩ 98GΩ 89GΩ

10.5. Relay configuration and testing

Relay Setting Record


Company 66/33/15KV Substation Date 8/06/2015E.C

Substation Bedessa Substation Equipment PMC-851X Relay

Configured Relay Setting Values


Substation Bedessa Substation
Name
Voltage Level 33KV
Feeder 33kv Outgoing line 1
Relay Type PMC-851Multi functional Relay
Manufacturer China
Serial Number PMC-851X-E11115ACA
CT Ratio 100/1A

Configured Relay Setting Values

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 26
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Current Current Delay time


Existing setting value setting value Setting value
Protection in Secondary in Primary
Existing 67P2 0.6 60A 0.05 sec
Protection Relay 67P3 1.2 120A 0.01 sec
50P6 0.6 60A 0.05 sec
67N1 0.07 7A 0.02 sec
67N2 0.1 10A 0.01sec
10.6. CT primary Injection Test Report

This test was conducted to


 Check the correct installation from CT to relay and metering devices
 Check the functionality of CT primary and secondary windings, relay coils, trip
and alarm circuit
 Compare the relay and meter reading with the injected current value and observe
the error
R-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

S-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 27
66/33/15Kv Bedessa Substation Rehabilitation Work Report

T-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR.No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

10.7. Secondary Current Injection Test Report

Secondary Injection Testing is carried out to determine the correct operation of circuits
connected to the secondary side of current transformer circuits. This testing relates to Protection
relay testing and Circuit Breaker trip tests. This test is performed to ensure that the trip functions
of a relay under various fault conditions are maintained within the setting values.
The testing relay includes:

 Trip Timing checks as per settings


 Correct operation of Auxiliary contacts
 Alarm functions
 Polarity checks
 Physical conditions
Relay Type: - PMC-851X multifunctional relay
CT ratio: - 100/1A
Sr.No:- PMC-851X-E11115ACA
Feeder: - 33Kv Outgoing Line 1
Test Instrument Used:-SMRT410 relay tester
Directional over Current and Earth Fault Relay
First Stage direction overcurrent (67P2)
Time setting
Current setting
Phase Operation
(I>=(67P2)=0.6) Relay and CB Status
(t67P2=0.05 sec )
The Relay as well as the CB trips
Pick-up 0.6 0.045 Sec
R according to the protection setting Values

Start-Value 0.58
Pick-up 0.6 0.049 Sec
S
Start-Value 0.58
Pick-up 0.6 0.049 Sec
T
Start-Value 0.59

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 28
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Second Stage direction overcurrent (67P3)

Time setting
Current setting
Phase Operation
(I>=(67P3)=1.2) Relay and CB Status
(t67P3=0.01sec )
The Relay as well as the CB trips
Pick-up 1.2 0.009 Sec
R according to the protection setting Values
Start-Value 1.19
Pick-up 1.2 0.008 Sec
S
Start-Value 1.19
Pick-up 1.2 0.02 Sec
T
Start-Value 1.19

First Stage Earth fault protection (67N-1)


Time setting
Current setting
Phase Operation
(Io>=(67N-1)=0.07) (t67N-1=0.02sec) Relay and CB Status

The Relay as well as the CB trips according


Pick-up 0.07 0.019 Sec
R to the protection setting Values

Start-Value 0.06
Pick-up 0.07 0.02 Sec
S
Start-Value 0.06
Pick-up 0.07 0.021 Sec
T
Start-Value 0.06

Second Stage Earth fault protection (67N-2)


Time setting
Current setting
Phase Operation
(Io>=(67N-2)=0.1) (t67N-2=0.01sec) Relay and CB Status

The Relay as well as the CB trips


Pick-up 0.06 0.02 Sec
R according to the protection setting Values

Start-Value 0.05
Pick-up 0.06 0.01Sec
S
Start-Value 0.05
Pick-up 0.06 0.009 Sec
T
Start-Value 0.05

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 29
66/33/15Kv Bedessa Substation Rehabilitation Work Report

10.8. Surge Arrester Testing

Type: - Metal Oxide Surge Arrester


Continuous Rated Voltage (Uc): - 41kv
Maximum Residual Voltage (Ur):- 51Kv
Feeder: - 33kv Outgoing Line 1
Sr.No:-001(R), 002(S), 082(T)
Surge Arrester IR test Results (@60sec,5kv)
R-G(top-bottom) S-G(top-bottom) T-G(top-bottom)
84GΩ 92GΩ 79GΩ

10.9. 33kv Outgoing line 1 Power cable Insulation Resistance (IR) Test

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min
33kv incoming Power Cable Insulation Resistance(IR) test results
R-G S-G T-G
>10TΩ 4.56TΩ >10TΩ

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 30
66/33/15Kv Bedessa Substation Rehabilitation Work Report

11. 33kv outgoing Line 2

Equipment Name Indoor vacuum Circuit Breaker

Site Location Bedessa substation Date of Test Feb 25,2023

System 33kv Outgoing Line 2

11.1 Specification
Sr.No Model Voltage Rated Making Breaking
Make/Type
Rating current capacity capacity
China 22080616 ZN85-40.5/T1250-31.5 40.5KV 1250A - 31.5kA

11.2 General Inspection

Status Remarks Electrical Check Status Remarks


Mechanical Check description Description
CB rack in/out operation Ok Spring charging operation Ok

CB rack in/out indications Ok Test/service position switch Ok


Manual spring charging Ok ON/OFF operation in Ok
operation Local/Remote
Spring charge indication Ok Spring Charge Indication Ok
CB Manual ON/OFF operation Ok CB ON/OFF indication Ok

CB ON/OFF indication Ok Lamp Indication Ok


Ok
Emergency Trip Operation
Ok
Power contact Alignment with
panel contacts
11.3 Insulation Resistance Test

Aim: To get the insulation resistance of the Circuit breaker and to insure the performance and
functionality.

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 31
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Circuit Breaker Close Condition


@1Min, 5kv
R-S S-T R-T R-E S-E T-E

>1TΩ >1TΩ >1TΩ 75.9GΩ 69.6GΩ 62GΩ

Circuit Breaker Open Condition

@1Min, 5kv
Phase Measured Between Insulation Resistance in GΩ
R R-R’ 74.4GΩ
S S-S’ 95.6GΩ

T T-T’ 137GΩ

Note R – upper CB R pole S-upper CB S pole T- upper CB T pole

R’ - Lower CB R pole S’- Lower CB S pole T’- lower CB T pole

Contact Resistance

Phase Measured Between Insulation Resistance in milliohms


R R-R’ 0.4Ω
S S-S’ 0.4Ω
T 0.4Ω
T-T’

11.4 Current Transformer inspection and testing

CT location 33kv Outgoing line 2


1s1-1s2 1s1-1s3 2s1-2s2 2s1-2s3 3s1-3s2 3s1-3s3
Rated current Ratio 100/1A 200/1A 100/1A 200/1A 100/1A 200/1A
Core 1 Core 2 Core 3
Burden 50VA 50VA 50VA
Core 1 Core 2 Core 3
Accuracy class 0.2 5P20 5P20
R S T
Serial Number 2202167 2202168 2202169

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 32
66/33/15Kv Bedessa Substation Rehabilitation Work Report

11.4.1Visual inspection

S.No Description of Items Status Remarks


1 No physical damage on The CT Ok
2 Prove that the wiring from CT to panel terminal block is as per Ok
the approved drawing
3 Check the CT star point is properly earthed Ok

4 Check all the CT connections properly tightened Ok


5 Check the CT body is grounded Ok
6 Check polarities of primary and secondary connection is as per Ok
schematic drawing
7 Check the desired ratio is correctly selected as per the Ok
schematic diagram and nameplate data

11.4.2 CT Insulation Resistance Test

 Megger Type:-Meggrer MIT525


 Applied Test voltage: - 5kv
 Test Time duration: - 1min
Primary-Ground IR test Results
R-G S-G T-G
79.5GΩ 80.8GΩ 87.0GΩ

11.5 .Relay configuration and testing

Relay Setting Record


Company 66/33/15KV Substation Date 17/06/2015E.C

Substation Bedessa Substation Equipment PMC-851X Relay

Configured Relay Setting Values


Substation Bedessa Substation
Name
Voltage Level 33KV
Feeder 33kv Outgoing line 2
Relay Type PMC-851Multi functional Relay
Manufacturer China
Serial Number PMC-851X-E11115ACA
CT Ratio 100/1A

Configured Relay Setting Values

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 33
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Current Current Delay time


Existing setting value setting value Setting value
Protection in Secondary in Primary
Existing 67P2 0.6 60A 0.05 sec
Protection Relay 67P3 1.2 120A 0.01 sec
50P6 0.6 60A 0.05 sec
67N1 0.07 7A 0.02 sec
67N2 0.1 10A 0.01sec

11.6. CT primary Injection Test Report

This test was conducted to

 Check the correct installation from CT to relay and metering devices


 Check the functionality of CT primary and secondary windings, relay coils, trip
and alarm circuit
 Compare the relay and meter reading with the injected current value and observe
the error
Test equipment
CT Tester; SCITS 100 range of 0-100A
Connector wires or Test leads
Digital multimeter: Fluke
Single Phase supply: - 220-240 V AC
R-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR. (A) (A) (A)
No
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 34
66/33/15Kv Bedessa Substation Rehabilitation Work Report

S-Phase
Sr. Injected Current Meter Reading Relay Reading Relay and CB Status
No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

T-Phase
Injected Current Meter Reading Relay Reading Relay and CB Status
SR.No (A) (A) (A)
1 10 10 10 The relay then CB trips
2 20 20 20
3 30 30 30 according to the above
4 50 50 50 relay setting values.
5 80 80 80
6 100 100 100
7 120 120 120

11.7. Secondary Current Injection Test Report

Secondary Injection Testing is carried out to determine the correct operation of circuits
connected to the secondary side of current transformer circuits. This testing relates to Protection
relay testing and Circuit Breaker trip tests. This test is performed to ensure that the trip functions
of a relay under various fault conditions are maintained within the setting values.
The testing relay includes:
 Trip Timing checks as per settings
 Correct operation of Auxiliary contacts
 Alarm functions
 Polarity checks
 Physical conditions

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 35
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Specifications
Relay Type: - PMC-851X multifunctional relay
CT ratio: - 100/1A
Sr.No:- PMC-851X-E11115ACA
Feeder: - 33Kv Outgoing Line 1
Test Instrument Used:-SCITS 100 secondary current Injection Test set
Directional over Current and Earth Fault Relay

First Stage direction overcurrent (67P2)


Time setting
Current setting
Phase Operation
(I>=(67P2)=0.6) Relay and CB Status
(t67P2=0.05 sec )
The Relay as well as the CB trips
Pick-up 0.59 0.045 Sec
R according to the protection setting Values

Start-Value 0.58
Pick-up 0.6 0.049 Sec
S
Start-Value 0.58
Pick-up 0.59 0.049 Sec
T
Start-Value 0.58
Second Stage direction overcurrent (67P3)

Time setting
Current setting
Phase Operation
(I>=(67P3)=1.2) Relay and CB Status
(t67P3=0.01sec )
The Relay as well as the CB trips
Pick-up 1.2 0.009 Sec
R according to the protection setting Values
Start-Value 1.19
Pick-up 1.2 0.008 Sec
S
Start-Value 1.19
Pick-up 1.2 0.02 Sec
T
Start-Value 1.19

First Stage Earth fault protection (67N-1)


Time setting
Current setting
Phase Operation
(Io>=(67N-1)=0.07) (t67N-1=0.02sec) Relay and CB Status

The Relay as well as the CB trips according


Pick-up 0.07 0.019 Sec
R to the protection setting Values

Start-Value 0.06
Pick-up 0.07 0.02 Sec
S
Start-Value 0.06
Pick-up 0.07 0.021 Sec
T
Start-Value 0.06

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 36
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Second Stage Earth fault protection (67N-2)


Time setting
Current setting
Phase Operation
(Io>=(67N-2)=0.1) (t67N-2=0.01sec) Relay and CB Status

The Relay as well as the CB trips


Pick-up 0.1 0.02 Sec
R according to the protection setting Values

Start-Value 0.09
Pick-up 0.1 0.01Sec
S
Start-Value 0.08
Pick-up 0.1 0.009 Sec
T
Start-Value 0.09

11.8. Surge Arrester Testing

Type: - Metal Oxide Surge Arrester


Continuous Rated Voltage (Uc): - 41kv
Maximum Residual Voltage (Ur):- 51Kv
Feeder: - 33kv Outgoing Line 2
Sr.No:-002(R), 016(S), 014(T)
Surge Arrester IR test Results(@ 5kv, 60sec)
R-G(top-bottom) S-G(top-bottom) T-G(top-bottom)
78.0GΩ 77.4GΩ 75.3GΩ

11.9. 33kv outgoing line 2 Power cable Insulation Resistance (IR) Test
 Megger Type:-Meggrer MIT525
 Applied Test voltage: - 5kv
 Test Time duration: - 1min
33kv incoming Power Cable Insulation Resistance(IR) test results(@ 5kv, 60sec)
R-G S-G T-G
>10TΩ >10TΩ >10TΩ

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 37
66/33/15Kv Bedessa Substation Rehabilitation Work Report

12. Final commissioning Between EEP and EEU

Name of Substation: 66/33/15kv Bedessa Substation

Sr.No Activity Approval Remark


OK/NOT OK
1.0 Bay Name:-33kv Transformer incoming Switchgear Panel

1.1 Checking of CB operational open/close OK

1.2 Checking of spring charging motor OK

1.3 Tightness of power cable OK

1.4 Connection of AC and DC wires OK

2 Tests for Protection Relay OK

2.1 Checking on Relay/meter reading OK

2.2 Signal or alarm check OK

2.3 Check on relay setting OK

2.4 Trip test for OC/EF OK

3 Energization OK

Commissioning Team

Name of Employee Signature Date Name of Employee Signature Date


EEU Eskinder Tesfaye EEP Girma Dechasa
19/06/2015 19/06/2015
Kasahun Seme 19/06/2015 Bitew Ayalew 19/06/2015
Biruk Tibebu 19/06/2015
Approved By

Name of Employee Signature Date Name of Employee Signature Date


EEU Diriba Teshome Wordi Mohamed
19/06/2015 EEP 19/06/2015
19/06/2015 Kedir Abdella 19/06/2015

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 38
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Name of Substation: 66/33/15kv Bedessa Substation

Sr.No Activity Approval Remark


OK/NOT OK
1.0 Bay Name:-33kv Outgoing line 1 Switchgear Panel

1.1 Checking of CB operational open/close OK

1.2 Checking of spring charging motor OK

1.3 Tightness of power cable OK

1.4 Connection of AC and DC wires OK

2 Tests for Protection Relay OK

2.1 Checking on Relay/meter reading OK

2.2 Signal or alarm check OK

2.3 Check on relay setting OK

2.4 Trip test for OC/EF OK

3 Energization OK

Commissioning Team

Name of Employee Signature Date Name of Employee Signature Date


EEU Eskinder Tesfaye EEP Girma Dechasa
19/06/2015 19/06/2015
Kasahun Seme 19/06/2015 Bitew Ayalew 19/06/2015
Biruk Tibebu 19/06/2015
Approved By

Name of Employee Signature Date Name of Employee Signature Date


EEU Diriba Teshome Wordi Mohamed
19/06/2015 EEP 19/06/2015
19/06/2015 Kedir Abdella 19/06/2015

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 39
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Name of Substation: 66/33/15kv Bedessa Substation

Sr.No Activity Approval Remark


OK/NOT OK
1.0 Bay Name:-33kv Outgoing line 2 Switchgear Panel

1.1 Checking of CB operational open/close OK

1.2 Checking of spring charging motor OK

1.3 Tightness of power cable OK

1.4 Connection of AC and DC wires OK

2 Tests for Protection Relay OK

2.1 Checking on Relay/meter reading OK

2.2 Signal or alarm check OK

2.3 Check on relay setting OK

2.4 Trip test for OC/EF OK

3 Energization OK

Commissioning Team

Name of Employee Signature Date Name of Employee Signature Date


EEU Eskinder Tesfaye EEP Girma Dechasa
19/06/2015 19/06/2015
Kasahun Seme 19/06/2015 Bitew Ayalew 19/06/2015
Biruk Tibebu 19/06/2015
Approved By

Name of Employee Signature Date Name of Employee Signature Date


EEU Diriba Teshome Wordi Mohamed
19/06/2015 EEP 19/06/2015
19/06/2015 Kedir Abdella 19/06/2015

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 40
66/33/15Kv Bedessa Substation Rehabilitation Work Report

Conclusion
The aim of this project was to made rehabilitation and upgrading work on 33kv switchgear
panels. The work includes:
Dismantling
Erecting
Testing and Commissioning
Energization

Each switchgear panel has been tested and commissioned and the results were analyzed to
confirm each panels were ready for energization.All the test results were good and according to
the standards. After all, the lines were energized successfully without any problems.

Challenge

The challenge we face during this project work includes:

 Heaviness of the new switchgear panels to lift


 Delay of machinery for lifting the switchgear panels
 Environment factors i.e. dust

Bedessa Substation 33kv switchgear rehabilitation and upgrading work report Page 41