Professional Documents
Culture Documents
Grupo135 - TP - Arias - Guerra - Arti - Largo Ingles
Grupo135 - TP - Arias - Guerra - Arti - Largo Ingles
Grupo135 - TP - Arias - Guerra - Arti - Largo Ingles
Abstract — The non-delivery of orders due to low productive The importance of this study lies in the economic impact,
capacity is one of the main problems faced by companies in the which is approximately 13.81% of the annual turnover. A
manufacturing sector. This has repercussions, creating significant amount for a developing company in the industry
customer dissatisfaction and directly affecting profits by and that is affected by the failure to meet delivery dates, losing
increasing production costs. The company under study is in the customer loyalty. There is no history of case studies or
manufacturing sector in the manufacture of poles covered with methodologies in similar companies worldwide. But, there is
fiberglass. The present work proposes to improve the fulfillment a similarity in the process to the carpentry industry, even
of delivery to the orders, whose key indicators will be the " On
automotive footwear where a main reason for analysis is the
time delivery , the availability and the lead time". These delays
production process. One of the main causes of delivery delays
in deliveries are caused by operational and maintenance errors
in the manufacture of fiberglass reinforced poles, which in turn
lies in downtime in the laminate, where the root cause lies in
cause large losses of money that are reflected in penalty the operation. Due to this, we analyzed the publication of G.
payments, rework, overtime, among others that are out of Kovacs [1]in his 2020 publication where he analyzes 13 Lean
planning. Delivery delays are caused by operational problems, methods, including SW and FLD, to improve the work cycle,
mechanical and electrical failures, as well as inadequate promoting continuous improvement, which he does by
warehouse management that takes time, not scheduled, in the reducing it by 11.7%, in the same way the WIP by 36%. On
delivery of materials. For this, a methodology is presented that the other hand, Braglia publishes a case study in 2019, where
implements 5 Lean Manufacturing tools based on Standard he implements a mixed SW methodology with an OTE
Works, TPM, Kanban and SLP. The research shares the legal measure ( Overall tasks Effectiveness ). The OTE has a
and regulatory framework relevant to the implementation in distinctive feature from other KPIs in that it provides a
this sector and to the manufacture of poles. The results of the breakdown structure for process losses that simplifies the task
methodology that is implemented in this project evaluate and of assessing current performance while individualizing it [2].
measure the performance of the manufacturing process of This author determines the effectiveness of the tasks in 81.3%.
fiberglass reinforced poles. This study also found it pertinent to implement TPM to solve
unscheduled stops in the laminating area. According to the
Keywords—Lean Manufacturing, Total Productivity publication by Xiang Z. [3]where the maintenance of plant
Management, Value Stream Mapping, Standard Work, Kanban.
equipment changes from passive to active, increasing the
overall effectiveness from 54.33% to 66.9%, highlighting that
these improvements are not temporary but must be in constant
change and analysis highlighting the study de Moscoso in
I. INTRODUCTION 2020, which, apart from implementing TPM, adds to this
methodology a cyclical analysis of RCM in annual periods
that guarantee equipment availability in 30 hours of
The company under study is in the manufacturing category production, that is, an increase of 15%[4]
of plastics coated with fiberglass resins (PRFV) in the Warehouse delays to deliver supplies, dies and other
manufacture of poles, previously not analyzed. The poles are consumables to internal customers affect the process by
a column to be used as a support or support for different cables 22.6%, it is essential to add to our methodology the SLP tool
that are laid for public services such as fiber optic cables, that will be focused on reducing the journey of operators in
electrical cables and related equipment such as transformers search of materials in the warehouse. For this, we will take
and street lighting. The company under study is JG4, it is a Silvestre's study as a reference in the 2022 publication, where
young company that has been in the market for around 4 years compliance with on-time deliveries improves with the
within the economic analysis of the year 2022. The problem optimization of the plant, analyzing the activities and the
of said company lies in external expenses, for this reason the different situations, thereby reducing the service time by 22%
main economic and financial expenses were analyzed. and increasing the productivity by 38% [5].
projects, making a Pareto diagram where the problems of costs
due to delays and penalties stood out with an overwhelming Composite utility poles currently account for around 1%
96.1% compared to the expenses for damaged product, of the total utility poles deployed globally. The main
incorrect billing, wrong order, wrong price and others. advantages are the material's corrosion resistance, low
maintenance requirements, termite immunity, practicability of
and pest infestation [6]. For this reason, the demand for the
mitigation of losses through the structured analysis of why and Reducir el tiempo de ciclo, el
Kovács, (2020) SW SLP número de estaciones,
FMEA or Weibull failure analysis, however , Vaz, et al., distancia de recorrido.
(2021) indicate that the implementation should only be carried Pekarcikova, M.,
Entregar información
Trebuna, P.,
out by only 6 to 8 technicians and Bataineh , et al., (2019) Kliment, M., SW K
adecuada eliminando
reprocesos y reduciendo
emphasizes the reduction of costs due to the waste generated Mizerak, M., & costos.
Kral, S. (2021)
by the identified causes of availability of lines increased by Reducir el tiempo de
13% (from 68.6 to 77.51%). The OEE increased by 62.6% espera,este debe fusionarse
Silvestre, et al., con la SW, incrementar el
(from 35.27 to 57.42%), thus achieving the 50 percent target (2022)
SW SLP
cumplimiento de las órdenes
de trabajo, optimizar la
set by the KSCC company. productividad
Reducir actividad de picking
v. SLP Balcazar, et al.,
SW SLP
(recojo), Incrementar el
(2019) rendimiento de los
operadores.
The SLP is a method of designing the procedural layout of Isidro, et al., (2021) SW SLP Aumentar a efectividad global
a plant, the process is direct, when the work areas are badly Xiang, y Chin,
Aumentar a efectividad global,
designed they generate long transfer times from one work (2021)
SW PME PMP aumentar el MTBF y disminuir
el MTTR
station to another. However, it is used for any area within a Sharma (2019) SW PME PMP Aumentar a efectividad global
company such as offices, warehouses, among others through
Bataineh, et al., Aumentar a efectividad global
the methodology. Sylvestre (2022) indicated that after (2019)
SW PME PMP
y disponibilidad
applying SLP, the waiting time of a service process was
reduced by 22% [5], however, it must be merged with the Table 1. Important articles for the creation of the proposed
work standardization tool, since, if the travel time is reduced, methodology.
At the time of applying the production process these
improvements should be considered. As for his study, after the Unlike the other models applied in different manufacturing
implementation of SLP, order fulfillment increased from sectors, the proposed model is regulated by legal norms and
94.43% to 98%, productivity variation increased from 30 to regulations that provide confidence in its implementation,
38% and production time was reduced from 15.94 to 12.75 highlighting the expected results. Likewise, the
min/pair implementation of MTTR and MTBF maintenance indicators
will highlight a radical change in maintenance management,
since definitions such as availability and reliability are new for
JG4, thus, more than optimization, the organizational culture
III. INPUT of the production area will be changed. .
B. General contribution subsection
To determine the technical gap, it has been indicated that Based on the research and previous review of 40 scientific
the level of compliance of delivery on time OTD ( On time articles, the study proposes a Lean model based on TPM tools
delivery ) must be no less than 95% [20]. The company under (focused improvement and planned maintenance), Kanban,
study presents an OTD of 59% for the year 2022 and 60% for SLP and SW for the optimization of GRP manufacturing and
the year 2021. In the year 2020, under a state of pandemic by as observed in Figure 1 the model is made up of these 5
COVID 19, the OTD was 82%, said year is considered an components.
atypical year since only 291 poles were produced, but 51 were
delivered out of time. For the years 2021 and 2022, the
production was greater than 1,000 posts, delivering more than
400 posts out of time.
The second component that you have is the TPM tool in the
focused improvement pillar, for this the artifacts that we will Figure 4Implementation flowchart of the TPM planned maintenance
use are. pillar tool
Likewise, for the implementation of the TPM tool in the Figure 5. Flowchart of the implementation of the KANBAN tool
planned maintenance pillar, we will make use of the artifacts.
• Wait for raw material: This wait is eliminated so it is
transferred to the general process and this wait is eliminated
for the lamination process.
Finally, SLP will be carried out for a redesign of the raw • Transport raw material to production: Eliminate this activity
material storage area, for which the following artifacts are since it is carried out with the delivery of the mold and wax,
used. as well as with the other inputs.
- warehouse layout • Placing fiberglass coils on shelves: Once the mold is placed
- List of activities and spaces in position, this activity is carried out in parallel. It is applied
- course diagrams in general process.
- materials flowchart
• Align glass fibers: Two operators at the same time, one on
The raw materials warehouse must be improved due to the each side of the winding machine, the process time is reduced.
generation of delays that it produces in the delivery of the • Place cylinders of resin in dispenser: It is applied in the
finished product, for the development of the new warehouse general process, in parallel to the activities before rolling.
distribution the flow of raw materials, relationship of activities
• Check adjustment of mold clamps: Operator 1 must carry out
and space requirement with the flow must be identified. of
this revision and Operator 2 the revision of the rails and
information in parallel, for this, the modifications must be
machine.
considered in accordance with the limitations and restrictions
of the warehouse design to later complement it with due • Review rails and machine: Eliminate this activity, it is
compliance with the process and control of metrics, if these carried out in parallel with the activity of reviewing
are improved, the development of the proposal for otherwise adjustment of mold clamps.
it returns to the material flow identification as shown in figure • Give approval for start of production: Eliminate this activity,
6. the approval is given when the operators have reviewed the
clamps, rails and machine, digitally and immediately.
These countermeasures and other less relevant ones are
applied to the laminating process, as shown in table 32,
reducing the time from 13.40 hours to 9.73 hours, reducing the
NVA to 3.89 hours and VA to 5.84 hours .
Consequently, the projection of posts delivered late by means
of the extrapolation tool is reduced to 20 posts per year due to
unproductive time in the rolling process, equivalent to 15% of
the total unscheduled stops in rolling, reducing the total of
poles delivered late from 93 to 20 poles and the total from 209
to 136 poles , reducing the days of delay from 263 to 56.42
days for a total of S/27,081.21 in penalties. By reducing posts
with delivery delays with the help of this tool , the level of on-
Figure 6. SLP Implementation Flowchart time delivery (OTD) compliance would be reduced from 452
to 379, increasing from 59.39% to 65.95% . The days of delay
are reduced from 3.01 to 2.37 days per process, the production
time is reduced from 30.74 hours to 23.99 hours and the
D. Input Subsection Process percentage of the availability factor is increased from 75.30%
For the implementation of our proposal we will adhere to the to 89.09%.
design of our implementation model 2. TPM focused improvement
1. work standardization For the implementation of the TPM focused improvement
For the implementation, the "laminated" bottleneck process pillar, unscheduled stops due to misuse of machines are
will be standardized with 13.4 hours due to constant analyzed as shown in the table.
operational errors, out of a total of 30.74 hours that the Table 2. List of most recurring operational failures.
manufacture of a post takes. To do this, within the DAP format
of our work, the activities are analyzed and divided into those
that generate added value and those that do not, such as
reprocessing and waiting.
For the development of the work standardization tool, it is
observed that the total 120 of NVA is 6.61 hours and VA is
6.69 hours. Therefore, the following countermeasures are
proposed .
• Request raw material required for the production of 1 post:
When the request for the mold is made, it must be done with
the raw material, including fiberglass and resin in the general
process.
The probability of occurrence of a delay in the delivery of cools down to do a test. The test is executed and the
poles is 0.07 and the occurrence of days of delay is 0.35 . maintenance technician gives approval for the continuity • A
total delay of 12 days.
b. Improvement points
It should be noted that the maintenance technicians only work
fiberglass winder 1 shift in the morning, which means that the stoppage lasts for
The problem is that the filament winder turns on when the more than 1 day. A total delay of 92 days
mold is carried, overheating without use. In the areas, a warning type poster must be placed, where it
The operators turn it on for convenience and not to return must be alerted to turn off the equipment properly, as shown
again, having stops for 248 days. So, to fix the problem, you below, it is also placed for each of the improvement points.
should turn it off to have maintenance personnel check for any The solution is to put up posters and signs in such a way that
damage and wait until it cools down to do a test. it helps the operators to better use the machines , the
improvement observations are given specifically to 5
resin dispenser activities and improvements:
The problem of the stop is why the operators do not turn off • Configure machine according to pole specifications
the dosing machine before placing the resin cylinders. (dimensions): Check that computer and screen have not been
The dosing machine has a malfunction so the operators call turned off .
maintenance. • Check clamps, rails and machine and start of production
To fix the problem, it should be turned off and checked by conformity: Lubricate rails, check coiler off, dosing machine
maintenance personnel for any damage and wait until it cools off
down to test. The test is executed and the maintenance • Start machine: Power on after placing molds and inspections
technician gives approval for continuity. A total delay of 69
days. 132 • Shut down machine: Ensure due shutdown (others)
Computer • Carry out curing (two lines of 4 posts are placed separately):
Check machine before starting production (others)
The computer was turned off before configuration, by the
operator. The computer does not turn on until a specialized By applying the improvements considering a probability of
technician reviews it, so the delay is to contact the service error of 5% and a confidence level of 95%, the time is reduced
provider and schedule a visit. So, to fix the problem, you from 9.73 hours to 9.67 hours as shown in table 46, reducing
should turn it off to have maintenance personnel check for any the NVA to 1.14 hours and VA to 8.54 hours
damage and wait until it cools down to do a test. The test is The calculation of the cost for the inappropriate use of
executed and the maintenance technician gives approval for machinery is reduced to S/6756.62 due to the reduction of the
continuity. A total delay of 41 days. delay time from 248 to 14.08 days, which reflects the
rails projection of the reduction from 78 to 4 posts
When checking the rails, the operators do not lubricate them, 3. TPM planned maintenance
which must be done every time a post production process In the history of stoppages that arose in production, from
begins. The dosing machine stops due to lack of lubrication which the 3-day MTTR and 35.23-day MTBF were
and the operators must turn off production until the problem calculated, broken down into notification time, stoppage
is solved. Therefore, they must call maintenance in case this awaiting corrective maintenance execution, corrective
anomaly complicates the production system, considering that maintenance execution, and notification of completion of
maintenance technicians only work one shift. So, to fix the maintenance
problem, you should turn it off to have maintenance personnel
check for any damage and wait until it cools down to do a test. The company planned the execution of preventive
The test is executed and the maintenance technician gives maintenance and projects a certain amount of corrective in a
approval for continuity. 133 with a total delay of 18 days. ratio of MP:MC of 5:1 , However , the execution of preventive
maintenance was not fulfilled, originating a greater amount of
Others
corrective maintenance. The reasons for the non-compliance
They are different stops for misuse of any other equipment or with the execution of PM are generally due to the fact that the
machinery. So they should call maintenance in case this production lines are busy and cannot stop to execute an MC.
anomaly complicates the production system . So, to fix the For the improvement of the process, it must be divided into
problem, it should be turned off to have maintenance two parts, the first is given in the month of December of the
personnel check for any damage and wait until it cools down year for the programming of the preventive maintenance
to do a test The test is executed and the maintenance management, according to the MTBF indicator, for this the
technician confirms for continuity A total delay of 16 days . dates of the planned maintenance, once finished it is sent to
Screen the production area for the approval of the dates and then it is
scheduled by the maintenance area .
It disconnects from power without turning off the screen
properly, which could damage the screen itself. The screen The second part focuses on the preventive maintenance
does not turn on until a specialized technician reviews it, so management process, that is, the management that must be
the delay is to contact the service provider and schedule a visit. executed every time a scheduled preventive maintenance
So, to fix the problem, you should turn it off to have occurs and only the production area is given the opportunity
maintenance personnel check for any damage and wait until it to change 3 times, otherwise the maintenance will be
executed. PM on an agreed date before the period expires and When projecting the OTD increases from 59.39% to 85.80%
the next schedule arrives, with a probability that a repair will (table 83), and the stability of the availability is reduced to
occur, such as figure 7. 96%, it is reduced by the stability of the tools,
𝐶𝑡𝑑 𝑑𝑒 𝑃𝑟𝑜𝑑. 𝑒𝑛𝑡𝑟𝑒𝑔𝑎𝑑𝑜𝑠 − 𝐶𝑡𝑑 𝑑𝑒 𝑝𝑟𝑜𝑑. 𝑒𝑛𝑡𝑟𝑒𝑔𝑎𝑑𝑜𝑠 𝑐𝑜𝑛 𝑑𝑒𝑚𝑜𝑟𝑎 Figure 8. Expression of the distribution of the activity Request raw
𝑂𝑇𝐷 =
𝐶𝑡𝑑 𝑑𝑒 𝑝𝑟𝑜𝑑 𝐸𝑛𝑡𝑟𝑒𝑔𝑎𝑑𝑜𝑠 material mold and wax in warehouse
In table 2 we will indicate our current status compared to the
initial objectives that will be the point of effectiveness of this The Input Analyzer tool provides the expression of the data
project. distribution when the squared error of the expression is
smaller than other distributions, as for example for the first
activity that is presented in figure 3, the smallest squared
Table 3. AS-IS TO BE indicators and project goals. error is 0.00243, which corresponds to a BETA distribution,
then we consign all our data to calculate the amount of our
replica, taking a confidence level of 95% with a z value of
1.96, we determine that the probability of the data with the
study characteristic is 0.6 and those that do not have such
characteristics is 0.4, the total number of processes is 1113,
assuming that the sample error is 0.1 for the current process,
the same conditions are considered for the simulation of the
proposed process, calculating a total of 88 replicates.
After data collection, they are entered into the Input The report regarding the simulation of the proposed
Analyzer tool of the Arena program Request mold raw process shows the times per activity, as well as the wait
material and wax in warehouse of the current process, where and/or delay, the total process time without delays or waits is
it is obtained that the expression of the data distribution is Total time 10.70 hours with a Queue of 4.29 hours , with a
total production of 1113 posts, with the total number of posts V. DISCUSSION
manufactured late for a total of 86. The goal posed by L ahrichi becomes very ambitious for the
manufacturing sector of fiberglass-based components in our
A. Metrics-traffic lights-results country. Since, the social culture and the technological risks
impact the organizational culture. As M.Braglia indicates, an
important factor is good social development and keeping any
The results of the indicators are presented in Table 4 where
country at the forefront of globalization, as well as good
the indicators of the current process have been calculated and
performance and participation, motivation and good
coincide with the calculation of the indicators after the
organization, to maintain perpetuity in the development of the
analysis of the current situation. The same occurs with those
process.
projected indicators for the proposed process.
Table 5. Comparison of current calculated and simulated Today our operators are over 50 years old, many of them are
indicators resistant to changes in their methods, which puts us at high
risk of failing in each of our implementations. On the other
hand, an important step that we skip in the process of
Planning, as Xiang indicated, is the interview of the staff to
take innovation ideas and rescue the good practices of the
employees, this was emphasized by our technical supervisor
who gave us more scope for improvements using the tools
that we presented to the management area.
Table 6. Comparison of calculated and simulated projected We still have 2.5% to reach to reach the goal and new ideas
indicators give us light to continue with the improvements, changing the
organizational culture, maintaining a loyal commitment and
a team committed to the continuous improvement of our
process in order to always deliver our orders. on time and
keeping the customer satisfied
VI. CONCLUSIONS