BOQ Summary Page 1 of 1

Academic license user


CONNECTED USER:

BOQ SUMMARY

Project Name: CEZA_BEAMS (RD)

Element :  Beam

No. Material Unit Quantity Rate $ Cost $


1 Concrete C21 (cum) 84.11 6500.00 546715
Sub Total 84.11 5,46,715

Rebar 10MM
2 (kg) 4446.83 53.00 235682
(Fy414)
Rebar 16MM
3 (kg) 4252.83 53.00 225400
(Fy414)
Rebar 20MM
4 (kg) 2239.26 53.00 118681
(Fy414)
Rebar 25MM
5 (kg) 3546.66 53.00 187973
(Fy414)
Sub Total 14485.58 7,67,735

6 Shuttering (sqm) 546.16 600.00 327696


Sub Total 3,27,696

Grand Total 16,42,146

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 172.22 kg/cum
2 Consumption : Reinforcement/Planarea = 15.54 kg/sqm
3 Consumption : Concrete/Planarea = 0.09 cum/sqm
4 Concrete % C21 = 100.00 % 
5 Shuttering  = 6.49 sqm/cum