PROPOSED ENHANCEMENT OF EXISTING MAIN SWITCHBOARD (MSB) AT SELECTED TOLL PLAZA'S OF NORTH-SOUTH EXPRESSWAY - 8 MONTH

ID Task Name Duration Start Finish Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
May Jun Jul Aug Sep Oct Nov Dec Jan
1 PROPOSED ENHANCEMENT OF EXISTING MAIN SWITCHBOARD 245 days Thu 1/6/23 Wed 31/1/24
(MSB) AT SELECTED TOLL PLAZA'S OF NORTH-SOUTH
EXPRESSWAY - 8 MONTH

2 Preliminaries 245 days Thu 1/6/23 Wed 31/1/24


3 LOA/ Contract Signing 1 day Thu 1/6/23 Thu 1/6/23
4 Kick Off Meeting 1 day Fri 2/6/23 Fri 2/6/23
5 a) Submission of Shop Drawing/Catalogs/Method Statement 30 days Sat 3/6/23 Sun 2/7/23
6 b) Approval of Shop Drawing/Catalogs/Method Statement 14 days Mon 3/7/23 Sun 16/7/23
7 c) Submission Of Insurance 2 days Fri 2/6/23 Sat 3/6/23
8 d) Monthly Report & Progress Photographs 245 days Thu 1/6/23 Wed 31/1/24
9 Procurement of Materials/Equipment 90 days Mon 17/7/23 Sat 14/10/23
10 i) Main Switchboard (MSB) 90 days Mon 17/7/23Sat 14/10/23
11 ii) Rental Genset 90 days Mon 17/7/23 Sat 14/10/23
12 Installation Of Main Switchboard (MSB) 86 days Sun 15/10/23 Mon 8/1/24
13 Sungai Besi Toll Plaza 24 days Sun 15/10/23 Tue 7/11/23
14 a) Site Preparation & Submission Work Permit 20 days Sun 15/10/23Fri 3/11/23
15 b) Delivery Rental Genset 1 day Sat 4/11/23 Sat 4/11/23
16 c) Delivery Temporary Switchboard & New MSB 1 day Sun 5/11/23 Sun 5/11/23
17 d) Lay Temporary Cables ( Rental Genset , Temporary 1 day Mon 6/11/23 Mon 6/11/23
Switchboard & PLUS SSB)
18 e) TNB Shutdown & Dismantle Works 1 day Mon 6/11/23Mon 6/11/23
19 f) Installation of MSB & Cable Termination 1 day Mon 6/11/23Mon 6/11/23
20 g) Testing & Commissioning 1 day Tue 7/11/23 Tue 7/11/23
21 Pedas Linggi Toll Plaza 19 days Wed 8/11/23 Sun 26/11/23
22 a) Site Preparation & Submission Work Permit 15 days Wed 8/11/23Wed 22/11/23
23 b) Delivery Rental Genset 1 day Thu Thu 23/11/23
23/11/23
24 c) Delivery Temporary Switchboard & New MSB 1 day Fri 24/11/23 Fri 24/11/23
25 d) Lay Temporary Cables ( Rental Genset , Temporary Switchboard
1 day & PLUS Sat
SSB)25/11/23 Sat 25/11/23
26 e) TNB Shutdown & Dismantle Works 1 day Sat 25/11/23 Sat 25/11/23
27 f) Installation of MSB & Cable Termination 1 day Sat 25/11/23 Sat 25/11/23
28 g) Testing & Commissioning 1 day Sun 26/11/23 Sun 26/11/23
29 Yong Peng (U) Toll Plaza 24 days Mon 27/11/23Wed 20/12/23
30 a) Site Preparation & Submission Work Permit 20 days Mon 27/11/23Sat 16/12/23
31 b) Delivery Rental Genset 1 day Sun 17/12/23Sun 17/12/23
32 c) Delivery Temporary Switchboard & New MSB 1 day Mon Mon 18/12/23
18/12/23
33 d) Lay Temporary Cables ( Rental Genset , Temporary Switchboard
1 day & PLUS Tue
SSB)19/12/23 Tue 19/12/23
34 e) TNB Shutdown & Dismantle Works 1 day Tue 19/12/23Tue 19/12/23
35 f) Installation of MSB & Cable Termination 1 day Tue 19/12/23Tue 19/12/23
36 g) Testing & Commissioning 1 day Wed 20/12/23 Wed 20/12/23
37 Kuala Kangsar Toll Plaza 19 days Thu 21/12/23 Mon 8/1/24
38 a) Site Preparation & Submission Work Permit 15 days Thu 21/12/23Thu 4/1/24
39 b) Delivery Rental Genset 1 day Fri 5/1/24 Fri 5/1/24
40 c) Delivery Temporary Switchboard & New MSB 1 day Sat 6/1/24 Sat 6/1/24
41 d) Lay Temporary Cables ( Rental Genset , Temporary Switchboard
1 day & PLUS Sun
SSB)7/1/24 Sun 7/1/24
42 e) TNB Shutdown & Dismantle Works 1 day Sun 7/1/24 Sun 7/1/24
43 f) Installation of MSB & Cable Termination 1 day Sun 7/1/24 Sun 7/1/24
44 g) Testing & Commissioning 1 day Mon 8/1/24 Mon 8/1/24
45 Authority Application & Documentation 17 days Tue 9/1/24 Thu 25/1/24
46 a) O&M & As Built Drawings 12 days Tue 9/1/24 Sat 20/1/24
47 b) Training 5 days Sun 21/1/24 Thu 25/1/24
48 Handover & Site Clearing 6 days Fri 26/1/24 Wed 31/1/24
49 Site Clearing 5 days Fri 26/1/24 Tue 30/1/24
50 Handover 1 day Wed 31/1/24Wed 31/1/24

Project: PLUS BERHAD Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Date: 24 May 2023 Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Company : SSL DEV SDN BHD Milestone Inactive Task Manual Task Manual Summary External Tasks Progress