Professional Documents
Culture Documents
Coach Manual Jan 2014
Coach Manual Jan 2014
Coach Manual Jan 2014
CHAPTER 1
COACH
Chapter 1, Page 1 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
105a On receipt of a coach for POH, it must be 105d The coach should never be lifted from one
taken on Lifting line/ Stripping line where end only. If lifted from one end, the
electrical fittings should be stripped and Centre pivots and the dash pot guides are
batteries removed. Furnishings, especially likely to suffer damages, body panels are
seats and backrests should be inspected likely to get dented near the body bolster.
thoroughly and only those that require The sealed windows of AC coaches are
repairs or attention should be removed. also likely to break.
105b Before lifting a coach, the following
components should be removed, 105e After the coach body is lifted, it should be
disengaged or disconnected:- kept on trestles. The revolving steel
(i) Dynamo belt on the axle pulley in trestles of the design shown in Figure 1.3
case of underframe mounted (sketch 77310) would prove useful for this
dynamos and disconnection of purpose Lines should be protected by
electrical connection from junction scotch blocks with locking arrangement
box on alternator in case of bogie and key should be kept with Engineer till
mounted alternator. the time maintenance work is carried out.
(ii) Lavatory chute, if situated over the 105f The entire under frame should be cleaned
bogie. of dust, rust etc. from underneath by
(iii) Brake pull rod from bogie brake pneumatic/water jet followed by wire
rigging. brushing at critical locations and check for
(iv) Centre pivot cotter. cracks/damage, corrosion etc. on the
(v) Axle box safety straps. under frame members. Refer chapter 2
(Shell) for carrying out repairs on the
(vi) Bolster safety straps.
coach shell.
(vii) Steel/ wooden blocks of requisite
thickness should be inserted in 105g After carrying out all repairs, the under
between the bolster and bogie frame should be painted as detailed in the
frame on both sides and of both the chapter on Painting.
bogies so as to keep the bolster
springs compressed. 106 LOWERING THE COACH BODY
(viii) Dismantle vertical shock absorbers. 106a After all the repairs are carried out refit all
(ix) Air vent screws on bogie frame repaired sub-assemblies which are
above dash pots should be removed for maintenance and lower the
unscrewed completely after coach body on the overhauled and tested
cleaning the area around the air bogies.
vent holes properly.
(x) Vacuum/air brake fittings 106b The Centre pivot cotter should be fitted
(xi) Buffer and draw gear into position and secured by means of a
(xii) Lavatory chutes split pin. A bottom cover should be fitted
in position to cover the entire assembly to
(xiii) Under slung water tanks & WRAS,
prevent dust getting in.
where provided.
Chapter 1, Page 2 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
F
7
3
A B C D E K L
1 2 3 4 5 10 11 12
1 1 2 3 9 1 1
G J
M
3 3
8 H 1
9
2
N
ACTIVITY DESCRIPTION 9 DURATION (Days)
A. VERIFICATION OF DEFICIENCIES.PB. PRE-INSPECTION & LIFTINGPC. STRIPPINGPD. BODY REPAIR, MODIFICATIONS
AND ALTERATIONSPE. PAINTINGPF. FITTING OF WATER TANK, PLUMBING & LEAKAGE TESTINGPG. REPAIRS TO INTERIOR 1P
PANELSPH. FITMENT OF SHUTTERSPI. FITMENT OF DOORSPJ. FITMENT OF BERTHS & SEATSPK. VACUUM / AIR BRAKE 1P
TESTING & FINAL WORKSPL. FINAL INSPECTION & DESPATCHPM. FITMENT OF AXLE PULLEY, TENSION ROD & TESTING OF 2P
COACH WIRINGPN. TESTING OF BRANCH WIRING & FITMENT OF ELECTRICAL EQUIPMENT 3P
9P
3P
3P
2P
1P
3P
1P
1P
1P TOTAL DURATION= P18 DAYS
9
FIGURE 1.1
LIFTING PADS
AIR VENT SCREWS IN BOGIE SIDE FRAME
SKETCH-68078
FIGURE 1.2
Chapter 1, Page 3 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
COACH 3250
NOTE:P1.
SEE C.R.DRG.
U/FRAME 2742
FOR DETAILS
NO. J&TP
SEE C.R.DRG.
150
DEV-99 &102
NO. J&T DEV-85P2. FOR ALTE RNATIVE DESIGNS
1100
1850
1200 FREE HEIGHT
25
600
275 3008
750
FIGURE 1.3
Chapter 1, Page 4 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
Chapter 1, Page 5 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
PART- I
BOGIE FRAME
C
BOGIE BOLSTER
G
A
E
L.S. BEAM
F
M
B
RAIL LEVEL
PART- II
BODY BOLSTER
H
BOGIE BOLSTER
J
NI
RAIL LEVEL
NOTE - P1. Dimensions E & J shall be maintained with required number of compensating rings of standard thickness of 4 mm.P2. Axle box springs : WTAC
-0-1-202P Bolster springs : WTAC -0-5-202
FIGURE 1.4a
Chapter 1, Page 6 of 41
Hindi Contents
Table 1.3
Tare 11 6
END
Gross 35+8/-5 43±5 33+5/-2 276+6/-4 287 ±3 683 ±5 1098 +8/-5 67 ±3 301+6/-4 307 ±3 43 ±5 640 +8/-5 - -
ARMVAC
Tare 38±5 40±5 36±3 272+6/-4 290 ±3 686 ±5 1104 +0/-10 70 ±3 296+6/-4 310 ±3 40 ±5 646 ±5 18 14
DRIVING
NON
END
Gross 33+8/-5 44±5 32+5/-2 268+6/-4 286 ±3 682 ±5 1095 +8/-5 65 ±3 291+7/-4 305 ±3 45 ±5 637 +8/-5 - -
Chapter 1, Page 7 of 41
Hindi Contents
Table 1.4
Chapter 1, Page 8 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
PART- I
%%
c9
15
BOGIE FRAME
X
BOGIE BOLSTER
Z
G
B
L.S. BEAM
F
#
RAIL LEVEL
PART- II
BODY BOLSTER
BOGIE BOLSTER
H
RAIL LEVEL
NOTE - P1. Dimensions A & B marked should be ensured less than dimensions C & D marked respectively.P2. # CR to drawing No.-CC01140 to be
provided.P3. * CR to drawing No. - CC05252 to be provided.P4. 'F' the variation in all the four bogie corner heights must be less than or equal to
10 mm.P5. Drawing No. WTAC3-9-0.306 alt -e, AE90014, AE90015 are superseded by this drawing.P6. The height of axle box spring and Bolster
spring in tare and gross conditions is for reference only.P7. The requirement of CR's as shown in the columns for primary & secondary suspension is for
reference only.P8. The compensation by means of CR's must not exceed 20 mm in primary in all coaches except ACCN (SG) inP ACCN (SG) it is
30 mm & 30 mm in secondary suspension for all coaches.
Chapter 1, Page 8 of 41
AC
of
(SG)
(SG)
Type
(EOG)
(EOG)
(EOG)
coach
ACCZ
ACCN
ACCN
ACCW
ACCW
43.1 52.53 48.3 49.1 44.8 In tonnes
Tare
weight
of coach
5.36 5.12 5.12 3.68 3.68 In tonnes
Normal
pay load
Chapter 1, Page 10 of 41
5.36 5.12 5.12 3.68 3.68 In tonnes
pay
load
Total
tare
tonnes Under
bogie
tonnes
Gross
Under
Maintenance Manual for BG coaches of ICF design
Gross
clearance
Gross
clearance
Nil 22 12 14 4 #
CR
Axle box spring height
Table 1.5
Nil 19 7 9 Nil *
Bolster spring
CR
X
Crown
clearance
Bogie bolster
of
VP
RA
AC)
IRQ
(SG)
(SG)
Type
(NON
FACZ
CITY)
(EOG)
coach
ACCZ
ACCN
CAPA
(HIGH
RA AC
46.69 41.3 32 41.3 42.6 46.83 In tonnes
Tare
weight
of coach
1.20 5.12 23 1.20 3.68 5.84 In tonnes
load
Norm
al pay
Chapter 1, Page 11 of 41
1.20 5.12 23 1.20 3.68 5.84 In tonnes
pay
load
Total
tonnes
Under
bogie
tonnes
Gross
Under
Maintenance Manual for BG coaches of ICF design
Gross
clearance
8 19 03 11 Nil 9 #
CR
Axle box spring height
3 15 Nil 17 Nil 3 *
Bolster spring
CR
X
Crown
clearance
PART- I
%%
c91
5
BOGIE FRAME
X
BOGIE BOLSTER
Z
G
B
L.S. BEAM
F
#
RAIL LEVEL
PART- II
D
BOGIE FRAME SIDE BEARER
C
BOGIE BOLSTER
Y
RAIL LEVEL
NOTE - P1. Dimensions A & B marked should be ensured less than dimensions C & D marked respectively.P2. # CR to drawing
No.-CC01140 to be provided.P3. * CR to drawing No. - CC05251 to be provided.P4. 'F' the variation in all the four bogie corner
heights must be less than or equal to 10 mm.P5. Drawing No. SG90002, SZ90004, SE90011, LB90002 are superseded by this
drawing.P6. The height of Axle box spring and bolster spring in tare & gross conditions is for reference only.P7. The requirement of CR's
as shown in the columns for primary & 30 mm in secondary suspension.P8. Only blue bend springs both in primary and secondary
stage are to be used in postal van coach.
Chapter 1, Page 13 of 41
AC
of
GS
Type
coach
SCN
SOC
38.03 37.00 36.99 In tonnes
of
Tare
coach
weight
5.76 7.02 5.85 In tonnes
load
Norm
al pay
Chapter 1, Page 13 of 41
- 100% 100% In tonnes
load
Over
5.76 14.04 11.70 In tonnes
pay
load
Total
13.12 12.6 12.6 In tonnes
tare
Under
Maintenance Manual for BG coaches of ICF design
bogie
Gross
Under
Gross
bolster
Gross
clearance
3 1 1 #
Hindi
CR
10 7 7 *
CR
X
Crown
Gross
clearance
height
bolster
Z
height
Buffer
of
al
VP
Type
IRQ
coach
Van
Post
SLR
SCN
36.5 37.2 32.00 37.10 In tonnes
of
Tare
coach
weight
3.0 5.76 18.00 10.60 In tonnes
load
Norm
al pay
Chapter 1, Page 13 of 41
- - - 2.6 In tonnes
load
Over
bogie
Gross
Under
Gross
bolster
Gross
clearance
#
Axle box spring
Nil 1 5 1 CR
Hindi
CR
*
5 7 13 7
X
Crown
Gross
clearance
height
bolster
Coach
107 EXAMINATION OF TRAINS b) Speed of the train shall not be more
than 30 KMPH,
107a Examination of originating trains c) It should cover the entire length of
i) All trains must be examined by the train,
mechanical train examining staff before d) Should have adequate space for fixing
dispatch to ensure that all coaches on the lighting arrangement and for staff.
the train are in fit condition and without ii) For rolling in examination of train it has
rejectable defects (for rejectable defects, to be ensured that proper lighting
please refer to IRCA Conference Rules, arrangement is provided on both the sides
Part IV). On formation of a rake and of the track at nominated spots for
after its placement for Examination, examination of undergear parts during
washing, cleaning and watering, the night. Focussing of lights shall be done by
station master (SM) shall pass necessary keeping a coach on the line and adjusting
memo to the Engineer (C&W). After the angle of light to illuminate undergear
carrying out all necessary work, the and bogie. Use of fixed lights as indicated
Engineer (C&W) shall communicate in figure 1.5 is preferable.
fitness of the train to Station Master.
Normally, Railways have standard iii) C&W staff should take position at
forms for the use of Station Masters and nominated rolling in place on both the
Engineers for this purpose. Railways, sides of the track before the arrival of
where such forms are not used, should train.
also start using these forms as uniform iv) As the train passes the nominated point,
practice for the guidance of both C&W staff should watch out vigilantly for
Engineer (C&W) and Station Master. loose/hanging/broken undergear parts of
The Station Master shall not dispatch the coaches, any unusual sound coming
the train unless the fitness certificate, in from the coaches or any other abnormality
the prescribed form, is received from the in the coaches.
Engineer (C&W).
ii) The level of the air pressure/vacuum on v) After train comes to halt, it should be
the train engine and the brake van ensured that the train is protected from
gauges as well as the percentage of both the sides (with the stop board/red
operative cylinders should be recorded flag during day time and red lamp during
on a prescribed certificate and night time) before commencing the
signatures of the driver and the guard of examination of the train. It should be
the train should be obtained by the ensured that a suitable indication board is
Engineer (C&W) as per the procedure placed at conspicuous location visible to
laid down by each Railway. A suggested the driver indicating that C&W staff is at
standard format for the certificate is work.
placed at Annexure 1.1. No train should vi) Temperature of the axle boxes should be
be allowed to leave with an measured preferably with the help of the
inoperative/defective Brake cylinder on electronic temperature measuring device.
any coach after pit attention. Trains
which have been attended on pitline vii) Brake release shall be checked by
should have 100% brake power. physically moving the brake beam.
Trains which are attended on platform However, in case where train locomotive
or where secondary examination has has to be detached, brakes of all coaches
been dispensed with or enroute should shall first be manually released. For
have minimum 90% brake power. checking the release of brakes the hook
may be used (drawing of hook is attached
107b Enroute/Terminating Examination of as figure 1.6).
Passenger Trains
viii) Other undergear parts should be examined
i) Sr.DME/DME incharge shall nominate visually to ensure that the train is safe to
the site for carrying out rolling in/rolling run further. During night the
out examination after personal inspection lamps/search light shall be used for
of site. While nominating the site illumination .
following should be kept in view:
ix) Repairs if required should be carried out
a) Site shall provide unobstructed view of promptly to avoid detention to train to the
undergear from both sides. extent possible.
Chapter 1, Page 13 of 41
Maintenance Manual for BG coaches of ICF design Hindi Contents
Coach
370
EXPANDED METAL
100
MESH
FOR ADJUSTING FOCUS
SWIVEL JOINT WITH NUT &
BOLT
450
250
225
30 MM FLAT
100
50
550
ISMC 100
HINGES
250 W FOCUS BULB
325
CONCRETE BASE
G.L.
1200
598
c
%
6
8 %
R9
MATERIAL :- M.S. ROUND BAR TO IS:2062PWEIGHT :- 0.590 KG
(Approx.)
21
Chapter 1, Page 13 of 41
Hindi Contents
x) Lavatories of the coaches should be properly cleaned using High pressure water jet machine provided at nominated stations during halt of the train. Any
complaint from passengers should be attended promptly to the satisfaction of the passenger.
xi) After attending to any required repairs stop board/red flag should be removed.
xii) Carriage controller (CCR) should be informed about any out of course work done.
xiii) CCR shall repeat the out of course work done to the Primary Maintenance (PM) depot after corrective action.
xiv) At the train examination stations where locomotives are changed on through trains, the level of air pressure/vacuum created on the locomotive and brake
van gauges should be recorded on the certificate to be issued to the guard and driver on prescribed form. The inoperative/blanked cylinders, if any, should
also be written in the certificate for their information. This certification should be an endorsement on the original brake power certificate; no fresh brake
power certificate needs to be issued.
108. MAINTENANCE PATTERN FOR COACHING TRAINS
(Railway Board letter no. 95/M(C)/141/1 dtd. 29.10.01 )
Table 1.8
Sr. Category of trains Preventive Under gear examination Internal cleaning, External Enroute/Terminating Brake system
No. maintenance and brake system passenger amenity cleaning on examination check prior to
schedules at pitline maintenance at pit line attention and nominated line start at platform
watering with proper at the other end
facilities
01 Mail/Exp. One- At primary end At both the ends At both the ends At both the ends Enroute: After every 250 Complete air/
way run>2500 to 350 kms of run at vacuum check with
kms locations to be decided fresh BPC.
by Railway for each train.
Terminating Exam
Terminating station
02 Mail/Exp. One At primary end At both the ends At both the ends At both the ends - do - Complete
way run<2500 air/vacuum check
kms but round with fresh BPC.
trip run> 2500
kms
3 Mail/Exp. Round At primary end At both the ends At both the ends At primary ends - do - Only continuity
(a) Trip run upto check if stabled at
2500 kms platform,
otherwise, brake
power check with
endorsement on
original BPC.
Chapter 1, Page 13 of 41
Hindi Contents
Sr. Category of trains Preventive Under gear examination Internal cleaning, External Enroute/Terminating Brake system
No. maintenance and brake system passenger amenity cleaning on examination check prior to
schedules at pitline maintenance at pit line attention and nominated line start at platform
watering with proper at the other end
facilities
3 Shuttles/Intercon At primary end To be done after 2500 At primary end and At primary end Enroute: After every 250 Only continuity
(b) nected Mail/Exp. kms or 4 days whichever each terminal or as Once a day for to 350 kms of run at check if stabled at
round trip run is earlier only at Primary decided by the shuttles. locations to be decided platform,
upto 2500 kms. end. CME to ensure by Railway for each train. otherwise, brake
proper cleanliness. Terminating Exam power check with
Each Terminating station endorsement on
original BPC.
4. Passenger trains At primary end To be done after 2500 At every terminal At primary end. Enroute: After every 250
with toilets kms or 7 days whichever or as decided by to 350 kms of run at
including is earlier at Primary end. the CME to ensure locations to be decided
interconnected proper cleanliness. by Railway for each train.
passenger Terminating Exam
trains/Shuttles Once a day at nominated
Terminating station
5. Passenger trains At primary end To be done after 2500 Once a day At primary end. Once a day at primary or Only continuity
without toilets. kms or 7 days whichever a nominated terminal. check if stabled at
is earlier at Primary end. platform,
otherwise brake
power check with
endorsement on
original BPC.
n Internal cleaning, Passenger amenity attention and watering may be done at platform line or nominated stabling line provided stipulated facilities are available at
such line.
n Incase the rake stabled in yard for more than 6 hours positive safety arrangement should be made for the rake and in case the security is considered inadequate, the
rakes should be taken to pit line for attention to under gear as given under column (4).
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
109b External Cleaning / Washing v) The flooring should be rubbed with nylon
bristles/sponge brush and cleaned with
i) Place the rake/coaches on the washing pit recommended cleaning agent. The drain
provided with equipments required for holes should be cleaned thoroughly for
washing and cleaning. It should be easy discharge of water.
ensured that the rake/coach is protected vi) The mirrors in toilet should be cleaned
with proper board/signal for safety of the with light wet cloth. Recommended
staff working on washing/cleaning job to solution should be used for cleaning the
prevent movement/disturbance in the dirty portion of glasses.
activity. Scotch blocks with locking vii) After all the washing and cleaning in the
arrangement should protect lines and keys toilets mentioned above, the toilets should
should be kept with Engineer (C&W) till be thoroughly cleaned with water jets and
the time rake is under maintenance. water should be flushed out. All fittings
ii) Before starting washing and cleaning of and floor should be wiped dry with a cloth.
side wall, ensure that the glass shutters viii) After cleaning, spray deodorant in the
and louver shutters of that side are toilet to remove the bad odour.
lowered. Remove dirt/dust accumulated
on shutters by compressed air or duster. 109d Internal cleaning of upper class AC and
sleeper coaches
iii) Remove old reservation charts/labels on
the body panels. Splash water on old i) Collect the cigarette ends from all Ash
charts so that they are wet for easy trays, news paper from magazine bag and
separation. Care should be taken to avoid waste from dust bin. Sweep the whole
any damage to the paint. coach with broom in sleeper coaches.
iv) The cleaning solution should be Clean the floor of AC coaches with
spread/rubbed with nylon brush or sponge vacuum cleaner.
brushes and then rubbed thoroughly to ii) Remove dust from floor, berths/seat,
clean the panels. Extra attention should be magazine nylon wire mesh bag fitted on
given to oily and badly stained surfaces. panels and fan guards with duster. Use of
v) Destination boards may be removed and vacuum cleaner is excellent in such areas.
cleaned with brush/duster. iii) Also remove dust/dirt from under the
vi) Clean the external surface by high berths, window sill, sliding door, railing
pressure jet where facilities are available. corner and all corner & crevices of coach
interior with vacuum cleaner if provided.
vii) All exterior panels including end panels
iv) Ceiling panels, wall panels, cushion
should be hosed with water and brushed
berths, fittings, table top, etc. should be
with diluted soft soap (detergent solution)
cleaned with duster and stain marks on
The strength of the solution may be
these should be removed by use of
increased or decreased according to
recommended soft detergent.
RDSO specification M&C/PCN/101/
v) Aluminum frames, strips, and other metal
2001.
fittings, etc. should be cleaned with
109c Cleaning of Toilet recommended cleaning agent.
vi) FRP window frames, louvers, etc. should
i) Before starting cleaning of toilets ensure be cleaned with recommended solution
that all repairs in the toilets have been and rubbed out by nylon brush or sponge
carried out and after cleaning no /duster to remove stain marks.
employee should enter in the toilet. vii) Alarm chain handle and its holding
ii) Doors and walls should be cleaned with bracket should be washed and cleaned.
water sprayed by high pressure jet up to viii) The coach flooring should be rubbed with
waist level. Apply specified solution and hard coir brush and PVC flooring should
rub thoroughly with sponge be rubbed with nylon bristles/sponge
brush/duster/nylon bristle brush. brush and cleaned with recommended
iii) Indian style lavatory pans have to be cleaning agent.
cleaned by thorough rubbing with ix) In AC coaches, the amenity fittings and
concentrated solution of recommended toilet fittings such as coat hanger, stools,
cleaning agent. arm rest, foot rest, towel hanger, etc.
iv) Western style commode shall be cleaned should be cleaned with duster. Stains on
as (iii) however due care should be taken these items should be removed with
that recommended solution should not fall recommended detergent solution.
on commode lid which may damage/spoil x) The compartment carpet should be
it. cleaned with vacuum cleaner. Every
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
month, the carpet should be cleaned (Railway Bd.'s letter no. 98/M( C)/137/19
thoroughly by taking it out from Pt. I dt. 28.7.99 & dt. 05.05.2000)
compartment and if necessary they should
be dry cleaned in every three to four 110a Infra structural Requirements
months. Before re-laying the carpet, the (i) 24 coach length fully equipped pit
compartment floor should be thoroughly line.
cleaned. (ii) High pressure jet cleaning pipeline
xi) Spray recommended air freshener in the with plant for cleaning at primary
coach. No employee should be allow to pit line. Mechanised external
enter the coach for any purpose/work after cleaning is preferable.
complete cleaning (iii) Water hydrants for 24 coach length
at en route watering stations with 20
xii) Curtains in the AC Coaches and Tourist
minutes stoppage at nominated
Cars should be removed for periodical
stations
washing and cleaning. Faded and
(iv) Availability of the prescribed air
damaged curtains should be replaced on
brake maintenance and testing
condition basis.
equipment.
xiii) Precaution should be taken to prevent
nuisance of cockroaches in AC coaches 110b Coach Design related Requirements
and pantry cars by periodical spray of (i) Air brake with twin pipe graduated
recommended insecticides release system
xiv) No repair works on Electrical train (ii) Only enhanced capacity draw gear
light/fan/AC) or Mechanical account and screw coupling to RDSO sketch
should be left to be carried out after No. 79061 and 79067 are to be
washing and cleaning of the coach.. provided on the rake
110c Maintenance Practices and system
109e Internal Cleaning of GS, SLR related requirements
(i) The integrity of the rakes to be
i) Cleaning of GS, guard and passenger maintained.
compartments of SLR should be done as (ii) Primary maintenance of the rake
mentioned under para 109d above should be done in one hook without
wherever applicable. splitting
(iii) Minimum maintenance time of 6
ii) If necessary clean the wooden seat and
hours on the pit during primary
their frames with recommended detergent
maintenance
solution and water.
(iv) It is mandatory to provide secondary
iii) Interior surfaces of parcel and luggage maintenance to all trains augmented
vans should be cleaned with to 24 coaches .
recommended detergent and water. (v) Trains leakage rate to be maintained
within prescribed limits by using
rake test rig.
109f Cleaning of buffers and screw couplings (vi) Provision of proportionate brake
system on the locomotive in good
i) Buffer plungers should be scrubbed with a working order
scraper to remove dirt and muck. (vii) Provision of audio visual alarm
Thereafter, they should be wiped clean system on the locomotive
with cleaning oil and rubbed with coir (viii)In case of double-headed diesel locos
rope. maximum traction motor current will
be restricted to 650 amperes and in
ii) Screw coupling threads should be cleaned case of double headed WAP1/WAP3
with wire brush to remove all dirt and electric locos, the traction motor
dust. Thereafter, it should be cleaned and current limit will be 750 amperes as
given a light coat of oil. Oiling should be prescribed in RDSO 's instructions
done on slack adjuster also. for operation of main line air brake
trains - C-9408.
110 CONDITIONS REQUIRED FOR
MAINTENANCE OF 24 COACH 110d Operational requirements
TRAINS
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
i) Communication between driver and guard the permission of the Chief Mechanical
should be provided through suitable Engineer and according to the calling in
means. program of the workshop.
iii) For requesting permission for non-POH
ii) Special care to ensure no gap between
repairs, the supervisor incharge of the
coach buffers after tightening the coupler.
depot should prepare a complete list of
iii) No additional coach attachment beyond damages and deficiencies and forward it
24 coaches will be permissible. to Divisional Mechanical Engineer for
getting permission of the Chief
111 MAINTENANCE PRACTICES IN Mechanical Engineer to book the coach to
OPEN LINE DEPOTS the shop for non-POH repairs. A copy of
the list of damages and deficiencies
111a Nomination of a Depot should simultaneously be sent to the
workshop concerned for planning it in
i) All passenger coaching vehicles (PCVs), their calling-in programme.
other coaching vehicles (OCVs), owned
by individual railways should be allotted a 111c Intermediate Overhaul
base depot for primary maintenance and a
base workshops for periodical overhaul i) All bogies of such ICF coaches shall be
and special repairs by the Chief
given IOH after six months ± 15 days of
Mechanical Engineer/Chief Operation
the date of last POH as per table 1.1. All
Manager of the Railway.
the newly built coaches shall be given
ii) The base depot to which the coaches are IOH after one year of service.
allotted will be responsible for their ii) During this lifting schedule,
maintenance. It will also be responsible bogies/underframe members and body
for the secondary maintenance of the including trough floors of integral type
coaches as prescribed by the Railway. coaches should be thoroughly examined
iii) If a coaching stock allotted to a particular and all parts of running gears are repaired/
depot, finds its way to another depot, it replaced as necessary. The bogie frames
should be despatched to the allotted depot should be particularly checked to detect
for proper service. damage, cracks or deformation and
necessary repairs carried out. Where it is
iv) Due to exigencies of service a coach of not possible for the maintenance depot to
another depot can be retained with the do these repairs or are prohibited to be
sanction of the Chief Mechanical done in the maintenance depots, the
Engineer (CME). It should, however, be bogies should be sent to the shops for
subjected to necessary examination and carrying out these repairs.
repairs including maintenance schedules iii) The detailed table of maintenance
in the manner as it belonged to the depot. activities to be carried out during IOH
v) No overdue periodical overhaul (POH) schedule is enclosed as appendix-G.
coaches of other railway should be iv) The date of intermediate lifting should
allowed in service but should be booked then be stencilled at the appropriate place
to the owning railway for POH. in schedule chart on the end panel.
vi) If home railway stock is retained in
service beyond return date for any reason, 111d Formation of Block Rakes
IRCA rule 2.2.4 should be followed.
i) For the purpose of maintaining the
vii) Standard integrated modular pit line coaches and the rakes in good condition
should be provided as given in Appendix and to avoid public complaints, the Chief
E. Mechanical Engineer, in consultation with
the Chief Operations Manager of the
111b Special Repairs
Railway, shall form Block Rakes for each
i) The special repairs (Non-POH repairs) by of the long distance trains and the inter-
workshops are those repairs, which can railway trains; and also nominate spare
not be done in the sickline with their block rake coaches of adequate number
existing facilities or are specifically for these block rakes to replace sick block
prohibited to be carried out on the rake coaches.
divisions.
ii) Special repair coaches should be sent to ii) The station staff shall ensure that no non-
the base workshops only after obtaining block coach is attached in any Block Rake
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
except with the express permission of the tanks of the train at each of the nominated
Divisional Mechanical Engineer, who will watering stations of the railway. If
grant such permission only in emergency necessary, where halts are small, boosters
and that too for a specified trip only. of adequate capacity should be provided
to increase the water pressure and
111e Destination Boards accelerate water filling.
iv) After completing watering, the staff, in
i) Coaches on originating trains should be case of overhead watering arrangement,
provided with destination boards of must ensure that water hosepipes are
approved types as prescribed by each coiled and secured properly with the
Railway. overhead hydrants and that the hydrants
111f Fire Extinguishers are fully closed. All leaky hydrants should
be reported to the Engineer
i) Fire Extinguishers should be provided on (C&W)/Engineer(Civil), as the case may
all originating trains according to the be, who will arrange to get them attended.
number prescribed by the Railways for In case of ground level side filling
air-conditioned coaches, brake vans, watering arrangements, it should be
postal vans, dining cars, etc. These fire ensured that water hose pipes are not
extinguishers should be checked every dragged or left over on the platform
three months and completely refilled after aprons, but are hung properly on the poles
one year. These extinguishers should not to prevent contamination of water.
be overdue testing / refilling. In case they v) Adequate staff and time should be
are used or damaged en route, the report provided to clean the compartment and
of the same should be obtained from the the bathrooms/ lavatories as prescribed at
guard, head sorter, etc., as the case may be, nominated cleaning stations of the railway.
and replaced. Portable pressure jet cleaning equipment
111g Brake Van Equipment should be used for efficient cleaning of
toilets.
i) Similarly, other brake van equipment, vi) Deployment of C&W staff on
which Mechanical Train Examining staff Rajdhani/Shatabdi Express/Rajdhani type
is responsible to supply, should be nominated trains/Other superfast and
provided according to the instructions of Mail/Express trains should be as per
each Railway. As per RDSO's letter no. Railway Board's letter no. 99/TG.V//12/2
MC/CB/28 dtd. 19.5.2000, racks have to dated 13.9.99. The `Safaiwalas' should
be provided in the SLRS for provision of wear identification armbands while on duty.
portable control telephones, portable train A suitable cleaning kit consisting of
lighting equipments, portable fire requisite cleaning agents, brushes, mops,
extinguisher, wooden wedges/skids and etc. should be standardised by the Railway
stretcher. Railways can modified existing and provided to them.
emergency equipments rooms in the
guard's compartment to provide racks for 111i Deficiency Rolling Stock (DRS) for
keeping the above mentioned items except Coaching Stock
fire extinguisher as shown in the figure
1.7 (RDSO's sketch K 0014) i) Railway should devise system for
detecting deficiencies. Reports of
111h Watering and cleaning of rakes. deficiencies/ defects in Rolling Stock
(DRS) reports in the proforma given in
i) Mechanical department of each railway Annexure 1.2, should be prepared for
will nominate the watering and the each mail/express/passenger originating
cleaning stations on the railway. train in duplicate by the Engineer
(C&W)/Electrical (TL) and should be
ii) All water tanks should be filled on a signed jointly with the RPF
washing line so that no watering is representatives. Reports for mechanical
necessary on a platform at the originating deficiencies should be prepared on
station. Arrangements should, however, Performa I (the fittings mentioned in these
be available at each of the platforms for Performa are selective and not exhaustive
filling the tanks in emergencies.
iii) Adequate staff and time should be
provided at intermediate stations to enable
complete replenishment of all the water
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
40
115 EXISTING FUNNEL 150
FIRE EXTINGUISHERS BELOW RACK 50 195 50
22,
50
TO BE
25
40
DOG BOX
FITTED INSIDE
EXISTING OBSERVATION
19 CEILING
WINDOW WHERE PROVIDED
EXISTING WATER PIPES
25
C 8 1,2 22,
SIDE WALL
TO BE
40
10 FITTED OUTSIDE
800
24 16
40 200 40 200 15
7 150
RACK FOR PORTABLE TRAIN
LIGHTING EQUIPMENT 3.15
60
20
1,2 23
130
EXISTING WATER 9 STRETCHER
150
PIPES WHERE LAV.
PROVIDED 254
25 17 , ANGLE FOR SLIDING FEED BOX 178
100
FLOOR LEVEL
11,12,13
200
B
18 Y
9
EXISTING DOG BOX
%%uDETAIL AT -A 3,4,5
1400
254
RACKS CAN BE LOCATED ON OPPOSITE SIDE,IF REQUIRED Y
DOUBLE FLAP M5 CSK HD.
TO AVOID INFRINGEMENT WITH SIDE FILLING PIPE. DOOR SCREW
STOPER FOR FEED BOX
SPACE FOR WOODEN NOTE:-
800
WEDGES/SKIDS ETC. 1. THE THREADED PORTION OF THE EYE (ITEM-2) TO BE CUT
300
300 THE PARTITION FRAME FOR FIXING THE RACKS.
14 M6 CSK HD. SCREW 3. THE WATER FILLING FUNNEL PRESENTLY LOCATED INSIDE THE
240
610
40
EMERGENCY EQUIPMENT ROOM,SHALL BE RELOCATED ABOVE
430
420
5 800 DOG BOX RETAINING EXISTING PIPE LINE AND WATER TRAY.
25
22, TO BE 4. THE EXISTING SWING TYPE FEED TRAY WILL BE REPLACED
180
FLOOR LEVEL
50
FLOOR LEVEL
50
FITTED INSIDE BY NEW FEED BOX OF SLIDING TYPE.SUITABLE OPENING
7
SHALL BE MADE IN DOG BOX AS SHOWN.
150
%%uVIEW
340 FROM C (WITH DOOR) %%uVIEW FROM C (WITHOUT DOOR) HOOK FOR FIRE EXTINGUISHER IS:2062-99
10 9
500
3.15 26 4
5x20x190 Fe 410 WC
25
FIG.-2
4 5 22 TOWER BOLT 125 mm 3
IS:204-91
=
PART-1
610 18 80 50 100
30
6 IS:1341-81
50
=
21 HINGE SIZE-100 mm
TABLE-3
200 200 200
%%uSECTION - YY
150
IS:1079
50
20 SHEET 3.15x195x200 2
GRADE-DD
800
200 45 %%uSECTION - XX 5 19 ANGLE 3.15x70x295 4
IS:1079
GRADE-DD
110 %%C5.5 HOLES FOR RIVETS
C 45
IS:1079
18 ANGLE 3.15x70x1900 4
CSK HOLE FOR M5 3
%%
%%C6.5 GRADE-DD
CSK HD. SCREW IS:808-76
R3.15 2 17 ANGLE ISA 5050x3 2
%%c10 (PART V)
2R
IS:737-74
16 FEED BOX 1
31000 H2
50
BEML DRG.No.
2 15 WATER CONTAINER 1
3.15 2 412-29100
20
1
109
CAP. 5 Kg
100
14 FIRE EXTINGUISHER 2 IS:2171-85
30 30 EACH
6 IS:3063
300
13 SPRING WASHER M6 20
26 4 5 TAB.1,TYPE-B
50
2R
30
2 IS:1364
5
100
CSK HOLE FOR M6 12 HEX.HD.NUT M6 20
75
PART-3
40 CSK HD. SCREW IS:1364
11 HEX.HD.BOLT M6x40 20
25
110
PART-1
50
11 238 11 100
75
28 IS:2907-64 IS:740-77
10 CSK.HD.RIVET %%c5x14
TAB-3,FIG-3 64430 WP
280
130
45
18 7 BRACKET 3.15x147x280 1
IS:1079
GRADE-DD
20
IS:1079
5mm THICK BACK PIECE 6 PLATE 3.15x40x220 4
GRADE-DD
WITH CUT A WAY
IS:1079
5 3.15x185x335
BRACKET 2
GRADE-DD
DOG BOX BELOW
AND TABLE WITH 2 IS:1079
4 ANGLE 3.15x75x800
FIRE EXTINGUISHERS GRADE-DD
PEGION HOLES ABOVE LAV.
2 IS:1079
3 ANGLE 3.15x80x1060
FIRE EXTINGUISHERS CSK.HD. BOLT20
M5X15 GRADE-DD
LAV. A WITH WASHER & NUT
1 IS:207-64 IS:1812-61
2 HOOK & EYE SIZE 250mm
TYPE-1
A
%%uDETAIL AT -B 1 BRACKET
2x30x462 1
IS:1079
GRADE-DD
LUGGAGE COMPT.
WT. OF
LUGGAGE COMPT.
SUITABLE CUT A WAY TO BE MADE IN THE ITEM DESCRIPTION & DIMENSION No. REF. DRG. REMARKS
MAT. & SPEC.
OFF ONE Kg
DOOR ANGLE FOR LOCK AND TOUNG.
FIRE EXTINGUISHERS
A
z
SLR & WLRRM COACHES
LAV.
EMERGENCY EQUIPMENT vuqeki ih
ROOM lh
EMERGENCY EQUIPMENT 1:10
EMERGENCY EQUIPMENT
DOG BOX BELOW & TABLE 1:5
Mh
ROOM PROVISION OF RACKS IN EMERGENCY
ROOM WITH PEGION HOLES ABOVE %%uGUARD'S COMPARTMENT(WLRRM COACH) 1:2 zz
Vsl
1:1 EQUIPMENT ROOM IN GUARD'S COMPARTMENT
ts,l STD-08/K0
%%uGUARD'S COMPARTMENT(BEML COACH) %%uGUARD'S COMPARTMENT(ICF COACH) FIGURE 1.7 1 STD-26/K0 12/2000 1
LK-8/K0014A1
SKETCH
- K0014
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
and may be altered by each Railway on the general inspection should be recorded
the basis of the items most prone to theft on DRS Cards as done at originating
on their system). This should be done stations. New DRS Cards showing
soon after the maintenance of the rake is deficiencies/ defects of each vehicle will
complete in the sick/ washing lines. In be prepared and sent to originating
case the train starts from the platform station along with the rake. In case
itself, these reports should be prepared by vandalism is suspected, suitable remarks
the train duty Engineer (C&W)/Electrical should also be given. The Engineer
(TL). The originating station must keep (C&W) staff, Electrical staff and RPF
copy of the report. It should be preferable staff should sign the report. On receipt of
if one booklet is maintained for each the report by the originating station, a
service so that the carbon copy is sent comparison will be made and statement
with train guard, retaining the original for prepared of deficiencies that occurred
record. enroute.
ii) After the coaches have been jointly vi) The Supervisors at the destination station,
checked, and DRS reports have been viz., Engineer (C&W)/Engineer (TL) shall
made, the coaches should be padlocked/ report the thefts on the form already
key locked and the key and report should prescribed by RPF, to the RPF/GRP as
be sent to the platform Engineer (C&W). quickly after arrival of the train as
possible and not later than 24 hours after
iii) Coaches with attendants the arrival of each rake. If the GRP
For the coaches, which have nominated refuses to accept such reports at the arrival
attendants, the DRS card will be given to station of train from the Mech. /Elec.
him. Deficiencies will be noted down by Supervisors, it shall be incumbent on the
the attendant and advised to Engineer RPF in-charge at the arrival station of the
(C&W) and Engineer (Electrical) at the train to get cases registered with GRP and
coaching depot after end of the journey. take further action as deemed fit to get the
So he will have to keep a register noting thefts traced/ reduced. If such reports are
down the deficiencies and the date of to be made to any other RPF post, this
advice and the date of recoupment. shall also be done by the RPF in-charge of
the train arriving station.
iv) Trains which are escorted by Engineer vii) The Supervisors of the originating station
(C&W) & Engineer (Elect.) should compare these DRS Reports with
For trains where an escorting C&W staff the original DRS Reports and prepare a
is provided on the train, he shall carry summary of the deficiencies/ thefts
DRS card for coaches other than para iii) occurring in the up and down trips
above and get them filled up at the separately.
secondary maintenance depot by the viii) A train wise summary of the deficiencies/
Mechanical/Electrical staff and get the defects shall be prepared and forwarded to
rake examined by RPF personnel in case the DME/DEE with a copy to Security
of any deficiency. Commissioner, RPF, of the division. The
cost of the fittings should also be shown
v) Trains/Coaches not covered in para iii) in the summary, price being taken from
& iv) IRCA Rules Part IV. For items not
covered in these, stores cost should be
a) For other trains/coaches not covered in given.
para iii) & iv), the DRS Reports should be ix) In the first week of every month,
handed over to the train guard and his Supervisors in charge of Mechanical,
signature obtained on the office copy. The Electrical and Officer- in charge of RPF
guard will be responsible for safe carriage Posts/Outposts should hold a joint
of the Report up to the destination. At the meeting to identify the areas where the
destination station, the outgoing guard deficiencies/ thefts are occurring and
must ensure that the reports are handed analyse the items more prone to
over to the Mechanical/Electrical staff breakage/losses/thefts. The officials
immediately on arrival of the train. should take remedial measures as possible
b) On arrival of the train at the destination at their level. A monthly statement of
station, the Engineer (C&W) staff and thefts, giving their cost and analysis
electrical staff shall check the rakes should be prepared by RPF but jointly
jointly with a representative of RPF and signed by Engineer(C&W), Engineer (TL)
comparison may be made with original
report. If original report is not received,
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
with the copy each sent to DME, DEE and important fittings and furniture in case of
Security Commissioner, RPF. Air Conditioned coaches, dining cars, etc.,
x) The Divisional Officers, viz. Sr. DME, Sr. defects and deficiencies of the fittings, if
DEE & SC must meet every three months any, to the base depot when a coach is
to carry out similar analysis and decide turned out of workshops after POH or
upon preventive steps to be taken in each special repairs. Any special instructions
area. They should submit similar joint regarding the coach for its base depot
report to their Headquarters Officers should also be maintained in the card. If
concerned, viz., CME, CEE and CSC. modifications are carried out, they should
xii) The CME, CEE and CSC should furnish be indicated in the card under its
every six months a report to the Director/ appropriate column. Similarly, if trial
Mechanical Engineering, the Director/ fittings/ components are fitted or materials
Electrical Engineering and DG/RPF in the are on trial on the coach, the details of the
Railway Board, indicating the extent of fittings/ components or the materials, the
theft of C&W and electrical fittings on authority for conducting such a trial, the
their system and the remedial measures purpose of the trial, the nature and the
taken by them bringing out any help in frequency of the observations to be made,
any area required from the Ministry of the type of interim/final reports required
Railways. to be submitted, the name and the address
of the authority to whom it is to be
111j Reporting of thefts submitted and any other instruction in
i) All damages/deficiencies which may detail should be maintained in a "Trial
apparently be due to mischief or theft Card" which should be sent by the
during service should be reported to the workshops to the base depot for
RPF/GRP and the Divisional Mechanical compliance of the instructions. The base
Engineer according to the procedure laid depot, on receipt of the coach from the
down in Railway Board's letter No.73M(c) shop, will check the fittings/ articles in the
/165/4 dt.4.7.77 circulated to General coach with the list sent by the workshops
Managers, all Indian Railways. and note all the instructions for
compliance. It will also make
111k Coach Maintenance History Card examinations and observations as
i) Every coaching depot shall have prescribed in respect of trial fittings,
computers for maintaining the coach components or materials and submit the
maintenance history in a software trial reports to the appropriate authority as
programme which should be compatible prescribed in the Trial Card received with
with the programme of the coaching the coach.
workshop. vii) The base workshops will also carry out a
ii) The "Coach Maintenance History Card" detailed examination when a new coach is
(MHC) for each of its coaches. The card received, register the coach, open its
will contain records of maintenance history book, make a list of all defects and
schedules including POH and special deficiencies and then, in consultation with
repairs in shops. It will also show the the CME's office, will allot a rake number
history of the coach from the time the and its base depot, stencil the same on the
coach is placed in service till its coach and, if it is fit in all respects, it will
condemnation and will give details of all then send the coach to the base depot for
major repairs like wheel changing, bogie service. Also, it will prepare a warranty
changing, etc. card as per Performa given in Annexure
iii) The complete history book of each coach, 1.3 and will forward it to the base depot
consisting of maintenance history cards, with detailed instructions for preferring
date card, trial card, etc. will, however, be claims from the manufacturers through
maintained by the base workshops. When Divisional Mechanical Engineer.
a coach is sent for POH or special repairs, 111 Warranty claim for defective/failed
a copy of its maintenance history card items
should be sent by its base depot to the
workshops for record in its complete There are some items for which it is
history book. mandatory for the manufacturers to give
warranty claim if the item fails or
iv) The workshops should send a new becomes defective during the warranty
maintenance history card (MHC) giving period as specified in the
the condition of the coach, the list of specification/drawings /purchase order.
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
Warranty period for few items is given in carriage depots on divisions where rake
below as an illustration: has been based for primary maintenance.
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
112d Maintenance Pattern for NMG rakes 113b Coaches shall be washed and cleaned
(as per Rly. Bd's Letter No. 91/M thoroughly from outside and inside as
(C)/650/1 dated 29.5.2000) prescribed in clause 109.
In order to optimize utilization of NMG 113c Brake system maintenance
rakes it has been decided to introduce the
following maintenance pattern : Air brake system (Bogie mounted and
underframe mounted )
i) NMG rakes may be run on goods
pattern with intensive examination at i) Visually check all the air brake
both the ends, following other equipments (DV, PEASD, PEAV,
conditions for enroute detention in etc.) including their mounting
case at stabling at road side stations. brackets and anti pilferage devices
In case of close circuit runs upto for any damage on coach of the rake
2500 km, the rake may be run on as per the check list given in clause
round trip basis. 423.
ii) Close circuit rake must be clearly ii) Check the operation of brake
identified and should have a cylinder while conducting brake tests.
nominated base depot where If the red paint on the piston rod is
adequate trained staff and spares visible, replace the brake blocks and
should be available. Also each NMG make necessary resetting of
coach should be marked with the Adjusting tube sub-assembly before
nominated POH workshop and the coaches are put into service runs.
return date. iii) Perform leakage test for brake pipe
iii) The maintenance schedules of the and feed pipe and its connecting
NMG coaches will continue to be on pipes as described in annexure 4.5
the coaching pattern to be carried out para 3 (Rake test).
by the base depot. iv) Performs service application and
iv) NMG coaches are fit for only 75 release tests as described in annexure
kmph. Also the revised maximum 4.5 para 3 (Rake test).
payload of NMG coaches is fixed at v) Carry out alarm chain pull test &
9.2 tonnes. Therefore, using these check the working of PEASD and
coaches as parcel vans for running Passenger emergency valve as per
on piecemeal basis on passenger annexure 4.4 para 4.6 (Rake test)..
carrying trains is strictly prohibited. vi) Drain the dirt collectors for removal
of water/moisture.
The instruction regarding POH and vii) Perform manual release test and
life of converted coaches continue to check the movement of brake
remain same which are as per Board's cylinder piston. Brakes should be in
letter no. 91/M(C)/650/1 dtd. 10.9.96. fully release condition.
112e Each coach should be stencilled at a Vacuum brake system
suitable place on its end panel, the code
name of the base depot and a schedule i) Entire vacuum brake system
chart. The date and station code of the including slack adjusters and direct
depot where a particular schedule is admission valves should be tested for
carried out should be stencilled at the leakage and proper functioning as
appropriate place in the schedule chart described in vacuum brake system
immediately when the schedule is chapter at para no. 509b (Balance
completed. vacuum test and normal vacuum test).
Balance vacuum test to be done as
113 PRIMARY/ SECONDARY per schedule when vacuum cylinder
MAINTENANCE is replaced.
ii) Test alarm chain apparatus under full
113a The rakes/ coaches of all trains should be vacuum. and check clappet for
given a Primary/Secondary Maintenance leakage.
examination as prescribed by the Chief
Mechanical Engineer of the Railway. 113d In addition to above the following items
of work should be attended during the
maintenance schedule examination:
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
* underframes
* bogie frames (i) Doors should be properly secured
* axle boxes with the hinges/pivots and should
* springs. not be grazing with floor or door sill
plates.
These items should be wiped with wet (ii) Door latches and safety catches
waste weaves or cotton waste as should be firmly secured with screw
necessary so as to facilitate examination. of correct sizes and engaging
All under gear components should then be properly and smoothly in their slots.
examined and repaired as necessary to The tongue of a gravity type latch
ensure that there is no `S' marked should be in proper alignment with
rejectable defect as mentioned in Chapter its slot plate.
IV of IRCA Conference Rules. (iii) Door lock handles should neither
113e The following items of undergear be stiff nor too loose and should be
components should, however, be specially properly engaging on the striking
examined and attended to:- plate.
(iv) Tower bolts should be complete
i) Oil in hydraulic dash pots of and should operate easily and be in
Rajdhani and Shatabdi coaches alignment with the clamp. Tower
should be checked once in 15 days to bolts should be fitted on a sound
detect oil leakage from them base with proper screws, at an
through defective seals or through angle of 15 o to the horizontal to
the vent screw. Add/ replenish with avoid locking by its self.
specified grade of oil if the oil level
is below 40 mm in the tare condition (v) Window shutters should neither be
for ensuring better riding comfort. tight nor loose in railings to allow
ii) Wheel profiles should be visually rattling and disengaging of catches
examined and gauged in case they on run.
appear to be near condemning limits. (vi) Window shutter safety catches
iii) The brake gear should be checked should properly engage in their
and so adjusted that the piston stroke slots.
is within the limits specified for (vii) Window frame should not be
different types of coaches. (see table broken and its glass, gauze wire or
1.10). 'A' and 'e' dimensions for venetian louvers should be in
slack adjuster should be as per table proper condition.
1.11.
(viii) Vestibule assemblies of all
vestibule coaches should be
Table – 1.10
checked and repaired as necessary.
Brake cylinder piston stroke
No coach with vestibule ends
should be allowed to work without
Type Minimum Maxi provision of proper fall plates and
mum end doors to make the vestibules
Bogie mounted air 32 95 functional.
brake cylinder
(ix) Any defective vestibule should be
Under frame mounted 75 95
checked with permanent locking.
air brake cylinder
Vacuum brake 125 135 (x) Water pipe connections, flushing
cylinder valves, cocks and shower roses
should not be leaking or choked.
Table – 1.11 (xi) Drain grills and drain holes in the
bathroom floors and wash basin
'A' & 'e' dimension for slack adjuster
drainpipes should be cleaned and
Type of 'A' 'e' dimension
opened where found choked.
bogie dimension
13 tonne 16 ±2 mm 375 ± 25 mm (xii) Any other deficiency as per
bogie Annexure 1.2 should be made
16.25 tonne 22 ± 2 mm 375 ± 25 mm good.
bogie
113f The following coach body components 113g After coaches are attended to in
and fittings should be specially checked washing/pit lines, they should be
and attended to : disinfected and insecticide sprayed
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
correct alignment and all wearing ii) For maintenance of major break–down/
parts, loose screws, etc. mal-functioning of any subassembly etc.
115 SCHEDULE `B' EXAMINATION the decision whether the coach is to be
detached from the formation for attending
115a Schedule `B' is required to be given every to maintenance/replacement of major
three months + 7 days at the nominated subassembly is dependent on maintenance
primary maintenance depot within the requirements, operational convenience,
normal time allowed for primary time availability etc. The decision is taken
maintenance on a washing line in rake. by the Engineer (C&W). Coach failure
Coach need not be detached from the rake report as per Annexure 1.4 should be
for purpose of this examination unless it made. For failure components/assemblies
requires such repairs which cannot be during warranty, action to be taken as per
attended to on the washing line or within para 111 .
the prescribed maintenance time on the iii) At depot, the coach that is detached for
washing line. schedule ‘C’ maintenance is taken over to
the washing line for cleaning, lubrication
115b The following items of work should be and minor maintenance. The coach that
attended. are detached due to a major defect in the
distributor valve, brake cylinder,
Brake system maintenance Auxiliary reservoir etc, is taken to the pit
Air brake system (Bogie mounted) line for the replacement of such sub-
assemblies, on unit exchange basis. The
(i) Same as 'A' schedule detachment of coach is carried out so as to
make the maintenance or testing activities
Vacuum Brake system convenient and faster so that the coach is
made ready for use without delay.
(i) Examination, overhauling and
testing of alarm chain apparatus as 116b PROCEDURE
prescribed in vacuum brake chapter. The activities performed to detach a coach
(ii) Overhauling of release valve, with Air Brake system are as follows:
replacement of its diaphragm and
sealing washers, if necessary. i) Safety precautions shall be taken to
(iii) Examination of neck rings and their prevent injury while detaching/attaching a
replacement, if necessary. coach.
ii) Remove the clamps on the cut-off angle
Other assembly maintenance cocks. Close the cut-off angle cock of
both feed pipe and brake pipe on both
(i) Besides brake system other items sides of the coach that has to be detached.
should be attended as given below: iii) Close the cut-off angle cocks of the feed
(ii) All items of Schedule`A' and brake pipe of adjacent coaches. This
(iii) Painting of lavatories from inside. is to ensure that the air pressure locked up
(iv) Thorough inspection and repairs of in the air hose coupling gets vented to
brake gear components. atmosphere through the vent hole of the
(v) Thorough checking of trough floor, cut-off angle cock.
turn unders, etc., from underneath iv) Observe above mentioned safety
for corrosion. measures to close all the four cut-off
(vi) Touching up of painted portion, if angle cocks on either side of the coach to
faded or soiled. be detached so that while opening air hose
coupling, it may not cause injury due to
116 DETACHMENT A COACH air pressure inside.
v) Release the brake of the coach to be
A coach is detached from the rake due to detached by pulling the manual release
several reasons such as: lever of the distributor valve.
vi) Open the Feed Pipe and Brake Pipe hose
116a For IOH and schedule ‘C’ coupling from both sides of the coach.
maintenance. vii) If the air pressure of brake cylinder does
not vent by pulling the manual release
i) Coaches required for detachment for valve of distributor valve, open the brake
maintenance under schedule 'C' and IOH cylinder vent plug to drain the air pressure.
maintenance.
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
viii) Uncouple Screw coupling and detach the (iii) Testing of vacuum gauges with
coach. the master gauge, and
ix) Observe all other safety measures as replacement of defective or
prescribed. inaccurate gauge. A set of two
master gauges should be kept for
117 SCHEDULE `C' EXAMINATION this purpose at every Primary
Maintenance Depot and each
Brake system Maintenance master gauge should be sent one
after the other to the base
Air brake maintenance: workshops for testing, repairs
(i) Schedule `C' is required to be given every and calibration.
six months + 15 days at the nominated (iv) Thorough checking of train pipes
primary depot. under pressure of 2 kg/cm2 to
(ii) Coaches are required to be detached from detect thin, corroded and
the rake and taken to the sick line for punctured pipes. A high pressure
schedule `C' examination and repairs. pump must be provided at each
Primary Maintenance Depot for
117a The following items of work should be this purpose.
attended during schedule `C' examination.
Other assemblies maintenance
Air brake system maintenance
(i) All items of Schedule `B'
(i) ‘C’ schedule maintenance as per para (ii) Thorough repairs of running gear
426 of air brake chapter. including running out of bogies
(ii) Check brake cylinder for loose where considered necessary. All
rocker arm plate and change on bogies which are working on
Bogie Mounted system. rake links earning more than 2.5
(iii) Check proper functioning of slack lakhs kms. per annum must
adjuster mechanism. however be run out and
(iv) Brake cylinder should be checked for thoroughly
smooth functioning and prescribed
attended to as laid down in
stroke. Defective brake cylinders
clause 111c under “Intermediate
shall be sent for repairs.
Overhaul”.
(v) Guard’s van valve should be tested
as per para 412d of air brake chapter. (iii) Touching up damaged paint of
(vi) Test BP & FP air pressure measuring coaches on outside as well as
gauges with master gauge and inside.
replace if found defective. A set of (iv) Polishing of the polished
two master gauges should be kept for surfaces.
this purpose at every Primary
Maintenance Depot and each master (v) Shock absorbers should be
gauge should be sent one after the replaced and sent to the base
other to the base workshops for workshops for repairs, testing
and return. For this purpose,
testing, repairs and calibration.
adequate spares must be
(vii) Thoroughly clean Dirt collector filter
in kerosene or replace on condition maintained in the depot.
basis. (vi) Thorough cleaning and removal
(viii) Check working of PEASD & PEAV of dust, rust, dirt, etc.,
by hearing the hissing sound of accumulated at the pillars
exhaust air. After resetting with the through the turn under holes,
help of key the exhaust of air should with coir brush and compressed
stop. Replace the defective air.
PEASD/PEAV. (vii) Thorough examination and
Vacuum brake system repairs of upholstery, cushions,
curtains, etc.
(i) All items of ‘B’ schedule (viii) Thorough checking and full
(ii) Overhauling of vacuum cylinders, if repairs of all window shutters,
due. safety catches, safety latches,
staples and hasps of
compartment, lavatory, body side
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
and vestibule doors for ease of 119. PROCEDURE FOR SENDING THE
operation. COACHES TO SHOPS FOR POH
(ix) Thorough checking and repairs
of UIC vestibules, their rubber The following procedure may be followed
flanges metal frames, doors, fall in regard to movement of coaching stock
plate, locking gear, etc., for ease for repair to shops -
of operation and safety . (a) Security Department shall arrange to
escort all coaches booked to shops when
(x) Thorough checking and repairs
booked by coaching specials or in lots of
of all cracks and worn out
3 coaches or more on receipt of memo
portions of flooring of the
from Engineer (C&W) of the booking
compartments.
station.
(b) All coaches booked to shops for POH will
117d Engineer (C&W) of Primary Coaching
be booked by passenger/parcel/Coaching
Maintenance Depots should be fully
special.
familiar with the vulnerable areas of ICF
coaches for corrosion, viz., sole bar at c) Before any carriage is allowed to proceed
doorways, lavatories and adjoining areas, to workshops a joint check should be
corridor sides - more so in case of those carried out by the representatives of the
SLRs which are used for Fish, Salt, etc. Mechanical, Electrical and Security
For facilitating inspection of sole bars Branches on the basis of which a
even spaced elongated holes of (215x127 deficiency list will be prepared at the
mm) are already provided in the turn rake/coach maintaining station under joint
unders. signature of the three representatives in
five legible copies with proper reference,
117e Special attention should be taken for the number and date out of which one copy
following:- should be pasted in side the compartment
on one of the end wall. Two copies of the
i) Pocket between sole bars and deficiency list will remain in the personal
turn unders should be thoroughly custody of the RPF sainik accompanying
cleaned through the inspection the rolling stock to the workshop (In case
opening of the sole bars and of unescorted coach, deficiency list will
inspected with the help of torch be sent by post to CWM concerned and
light or inspection lamps. one copy will be sent to OC/RPF).the
ii) Drain holes provided in the remaining two copies will be retained by
trough floors should be kept the Engineer (C&W) /Electrical
clean and unclogged. If during Supervisor of the base station. Upper class
the cleaning of these drain holes coaches must be pad locked/locked with
any accumulation of water is carriage key and also sealed after the joint
observed, the affected area check at the starting station by the
should be very carefully booking Engineer (C&W).
inspected for possible corrosion. d) Once a Joint check has been carried out
iii) A register should be maintained and the deficiency list drawn out no
of the primary maintenance removal of fitting from the stock at the
coaches on the subject. starting depot should be entertained.
e) Coaches escorted by the RPF staff will
118 SPECIAL SCHEDULE continue to be under watch of the Security
Force (RPF) until coaches are taken over
118a For high speed trains and some special by the shops. On arrival of carriage at the
coaches like Power Vans, etc., special Workshops, a careful check be made out
maintenance schedules by the individual jointly by the representatives of the
railways may be followed. Mechanical & Electrical Departments in
118b For maintenance of coaches of Rajdhani/ presence of RPF staff in four copies. In
Shatabdi Express Rakes, the instructions case of any additional deficiency being
given in RDSO Technical Pamphlet No. noticed, a list of such additional
C-7807 should be followed. deficiencies be made out in four copies
jointly by all the three staff.
118c The IOH of Rajdhani/Shatabdi high speed
coaches should be carried out in
(f) One copy each of the deficiency list
workshops. prepared by the representatives of
workshop duly signed by RPF be sent to
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF Coaches Coach
Chapter 1, Page 13 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
Annexure 1.1
Indian Railways Hkkjrh; jsy
czsd ikoj izek.k Ik=
BRAKE POWER CERTIFICATE
1. Date 2. Station/Railways
fnukWad LVs’ku@ jsYos
10. Individual numbers of two coaches next to the Engine and at rear in case of Vacuum trains and of 4
middle coaches also in case of Air Brake Trains
oSD;we Vªsukas esa batu@ czsdoku esa yxs nks nks dksp ds ua- ,;j izizS’kj VªSu esa buds vfrfjDr chp ds pkj dsUnz ds dkspksa ds u-
u- Hkh
vafdr djsaA
Middle
e/;
THIS CERTIFICATE IS VALID UPTO DESTINATION PROVIDED THE RAKE INTEGRITY IS NOT
BROKEN OR CHANGED BY MORE THAN TWO VEHICLE UNITS OR THE TRAIN ENGINE IS
NOT CHANGED IF RAKE INTEGRITY IS BROKEN BY MORE THAN TWO VEHICLE UNITS, A
FRESH CERTIFICATE IS REQUIRED. IF THE TRAIN ENGINE IS CHANGED. THE CERTIFICATE
SHOULD BE VALIDATED BY ENGINEER (C&W) THROUGH ENDORSEMENT IN THE COLUMN
ON THE REVERSE.
;g izek.k Ik= iwjs jSd ds xarO; LFkku rd ;fn [kafMr u gqbZ gks tkjh fd;k tk;sxk ;k nks dksp ls vf/kd bdkbZ esa ifjofrZr gqbZ
gks ;k Vªsu batu dks u cnyk x;k gksA ;fn jSd dh v[kaMrk nks dksp ls vf/kd bdkbZ esa ifjofrZr gqbZ gks rks izek.k Ik= dh
vko’;drk gksrh gSA izek.k Ik= dh oS/krk vfHk;ark ¼dS ,oa oS- ½ }kjk fiNyh rjQ fy[ks dkWye }kjk fd;k tk;sxkA
Driver’s name & signature Guard’s name & signature Engineer (C&W)
Mªkboj dk uke o gLrk{kj xkMZ dk uke o gLrk{kj vfHk;ark ¼dS ,oa oS-½
Chapter 1, Page 35 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
IMPORTANT
1. The incoming Driver shall handover the certificate to relieving driver. If he is leaving the train without
relief, it shall be deposited with the authority nominated to receive it, who will give it to the outgoing
Driver.
bu dfeax Mªkboj dks pkfg, fd og vius izek.k Ik= vkmV xksbax Mªkboj dks lkSai ns vkSj ;fn og fcuk fjyhoj ds Vªsu NksM+
jgk gS rks og vius izek.k Ik= ml vf/kd`r O;fDr ds ikl tek djsa tks fjyhfoax Mªkboj dks lkSaisaA
2. The outgoing Driver & Guard will satisfy themselves from the coach nos. given in item 10 that the
certificate pertains to their train.
tkus okys Mªkboj rFkk xkMZ] vkbVe dzekad 10 esa fn;s x;s dksp la[;kvksa ls vius vki dks larq"V djsxsa tks mldh xkM+h ls
lEcfU/kr izek.k i= gksrs gSaA
3. It is responsibility of the Driver of train to satisfy himself that the brake power certificate is proper and
valid, before working the train shall handover the certificate to relieving driver. If he is leaving the
train without relief, it shall be deposited with the authority nominated to receive it, who will give it to
the outgoing Driver.
;g Vªsu Mªkboj dh ftEesnkjh gS fd og vius vki dks larq"V djsa fd czsd ikoj dk izek.k i= mfpr ,oa oS/k gSA xkM+h ds dk;Z
djus ls igys og ;g izek.k i= fjyhfoax Mªkboj dks gLrkUrfjr djsxkA ;fn og xkM+h dks fcuk fjyhoj vk;s NksM+rk gS rks og
ukekafdr ,oa ftEesnkj O;fDr dks gLrkUrfjr djsxk tks
tks ckgj tkus okys pkyd dks gLrkUrfjr djsxkA
Chapter 1, Page 36 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
Annexure 1.2
CENTRAL RAILWAY
DRS CARD IN THE TRAIN SHOWING CONDITION OF MECHANICAL EQUIPMENTS
Rake No. …… Train No. ………………. Date: ………. Card No. ………………
Shower roses
Type & enroute
Push Cocks
Towel Rail
Coat hook
Ladder or
foot steps
Owning Rly.
Tumbler
Ash tray
& valves
Window
Mirrors
Folding
Shutter
Mirror
shelves
holder
Table
1 2 3 4 5 6 7 8 9 10 11 12 13 14
At Departure On Arrival
RPF RPF
Guard
Checking official will enter date, time and place after signature.
Chapter 1, Page 37 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
Annexure 1.3
WARRANTY CARD
PROFORMA FOR REPORTING DEFECTS ON THE NEWLY BUILT COACHES DURING THE
WARRANTY PERIOD
1. Coach No.
3. Owning Railways
4. Name of manufacturer
5. Date of manufacture
6. Date of commission
Engineer (C&W)
(Rubber stamp of the depot)
Chapter 1, Page 38 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
Annexure 1.4
------------ Railway
Carriage Depot ………….. (station)
Train Details:
Date Train No.
Station Division
Originating Stn. Last Exam. Stn
Prim. Maint. Depot
Sec. Maint. Depot.
Coach Details:
Coach Number Owning Railway & Base Depot
Coach type code Coach Make: IRS/ICF/BEML/RCF
Last POH Date & Shop Return Date
Failure Particulars:
Cause of Failure (Detachment)
Remarks:
(Signature)
(Name and Designation)
Chapter 1, Page 39 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
Annexure - 1.5
File No.
CWM's Office
Carriage Workshop
__________Railway
Tele/Fax. no.
e.mail no.
Date:
To,
M/s
--------------------------------
--------------------------------
--------------------------------
Inspecting Officer
For CWM
Copy to:-
1. CME/ Rly. for kind information
2. COS/ Rly. for kind information
3. ED/Carriage/ RDSO Manak nagar Lucknow - 226011
4. CME/ ICF Perambur, Chennai/ RCF Kapurthala & BEML Bangalore
5. COS/ ICF Perambur, Chennai/ RCF Kapurthala & BEML Bangalore
6. Dy COS/Workshop for proper storage, delivery and receipt
7. Inspecting agency
Chapter 1, Page 40 of 41
Hindi Contents
Maintenance Manual for BG ICF coaches Coach
Annexure - 1.6
File No.
CDO's/ DRM's Office
_________ Division
___________Railway
Tele/Fax. no.
e.mail
Date:
To,
M/s
--------------------------------
--------------------------------
--------------------------------
Depot Officer/DME
For DRM(M)
Copy to:-
1. CME/ Rly. for kind information
2. COS/ Rly. for kind information
3. ED/Carriage/ RDSO Manak nagar Lucknow - 226011
4. CME/ ICF Perambur, Chennai/ RCF Kapurthala & BEML Bangalore
5. COS/ ICF Perambur, Chennai/ RCF Kapurthala & BEML Bangalore
6. CWM/Workshop
7. Dy COS/Workshop for proper storage, delivery and receipt
8. Inspecting agency
Chapter 1, Page 41 of 41
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
CHAPTER 3
BOGIES
Chapter 3, Page 1 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
SAFETY STRAP
BOLSTER SUSPENSIONPHANGER
AXLE BOX SPRING LOWER SPRING BEAM
2364
3950
EQUALISING STAY
WHEEL AXLE
BOGIE BOLSTER
SIDE BEARER
I.C.F. BOGIE
FIGURE 3.1
Chapter 3, Page 2 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
Figure 3.2a & 3.2b show modified The side bearer arrangement consists
and unmodified guide arrangement of a machined steel wearing plate
respectively. The quantity of oil immersed in an oil bath and a floating
required to achieve 40 mm oil level bronze-wearing piece with a spherical
above the guide cap in modified top surface kept in it, on both sides of
arrangement is approximately 1.6 the bogie bolster. The coach body
liters and in unmodified arrangement rests on the top spherical surface of
is approximately 1.4 liters. As it is these bronze-wearing pieces through
not possible in open line to the corresponding attachments on the
distinguish between modified and bottom of the body-bolster. The
unmodified arrangements, 40 mm whole arrangement is provided with a
oil level is standardised for both. cover to prevent entry of dust in the
oil sump. (see figure 3.4 )
305 AIR VENT SCREWS
Table 3.2
On the bogie side frames, directly
above the dash-pots, tapped holes are Wear limit for wearing plate
provided for replenishing oil in the
dash pots. Special screws with New Shop renewal Condemning
copper asbestos washers are screwed size size size
on the tapped hole to make it air tight. 10 mm 9 mm 8.5 mm
Chapter 3, Page 3 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
2
1. SPECIAL SEREW WITH
3
SEALING WASHER
4 2. GUIDE
8. HELICAL SPRING
8 9. GUIDE RING
OIL LEVEL
UNDER TARE
10. RUBBER PACKING RING
9
40
11. GUIDE BUSH
OIL LEVEL BEFORE
ASSEMBLING
12. CIRCLIP
10
X TO RAIL LEVEL
13. COMPENSATING RING
142.5
12
13
X TO RAIL LEVEL-
POWER CAR-
Chapter 3, Page 4 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
1
2
1. SPECIAL SEREW WITH
3
SEALING WASHER
4 2. GUIDE
8. HELICAL SPRING
8 9. GUIDE RING
40
10 ASSEMBLING
X TO RAIL LEVEL
13. COMPENSATING RING
66.5
11
88
13
17
14 X TO RAIL LEVEL-
15 POWER CAR-
16
670 FOR BOGIE ON LUGGAGE SIDE
Chapter 3, Page 5 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
TO BE TACK WELDEDPAFTER
ASSEMBLY
SEALING CAP
BOGIE BOLSTER
SILENT BLOCK
SLEEVE
HEX. HEAD SCREWP& SPRING
WASHER
BOTTOM COVER
PCOMPLETE
COTTER
SPLIT PIN
Chapter 3, Page 6 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
10
%
%
°
R1
c
9.5
0
45
3
WEARING PIECE FOR SIDE BEARER
5
REF. DRG. NO. T-O-5-649
5
13 %
%
c
FELT
OIL LEVEL
CHECK FOR POROUS WELDING
WEARING PIECE
Note:-P1. Bronze Wearing Piece should be renewed when the wear on the mating surface reaches
3mm that is, height is less than 42 mm or damages occur to the oil grooves.P2. The hard ground
plate should be renewed when the wear exceeds 1.5mm that is, thickness is less than 8.5 mm or
ridges are observed on the plate.
Chapter 3, Page 7 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
Brake rigging is provided to control The brake rigging is as per figure 3.6.
the speed of the coach by transferring In 16.25 t axle load bogie the four
the braking force from the brake lever used in bogie brake rigging are
cylinder to the wheel tread. Brake each with lever ratio of 1:1.376 and
rigging can be divided into two hence the total Mechanical advantage
groups i.e. Bogie mounted brake in a bogie is 5.504 .
rigging and coach under frame The components details of 16 t bogie
mounted brake rigging. are given in table 3.3 (Refer ICF
drawing No. WTAC3-3-2-305).
Chapter 3, Page 8 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
Table 3.3
In 13 t axle load bogie the four lever used in bogie brake rigging are each with lever ratio of
1:1 and hence the total Mechanical advantage in a bogie is 4.
The components details of 13 t bogie are given in table 3.4 (Refer ICF drawing No. T-3-2-
601).
Table 3.4
Chapter 3, Page 9 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
iii) CONVENTIONAL AIR BRAKE COACH NON AC COACHES (refer figure 3.9)
Levers
Chapter 3, Page 10 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
282
245
245
245
178
178
205
178
2,896±1
FIGURE 3.7
282
245
245
245
178
178
205
178
2,896±1
CONVENTIONAL AIR BRAKE COACH SELF GENERATING AC COACHES
RDSO DRAWING NO. SK-93371
FIGURE 3.8
Chapter 3, Page 11 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
Chapter 3, Page 12 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
i) AC COACHES WITH BOGIE MOUNTED AIR BRAKE CYLINDER (refer figure 3.10)
Levers
ii) NON - AC COACHES WITH BOGIE MOUNTED AIR BRAKE CYLINDER (refer figure 3.11)
Levers
Chapter 3, Page 13 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
31 1
36 6
31 1
412
36 6
412
148
174
14 8
174
2896±1
AC COACHES WITH BOGIE MOUNTED AIR BRAKE CYLINDER P (FITTED WITH K TYPE COMPOSITION BLOCK) RDSO DRAWING NO. SK-98032)
FIGURE 3.10
256
302
405
256
405
30 2
13 4
158
13 4
158
FIGURE 3.11
Chapter 3, Page 14 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
This device has been provided on i) Remove all the oil from the side
bogies between the lower spring bearer oil bath.
plank and the bolster to prevent
ii) Wash the bogie with high
lateral thrust on the bolster springs
pressure hot water jet to remove
which have not been designed to take
all dust, mud, scales, grease and
the lateral forces. These links have
other muck without damaging
pin connections at both ends and,
the base primer coating.
therefore, can swivel freely.
(see figure 3.13) After washing and drying, roll the
bogies to dismantling line.
314 BOLSTER SPRING SUSPENSION
HANGERS (BSS HANGERS) 316b Dismantling
In the secondary suspension, the i) Make sure that the vent screws
bolster is supported on helical coil are opened. Lift the bogie frame
springs which are placed on the lower along with the bolster using
spring plank. The lower spring plank overhead crane till all the eight
is suspended from the bogie side axle guides disengage from the
frame through BSS hangers on lower spring seats.
hanger blocks. (see figure 3.14) ii) Lower the bogie frame and
bolster on to the shop floor.
315 SHOCK ABSORBERS iii) Remove and collect the axle box
guide components and helical
Hydraulic shock absorbers with
springs in respective bins/ pallets
capacity of ± 600 kg at a speed of 10
and send to washing plant for
cm/sec. are fitted to work in parallel
thorough cleaning.
with the bolster springs to provide
iv) Wheel sets must be first cleaned
damping for vertical oscillations.
thoroughly in the washing plant
and then sent to wheel shop.
316 WORKSHOP MAINTENANCE-
v) Remove vertical shock absorber
BOGIE SHOP
and send to shock absorber
maintenance section.
MAINTENANCE OF BOGIES
vi) Disconnect anchor links.
(Flow Diagram)
Dismantle bolster suspension
hangers by placing a dead
LIFTING WASHING BOGIE SERVICE
PLANT SHOPS
weight on the bogie frame and
SHOP SHOP
by using a jack.
1 2 (Fitting shop
3 5 & vii) Disconnect equalising stays. Lift
9 4 Smith shop) the bolster off the bolster springs
7 8 and remove the bolster springs.
10 6
viii) Collect anchor links, equalising
stays, bolster spring suspension
1. Coach lifting
(BSS) hanger pins, BSS hanger
2. Bogie cleaning
blocks (stones), BSS hangers,
3. Bogie dismantling
pins of equalising stays, brake
4. Component cleaning
rigging components and bolster
5. Attention to components
springs into respective bins/
6. Repair of components
pallets and send to washing plant
7. Bogie assembly
for thorough cleaning.
8. Load testing and adjustment
ix) Send the bogie frame, bolsters,
9. Lowering of coach
and lower spring planks to
10. Final adjustment
washing plant for thorough
cleaning and drying.
Figure 3.12
Transport the cleaned and dried bogie
After lifting the coach body (refer
frame, bolster and spring planks to
para 105 of chapter ‘Coach’), roll out
inspection and repair stands. Place the
the bogies and send them to bogie
bogie frame on repair stands in the
washing plant in bogie shop.
inverted position.
Chapter 3, Page 15 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
3 2
3 3
1
5
Bracket on Bogie Bolster
4
134 526
67
200
7
263
3
3
3
3
7 6
672
No. off per
ITEM Description & assembly
dimensions
7 RIB 120x30x5 2
(16.25 t Axle Load Bogie) (RDSO Sketch 88105) 5 BUSH%%c 42/32 x32L 8
2 1
TUBE %%c 50 BOREx462
FIGURE 3.13 1 TUBE %%c 50 BOREx640 1
Chapter 3, Page 16 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
PIN
37 35.5 1.5 36.00
HANGER
38.4 36.5 1.5 37.00
26
R1
9.5
-
0.25P-
HANGER AND HANGER BLOCKS
450.5
FIGURE 3.14
Chapter 3, Page 17 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
i) Check the bogie thoroughly for for axle guide and 0.5 mm for
any possible cracks. Check the BSS bracket bush), damaged or
BSS brackets, axle guides, area cracked, they should be
surrounding the BSS bracket and replaced.
axle guide and all the welding iii) Bent or damaged suspension
joints of bogie frame. If cracks straps should be attended to as
are detected, hold the bogie required.
frame in bogie manipulator. iv) Safety wire rope arrangement
After proper gouging, weld the and safety straps should be used
cracks and finish by grinding. for brake beams as per revised
ii) If the BSS brackets or axle RDSO instructions.
guides are worn (limits: 1 mm
Table 3.7
v) Check the squareness and vii) The relevant axle guides should
alignment of BSS brackets and be cut using special gouging
axle guides with the help of nozzles (PO 18 or 19) to prevent
transverse, longitudinal, undercutting of bogie frame.
diagonal gauges and straight Axle guides found bent/cracked
edge. Axle guide alignment should also be cut out and
should be checked with replaced.
reference to the BSS brackets
viii) Weld the new axle guides with
and recorded in RDSO
the help of axle guide welding
dimensional check report . A
fixture, if the axle guides are
coordinate measuring machine,
damaged or worn. Check the
preferably CNC type, can do
alignment of new axle guides
these checks accurately.
with respect to other axle guides
vi) If the BSS brackets do not lie using master gauges and straight
within the tolerances, relocate edge. Any slight discrepancy in
one or more BSS brackets with location can be rectified by
correct alignment. After suitable local heating of the
ensuring correct alignment of the frame. After complete
BSS brackets, measure the rectification, record important
location of the axle guide from dimensions in RDSO
the BSS brackets and record in dimensional check report. (See
RDSO dimensional check report. fig. 3.15 a&b, fig. 3.16 a&b)
If the measurements deviate
from the standard measurements, ix) Replace the BSS bracket bushes
relocate mis- aligned pair of axle and pins if they were damaged
guides. or worn.
Chapter 3, Page 18 of 36
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
a
DIMENSIONAL CHECK REPORT b
C D
35
z
+
413 - 1
F
E
876
g 1 g2 2
61 g3
K
3 g4
N
2159
T
+ 0.5
- 0.5
26
29
+
+ 1
1752
1752
-
+ 1
-
+ 1
- 1
-
35
+
M
S
J
+ 1
-
876
- 0.5
- 0.5
C.L. OF AXLE
C.L.OF AXLE
+
+
876
R
L
750 570
I
G 1500 H d
c
g 8 g 7 +
- 0.5
g 6 + 1
- g 5
2896
z
+ 1
- +
- 1
570
+ 1
-
A B
1. BOGIE SIDE FRAME & HEAD STOCK CENTRES ON EITHER SIDE OF THE BOGIE
FRAME AS SHOWN THUS WILL BE PERMANENTLY PUNCH MARKED IN
CONSPICUOUS MANNER.TO ENSURE THIS 2mmTHICK X 25mmWIDE STRIP SHOULD
BE WELDED AT THE LONGITUDINAL AND TRANSVERSE CENTRES OF THE BOGIE
FRAME.PUNCH MARK SHOULD BE PUNCHED ON THIS STRIP ACCORDINGLY.
2. g TO
1 g REPRESENT
8 LOCATIONS OF BOGIE GUIDES.
750 +
0.5mm FROM THE TRANSVERSE CENTRE LINE PUNCH MARKS ON BOGIE
-
No. ………………….
ICF DRG. NO. WTAC3 0-3-301
Measuring Nominal Size Actual Size Variation Measuring Nominal Size Actual Size Variation
Point (mm) (mm) (mm) Point (mm) (mm) (mm)
E -F 1500 ± 1.0 I-J 876 ± 0.5
G -H 1500 ± 1.0 J-K 876 ± 0.5
E -G 2159 ± 1.0 L-M 876 ± 0.5
F -H 2159 ± 1.0 M-N 876 ± 0.5
E -H 2629 ± 1.0 O-P 876 ± 0.5
F -G 2629 ± 1.0 P- Q 876 ± 0.5
a 413 ± 1.0 R-S 876 ± 0.5
b 413 ± 1.0 S-T 876 ± 0.5
c 413 ± 1.0 I-K 1752 ± 1.0
d 413 ± 1.0 L-N 1752 ± 1.0
g1 - g2 570 ± 1.0 O-Q 1752 ± 1.0
g3 - g4 570 ± 1.0 R-T 1752 ± 1.0
Figure - 3.15b
SHEET 2 OF 2
DIMENSIONAL
a CHECK REPORT b
C D
35
z
+ 1
463 -
F
E
876
g 1 g2 12 g 3
K
36 g4
N
2159
T
- 0.5
+ 0.5
+
-
1
1752
+
1752
-
+ 1
-
- 1
25
- 1
+
35
+
73
M
S
J
+ 1
-
876
- 0.5
- 0.5
C.L. OF AXLE
C.L. OF AXLE
+
+
876
R
L
570
I
G H d
c
g 8 g 7 + 0.5
- g6 +
- 1 g 5
2896 700
z
+ 1 +
- - 1
570 1400
+
- 1
A B
1. BOGIE SIDE FRAME & HEAD STOCK CENTRES ON EITHER SIDE OF THE BOGIE
FRAME AS SHOWN THUS WILL BE PERMANENTLY PUNCH MARKED IN
CONSPICUOUS MANNER.TO ENSURE THIS 2mmTHICK X 25mmWIDE STRIP SHOULD
BE WELDED AT THE LONGITUDINAL AND TRANSVERSE CENTRES OF THE BOGIE
FRAME.PUNCH MARK SHOULD BE PUNCHED ON THIS STRIP ACCORDINGLY.
2. g TO
1 g REPRESENT
8 LOCATIONS OF BOGIE GUIDES.
R.D.S.O./CARR./SK93280
FIGURE-3.16a
SHEET 1 OF 2
Hindi Contents
No. ………………….
RDSO/SK/93280
Measuring Nominal Size Actual Size Variation Measuring Nominal Size Actual Size Variation
Point (mm) (mm) (mm) Point (mm) (mm) (mm)
E -F 1400 ± 1.0 I-J 876 ± 0.5
G -H 1400 ± 1.0 J-K 876 ± 0.5
E -G 2159 ± 1.0 L-M 876 ± 0.5
F -H 2159 ± 1.0 M-N 876 ± 0.5
E -H 2573 ± 1.0 O-P 876 ± 0.5
F -G 2573 ± 1.0 P- Q 876 ± 0.5
a 463 ± 1.0 R-S 876 ± 0.5
b 463 ± 1.0 S-T 876 ± 0.5
c 463 ± 1.0 I-K 1752 ± 1.0
d 463 ± 1.0 L-N 1752 ± 1..0
g1 - g2 570 ± 1.0 O-Q 1752 ± 1.0
g3 - g4 570 ± 1.0 R-T 1752 ± 1.0
Figure - 3.16b
SHEET 2 OF 2
x) Replace the anchor link brackets if hanger bracket for renewal. Replace the bushes
they are worn or damaged. The M12 in the brake hanger brackets at every POH.
threaded hole should be cleaned and xii) Replace the brake lever hanger
checked and attended to, as required. brackets if the holes are
xi) Bent, damaged, or worn brake hanger oblong/worn or damaged.
brackets should be replaced. If the holes are xiii) Replace all the axle box housing
not aligned/located as per drawing, replace the crown bolt and screwing piece
brackets. Use single piece design of brake by rubber stoppers.
Table 3.8
xiv) The locations where the repairs 316d Attention to Bogie Bolster
have been carried out should be Arrangement
cleaned to bare metal and (Refer drg. no.WTAC3-0-5-301 &
painted with two coats of primer WLRRM-0-4-001 for 16.25t bogie and
to IS:2074 to a minimum Dry T-0-5-601 & T-0-4-601 for 13t bogie)
Film Thickness (DFT) of 50 i) Check the bolster for twist,
microns followed by one coat crack, corrosion, etc. Repair or
of anti-corrosive Black Japan replace the bolster as required,
Type-B to IS:341 to a DFT of and attend to the lug as required.
35 microns, after which entire ii) Repair or replace the equalising
bogie frame is to be given one stay bracket if found bent,
coat of Black Japan Type-B to damaged, or corroded.
IS:341 to a minimum DFT of 35
microns.
Table 3.9
iii) Replace the anchor link bracket xiii) The locations where the repairs
by holding in bolster repair have been carried out or found
fixture, if found worn or corroded should be cleaned to
damaged. bare metal and painted with two
iv) Replace the bushes in the stay coats of primer to IS:2074 to a
rod brackets, if found worn or minimum Dry Film Thickness
damaged. (DFT) of 50 microns followed
v) Replace the centre pivot silent by one coat of anti-corrosive
block if found worn, damaged or Black Japan Type-B to IS:341
rubber has perished. to a DFT of 35 microns, after
vi) Replace the centre pivot sleeve if which entire bogie bolster is to
worn or damaged or corroded. be given one coat of Black
vii) Replace the bolster centre pivot Japan Type-B to IS:341 to a
sleeve if worn or cracked. minimum DFT of 35 microns.
viii) Replace the rubber sealing cap 316e Anchor Link
of centre pivot silent block, if
torn or damaged or perished. (Ref: Drawing No. T – 0 – 7 – 603
ix) Replace the centre pivot pin if and T – 0 – 7 –607)
worn or cracked. Chalk test the
centre pivot pin ‘in position’ or i) Replace the anchor link, if worn
‘off position’ to detect cracks. or corroded. Repair the anchor
x) Force fit between silent block link, if found cracked (normally
and sleeve and tolerance on at weld joints) under magna flux
pivot pin, i.e., c9 (-0.18/-0.27) testing, by re welding after
should be maintained in every gouging. Refit new silent block
POH/IOH. in every POH.
xi) Ensure that there is no leakage
of oil from the side bearer oil- ii) Replace the silent block, if the
bath welding portion. Replace rubber is perished (indicated by
the hard ground plate in side fretting) or loose in the anchor
bearer, if worn more than 1.0mm link housing, or the silent block
(ref. table 3.2) in thickness or pin is worn thin or loose in
ridges formed on the plate. silent block rubber. The silent
Replace the bronze wearing block should be force fit in the
piece for side bearer, if worn anchor link and the silent block
more than 1.5 mm in thickness. pin should be slide fit in the
Sharp edges on wearing piece anchor link bracket.
should be rounded off before re-
use. Ensure that the dust seal iii) The locations where the repairs
cover sits effectively all around have been carried out should be
without any gap on the oil-bath cleaned to bare metal and
and the sleeves slide freely on painted with two coats of primer
the guide to ward off dust and to IS: 2074 to a minimum Dry
moisture coming in contact with Film Thickness (DFT) of 50
the oil. Clean refilling passages microns followed by one coat
and deficient or damaged oil of anti-corrosive Black Japan
refilling cups with caps and Type-B to IS:341 to a DFT of
pipes should be replaced. The oil 35 microns, after which entire
filling plugs should be well anchor link is to be given one
secured by chain to prevent it coat of Black Japan Type-B to
from dropping. IS:341 to a minimum DFT of 35
xii) Repair or replace the bent or microns.
damaged or broken equalising
stay rod safety loops.
Table 3.10
(all dimensions in mm)
Part name Wear location Drg. No.
Anchor link silent block pin 25 mm -0.012/-0.052, thick ends RDSO-Sketch-94101 alt.1
Anchor link silent block Outer dia. 90.5 +0.05/+0.025 RDSO-Sketch-94101 alt.1
Anchor link housing Hole dia 90.5 +0.015/ -0.03 T-0-7-605
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
316f Equalising Stay Rod and Pins iii) Replace the following parts:
(Small & Big) § bushes of BSS brackets if
(Ref: Drawing No. RDSO Sk-88105 worn beyond permissible
Alt.2 for 16.25t bogie and Sk-88018 limits
Alt.6 for 13t bogie) § equalising stay bracket
bushes
i) Hot dip galvanised equalising
§ BSS pins if worn beyond
stay of 16.25t bogie is used on
permissible limits.
all new coaches. The choice of
iv) The locations where the repairs
retro-fitment of these stays on
have been carried out or found
existing coaches is left to the
corroded should be cleaned to
Railways. For fitment of
bare metal and painted with two
equalising stays to Sk-88105
coats of primer to IS: 2074 to a
Alt.2 on 13t bogies, follow
minimum Dry Film Thickness
RDSO Sk-93236.
(DFT) of 50 microns followed
ii) Replace the corroded equalising
by one coat of anti-corrosive
stays with new hot dip
Black Japan Type-B to IS:341
galvanised stays. If any repair
to a DFT of 35 microns, after
like welding or straightening is
which entire lower spring beam
carried out, which damages the
is to be given one coat of Black
galvanising, repaint the
Japan Type-B to IS:341 to a
equalising stay with epoxy paint.
minimum DFT of 35 microns.
iii) Bushes should be replaced in
every POH and fitted with Table 3.12
washers and split pins. Replace (all dimensions in mm)
the equalising stay pins if worn Part name Wear Drg. No.
out more than 1 mm in diameter. location
BSS bracket Hole 38 H11 WLRRM-
Table 3.11 bush (+0.16/-0.00) 0-5-002
Wear Location (Dimensions in mm) Eq. Stay Hole 42 H7 WLRRM -
bracket (+0.025/-0.0) 0-4-002
Part name Wear location
Pins for 16.25t axle Dia.31 (+0.5/-0.2) 316h BSS Hanger
load bearing capacity (Ref: Drawing No. T – 0 – 5 – 639)
equalising stay
Pins For 13t axle load Dia. 24 (+0.2/-0.1) i) Check the cleaned hangers for
bearing capacity cracks and wear. Replace the
equalising stay hangers if cracked or wear
exceeds 1 mm. Magna flux
316g Lower Spring Beam crack detection equipment shall
(Ref: Drawing No.WLRRM - 0 -5 - be used for checking.
002 for 16.25t bogie and T-0 -5 - 643 ii) The horizontal wearing surface
for 13t bogie) may be built up using 2B
electrodes, filed and ground to
i) Check the lower spring beam size. Then hard powder coating
(plank) for cracks, corrosion, etc. may be applied. Hardness value
and repair or replace as required. should be 55-60 Rockwell-C
ii) The following parts of the lower iii) The vertical gap should be within
spring plank should be inspected the permissible limit i.e.,
and repaired or replaced as 384+0.0/-1.0 mm. All the hangers
required: should be tested to tensile load
§ bolster suspension straps if of 8 tonnes and replaced if any
bent or damaged permanent set is observed in the
§ stay rod brackets if worn, hangers.
bent or corroded iv) After repair and testing all the
§ shock absorber fixing bosses BSS hangers should be painted
if damaged with one coat of anti corrosive
§ spring guide rings if required black paint. Write the actual
§ lug if damaged. length between the wearing
arms on the BSS hanger with
paint.
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
Table 3.13
(all dimensions in mm)
Table 3.15
Table 3.16
Load deflection testing and grouping of Axle box spring (B.G Main line coaches)
Code Wire Free Test Acceptable Groups as per loaded spring height
dia height Load height under
test load
A B C
Yellow Oxford Green
Blue*
A01 33.5 360 2000 279-295 279-284 285-289 290-295
A03 33.5 375 2800 264-282 264-269 270-275 276-282
A04 35 372 3000 265-282 265-270 271-276 277-282
A06 36 337 2400 269-284 269-273 274-279 280-284
A09 37 360 3000 277-293 277-282 283-288 289-293
A10 39 315 1800 276-289 276-279 280-284 285-289
* As per RDSO's letter no. MC/SPG dated 25.7.01
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
Table 3.17
Code Wire Free Test Acceptable Groups as per loaded spring height
dia height Load height under
test load
A B C
Yellow Oxford Green
Blue #
B01 42 385 3300 301-317 301-305 306-311 312-317
B03 42 400 4800 291-308 291-296 297-303 304-308
B04 47 400 6100 286-304 286-291 292-297 298-304
B06 36 416 4200 280-299 280-286 287-292 293-299
B11 47
*386 6700 306-322 306-311 312-317 318-322
B13 34
B15 40 393**
6000 256-272 256-261 262-267 268-272
B16 32.5 286 **
* Combined load deflection test is done
** As per RDSO's letter no. MC/MV dtd. 21.11.01
# As per RDSO's letter no. MC/SPG dtd. 25.7.01
ii. Assemble the lower rubber exceed 1.6 mm. The bogie
washer, lower spring seat, should sit evenly on the four
compensating ring, hard packing axle boxes.
ring, selected axle box springs,
upper spring seats, upper rubber v. The assembled bogie should be
washer, protective tube, etc., as load tested on a bogie test stand
per the drawing for axle box where it is loaded up to its
guide arrangement. Put dash pot normal working load and the
oil of approved brand in lower height of bolster top surface
spring seat to a level of 60 mm form rail level should be
from bottom. The approved measured for comparison with
brands of dash pot oil are the pre-determined dimension
following: corresponding to correct coach
buffer height. Adjustment for
a. Servoline - 100 of getting correct buffer height
IOC b. Yantrol - 100 should be made, if needed. If the
of HPC c. Bharat univol – buffer height requires further
100 of BPC adjustment, the load on the axle
box spring should be released
iii. For obtaining correct buffer and compensating rings should
height when the coach body is be inserted below the axle box
lowered on the bogies, while spring ensuring that the bogie
assembling the bogie hard frame height is 686 ± 5 mm.
rubber, UHMWPE or NFTC
packing of required thickness, vi. Safety straps of the axle box
depending on the wheel wing lugs and bogie bolster
diameter, should be provided should be adjusted so as to
under the flanges of the lower ensure a minimum clearance of
spring seats. Packing rings of 40 mm between the lugs and
thickness as given in table 3.18 bottom of safety straps.
and as shown in figure 3.17
(RDSO sketch 77354) should be vii. Fit the vertical shock absorber
used. Compensating rings of between the bolster and bottom
suitable thickness as per spring plank.
suspension diagram for relevant
coach should be placed over the viii. Check the oil in the dash pots
flange of the lower spring seat. with the flexible wire gauge and
if necessary, top up the dash pots
Table 3.18 with the approved brand of dash
pot oil to bring the level to 60
Average tread Thickness of mm from under surface of dash
diameter of two hard packing pot. If the flexible gauge
wheel sets of bogie ring indicates a higher level of oil,
889 to 864 mm 13 mm the guide cap may have fallen in
dash pot. This should be checked
863 to 840 mm 26 mm
and attended to.
839 to 820 mm 38 mm
819 mm 48 mm
ix. Axle box rubber bump stopper
should be adjusted to obtain the
iv. Lower the bogie frame with the
required clearance between the
bolster assembly on the wheel
axle box crown and the bogie
sets thus prepared, taking care to
frame.
ensure that the rubber packing
ring does not get damaged while
x. After testing and making
lowering the guide bushes on to
adjustments for correct buffer
the lower spring seat. The
height, dispatch the bogie to
maximum diametrical clearance
Lifting shop for lowering the
between the lower spring seat
coach body.
and guide bush should not
Hindi Contents
Maintenance Manual for BG Coaches of ICF design Bogie
CROWN
TYPE OF COACH
CLEARANCE
A mm
+0
GS,SDC,SLR,SCN 43 -3
A
WCB,WCBAC,WFC,WFAC
+0
-3
WGFAC,WSCWAC,WGCWAC 27
WGACCN,WACCN,WSCZAC
WGSCZAC,WFCZAC,WLRRM
Table 3.19
M/s ESCORTS
250 ± 3 320 ± 3 360 ± 3 110 -70 40
M/s KNORR BREMSE
M/s GABRIEL
ICF/SK-0-5-015
Annexure - 3.1
1. Perished rubber Poor quality of rubber 1) Replace rubber packing ring at every
packing ring packing ring examination.
2) Use only rubber packing rings
conforming to IRS specification no. R-
47-72 and the relevant drawing.
2. Axle guide found 1) Misaligned fitment 1) The alignment of axle box guide
worn on one side of axle guides to should be checked with alignment
bogie frame. gauges and corrected.
2) Dust ingress to 2) Vent hole should be sealed with
lower spring seat. gaskets. Screw to be tightened well
after oil topping.
******
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
CHAPTER 4
In Air Brake system compressed air is § Brake pipe throughout the length of
used for operating the brake system. The train is charged with compressed air
locomotive compressor charges the feed at 5 Kg/cm2.
pipe and the brake pipes throughout the § Feed pipe throughout the length of
length of the train. The feed pipe is train is charged with compressed air
connected to the auxiliary reservoir and at 6 Kg/cm2.
the brake pipe is connected to the brake § Control reservoir is charged to
cylinder through the distributor valve. 5 Kg/cm2.
Brake application takes place by § Auxiliary reservoir is charged to 6
dropping the pressure in the brake pipe. Kg/cm2.
Figure 4.1 SCHEMATIC LAYOUT OF TWIN PIPE GRADUATED REL EASE AIR BRAKE SYSTEM
Note: Pressure gauges are installed only in guard’s brake van.
Chapter 4, Page 1 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
§ The distributor valve connects The brief details of the air brake
the auxiliary reservoir to the components and it’s maintenance and test
brake cylinder and the brake procedure is described below:
cylinder piston is pushed
outwards for application of 405 COMMON PIPE BRACKET
brakes.
§ The auxiliary reservoir is Common pipe bracket is mounted on the
however continuously charged coach under frame and is suitable for use
from feed pipe at 6 Kg/cm2. with all type of distributor valves
presently in use on main line coaches.
Table 4.1
406 INTERMEDIATE PIECE
Description Reduction in B. P. (SANDWICH PIECE)
Pressure
Minimum Brake 0.5 to 0.8Kg/cm2 An intermediate piece is mounted on the
common pipe bracket to fit the distributor
Application
valve on the common pipe bracket. The
Service Brake 0.8 to 1.0Kg/cm2
intermediate piece serves the purpose of
Application
blanking all the other ports on the
Full Service Brake 1.0 to 1.5Kg/cm2
common pipe bracket other than required
Application
for a particular make of distributor valve.
Emergency Brake Brake pipe is fully Each type of distributor valve is mounted
Application exhausted and its on the common pipe bracket with its own
pressure reduces to intermediate piece.
almost zero.
407 AIR BRAKE HOSES
403c Brake release stage:
407a Brake Pipe & Feed Pipe Hoses
§ Brakes are released by recharging (see figure 4.2)
brake pipe to 5 Kg/cm2 pressure
through the driver’s brake valve.
To maintain continuity through out the
§ The distributor valve isolates the length of train, the brake pipe (BP) and
brake cylinder from the auxiliary
feed pipe (FP) are fitted with flexible
reservoirs.
hoses. Each hose is provided with palm
§ The brake cylinder pressure is vented end coupling. For easy identification,
to atmosphere through DV and the
coupling heads are painted with green
Brake cylinder piston moves
colour for B.P and white colour for F.P.
inwards. Also raised letters 'BP' and 'FP' are
404 AIR BRAKE SUB ASSEMBLIES embossed on coupling heads representing
Brake Pipe and Feed Pipe respectively.
The various Air Brake sub-assemblies and Hose couplings must be checked for
components are: leakage of air as per the test procedure
given below:
i) Common pipe bracket
ii) Intermediate piece
iii) Brake pipe and feed
pipe
iv) Brake pipe coupling
v) Cut-off angle cock
vi) Brake cylinder
vii) Dirt collector
viii) Auxiliary reservoir
ix) Slack adjuster
x) Distributor valve
xi) isolating cock
xii) PEASD
xiii) PEAV
xiv) Check valve
Figure 4.2 - AIR BRAKE HOSES
Chapter 4, Page 2 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
407b Test Procedure (see figure 4.3) § Observe leakage, if any from all
parts of the hose coupling.
For testing the hose coupling the steps § Close the isolating cock 1(b).
given below should be followed: § Disconnect the hose coupling from
§ Use a dummy coupling head to test bed.
block the outlet port of the hose § If the leakage is observed through
the coupling head, replace the
coupling.
§ Connect to hose coupling under gasket and test again.
test to the end of flexible hose. § If leakage persist even after change
of gasket the coupling head is
§ Open isolating cock 1(a)
§ Adjust pressure regulator (2) so unserviceable and complete
assembly shall be rejected.
that pressure gauge (6a) shows
However if leakage occurs at the
10Kg./cm2 air pressure.
hose nipple or coupling end hose
§ Immerse the hose coupling
joint the clamp should be
assembly completely in the tub of
attended/replaced to make the
water.
assembly leak proof.
§ Open isolating cock (1b) and see
that (6b) shows 10 Kg/cm2
pressure.
Kg Cm
6a MR
6b Kg Cm
CHARGING PRESSURE GAUGE 11/4” BSP
SOCKET TO
MAIN RESERVOIR ISOLATING COCK COUPLE HOSE
ISOLATING COCK PRESSURE REDUCER COUPLING
NIPPLE END
6
1a 1b
4 1c FLEXIBLE HOSE
2
HIGH PRESSURE
EXHAUST COCK (10 KG/CM2 CAL)
408 CUT OFF ANGLE COCK on either end of each coach to facilitate
(see figure 4.4) coupling and uncoupling of air hoses. When
(Ref: Drg. No. WD-88123-S -01 the handle of the cut off angle cock is
and WD-88123-S-01) placed in closed position it cuts off the
passage of compressed air, there by
Cut off angle cocks are provided facilitating coupling and uncoupling action.
both on brake pipe & feed pipe
Chapter 4, Page 3 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
The cut off angle cock consists of two (b) Screw driver 12”/300 mm long.
parts viz. cap and body which are secured (c) Vice.
together by bolts. The cap and the body (d) Light hammer.
together hold firmly the steel ball inside
it, which seated is on nitrile rubber seat. 408c Procedure
The ball has a special profile with the
provision of a groove at the bottom i) Dismantling
portion for venting the air to the
atmosphere. § Hold the cut – off angle cock in a
vice.
On the top surface of the body a bore is § Unscrew the lock nut from the stem.
provided for placing the stem, to which a § Take out the handle assembly (The
self locking type handle is fixed. When handle assembly need not be
the handle is placed parallel to the cut off dismantled further unless it is
angle cock the inlet port of the cut off necessary to change the plate spring
angle cock body is connected to the outlet i.e. if it is found, heavily rusted,
port, through the hole provided in steel pitting crack or the spring is
ball. Thus air can easily pass through the permanent set).
cock. This position of the handle is known § Unscrew the four hexagonal bolts
as open position. When the handle is and spring washers.
placed perpendicular to the cock body the § Detach cap from the body.
steel ball gets rotated and the spherical § Remove ‘O’ ring and ball seat from
and groove portion of the ball presses the cap.
against the sealing ring at inlet and outlet § Turn the stem in such a way that the
port, there by closing the passage of inlet ball can be pulled from the stem.
air and venting the outlet air through the § Slightly hammer the stem at its top
vent hole. This position of the handle is and take out the stem through the
known as closed position. bore of the body.
With the stem one leaf spring is provided § Remove the ball seat from the body.
which presses the operating handle
downwards. By virtue of this, handle gets ii) Cleaning of Parts
seated in deep grooves at ON / OFF
position resulting in a mechanical lock. § Clean out side portion of the body
and cap with wire brush.
Under normal working conditions, the § Direct a jet of air to remove the dust.
handle of all cut off angle cocks of BP are § Clean all metallic parts with
kept open except the rear end angle cocks kerosene oil and wipe dry.
(BP). This facilitates in charging the
complete air brake system with iii) Replacement of Parts
compressed air supplied by the
compressor housed in the locomotive. Cut § Replace all rubber parts.
off angle cock fitted on the brake pipe is § Replace spring-washer, nut & bolts
painted green. in case they are excessively
corroded or defective.
408a Overhauling of Cut Off Angle Cock § Replace handle spring if it is found
heavily rusted, is having pitting
The cut-off angle cock is to be completely
crack or is permanently set
dismantled and overhauled in every POH
(Dismantle the handle assembly, and
or when there is some specific trouble.
fit a new spring along with a snap
During overhauling, it is dismantled for
head rivet).
cleaning, replacement of parts and
§ Replace stainless steel ball if found
checking for effective functioning. The
with scratch marks on the outer
POH kit should be as per annexure 4.3.
surface or dented.
408b Tools & Equipment
iv) Assembly
The following tools and fixtures are
required for overhauling § Insert the two ‘O’ rings in their
respective grooves on the stem.
(a) Single end spanner.
1) A/F 17 for M10 nut pivot screw.
2) A/F 10 for M6 nut.
Chapter 4, Page 4 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
§ Keeping the threaded end of the § Check pressure drop in gauge (6b)
stem first, insert the stem into the there should not be any leakage from
body through the bore of the body. flange joints, vent and outlet port of
§ Place one ball seat in its groove the angle cock.
inside the body. § Close cock (1c) and tighten the
§ Position the ball after correctly dummy plug and seal the outlet of
aligning its venting slot in the bore the angle cock.
of the body. § Move the handle to the open
§ Place the second ball seat and ‘O’ position. Open cock 1c.
ring in their respective positions on § Check for leakage from body and
the cap. cap joint, vent and all over the stem
§ Secure the body and cap by Hex. periphery using soap water. No
Hd. Bolt (M6) and spring washer leakage is permissible.
(for M6). § Move the handle to closed position
§ Place the handle assembly on the and notice a short blast of air through
stem and secure it with Hex. Hd. the vent.
Nut (M10). § Close cock 1c then Open cock (1d)
§ During assembly apply a light coat and exhaust the pressure to zero.
of shell MP2 or equivalent grease on § Remove the angle cock.
the external surface of the threads § Report results of the test.
and the ball.
iii) Safety Precautions
408d Testing of Cut Off Angle Cock
§ Specified tools and fixtures should
be used for assembly and
i) Tools and Equipment
disassembly operations.
§ The small metal parts like leaf
§ Test Bench
spring, nut, bolts, washers, screws
§ Compressor to build pressure upto
etc should be kept in a safe place
10 kg/cm2. and replaced in case found
§ Single ended spanner as per IS 2027
defective.
a) Across face 17 (for M10 lock
§ Inlet and outlet port of the tested
nut) 1No. angle cock should be plugged with
b) Across Face 13 (for M8 studs) 2
protection cap to prevent entry of
No.
dust and moisture inside the cut off
§ Screw Driver –300mm,1 No. angle cock.
§ 1 ¼ “ BSP dummy Plug with seal.
§ Dummy plug for angle cock. 409 BRAKE CYLINDER (see figure 4.5)
(Refer Drg. RDSO SK-97015)
ii) Test Procedure (refer figure 4.9)
On every coach fitted with air brake
Following test procedure sh ould be system two brake cylinders are provided
adopted for performing the leakage test. for actuating the brake rigging for the
application and release of brakes. During
§ Mount the angle cock on the base of application of brakes the brake cylinder
the test bench (Part No. 7 of the develops mechanical brake power by
figure 4.9 of the test bench). outward movement of its piston assembly
§ Move the handle to the closed after receiving air pressure from Auxiliary
position. reservoir through the distributor valve.
§ See that cock (1e) and (1c) are in This is transmitted to the brake shoes
closed position. through a combination of levers. During
§ Now open cock 1(a) and 1(b) till release action of brakes the compression
MR indicates a pressure of 10 spring provided in the brake cylinder
Kg/Cm 2. brings back the rigging to its original
§ If necessary, adjust pressure position. The cylinder body is made out of
regulator (2) to maintain the sheet metal or cast iron and carries the
pressure at 10 kg/Cm2 . mounting bracket, air inlet connection,
§ Open cock (1c) and check the ribs and flange. To the cylinder body, a
leakage with soap solution. There dome cover is fitted with the help of bolts
should not be any leakage. and nuts. The dome cover encloses the
spring and the passage for the piston
Chapter 4, Page 5 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
Chapter 4, Page 6 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
409d Cleaning of Parts § Smear the piston head & inside the
cylinder body with MP 2 grease or
§ Blow a jet of air to clean the dust equivalent.
on the external surface. § Ease the packing into the cylinder
§ Clean the metallic parts using wire with a wooden spatula with a
brush and kerosene oil. round nose and round edge to
§ Clean the internal parts with nylon avoid damage to the piston
bristle brush. packing.
§ Clean piston packing, wear ring § Push the piston assembly
and rubber parts with soap water approximately to the central
solution. position of the cylinder.
409e Replacement of Parts § With the help of special fixture,
bring down the dome cover on to
§ Replace return spring in case of the cylinder body and fasten the 8
crack, kinks or permanent set. Hex. HD bolt, nut and spring
§ Replace the brake cylinder body if washer with required torque.
found with deep marks, heavily § Take out the φ 12x25 long pin
corroded, or the bor e is worn from the piston trunk hole.
uneven or having ovality. § Fit back the plug at the rear of the
§ Replace all rubber parts. cylinder.
§ If piston trunk is worn excessively
it should be replaced. 409i Testing of Brake Cylinder (see
409f Inspection and Repairs of the Parts figure 4.6)
Chapter 4, Page 7 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
After the overhauling of the brake § Check the brake cylinder piston
cylinder, it is mounted on the test bench stroke at 0-5 kg/Cm2 pressure
and tested. It should be operated a few for its jerk free smooth
times on the test bench to ease the piston. movement.
Each brake cylinder after its maintenance § Close the safety guar d.
and overhaul shall be subjected to the § Close the cock (1b), (1c) and
following tests on the test bench. (1d).
§ Open cock (1a) and (1f) and let
a) Strength test
the reservoir pressure increase.
b) Pressure Tightness Test.
§ Set pressure regulator (2a) at
iii) Strength Test 10Kg/cm2.
§ Monitor the pressure in the
For strength test, procedure reservoir with the help of the MR
described below should be follow: Gauge (6a).
§ Let the pressure reach upto 10
§ Place the repaired/overhauled kg/cm2.
brake cylinder body on mount ing § Open cock (1b) so that air
base of the test stand. This collected in the reservoir is
mounting base (4) is provided transferred to the brake cylinder.
with a safety guard.
§ Adjust the pressure in the brake
§ Connect the air pressure line to cylinder with the help of the
the brake cylinder. pressure regulator (2b).
Chapter 4, Page 8 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
§ Monitor the pressure in the brake This will discharge the brake
cylinder with the help of the cylinder.
pressure gauge (6b). § Remove the brake cylinder from
§ Close the cock 1(b) as soon as the test stand.
pressure reaches 6 kg/cm2. § If operation is not correct or
§ Wait for 2 minutes. leakage rate is higher, dismantle
§ Brake cylinder should withstand the brake cylinder and examine
this pressure. the piston packing wear ring for
§ Open cock (1e), this will proper fitment, examine the
discharge the air pressure from fitment of the plug for leakage,
the brake cylinder and the piston reassemble the components and
assembly will come back. retest.
Chapter 4, Page 9 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
a) Spanner 19 x 22mm
b) Vice.
c) Screw Driver
i) Disassembly
Chapter 4, Page 10 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
iv) Assembly
§ Keep cocks ( 1f), (1c) and 1(e)
§ Assemble body after smearing closed.
grease. § Open cock (1a) and (1b).
§ Locate filter in position and § Charge the reservoir (5) to 10
assemble top cover with new kg/cm2.
gasket. § Close two openings on the dirt
§ Fix hexagonal bolts/nuts along collector using dummy flanges.
with the spring washer. § Open cock (1e), check the
§ Fix new sealing ring to the pressure at (6c). it should be
bottom and assemble drain plug. equal to 10 kg/sq. cm.
§ If not develop pressure up to 10
410d Testing of Dirt Collector
kg/cm2 by adjusting pressure
Testing of dirt collector is needed after its regulator (2).
overhauling. § Close cock ( 1e)
§ Check for leak over the body and
i) Tools and Equipment joints with the help of soap
§ Test Bench solution, no leak is permitted.
§ Compressor, capable of building § Also check for pressure drop in
air pressure up to 10 kg/sq. cm. gauge 6 (c)- for 3 minutes
§ Double ended spanner (Across § Pressure in the gauge 6c should
Face 19x22) – One No. be maintained.
§ Dummy flange for dirt collector § Reduce the pressure in the main
– 2 nos. reservoir (5) to 5 kg/cm2 by
opening cock (1f) and adjusting
ii) Test Procedure (refer figure 4.9) the pressure regulator (2).
§ Close cock (1f) as soon as
§ Mount the dirt collector on base pressure reaches upto 5 kg/cm2.
of the test bench.
Fig. 4.9 - TEST BENCH FOR ANGLE COCK, ISOLATING COCK, DIRT
COLLECTOR, CHECK VALVE AND GUARD'S EMERGENCY VAN VALVE
Chapter 4, Page 11 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
Chapter 4, Page 12 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
§ Specified tools and fixtures should Note: The general design and controlling
be used for assembly and dimension of guard’s emergency
dismantling operations. valve shall conform to the latest
§ Rubber / leather components should revision of RDSO drawing no SK-
be stored in a safe place away from 73549.
heat, alcohol & acids. All metal parts
like washers should be kept in a safe The guard's emergency brake valve
place. should be completely dismantled and
overhauled in every POH.
412 GUARD'S EMERGENCY BRAKE
VALVE (refer figure 4.11)
Chapter 4, Page 13 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
The following tools and fixtures are § Place seat ring in its position in the
required for overhauling bore of the body on one side.
§ Apply grease lightly on the ball.
§ Test rig/stand § Fit ‘O’ rings on the spindle.
§ Spanner A/F 19/22. § Insert the ball in the bore of the body
§ Special spanner for removing thread in such a way that the ball sits on the
plug. seat ring and the groove seat for
§ Spanner for removing gland. spindle is in top position.
§ Light hammer § Insert the spindle with ‘O’ rings such
§ Vice. that the sp indle enters in to the
groove.
412c Procedure for Overhauling § Screw the gland in to the body.
§ Insert the second seat ring through
i) Dismantling the bore of the housing.
§ Fit ‘O’ ring on the threaded plug.
§ Hold the valve in the vice. With a special tool screw the
§ Unscrew the nut on the stem and threaded plug.
remove the nut and the spring § Screw the threaded plug along with
washer. the ‘O’ ring into the housing till the
§ Remove the handle. ball seat touches the ball.
§ Unscrew the gland and pull out the § The handle shall be put on the
stem from the body. spindle and tightened with spring
§ Remove the two -gland packing on washer and nut.
the stems.
§ Unscrew the threaded plug from the 412d Testing of Guard’s Emergency Brake
body using a special spanner. Valve
§ Remove the ‘O’ ring and the ball
seat from the body. § After overhauling, fix the valve to
§ Remove the ball and the second ball the test bench. (refer figure 4.9 &
seat from the body. 4.11)
§ Put the handle of the valve in off
ii) Cleaning of Parts position (close position).
§ Charge the inlet port with a pressure
§ Direct a jet of air on the valve body of 10 Kg./cm2.
to remove the dust & dirt. § Check for leakage on the spindle
§ Clean the external parts of the valve portion and on the exhaust port with
with wire brush. soap water solution.
§ All metal parts shall be washed with § No leakage is permitted.
kerosene oil and wiped dry. § Operate guard’s emergency brake
§ Rubber parts shall be washed with valve, by putting the handle in open
soap water solution. position. Air should escape through
§ Steel ball shall be handled carefully the vent of the valve.
to avoid scratch marks or dent.
412e Safety Precautions
iii) Replacement of Parts
§ Specified tools and fixtures should
§ Replace all the rubber parts such as be used for assembly and
gland packing and ‘O’ ring. dismantling operations.
§ If spindle thread is corroded or § Rubber components should be stored
damaged, the spindle shall be in a safe place away from heat,
replaced with a new one. alcohol & acids.
§ If threads on the threaded plug are § All metal parts like nuts, washers
damaged or corroded badly, the plug should be kept in a safe place.
shall be replaced with a new one.
§ If ball of the valve has dent or
scratch marks it should be replaced
with a new one.
Chapter 4, Page 14 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
413 SLACK ADJUSTER (see figure 4.12) adjuster does not pay out slack
immediately, but indexes the amount of
413a Salient Features slack to be paid out. If the slack really is
Slack adjuster (also known as brake too small, the slack adjuster will pay out
regulator) is a device provided in the this indexed slack at the next brake
brake rigging for automatic adjustment of application. Thus false payout will not
clearance/slack between brake blocks and occur.
wheel. It is fitted into the brake rigging as True Slack Adjuster i.e. The slack
a part of mechanical pull rod. The slack adjuster adjusts incorrect slack only, thus
adjuster is double acting and rapid giving the brake its best possible pre-
working i.e. it quickly adjusts too large or adjusted limit of piston strokes, ensuring a
too small clearance to a predetermined smooth and efficient braking force at all
value known as `A’ dimension. The slack times.
adjuster maintains this `A’ dimension
throughout its operation. The slack Shock Resistant i.e. Train shocks will not
adjuster, type IRSA-450 is used in cause false take-up or payout of slack.
passenger coaches, It is composed of the When brakes are released, the moving
following parts parts of the slack adjuster are securely
§ Adjuster spindle with screw thread of locked.
quick pitches (non self-locking).
§ Traction unit containing adjuster nut, 413b Overhauling of Slack Adjuster
adjuster tube and adjuster ear etc.
§ i) Tools & Equipment
Leader nut unit containing leader nut
and barrel etc.
The following tools and fixture are
§ Control rod with head.
required for overhauling of slack adjuster;
The out standing features of slack adjuster
IRSA-450 are: (i) Jacking tool – for mass repair /
Fully Automatic i.e. once initially set, no overhauling of Slack Adjuster
manual adjustment is further necessary at pneumatically operated fixture is
any time during its operation. used.
(ii) Special Spanner
Double-Acting i.e. The brake shoe
clearance is adjusted to its correct value (iii) Straight Nose pliers (external)
both ways, either when it has become too (spring type)18 mm to 25 mm-
large (owing to wear of the brake shoes external
and wheels) or when it has become too (iv) Bend nose pliers (internal) 25 -30
small (e.g. owing to renewal of `worn out mm –internal
brake blocks’). (v) Screw driver
Rapid working i.e. correct brake shoe (vi) Pipe vice & simple 6” vice
clearance is automatically restored after (vii) Open end spanner 11-13 mm.
one or two applications of the brake. (viii) Hand punches
(ix) Kerosene oil bath
Verification i.e. If resistance occurs early
in the brake application, caused by heavy (x) Air jet gun
brake rigging, e.g. an ice coating on the (xi) SAB test bench
brake shoes, etc., in such cases the slack
A1
A1
A
A
Note: The Slack Adjuster takes up100 mm per braking. Dimension A1 will be 98 + 1/-4 mm (refer G-92)
Figure 4.12 – SLACK ADJUSTER
Chapter 4, Page 15 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
The slack adjuster shall be overhauled at The following safety precautions should
the time of POH of rolling stock. While be observed during overhauling of slack
dimantaling or assembling it is essential to adjuster.
use special tools. Each component of § The place of overhauling must be
slack adjuster shall be examined. Worn clean and free from dust.
out part shall be checked according to the § Ensure that no foreign
limits. For details, refer RDSO Technical matter/particle remain inside the sub -
pamphlet No. G-92(October-91). assemblies during re-assembly.
§ All rubber gasket, seal ring, washers
The minimum desired characteristic of must be replaced during overhaul.
each spring should be taken as under [Ref: § Specified tools and fixtures are used
RDSO Technical pamphlet No. G-92 for disassembly and assembly
(October -91)]: operations.
2. Pay out 11 100 mm 58 Kg. a) Attach the adjuster ear to the free
spring end of the cylinder lever of the test
rack
3. Take out 37 21.5 mm 22 Kg. b) Screw the test rack spindle into the
spring Slack Adjuster until the entire length
of thread is covered by spindle
4. Clutch 39 38 mm 300 Kg. sleeve and attach the free end of the
sprin g spindle to the test rack.
i) Pay-in test
Any spring, which does not conform, to
the above characteristic should not be § Let down the control rod, so that the
used. In addition any of the springs is fork of the rod clasps the adjuster
badly rusted or having compressed coil tube of the Slack Adjuster
turns should not be used. § Apply and release the brake a few
times letting the slack Adjuster take
The following parts must be replaced up until the correct piston stroke is
during POH of the slack adjuster[Ref: obtained (until the indicator is within
RDSO Technical pamphlet No. G-92 + 5 mm tolerance field of the scale).
(October -91)];
ii) Pay-out test
§ Spring dowel sleeve part No. (18)
§ Lock washer part No. (27) § Turn up control rod and make two
§ Seal ring part No. (2) brake applications letting the slack
§ Seal ring part No. (43) adjuster pay out.
§ Rubber gasket part No. (4) § Repeat the above pay in and pay-out
§ Spring dowel sleeve part No. (25) tests a couple of times.
§ Dog pin part No. (6) § satisfactorily, dismantle it and check
§ Tab washer part No. (34) that the parts are placed correctly.
§ The slack adjuster must then be
413d Lubrication tested once more in the test rack in
accordance with the above
After cleaning and inspection all parts of instruction.
slack adjuster should be coated with semi- § After the test is finished, remove the
fluid grease SERVOGEM -RR3 or spindle from the slack adjuster.
MALMEROL MULTIGREASE LL3 § Remove the slack adjuster from the
(refer G-92) before undertaking re- test rack and unscrew adjuster ear.
assembly.
Chapter 4, Page 16 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
Chapter 4, Page 17 of 50
Hindi Contents
Maintenance Manual for BG coaches of ICF design Air Brake System
413h Procedure for Brake Rigging setting such cases the `e' dimension can
and measurement of “A” and “e” be restored by adjusting link
dimensions:- provided on the bogie frame
head stock.
The procedure to be adopted for operating
brake rigging setting and measuring ‘A’ (ii) Measure ‘e’ dimension i.e.
and ‘e’ dimension is listed below:- distance between protection tube
end and mark on adjuster spindle
For ‘A’ dimension (16 +2/-0 mm for 13 using measuring stick after two
t bogie and 22 +2/-0 mm for 16.25 t or three brake application. It
bogie) (refer G-92) should be set to nearly to its
maximum limit i.e. 375± 25mm.
(i) Ensure the air brake is in fully
released condition and all the 413i Safety Precautions
brake rigging gears are in proper
condition. § Always use wedge between wheel
and rail before application and
(ii) Apply brake three to four times
release operations for setting and
to ease the rigging, by dropping
measuring A and e dimension to
and re-charging the air pressure
prevent rolling of coach.
in the brake pipe
§ Ensure no part of the worker’s body
(iii) Ensure once again that brake
rigging is in fully released is in touch with moving brake
condition. rigging gears during application and
releasing of brakes.
If ‘A’ dimension is not correct § Do not touch or hold slack adjuster
barrel while it is in motion.
1. Remove pin securing the control
rod in U bracket. § Before setting any dimension ensure
wear of brake shoe does not exceed
2. Detach control rod and rotate it
to its minimum permissible worn
to adjust the gap between barrel
limit (i.e. thickness of the shoe
end face & control rod head as
should not be less then 20 mm).
specified in note above. Secure
the control rod in U bracket. § There won't be any slack take up
3. Apply brakes two to three times. provision in the slack adjuster and
slack adjuster will only act as
4. Check the ‘A’ dimension using strut/pull rod. This is because of
the gauge. brake shoes and wheel wear reaching
their condemning limit/near
5. Recheck dimension ‘A’ with
brakes fully released after every condemning ilmit. In such cases the
`e' dimension can be restored by
brake release.
adjusting link provided on the bogie
6. Lock the control rod head firmly frame head stock.
with check nut and tooth lock
washer. § Measure ‘e’ dimension i.e. distance
between protection tube end and
7. Secure pin with split pin.
mark on adjuster spindle using
measuring stick after two or three
For ‘e’ dimension
brake application. It should be set to
nearly to its maximum limit i.e.
(i) If slack is in excess beyond the
± 25 mm.
375±
capacity of slack adjuster (`e'
dimension 375+25mm) there
won't be any slack take up
provision in the slack adjuster
and slack adjuster will only act
as strut/pull rod. This is because
of brake shoes and wheel wear
reaching their condemning
limit/near condemning limit. In
Chapter 4, Page 18 of 50
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
CHAPTER 5
502a During POH all components of the brake 503b Train pipe
gear system shall be examined, repaired and
replaced as necessary. The pins and bushes i) Check the train pipe with compressed
shall be examined for wear and replaced if air of 2 kg/cm2 for leakage specially at
the radial clearance exceeds 0.75 mm. threaded joints, bends and portions
where clamps are fitted, tee joints,
502b Following items should receive particular swan neck, etc. with one end dummy.
attention during POH: ii) Check and replace corroded, dented,
bent more than 10 mm, or thin walled
portions of the train pipes. Spiked
i) Safety brackets provided for brake gear
hammer should be used to check thin
components should be in accordance
wall, corrosion, etc. While renewing
with the approved drawings and shall
the pipe, it should be ensured that
be examined for proper condition and
bending do not decrease the cross
secured according to the prescribed
sectional area of pipe passage at the
method.
bends. New brake pipe should be given
a coat of anti-corrosive paint before
ii) Vacuum cylinders and their trunnion
fitting.
brackets, vacuum reservoirs and train
pipes, rubber hose & syphon pipes, iii) Renew the damaged/ missing brackets
alarm chain apparatus including the or clamps used for clamping the train
chain, disc and locking arrangement, pipe.
brake beams, hangers, and brake
iv) All the pipe threads must be cleaned
blocks shall be secured as prescribed.
and applied with white lead before
All brake gear pins (should be
couplings are fitted. Clean the grooves
chromium plated) shall be secured
on swan neck.
with washers and split cotters.
v) After attending to all the repairs, test
iii) Vacuum gauges shall be properly the train pipe for sound joints and
tested and adjusted using master bends with compressed air at 2 kg/cm2
gauges before being fitted. pressure. There should not be any
leakage of air over the entire length of
the train pipe.
503 LIFTING SHOP
vi) After repairs and testing, the train pipe
503a After lifting the coach body and placing it should be given a coat of anti-
on trestles, dismantle the following parts of corrosive paint.
the vacuum brake system and send to the
Chapter 5, Page 1 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
RAIL LEVEL
D.A. VALVE
FIGURE 5.1
Chapter 5, Page 2 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
503c Rubber hose pipe and syphon pipe surfaces and cages fitted before the
couplings are inserted into the hoses.
i) Renew the hose pipe and syphon pipes They should be clipped firmly.
if they had cracked or lost the bond
between the various layers/ 503d Vacuum Reservoir Straps
components.
ii) Reusable hose/ syphon pipes should be Vacuum reservoir straps should be
tested for vacuum retention. For this examined for slackness, corrosion and
test, the hose should be connected by thinning, and damaged or worn out threads
means of a cylindrical nozzle of size at their ends. and entire straps or threaded
corresponding to the vacuum/ syphon ends, as required, should be replaced. If the
hose bore to a chamber of 1640 cu. securing holes in the under frame are worn
cm. volume and the free end of hose more than 3 mm, build up by welding and
closed with a cylindrical plug. 510 mm redrill the holes. The reservoir straps should
Hg of vacuum should be created in the be double secured with spring washer and
chamber and hose system. On isolation check nuts. After all repairs, the reservoir
from the source of vacuum, the drop of straps should be given a coat of anti-
vacuum should not be more than 75 corrosive paint. FRP tissue should be placed
mm Hg in one hour on the chamber in between reservoir and safety straps. APD
gauge. The pipe should not be clipped should be done.
or otherwise bound to t he chamber 503e Vacuum cylinder trunnion bracket
nozzle or plug for this test. The hose
should also be bent around a mandrel Where bushes are provided in the brackets,
of 228 mm diameter till the ends of the they should be renewed and a light coat of
hose are parallel. This should not result graphite grease applied before fitting a
in any displacement or distortion of cylinder. Trunnions of the cylinder must
wire. neither be too loose nor too tight in their
iii) Cracks, porosity, tears, etc., of the hose brackets. Lateral clearances on the trunnions
should be detected by giving it a (on each side) should not exceed 3 mm. It
stretch test. For this purpose, hose pipe should be adjusted by renewing the bushes.
should be secured to a special jig and If there are no bushes, the trunnions should
should be stretched to 20% over its be bored and bushes of correct size fitted to
original length and released 100 times. get the required clearance.
Thereafter, in the stretched position, its
surface should be examined to detect 503f Brake shaft
the defects, if any. Cracked, torn,
porous, or collapsed hose pipes or hose Brake shaft should be examined for
pipes with coiled wire loose or straightness, bending and wear on its
missing, or length reduced below 50 bearing surfaces. The shaft bearing worn
cms . should be rejected. beyond 3 mm should be built up by welding
and machined to its original size. Before the
iv) Serviceable hose pipe should be
shaft is fitted into its brackets its bearing
secured on swan neck (after applying
surfaces should be smeared lightly with
rubber solution on swan neck) with
grease. The fork arm should also be
clip and tighten with spanner.
examined for bending, distortion and wear
v) Renew the corroded or damaged hose on its forked ends and restored to its original
pipe clips. shape and size as required. The brake shaft
vi) Broken, damaged, or distorted cages mounted in its brackets under a coach
should be replaced with modified should be parallel to the trunnions on which
cages to drg.No.VB 409/M. the cylinder swings to avoid setting up of
side or crosses stresses and hence damage to
vii) Universal coupling should be
the arm. The brake shaft should not have a
examined for broken, cracked and
side play in its bracket bushes in excess of 2
distorted lugs and renewed on
mm after POH.
condition basis. Rubber solution
should be applied on the mating
Chapter 5, Page 3 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
503g Brake shaft brackets the vertical pipe should be blown clear
with compressed air and the pipe
Brake shaft bracket bolts and nuts should be threads should be checked before the
examined for rusting, looseness, thinning assembly is connected to train pipe.
and worn out or damaged threads and v) All moving parts including spring
replaced, if required. Good bolts and nuts
should be greased and checked for
should otherwise be reused after greasing proper movement.
their threads. The brackets should be
checked for cracks, corrosion and thinning vi) The clappet operating chain and the
or damage and repaired/ replaced as pipe through which the chain passes
required. The brake shaft bracket bushes should be dismantled, examined and
should invariably be changed. renewed with standard chain or 6 mm
wire. If in normal position of the
503h Slack adjuster support bracket on coach clappet valve, the chain hangs loose in
any of the compartment openings, its
The support brackets should be stripped and length should be adjusted by cutting it
examined for missing or worn out rollers out to the extent necessary. Wooden
and bent, defective or missing springs. The handles provided in the compartment
defective or missing roller and springs openings for pulling the chain should
should be replaced. Defective spring should also be checked and replaced where
be repaired by restoring them to their found broken or cracked.
original shape and size and hardened and
tempered to give correct tension. The vii) After the clappet valve assembly is
securing brackets and nuts as well as pins overhauled and refitted, its chains, etc.,
should also be checked and replaced or are checked and replaced, the alarm
repaired as required. chain apparatus should be tested at the
outgoing pit for its operation in
503i Alarm chain apparatus accordance with the following
procedure.
i) During POH, alarm chain apparatus
should be opened, cleaned and 503j Alarm chain apparatus test
overhauled.
i) Create 460 mm to 510 mm of vacuum,
ii) The chain must be of the prescribed
pull the chain, using a spring balance,
specification and each link must be at both sides of the coach from the end
physically examined for crack/ wear/ where the chain is anchored, ie., from
elongation. Proper fitment/ anchoring the end which is farthest away from
of all the components should be the clappet valve.
checked and ensured to avoid their ii) The alarm chain should not operate the
failure/ non-operation/ mal-functioning clappet valve if the pull applied
during service.
vertically down wards is less than 6.4
iii) The clappet valve should be removed kgs. It should also not require a pull of
from the coach for overhauling. more than 10 kgs. for its operation.
Replace the rubber washer. The iii) When the chain is pulled, the brakes
clappet valve cover should be checked should apply on the coach and the drop
and repaired or replaced as necessary. of vacuum in the train pipe should be
The clappet valve operating rods, between 180 mm and 200 mm if one
levers, indicating discs and other coach is being tested, or between 130
moving parts should be cleaned and mm and 180 mm when a rake as a
checked and straightened if bent, or whole is being tested. If the drop in
replaced if broken or deficient. The vacuum is less than 130 mm and still
pins if worn should be renewed, if not the brakes are applied, it shows an
they should be cleaned before reuse. obstruction in the vertical pipe, in
iv) The vertical pipe connecting the which case it is necessary to locate and
clappet valve with train pipe should be clear the obstruction in vacuum
examined to ensure that it is neither vertical pipe.
leaking nor blocked. The air passage in
Chapter 5, Page 4 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
Chapter 5, Page 5 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
3) With vacuum throughout the Renew all the rubber items like the neck
assembly, the guard van valve ring and gland box joint washer invariably.
should automatically lift on a Renew the worn/ loose guide bush. Replace
rapid destruction in the train the worn, damaged, or broken studs. Secure
pipe of approximately 225 mm the gland box on the cylinder cover with
of vacuum, and on the operating spring washers and nuts.
handle of the test apparatus
being placed in the "running" 504g Piston rod
position, the guard van valve
Dismantle the piston rod from the piston.
should re-set itself within 3 to
Renew the bent, damaged, dented, worn,
5 seconds.
corroded, or pitted piston rods. If the threads
of the piston rod are damaged, the rod
Note:- Above tests 2 & 3 apply only to should be replaced.
automatic type of guard van valves
having a diaphragm and dome above 504h Piston
the atmospheric valve.
The cracked piston should be replaced. The
504c Vacuum gauge piston skirt serrations should be cleaned free
of dust, rust and sediments. Visually check
Vacuum gauge which is permanently fitted the piston for worn or cracks. Replace the
in guard's van should be removed and piston if found damaged beyond salvage.
calibrated with master gauge before Measure the out side diameter with
refitting. If defective, it should be repaired micrometer of range 575-600 mm & record
and again calibrated with master gauge and the dimensions. While assembling the
refitted. The vacuum gauge guard must be Piston and Vacuum cylinder the diametrical
invariably provided to protect the gauge difference between the two should be 20.3
from damage or theft. mm. The blind holes for the piston rod
cover bolts should be tapped and eased.
504d Vacuum brake cylinder
504i Ball valve cage
Strip the vacuum cylinder completely.
Thoroughly clean and dry the components The ball valve should be opened, thoroughly
and check for defects like cracks, damages cleaned free of dust, dirt and sediments and
and wear. lightly lapped. Four holes in the cage which
should be of 6 mm diameter should be
504e Pan (Cylinder cover) cleaned thoroughly. The ball valve cage
cover should be checked for good threads.
Replace the cracked/ broken cover or if the The ball should be replaced even when
welded lugs are more than 50% of the total slightly worn. Ball valve should be changed
lugs. Broken/ cracked lugs should be when its seating is worn out or pitted and
replaced with new lugs by welding and the surface is not smooth to provide good
grinding. After attending to the defects, the seating for the ball. the ball and the ball seat
pan should be painted with one coat of anti- should otherwise be cleaned with emery
corrosive paint. paper and lapped together before assembly.
The cage cover should be replaced if its
threads are damaged.
Chapter 5, Page 6 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
Chapter 5, Page 7 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
vacuum, record a drop of more vacuum exhauster and train pipe. This
than 20 mm in one minute on valve will automatically control the
the chamber gauge. vacuum to a maximum of 460 mm
♦ Release valve, connected with lever in horizontal position and a
through the chamber port to a minimum of 356 mm with the lever in
chamber of 1640 cu. cm. vertical position with, exhauster
volume with 510 mm of working.
vacuum throughout the ii) Create 460 mm of vacuum (lever of
assembly, shall not, on control valve horizontal).
destruction of the vacuum, iii) Destroy the vacuum.
record a drop of more than 20
iv) 20 minutes after destruction, create the
mm in 1 minute on the
balancing vacuum of 356 mm (lever of
chamber gauge.
control valve vertical). The piston of
B) Operation test: cylinder in good condition should
partly descend but not completely.
♦ Release valve, connected That which completely descends is
through the chamber port to a faulty and should be dismantled and
reservoir with vacuum repaired again.
throughout the assembly shall, v) Increase vacuum to 460 mm (lever of
when the vacuum is destroyed control valve in horizontal) when
in the train pipe by pulling on piston should completely descend.
the operating lever wire thus That which does not descend
operating the valve, remain in completely is faulty and should be
the open position till there is dismantled and repaired again.
pull on the lever wire. It After successful BVT testing, supply the
should re-set immediately on brake cylinder to lifting shop for fitting on
removal of the pull. coach.
♦ On re-creation of not more
than 205 mm of vacuum, the 506 D.A.VALVE (ESCORT- KNORR D.A.
valve shall re-set itself. VALVE)
505 ASSEMBLING AND TESTING OF 506a Open the two halves of DA valve by
VACUUM CYLINDER removing the four M8 hexagonal nuts.
Clean all the components and sub
505a After attending to the defects of vacuum assemblies like lower locking screw
cylinder parts, assemble the Parts as per subassembly of the lower housing, housing
IRS drawing No.VBA - 16 / M. alt 6. Care upper subassembly, diaphragm sub
should be taken to invariably replace all assembly, valve seat subassembly, etc. All
the rubber items like rolling ring, joint the rubber items should be replaced
ring, release valve joint washer, piston cap invariably and other parts should be
washer, etc. While assembling the Piston changed on condition basis.
and Vacuum cylinder the diametrical
difference between the two should be 20.3 List of Rubber Items which should be
mm. After complete assembly, the changed
vacuum cylinder should be tested on the Table 5.2
test bed and stencil the date of overhaul,
the date of testing and shop code on the Part Name Drawing Number
vacuum cylinder body. Diaphragm 4A 38266
Seal 48174
505b Testing of Brake cylinder (Balanced
Nylon guide bush KB 408
Vacuum Test )
Sealing ring A 35 x 41 Dln 7603
i) Attach the overhauled brake cylinder Sealing ring A 30 x 36 Dln 7603
to test stand train pipe and test K Ring N 891 / 20.2
reservoir. The balanced vacuum Joint ring KB 115
control valve is connected in between
Chapter 5, Page 8 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
506b The filter element of (Escort-Knorr 506d Testing of DA valve: After the DA valve is
D.A.Valve) should be thoroughly washed in overhauled and assembled, it should be
kerosen and blow with compressed air to tested on the test bench as indictated in
remove the entire collected dirt. Before figure 5.2 for its functional performance
fitting back, the filter element should be and leakage.
immersed in light machine oil and the oil
allowed to be drained. i) Retention test : Mount the DA valve
on the test stand and create vacuum till
The filter element of (Greysham 530 mm Hg is indicated on both
D.A.Valve) should be thoroughly washed in gauges A and B of the test stand. Close
parafin to remove the entire collected dirt. stop cock "Y" and then stop cock "X".
Record the drop of vacuum in both the
List of Items to be Changed in Escort gauges A & B, which should not be
type DA valve on Condition Basis more than 12.5 mm in 10 minutes.
ii) Operation test : The stop cock "X" is
Table 5.3 opened till the gauges A & B again
record 530 mm of vacuum. Then stop
Part Name Drawing Number cock "X" is closed and "Y" is opened.
Pin and screw assembly 4KB 613 Record the drop in gauge B (brake
cylinder) from 530 mm to 25 mm
Diaphragm seat 4A 50314
which should be within 3 seconds.
Valve seat 4A 50807
iii) Proportionality test : Open stop cock
Locking screw 4A 55757 "X". Vary vacuum in gauge A by
Valve seat 4A 54952 opening and closing cock "Y". It will
be observed the gauge B follows gauge
Locking screw 4A 69805 A very closely both during creation of
Hex. nut M8, DIN 934 vacuum and brake application.
Spring washer B8, DIN 127
Hexagonal bolt M8x35 DIN 931 507 SLACK ADJUSTER (SAB DRV2-450)
Self tapping screw
4x5/16" Refer to write-up on Slack adjuster in para
413 of Air Brake Chapter.
Filter assembly KB 137
Cup plate KB 409 507a End piece for slack adjuster pull rod
Hex. nut M10 x 1.5 DIN 439
Prepare end piece for pull rod as per the
Washer DIN 433 RDSO SK - 96102 alt. 3 to be used in
Compression spring 4A 30485 / 8 modified vacuum brake system to provide
horizontal movement to slack adjuster:
506c The DA valves should be closely examined Type of coaches Length of end
and seats ground lightly to avoid leaks. piece
While assembling care should be taken for
fitting the diaphragm on to the lower WFSCN, SL, SCNLR 265 mm
housing groove properly. The end corners
must be pressed inside the groove. Free
All other vacuum 155 mm
movement of the diaphragm subassembly
braked coaches
should be checked by hand. During the final
assembly of upper and lower housing,
tightening of hexagonal nuts should start
from the O-ring end and the 4 nuts must be
tightened evenly.
Chapter 5, Page 9 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
GAUGE ‘B’
GAUGE ‘A’ (BRAKE CYLINDER)
(TRAIN PIPE)
COCK - X
FILTER
1/2” 1/2" TP
TO VACUUM
PUMP
DA VALVE
UNDER
LC TEST
RESERVOIR
3/4"
34 LITER
1.2 Cu. ft.
COCK - Y
RESERVOIR
1/2" 34 LITER
1.2 Cu. ft.
TESTING OF DA VALVE
Figure 5.2
Chapter 5, Page 10 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
Table 5.4
Chapter 5, Page 11 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
Table 5.5
h) Defective brake Check that all brake Change brake gear compo-
rigging rigging components nents, pins and bushes as
are as per drawing necessary.
and the clearance
between brake gear
pins & bushes are
within the
permissible limit.
Chapter 5, Page 12 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
2) Brake on a coach (a) Brake rigging pin & Move or shake by Ease the jammed compo-
do not release. brake shaft jammed. hand and feet. nents.
(b) External leak in the Test by a flame Rectify the leak or change
train space of vac. which will be drawn the neck ring or the piston
cylinder commonly in at places of rod as required.
due to worn out neck leakage or close the
ring or scored piston valve connecting the
rod source of vacuum,
after creation of
vacuum and check
the train needle in the
vacuum gauge which
will come down.
Chapter 5, Page 13 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Vacuum Brake System
*****
Chapter 5, Page 14 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
CHAPTER 6
Chapter 6, Page 1 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
1 27
STROKE
95 MAX. (MUST BE
IN A STRAIGHT
STROKE
WORKING STROKE,32mm FOR SELF LINE)
*
% % p 0 .5
GENERATING MAIN LINE COACHES, 117.5
281 22
A
60mm FOR BG EMU COACHES.
*
127
130
= =
%%p0.5
204
12 7
LEVERS MUST BE
ARRANGED SUCH THAT
POSITION A FOR MAIN LINE SELF
R EL EA SE PO SITION AF TE R
THE CROSSHEAD IS
25
HAND BRAKE TRUNNION
PO SITIO N
IN ITIA L R E LE ASE
2 Nos.AIR INLET PIPE CONNECTION,
ONE CONNECTION IS TO BE MADE
DUMMY BY PLUGGING.
400
365
B
MAX. WORKING MOVEMENT
% % p0 . 5
M A X.
31
204
MA X.
47 . .
=
M A X.
47
M AX.
31
RESETTING LATCH
Chapter 6, Page 2 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
Chapter 6, Page 3 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
INLET PLUG
compressed air is
supplied from loco
2
3
C
4
8
7
10
6 9
b
Chapter 6, Page 4 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
Chapter 6, Page 5 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
Chapter 6, Page 6 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
Chapter 6, Page 7 of 14
29
30 19
26
18
31
52
50
51
61
47,48,49
117.5
%%p0.5
CRS
L HEAD EYE
546 TO C OF CROSS
TOLERANCES ADDED ON
C
3 - CD/3/99 8/99 1:1
DIMENSION 204 CRS %%P 0.5 D SK SRIVASTAVA 203mm AIR BRAKE CYLINDER
T
2 - CD/35/98 TITEL CHANGED. 12/98 (WITH SLACK ADJUSTER)
J.S.
1 1,16 CD/24/98 VIEW CORRECTED. 8/98 FLOPY No. :-
R . D . S . O.
GROUP 1 2
Chapter 6, Page 7 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
58,37,38
57
56,11
%%p0.5
60
27
55
130
59
54
53 %%uNOTE:-
+0.5
-0 204 CRS
FIGURE 6.3b
CHANGED TO 130%%P0.5mm
TOLERANCES ADDED ON
C
3 - CD/3/99 8/99 1:1
DIMENSION 204 CRS %%P 0.5 D SK SRIVASTAVA 203mm AIR BRAKE CYLINDER
T
2 - CD/35/98 TITEL CHANGED. 12/98 (WITH SLACK ADJUSTER)
J.S.
1 1,16 CD/24/98 VIEW CORRECTED. 8/98 FLOPY No. :-
R . D . S . O.
GROUP 1 2
Chapter 6, Page 8 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
TABLE 6.2
Item Description & dimensions No. off Ref. Drg. Mtl. & Remarks
spec.
1 Cylinder Body 1 SK-81201 Item 1, 3,4 & 5
2 Piston 1 SK-81203 Item - 1
3 Piston packing 1 SK-81204 Item -10
4 Plunger 1 SK-81206 Item - 2
5 Circlip Light B22 1 - IS:3075 Galv.
6 Special Washer 1 SK-81206 Item-14
7 Plunger Spring 1 SK-81206 Item-18
8 Piston Trunk 1 SK-81204 Item-1 & 2
9 Tee bolt M12x35 4 - Galv.
Alternatively M12x45
10 Hex. head nut M12 4 - IS:1363 Galv.
11 Spring washer M12 type A 8 - IS:3063 Galv.
12 Dome cover 1 SK-81202 Item-1
13 Ratchet with adjusting screw 1 SK-81204 Item-9
14 Adjusting tube 1 SK-81204 Item-6, 7 & 8
15 Release Spring 1 SK-81206 Item-20
16 Guide bush 1 SK-81202 Item-2
17 Hand brake trunion 1 SK-81205 Item-12
18 Split pin φ5 x 40 3 - IS:549 Galv.
19 Washer M22 type -C 3 - IS:2016 Galv.
20 Slotted head grub screw 'C' 2 - IS:2388 Galv.
M6x6
21 Jubilee clip size-5 1 - Galv.
22 Dust excluder 1 SK-81204 Item-11
23 Latch 1 SK-81206 Item-3
24 Latch spring 1 SK-81206 Item-21
25 Ring 1 SK-81206 Item-23
26 Slotted Nut 7/8" B.S.W. 1 - Galv.
(20 mm high)
27 Shims for plunger As SK-81206 Item-16
required
28 Special washer 1 SK-81206 Item-12
29 Trunion Body 1 SK-81205 Item-1
30 Coller 1 SK-81206 Item-4
31 Circlip light A32 1 - IS:3075 Galv.
Chapter 6, Page 9 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
Item Description & dimensions No. off Ref. Drg. Mtl. & Remarks
spec.
32 Plug ½" B.S.P. 1 - Galv.
33 Solid Taper pin φ 2 x14 1 - IS:2393 Galv.
34 Plunger pin 1 SK-81206 Item-11
35 Rocker arm 1 SK-81206 Item-1
36 Rocker arm pivot pin 1 SK-81206 Item-10
37 Special washer 2 SK-81206 Item-9
38 Split pin φ 3.2x18 3 - IS:549 Galv.
39 Roller 2 SK-81206 Item-5
40 Rocker arm roller pin 1 SK-81206 Item-9
41 Washer 1 SK-81206 Item-5
42 Roller Plate 1 SK-81201 Item-2
43 Bush 1 SK-81202 Item-3
44 Filter 1 SK-81202 Item-4
45 Guide bar 1 SK-81204 Item-3
46 Snap Head rivet φ 2.5x8 2 - IS:2155 Galv.
47 Hex. head bolt M6x25 8 - IS:2155 Galv.
48 Hex. nut M6 8 - IS:1363 Galv.
49 Spring washer M6 type A 8 - IS:3063 Galv.
50 Bush 1 SK-81206 Item-17
51 Jubilee clip size 2 1 - Galv.
52 Cross head 1 SK-81203 Item-2
53 Circlip light B16 2 - IS:3075 Galv.
54 Special washer 2 SK-81206 Item-15
55 Pawl spring 2 SK-81206 Item-19
56 Alen screw ½" BSFx 2"x7/8" 4 - Galv
TD. length
57 Pawl housing ring 1 SK-81206 Item-6
58 Pivot pin 1 SK-81205 Item-3
59 Pawl 2 SK-81206 Item-8
60 Plunger 1 SK-81206 Item-7
61 Retaining nut 1 SK-81206 Item-24
Chapter 6, Page 10 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
63
Chapter 6, Page11of 14
5
+0
+0.5
- -0.1
3
69.9
%%C21
6
%%C20 = =
60%%d
2 3 4
5 %%c14 +0.5
-0
1x45 %% D
2 +0.1
-0.5
%%c82
5
=
%%c80
73
%%C52
+0.2
+0.2
-0. 5
2 3R
.5
3 R %%C47
% %c8 9 16 TP I (BSP)
+0
-
98 .5
1 02
1 08
13 4
+0. 5
+0.0
3 0.5
%% C89 .5-0.5
+
-
-
3R
7
C8
48 .5
%%
%% c95
04 3R
2 %
C1
-0.1
-0. 2
+0
%
+0
=
L)
MA
OR
306 0(N +0
c8 .5
%%
3R
59R
%%C14
1x45 % %D
+0.1
-
=
=
3
25 20 %%C13 DRILL +0.1
-0
10
16 SECTION-`AA' 13R
19
3
+0
120 52 = = -0.1
+0.5
- 333
13 73.1
A
9
18
%%c168
3R L
4 9 4 24 2.5
THIS MACHINING TO BE
52
25
% %C1 8
DONE AFTER BOLTING
4R 4R
PISTON(SK-81203,ITEM-1)
10
IN POSITION.
18
+0. 0
-0.1
X 74%%d
1 0.2 5
% %C4 0
%% C3 1 .5
% %C2 0
16
+0.05
%% C36 .5
+0.05 %%C171.45 -0
-0
+0.5
50
-0.0
+0.0
%%c35-0.02 3R %%C186.5
76
% %C45
16
3X45%%D
16R
2 18
1 10
13
TEETH OF RATCHET ONLY TO
9
9.5
BE HEAT TREATED.
24
18 TEETH EQUI-SPACED
+0
35
(1) QUENCHING IN OIL FOR CORE
B 4 -0.1
130
46
REFINING (850%%DC BEFORE QUENCHING)
3 (2) HARDENING (760%%DC BEFORE
" , 2 START, 1/4" LEAD, 1/8" PITCH,
%%C1 1.5 1.5x45%%D 391
64
8 9 QUENCHING IN OIL)
WHIT. FORM THREAD. 0.4R HARDNESS HRC-50, CASE DEPTH 0.5mm. 463
%%
C4
4. 5 +0
3 %% d
. .
+0
X
R-48-88 GRADE-`C' OF CL.5.2.4.1
.
.
-0. -0.02
05 +0 0.8
-0. 01 3.2
R %% C5 HARDNESS: 70+5 SHORE `A'
-
%% C44
+0.0
% % C25. 31 -0. 05
3R
%%c95
1R
1.6 %%C98
49.2 34
% %C19. 05 - 0.13
+0
%%c103
ANNEXURE-'A'
10 PISTON PACKING 1 of Spec.C-K013
492
SECTION-`BB'
%% C2 5
IS:2062-92
.
5 DUST EXCLUDER 1
X.
.
.
21 WHERE MARKED THUS, & 4. ALTERNATIVELY PISTON FOLLOWER MAY BE CAST IN SINGLE PIECE,
3 MATERIAL SHALL CONFORM TO GRADE SG 400/18 OF IS:1865-91 4 SNAP HD. RIVET %%C2.5X8 2 GALV.
TO BE PAINTED RED. IS:2155
13 533
7
IS:2062-92
3 GUIDE BAR 1
Fe-410WA
STEEL
15
2 PISTON TRUNK 1 HEAVY
+0.0
6
DESCRIPTION DIMENSION `L' IS:1239-90 PART-1
%% C36 .5 +0.1
-
SEE NOTE
%% C8
+0.1
IS:2062-92
-
%% c7 /8" 9T PI
-0.5
1 PISTON FOLLOWER 1
+0
102
%%c208 No. WT. OF
50 ITEM DESCRIPTION & DIMENSIONS REF. DRG. &
MTL. SPEC. REMARKS
WITHOUT HAND BRAKE OFF ONE kg.
%%c172
RDSO/SK-81200
SUPERSEDED BY: INDIAN RAILWAY STANDARDS
%%c168
ASSEMBLY DRAWINGS SUPERSEDES: EMU STOCK SELF GENARATING
1
%%C5
3"
DIA 2 START;1 1/4" LEAD, REFERENCE:- SCALE P MAIN LINE COACHES
19
8
4.5 6
C
2
1/8" PITCH WHITWORTH THREADS 3 1 CD/8/2000 NOTE 4 ADDED. PISTON,PACKING
PROFILE MODIFIED.
11/2000 1:1 DETAILS OF 203 mm. AIR
D SK.SRIVASTAVA
8 8
2 - CD/35/98 TITLE CHANGED 12/98
2:1
T
BRAKE CYLINDER
4 Nos-%%C12 HOLES
(WITH SLACK ADJUSTER)
FIGURE 6.4
4-%%c15 mm. DRILL
EQUISPACED FOR 1. MATERIAL SPEC. CHANGED J.S.
PLUG WELDING %%c171.45 1 10 CD/24/98 2. DIMENSION 182 CHANGED TO 8/98
FLOPY No. :- GROUP 1 2
186.5, TOLERANCE CORRECTED R . D . S . O.
%%C186.5
ALT. ITEM AUTHY. DESCRIPTION DATE B.G. (C)
3
SKETCH-81204
%%c191
%%c203.2
Chapter 6, Page 11 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
Chapter 6, Page 12 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
3
UNION
2
BED PLATE
SCREW DOWN
COCK-2
AIR SUPPLY
1 MAIN RESERVOIR
Chapter 6, Page 13 of 14
Hindi Contents
Maintenance Manual for BG coaches of ICF design Bogie Mounted Air Brake System
§ Remove the pin from the cross head and iii) At the time of re-assembly check
unscrew the adjusting tube until the red that the tooth of pawl housing ring
resetting mark on the adjusting Tube is matches with the teeth of Ratchet
visible. with adjusting screw. The pawl
housing ring must go smoothly
§ Disengage resetting latch and screw in inside the teeth of Ratchet. If it is not
the Adjusting Tube. matching then the notch portion of
§ Re-engage resetting latch. the tooth of pawl housing ring
should be filed till it matches with
§ Check that the Dust Excluder Collar is the teeth of Ratchet screw.
free and does not twist when the
Adjusting Tube is being rotated. iv) Before final assembly of piston and
piston trunk sub-assembly ensures
§ Close cock 1 and open cock 2. that the threads of adjusting tube
§ Close all cocks when the system is at (turns in clock wise direction)
atmospheric pressure. smoothly matches with the threads
of Ratchet screw.
D. Take-up Length (With Quick Resetting Gear)
v) Before fixing the front cover in the
§ Close cock 2 and open cock 3. cylinder body check visually the red
§ Remove the pin from the cross head and paint mark appears in the Adjusting
turn the resetting screw until the red tube. If it is not visible then repaint.
resetting mark on Adjusting tube is 608k Special Tools
visible.
Table 6.3
§ Screw in the Adjusting Tube with the
resetting screw.
§ Check that the Dust Excluder Collar is Description No. off
free and does not twist when the
Adjusting tube is rotated . Close cock 1 Ball peen hammer 1/2 kg 1
and open cock 2.
Screw driver big 1
§ Close all cocks when the system is at
atmospheric pressure Screw driver small 1
608j Important Instructions for Double end spanner to 1
Reassembling the Brake Cylinder at the tighten/loosen M6 nut
Workshops
Press machine to apply 60 kg force 1
for assembling front cover with
i) While fixing the Roller plate with body
front cover 4 pairs of hex. Bolts
M 6x25 along with spring washer A6 Scriber to remove Split pin 1
and hex nut M6 are required. Before
fixing the roller plate, the inner 5 mm Allen key 1
surface of front cover should be
checked for perfect plane. At the Torque wrench with 200 kg cm 1
time of fixing the roller plate with
front cover 2 Nos. of spring washers
*****
are kept inside in between them (one
each side) in first two bolts, so that
the rollers can move smoothly in the
cover plate in angular position.
ii) While matching the holes of plunger
and plunger pin number of shims are
added (say 2 or 3) as per the
Chapter 6, Page 14 of 14
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC coaches)
CHAPTER 7
701 INTRODUCTION
Depending upon the train lighting
The following systems of Train Lighting systems, the coaches are of following
are in use on Indian Railways BG types.
coaching stock:
In this chapter the train lighting system
1. End On Generation (EOG) of Non AC and AC SG coaches will
be discussed.
2. Self Generation (SG)
3. Mid On Generation (MOG)
BG COACHES
Chapter 7, Page 1 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
4.5 kW Brush less alternators are used i To rectify the 3 phase AC output of
on Non AC BG Coaches. It consists of the alternator through DC full
a three-phase hetropolar inductor type wave bridge rectifier.
Alternator and a static Rectifier-Cum- ii Regulating the voltage generated by
Regulator Unit (RRU).
the alternator at the set value.
Earlier AC coaches provided iii Regulating the output current.
with under slung split type AC units
were fitted with two nos. of 18 kW Recently electronic rectifier cum
brush less alternators. After the regulator (ERRU) confirming to
development of roof mounted AC units RDSO specification
(RMPU) and 25 KVA inverters, 22.75 No.RDSO/PE/SPEC/D/AC/0013
kW (Optimized) brush less alternator (Rev.0), developed, which has
was developed within the same frame been fitted on a very few coaches
size of 18 kW alternator. Subsequently on trial.
25 KW alternator with new design was
developed for 2 tier and 3 tier AC 702c BATTERIES
sleeper coaches with RMPU and 25
kVA inverters and for AC 1s t class one The following types of batteries are
25 kW alternator with 25 kVA inverter provided on under -frame of AC & non
provided. AC Self Generating type and End On
Generation type coaches.
The brushless Alternator with
the help of static rectifier cum regulator i. 6V/120 Ah flooded type (Mono
unit is capable of developing voltage at block cells) on Non AC BG SG
the set value to meet the coach load coaches.
Chapter 7, Page 2 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
ii. 2V/120 Ah , VRLA cells on Non battery box is painted with anti-
AC BG SG (Self Generating) corrosive paint.
coaches.
iii. 2V,1100 Ah 56 cells VRLA 110 V While mounting the battery
SG AC coaches fitted with RMPUs box in underframe of the coaches,
and 25 kVA Inverter special care is taken to provide
locking nuts and split pins to avoid
iv. 2 V, 800 Ah flooded type cells on any accidental falling of batteries
under -slung mounted split type AC while running.
equipment .
v. 90/120 Ah, 24V on EOG (End- Recently both the Production
On-Generation) type AC coaches Units have been instructed to provide
(Emergency batteries for lighting ) battery boxes as per RDSO drg. No.
RDSO/SK/K/0037, which is suitable
The 2V,120 Ah TL batteries are for both makes of VRLA batteries i.e.
used in conjunction with brushless M/S Exide and M/S Amar Raja. The
alternator with suitable Rectifier-cum battery box is having improved safety
Regulator of 4.5 kW capacity for train factor coup led with flexibility to
lighting system of TL BG SG type accommodate both makes of VRLA
coaches. The 2V, 56 cells 800 Ah / 2V, batteries.
56 cells 1100 Ah VRLA batteries are
used in conjunction with brushless 702e BCT (Battery Charging Terminals)
alternator with Rectifier -cum Regulator
unit of 18/22.75/25 kW capacity for AC BCT is provided at the both
coaches. 1100 Ah batteries are used on sides of the coaches for external
AC coaches equipped with the Roof charging of the batteries at stations of
Mounted Package type AC plants. 1100 maintenance lines .
Ah capacity battary are of the valve
regulated lead acid (VRLA) type which 702f RJB (Rotary Junction Box)
has its inherent advantages like :
Rotary Junction Box is
provided inside the coach. It is used to
• Topping up with water is not
arrange and control the power supply to
required.
various circuit of the coach (e.g. light,
• Periodical checking of specific fan) with the help of rotary switches
gravity is not required. and HRC fuses.
• Regular maintenance to avoid
sulphation of terminals and 702g EFT (Emergency Feed Terminals)
connections not required.
It is provided at the both ends
of the coach to feed the additional
The VRLA batteries are also known as
supply to the adjacent coach in case of
Sealed Maintenance Free (SMF)
emergency. Supply from the healthy
batteries.
coach may be extended to him/dark
coach by connecting supply to the
702d BATTERY BOX
positive and negative terminals of the
EFT.
ICF type design battery box
for AC coaches is a fabricated
702h TL Lamps
framework made of mild steel
confirming to drg. No. WGFAC-7-1-
25 and 40 Watt lamps are
026. Whereas RCF design is of closed
provided in the non AC coaches. The
type confirming to drg. No. CC71448
power supply is at 110 Volt DC. 25
(PP side) & CC71451 (NPP side), It is
Watt lamps are used in corridor, light
suspended on coach in the under
lamp, wash-basin, toilet. 40 W lamps
frame and is provided with front
are used for lights in the coach.
opening doors for paying attention to
batteries. FRP trays are provided to
prevent corrosion. The interior of the
Chapter 7, Page 3 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 4 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 5 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 9 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
n Remove end cell connectors, clean n Apply petroleum jelly on inter cell
the connecting surface both in cell connection and end cell
and connector thoroughly and connections. Do not use grease.
provide back. Check for proper
crimping of terminal. In case n Check battery fuses and replace
strands of connecting cable are overheated/incorrect size fuses by
found cut at the crimping end, cut correct size.
wire at the crimping end and re-
crimp with a new inter cell n Check battery box fixing nuts for
connector. End cell connector tightness.
confirming to IS:6848 should only
be provided. Tinned copper n VRLA Batteries : SMI.No.
crimping sockets with a single RDSO/PE/TL/SMI/0001-98 IRev
hole, if any, provided as a stop 0) dtd. 01.06.98 to be followed.
gap measure should be replaced by
standard end cell connector. 705 MONTHLY SCHEDULE
Provide end cell connectors with
both the fasteners each with one In addition to the works mentioned in
spring washer to IS: 3063 and one Trip & Fortnightly Examination, carry
punched steel washer to IS:2016. out the following:
Chapter 7, Page 10 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 11 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
n Check Rotary Switch / MCBs n Studs used for fixing the fan to
provided for lights, fans circuits for coach body, shall be checked and
correct condition and Rotary tightened, wherever necessary.
Switch and EFTs for proper Availability of all the three fixing
operation. Replace/ repair studs should be ensured.
defective MCBs. If MCBs are not
n All the switches controlling the
readily available provide
fans shall be checked for its
rewirable fuses of appropriate
smooth operation and correct
ratings, purely as a stop gap
working and replaced, where
measure. Check up negative fuse
necessary.
and replace if necessary by
different ratings of HRC fuse for n Fan regulators in Upper class
AC and non AC coaches. If rotary coaches shall be checked for
switches are provided instead of smooth operation from one
MCBs, Check for proper operation. position to the other. In case the
Check up HRC fuses provided with regulators are not regulating the
rotary switches for correct rating fan speed, the resistance box shall
and replace, if necessary. be checked and replaced, where
n Close front door and secure necessary.
properly by the locking key. If
n Fan blades shall be replaced if
found defective, the same may be
attended/replaced. found bent, or if there is no proper
air discharge.
705e WIRING AND ACCESSORIES
In addition to the items listed under trip 705g CARRIAGE LIGHTING
inspection, the following items shall
In addition to the items listed out under
be inspected:
"Trip Examination" proceed as follows.
Superstructure wiring and underframe
wiring shall be tested separately for n Open each fitting with the dome
which the main negative fuse in shall be key and remove the dust of the
opened and controlling MCBs for all fitting both from inside and
circuits kept off. All other fuses shall outside. Ensure free operation of
remain in circuit. Insulation resistance locking mechanism and er place
shall be measured with all fittings and defective fitting. Clean glass
equipment connected both on domes first with wet cloth and then
underframe and superstructure. The with a clean dry cloth.
underframe wiring shall be tested with
battery fuse open. The IR value n Replace rusted fittings and fittings
should be minimum 2 Mega-Ohm in with damaged surface.
fair weather condition and min. 1
Mega-Ohm under adverse weather n Check up wattage of lamps and
condition. Availability of inspection replace with that of correct
cover of DFBs should ensured. wattage.
705f FANS
n Check up whether toggle switches
In addition to the items listed under " are marked to indicate lighting
trip examination ", the following control "L", night light control
works shall be carried out : `NL', side lamps in guards
compartment as `SL', tail lamps as
n The fan body, guards and blade `TL-Rear', `TL-Front', luggage
shall be thoroughly cleaned with room as `LRL'. If not, stencil
cloth. legends with fluorescent paint.
n All fans shall be opened and
n Check up all lighting circuit fuses
condition of commutator, brushes
in each coach for correct sizes and
and brush gear shall be thoroughly
replace if necessary. Stencil the
checked. Action should be taken
size of fuses near the locations, if
where necessary as given under
not already done.
"Trip Attention".
Chapter 7, Page 12 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 13 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
n Check all fuses and MCBs for n Surface of aluminum sockets and
correct rating and MCBs for proper bus bars, whenever removed for
functioning. Replace if necessary. attention shall be cleaned to
remove the oxide film from the
n Provide spare fuse wires of correct jointing surface before making a
rating for use in branch circuits on bolted joint and shall be coated
the bobbins located on distribution with corrosion inhibiting
fuse boards. conducting grease to prevent re-
formation of oxide film.
Chapter 7, Page 14 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 15 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 17 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 18 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 19 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
Chapter 7, Page 20 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Train Lighting (Non - AC) coaches
n Do ensure that DC ‘+’ and upto the split pin for the 18
DC ‘-’ are connected to kW, 22.75 kW, 25 kW
battery positive and battery Alternators and 55 mm for
negative respectively. 4.5 kW alternators.
Wrong connection will
damage main diodes. n Maintain proper alignment
between axle pulley and
ii. DON’TS
alternator pulley.
n Don’t disturb the settings of
the regulator shunt and n Replace pulley with burn
potentiometer. out grooves i.e. 0.8 mm
depression on sides and
n In any circumstances the bottom of grooves with
burden resistance setting uniformly shining surface.
should not be disturbed.
n n Form grades of the belts
Don’t open the regulator
received from the
box unless there is a defect.
stores/suppliers after
n Don’t use a megger to test checking on belt
the components . Use measurement gadgets. The
multimeter. grading of belts should be
between 48 and 52 only of
n Don’t reverse the field matched sets.
terminals on regulator and
alternator. ii. DON’TS
n Never use a fuse wire for
field fuse. Always use HRC n Do not allow loose belts.
fuse of specified value.
n Do not disturb the nut and
709c `V’ BELTS check-nut on free end of
tension rod if proper gap is
i. DO’S available between
n Use belt of the same length supporting plate and fixing
for a set. nut i.e. 75 mm for AC coach
alternators and 55 mm for
n Belts should be stocked in TL alternator.
lots as per date of receipt
and use in the principle of n Do not use repaired pulleys.
first in first out basis. The
belts shall be stored in a n Do not use old and new
well ventilated room free mixed belts in sets.
from direct sunlight and
moisture. n Belt should not have any oil
or grease traces ,if persist
n Ensure correct belt tension clean it by soap and water.
i.e. 330 Kg for 18 kW, 22.75
kW and 25 kW alternators n The matched set should
and 105 kg for 4,5 kW have belts of one
alternators. The tolerance of manufacturer only. Do not
tension shall be ± 5 kg in use belt of same grade of
both cases. different manufacturer in a
set.
n Re-tension newly fitted belts
after first trip. 709d VRLA Batteries : Do's and Don'ts
from SMI no. RDSO/PE/TL/ SMI/
n Maintain a gap of approx. 0001 - 98 (Rev.0) dt. 01.06.98 to be
75 mm between supporting followed.
plate and fixing nut on the
free end of tension rod or
Chapter 7, Page 21 of 21
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
CHAPTER 8
801 INTRODUCTION
AC COACHES
801a Power Supply System: As far as power 801b MAJOR EQUIPMENTS USED IN AC
supply system is concerned, the coaches UNIT ARE :
are of the following two types :
1. Compressor (open type for under
(i) End-On-Generation (EOG) : In this
slung, sealed type for Roof Mounted
system two types of Power cars are
used Package Unit (RMPU)
2. Condenser including liquid receiver
a. Coaches mounted with 50
KVA, 750 V/415V, 3 φ and dehydrator.
transformer. 3. Expansion Valve
b. Coaches with out stepdown 4. Evaporator with heater element.
transformer suitable only for
old low capacity power cars. 5. Motors for compressor, condenser,
(ii) Self Generating (SG) : Based on evaporator .
AC equipment, there are two types 6. Other protective devices and control
of Self Generating coaches.
panels.
a. 110 V DC with under slung
type AC equipment working 7. Thermostat, Filters etc.
from 110 V DC.
802 MAINTENANCE SCHEDULES FOR
b. 110 V DC with Roof SELF GENERATING AIR
Mounted AC Package Units CONDITIONED COACHES FITTED
working from 415 V, 3 φ, WITH UNDER SLUNG EQUIPMENT:
obtained with the help of 25 (Ref: RDSO’s maintenance
KVA inverters mounted on schedule No EL/TL-
underslung as well as AC/Maint.Sched./Rev.1)
onboard.
Chapter 8 – Page 1 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 2 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 3 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 4 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
n If the report of the attendant n Check all the lights and fans
indicates that thermostate for proper working. Rectify
do not work, examine the or replace if necessary.
thermostats for break in
mercury, break in stem, etc. n Clean the fan and light
Replace the thermostats, if fitting externally.
necessary. Follow RDSO
SMI No RDSO/SMI/AC/15. n Check all switches, fan
regulators, call bells and
n Clean thermostat bulb with push buttons for proper
cotton. working. Replace if
necessary.
n Ensure working of plants in
auto mode for all xv. Pre-Cooling Unit
temperature setting.
n Clean rectifier unit
xii. Panel Board externally with dry
compressed air.
n Clean the panel and remove
dust. n Check the presence of water
in terminal box, drain out if
n Check the working of necessary.
indication lamps, replace it
if necessary. n Load the pre-cooling unit to
its maximum capacity and
n Check the availability of check for any overheating.
spare fuses in the place
provided for the same and n Check suspension of battery
provide if necessary. charger for sign of any
crack, corrosion or rusting
n Check the availability of arc and take action if required.
chute and provide if
necessary. n Check the pre-cooling socket
n Check and clean the contacts pins and its fixing
of contactors 12, 13 and arrangements.
13A.
xvi. General
n Check the operation of
cooling pilot relay (by short n Check log- sheet of last trip
circuiting terminals C.T.). and attend all the faults
Remove short after the recorded in the log sheet.
completion of check.
Chapter 8 – Page 5 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
n Run the plant for half an iii. Rectifier Cum Regulator Box
hour. Check system
operation, specially the n Clean all dust with dry
following: compressed air externally.
1. Suction pressure gauge
n Open the cover and check
reading should be 2-3
sealing rubber gasket for signs
Kg/cm2 .
of fraying. Drain out water if
2. Delivery pressure gauge
any.
reading should be 10 –
14 Kg/cm2. n Clean all dust with dry
3. Oil pressure should be compressed air. preferably a
minimum 3kg/cm2 above hand blower from inside to
suction pressure. remove all dust particularly
4. Suction should be cold from heat sink of electronic
and sweaty. Delivery components and terminal
should be very hot and board.
liquid line should be
warm. n Check that the voltage and
5. Feel the expansion valve current setting. Ensure that
by hand. It should be they have not been disturbed
cold. and are in locked position.
Chapter 8 – Page 6 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 7 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 8 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
with pre-cleaned/new-filter
v. Dehydrator and Liquid
and close access doors
Receiver
properly.
n Clean the strainer in the v. Check the log sheet maintained
dehydrator-cum-filter for each AC coach and attend
unit. the defects noticed during run
as reported by escorting staff.
vi. Evaporator And Expansion
Valve vi. Check for working of Roof
Mounted Package Unit
n Clean the strainer used (RMPU) and Control panel as
before expansion valve. following:.
n Clean the assembly of n Switch `ON’ RSW-I and
evaporator coil and check that all the three
surroundings with pilot indication lamps
vacuum cleaner. (Red, yellow and blue) for
R.Y.B. phases and power
n Clean the drip tray and `ON’ indication LED
drain-pipe thoroughly and
(Green) are glowing.
check for water leakages.
n Put RSW-2 in ``ON’
vii. General position and keep RSW-3
in `VENT’ position and
n Adjust the air distribution
check that:
by measuring the
temperature of each q Indication LED (green
compartment. colour) for Blower
`ON’ is glowing and
803 MAINTENANCE SCHEDULE
q Blower fan is working
FOR ROOF MOUNTED AC
PACKAGE UNITS AND ITS
CONTROL PANEL n Check for satisfactory
operation of vane relay by
803a TRIP SCHEDULE (PRIMARY moving the flap by hand
AND SECONDARY gently.
MAINTENANCE)
n Check for satisfactory
i. Clean all dust from panel by operation of the package
dry compressor air from the unit by moving RSW-3, in
panel. AUTO, MANUAL
HEATING & MANUAL
ii. Check that all the safety and COOLING modes. This
protection devices are in can also be verified from
working condition and not in indication LEDs (green
the by passed condition. colour).
iii. Replace defective/by passed n Check that cooling system
components including is working even if only
indication LEDs and lamps, if one condenser fan out of
any. the two is working. This
iv. Remove fresh air and return air can be done by simply
filters by opening the access switching off MCB 2 or
doors provided under the MCB 3/taking out fuses of
bottom of unit. Clean these condenser motor 1 or
filters with pressurised air and condenser motor 2.
jet of water and place them in
their place or replace them
Chapter 8 – Page 9 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 10 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 11 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 12 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
During this activity, the following air- In this activity fit all the
conditioning and electrical equipment refrigeration and electrical
will be removed: equipment to their respective
n Fresh air and return air filter positions. Connect all the wiring and
flanges in the refrigeration system
n Compressors and their motors
wherever necessary. Charge the gas
n Condenser including liquid into the system.
receiver cum dehydrator and
condenser motors vii. Static testing
n Evaporator unit and its motor
Run the plant through pre-cooling
n Water raising apparatus
terminal and check for proper
n Battery and battery box for functioning of electrical and AC
repairs. equipment.
n Battery charger-cum-pre-cooling
transformer viii. Alternator Connection and
Tensioning
n Thermostats
n Control p anel Join the connections of alternators
n Expansion valve and fit the belt-tensioning device.
Provide the new 6+6 `V' belts for
n Gauges and cutouts
alternators.
n Carriage fans
n Berth light fittings
n Ammeters and voltmeters of
power panel
Chapter 8 – Page 13 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 14 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 15 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 16 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 17 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 18 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 19 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 20 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 21 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 22 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 23 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 24 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 25 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 26 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 27 of 28
Hindi CONTENTS
Maintenance Manual for BG coaches of ICF design Air Conditioned Coaches
Chapter 8 – Page 28 of 28
Hindi Contents
Maintenance Manual for BG coaches of ICF design Rolling Gear
CHAPTER 10
ROLLING GEAR
Ø 145
Ø 172
Ø 152
Ø 178
Ø 130
Ø 145
Ø 913
Ø 915
NOTE:-
1. THE VARIATION IN THE TREAD CIRCUMFERENCE OF WHEELS ON
THENOT
SAME AXLE1.6
XCEED SHOULD
mm (i.e.) ON DIA.
2. THE VARIATION IN WHEEL DIA BETWEEN ONE PAIR WHEELS AND
THE EXCEED
OTHER SHOULD
5 mm ONNOT
THE SAME BOGIE.
3. THE VARIATION ON DIA UNDER THE SAME COACH SHOULD NOT
EXCEED 13 mm.
WHEEL AND AXLE COMPLETE
Figure 10.1
+3
-1
IN E
INCLINE 1 IN 20
30
W/WL-1660/R
2.5
INCL
14%%p2R
1 IN
45%%d
18%%p2R
I.R. PART No.
N9 70%%D%%P1%%D NOTE:-
6
47%%d-30'%%p1%%d
%%P2
130
38R
R
10
11%%D%%P1%%D
DIA.
47%%d-30'
13 TO BE MACHINED IF NECESSARY TO
LIMIT
+1
-0
+5
70%%d PREVENT HUB ECCENTRICITY.
-0
813
29
%%c660
3. COORDINATES OF CENTER POINT
+3
+0
%%C918- 0
%%C165- 3
+5
22 -0
OF 330R & 100R ARCS ARE BASED
+10
INSIDE
-0
190.5
+10
ON NOMINAL DIMENSIONS.
-5
* %%c260
763
-0
63.5
ON TREAD (ECCENTRICITY 0 .25 mm MAX.)
18 7
+3 655.
190 -0
+10 151
8.7
R 11%%d%%P1%%d
-0 10
N9
%%c172- 0.4
+0
230R
* %%c260
165R 51R
10
91
153
65.5 230 R
190
8
+3
44
-0
180 R
N9
%%c 915
(91,328.9)
151
8.7
29.4 191
219
(65.5,100.3) 6R
1 IN
6R
N6
2.5
N
6 151
8.7
1 IN 20
13
+1
10 0R
330R
R
-0
14 .5
R
14
28.5
65
WHEEL PROFILE
WHEEL & AXLE SOLID
WA/WL-32 2 FORGED (B.G.) FOR LIGHT
TO IS:3073
SURFACE
Ra m 1.6 3.2 6.3 12.5 25 50 RLY. PATT. SCALE DO NOT SCALE W/WL-1660/R
WHEEL SOLID FORGED (B.G.)
SYMBOL CONCERNED RLYS. TO FILL REF. DRG.
I.R. PART No.
85 191 1473
119 26.5
Ø 130
R40 R75
R75
127
63.5
1 IN 20
1 IN 2.
R
14
28.5
5
100
R
0
10
0R
329
33
13
9R
20
33.5
FIGURE - 1 65.5
91
91
1 IN 20
1 IN 2.5
R
14
100
R
0
10
0R
329
33
R
13
10
22
35.5
65.5
FIGURE - 2
1 IN 20
1 IN 2.5
R
14
100
R
0
10
R
329
R
33
.5
13
11
25
38.5
FIGURE - 3 65.5
DEVELOPED BY:
SUPERSEDES:
1. FIG.3 SHOULD BE THE LAST PINTERMEDIATE WHEEL
PROFILEPFOR THE WHEELS MEANT FOR PTHE COACHES TO
RUN AT MAX.PKMPH AND ABOVE.P2. ALL THE THREE
SCALE P
C
INTERMEDIATE
INTERMEDIATE WORNPWHEEL PROFILE (FIG.1,2&3)PCAN BE
USED FOR THE WHEELS FOR POTHER TYPES OF COACHES. D
PAINT 9/92
WORN WHEEL
1:1 T
PROFILE
JS FOR COACHING
STOCK
B.G. RDSO[C] SKETCH-92082
FIGURE 10.4
The activities involved in replacement The serviceable wheel discs are re-
of an axle are as follows: bored on the vertical boring machine.
Care should be taken that the finished
§ Pressing off a rejected axle from a bore is straight, concentric to the tread
wheel of the wheel and has a smooth surface
free from ridges, scores and chatter
The wheel is taken on the wheel press marks. A radius of 2.5 mm is provided
for separating the rejected axle from on the hub to facilitate mounting. It
the wheels. must be made after the finishing cut.
§ Inspection of re-bored wheel disc
§ Machining of new axles
The rebored wheel disc should be
New axles should be machined to the inspected with the help of an inside
correct drawing dimensions. Journal, micrometer to ensure consistent
journal fillets and shoulders should be results. Each wheel bore must be
finished smooth, concentric and checked at not less than three points in
without ridges, burrs or chatter marks. its length and on the different
diameters at each of these points to
§ Inspection of machined axles ensure roundness and absence of
tapers. The variation for any of these
Dimensional checks measurements must not exceed 0.05
mm.
A machined axle should be inspected
for dimensional accuracy with the help If any taper does exist, the small
of a micrometer with least count of diameter must be outside ends of the
0.01 mm. Journal diameters should be hub (a reverse taper is not allowed).
measured at three points along the The surface finish of the bore should
length of journals both on the vertical be within the permissible limits.
and horizontal axis. The ovality and
§ Machining of wheel seats for
taper must not exceed the limits
matching of wheel disc bores
prescribed in the drawing..
The wheel seat of the axle to be used
Surface finish checks for re-axling is machined to suit the
bore of the wheel disc keeping
Surface finish of the axle on journals, interference allowance as specified.
wheel seat and middle portions should
be checked with the help of a surface The bore of wheel disc and wheel seat
finish tester and the prescribed limits on the axle should be maintained to
are as below: - the specified surface finish and
diameters to achieve correct
Table 10.2 interference fit and pressing in
pressure
Axle portions Prescribed (RA) § Pressing on Wheel Discs on Axle
value for Surface
finish in microns § Before pressing on operation,
wheel seats on the axle and bore of
Journal portion 0.8 the wheel centres should be
carefully cleaned to remove rust,
grit, swarf, dirt etc.
Wheel seat 1.6
portion § The wheel seat should be
lubricated with a mixture of basic
Middle portion 3.2 carbonate white lead and boiled
linseed oil, in the proportion of 1.2
kg. of white lead paste to 1 litre of
Ultrasonic flaw detection checks boiled linseed oil. The wheel and
axle should be properly aligned on
Ultrasonic flaw detection test is the wheel press.
carried out as per annexure 10.1.
The activities involved in replacement The bore and the wheel seat should be
of discs: machined to the specified surface
finish to achieve correct interference
§ Dismounting of Axle boxes & Roller fit and pressing in pressure.
Bearings
§ Pressing on Wheel on Axle
Axle boxes are dropped from the RD § Before pressing on operation,
Wheel. The wheel is then taken for wheel seats on the axle and bore of
dismounting of roller bearings from the wheel should be carefully
journals. cleaned to remove rust, grit, swarf,
dirt etc.
§ Inspection of Axle journals/ § The wheel seat should be
Ultrasonic testing of the axle lubricated with a mixture of basic
carbonate white lead and boiled
Journal diameters should be measured linseed oil, in the proportion of 1.2
with an outside diameter to confirm to kg. of white lead paste to 1 litre of
be within the permissible limits. The boiled linseed oil. The wheel and
axle should be ultrasonically tested for axle should be properly aligned on
flaw detection and should be flawless. the wheel press.
§ The wheel press should be
§ Pressing off rejected discs from a equipped with a dial pressure
wheel gauge and pressure recording
gauge with graphs to record
The wheel is taken on the wheel press mounting pressure diagrams for
for separating the rejected discs from each assembly.
the wheels.
§ Wheels should be mounted within raceway within which operate, two rows
the prescribed pressure limits. of barrel shaped rollers, which in turn are
Pressing pressure should be 400 to guided by an inner ring with two
600 kg/mm of diameter of wheel raceways separated by a centre rib. The
seat. For ICF 16t axle with wheel spherical roller bearings have self-
seat diameter from 176mm to aligning properties and therefore can
178mm, the pressing pressure automatically adjust to any deviation in
should be 71t to 108t. the centre line of the axle.
§ Wheels should be mounted Spherical roller bearings have a large
(pressed in) carefully on the axle capacity for radial loads, axle loads in
such that the wheel gauge distance either direction, and complex loads. They
is maintained. are suited for the applications such as
§ The axle end should be stamped railway rolling stocks where vibrations
with the shop code, date of and shock loads are encountered.
mounting, pressing in pressure,
axle no., cast no., cons. no. to Roller Bearings are named according to
enable identification of wheels. the shape of rollers. Roller Bearings with
(see figure 10.5) spherical rollers are called as Spherical
§ The wheel gauge should be Roller Bearings. (see figure 10.7 for roller
checked by gauging at three or bearing arrangement)
more equi-angular points around Spherical Roller bearing no. 22326/C3
the circumference. (see figure with 130 mm parallel bore on the inner
10.6) ring are being used on ICF type coaches.
List of Tools and Plant They are directly shrunk fit on the axle
1. EOT crane 5 tonnes journals.
2. Wheel profiling lathe These roller bearings need to be inspected
3. Axle journal turning and periodically at a pre-defined schedule in
burnishing lathe the workshop in a Roller Bearing
4. Axle journal grinding machine Maintenance Shop well equipped with all
for assembled wheel set. the facilities and proper lay out. The
5. Hydraulic wheel press with period of maintenance specified is as
facility for mounting pressure follows:
diagram
6. Axle turning lathe Periodicity of Inspection of Roller
7. Vertical turning lathe Bearing
8. Axle centering machine
9. Axle end drilling machine § All roller bearings should be cleaned,
10. Axle grinder inspected and filled with fresh grease
at every POH.
1004 AXLE BOX ASSEMBLY § All bearings should be dismounted
every alternate POH or 2 lakh km
In passenger coaches of Indian Railway
whichever is earlier in the workshop
system, only single bearing type axle box
for renewal of felt sealing ring and
arrangement is used. The inner ring of the
overhaul of the roller bearings.
bearing is provided with either a
cylindrical bore (Direct Mounted type) or 1005b Roller Bearing Maintenance in Shop
with a taper bore and withdrawal sleeve
(Sleeve Mounted type). All new Roller Bearing Maintenance Shop should
passenger coaches built by Indian be well equipped with all the tools,
Railways, use only direct mounted type equipment and facilities for careful
spherical roller bearings. Therefore, bearing handling. It should have proper
practices related to the sleeve mounted workflow for easy maintenance of roller
bearings, have not been covered in this bearings. Clean surroundings and dust
manual. free atmosphere should be maintained in
the shop. It should have adequate
1005 ROLLER BEARINGS equipment and facilities for cleaning,
1005a Construction feature of Roller Bearings handling, dismounting, dismounting,
inspection, repair and storage of roller
Spherical roller bearing consist of an bearings.
outer ring having a continuous spherical
T.
O 8
N
W
03
O N N
2A
T
C
0
E
6
M V
15
O.
IR
1.4
P.
24
0 5
C
C 3 0
04
A
O S 43
N T N 0
S N O 2
L 5
I W 30
W O N N
T
A
S. 0
M
6
S
I. R.
O.
468
V
P.
6 E .
N 6. C O
FIGURE 10.5
Newly assembled wheel set should be checked for the distance between inner face of wheel i.e. 1600 +2/-1 mm using Wheel Distance Gauge.
The wheels to be gauged on a level track after taking off from coaching vehicle.
Under loaded conditions the limits are not applicable. Wheel Distance Gauge
Scale (Line Gauge)
SPRIT LEVEL
INDICATOR
Following are the tools and plants required for a Roller Bearing Maintenance Shop.
Table 10.3
Figure 10.10
Chapter 10, Page 13 of 23
Hindi Contents
Maintenance Manual for BG coaches of ICF design Rolling Gear
Figure 10.11
Figure 10.12
Chapter 10, Page 14 of 23