DAIS-I192-HSE-JHA-AIPL-04 (Painting Work)
DAIS-I192-HSE-JHA-AIPL-04 (Painting Work)
Ltd
Job Hazard Analysis
Location of Works Activity : B1.1, Ground Floor & Level 7 Method Statement Reference: I1912-AI-OPR-MST-0066-00
Works Activity : Painting work
Risk Assessment Reference: DAIS-11912-HSE-CRA-AIPL-04
Other Document Reference: WAH & Electrical
FIELD CONTROL INSPECTION CHECKS
Expected Duration of Works : Jan. -2023 March-2023 Designate the number of checks required in line with stated frequency
From To Person undertaking inspection checks to indicate which planned check is being conducted by
“circling” the related sequence number of check(s) below:
Field Control Check – :
Frequency A. Work Commencement – All Checks 1 2 3 4 5 6 7 8 9 10 11
12 13 14 15 16 17 18 19 20 21 22
23 24 25 26 27 28 29 30 31 32 33
B. Every Month
34 35 36 37 38 39 40 41 42 43 44
Field Control Inspection Checks – control measures requiring inspection, check and signoff will be identified using ” “ indicator in either the “PRE-WORKS” or “DURING” works
columns within the “Action(s) Complete/Control in Place” column as appropriate. Inspections and checks are related to the stated control measures per “job/task”.
“Job/Task” steps that do not show an inspection/check, i.e. no cross indicated in box “ “ do not require formal inspection check or signoff but should be referenced / observed
and considered during inspections activities.
DAIS- I1912-HSE-FM-001B(02)
Page 1 of 6
10th March, 2022.
Leighton India Contractors Pvt. Ltd
Job Hazard Analysis
Reviewed By Name: Tejveer Singh Signature: Date:
Position: Manager- HSE
Name: Ajay Korde Name: Tejveer Singh Name: Name: Name: Name:
Title: Finishing Manager Title: HSE Manager Title: Title: Title: Title:
Contact: 77000098352 Contact: 9871971793 Contact: Contact: Contact: Contact:
Signature: Signature: Signature: Signature: Signature: Signature:
Name: Sandeep Sudra Name: Akash Shinde Name: Amit Vishwakrama Name: Ehtesham Ansari Name: Name:
Senior Project Manager -
Title: Title: Site In charge Title: Site Engineer Title: Safety Officer - AIPL Title: Title:
AIPL
Contact: 8898889499 Contact: 9137050053 Contact: 9702844890 Contact: 9702388589 Contact: Contact:
Sl no. Job / Task Class 1 Risks Control Measures Responsible Action (s) Complete /
Person
Control in Place
DAIS- I1912-HSE-FM-001B(02)
Page 2 of 6
10th March, 2022.
Leighton India Contractors Pvt. Ltd
Job Hazard Analysis
Checked by/
Image / Photo Description Pre- Work During Signature
1 Usage of
power tools
Electrocution All Machine inspected by LIN Electrician
Slip trip hazard
from cable
Using certified industrial plug top Electrician
&material Cable routing to be over headed
Electrician
Dust inhalation
Eye injury due to
All rotating machine should be guarded Ehtesham
Ansari
flying partial
Material may
Dust mask provided
Amit
Vishwakarma
have sharp
edges Maintain housekeeping Before & after work
Amit
Vishwakarma
Inspected power tools with inspection tags to be Ehtesham
Ansari
used
Electrical connection should be routed through Electrician
RCCB and by authorized electrician only
Ehtesham
Ansari
Height work training should be given to workers.
Remarks
DAIS- I1912-HSE-FM-001B(02)
Page 4 of 6
10th March, 2022.
Leighton India Contractors Pvt. Ltd
Job Hazard Analysis
Note: Please issue the completed copies to Safety Department for filing
DAIS- I1912-HSE-FM-001B(02)
Page 5 of 6
10th March, 2022.
Leighton India Contractors Pvt. Ltd
Job Hazard Analysis
DAIS- I1912-HSE-FM-001B(02)
Page 6 of 6
10th March, 2022.