Bloom/IE/Coimbatore Bypass /NH-381/NHAI/2023/ Date:

To

The DGM (Tech & Project Director),


National Highway Authority of India,
No, 11/1, Kongu Nagar east,
Back side of Appasamy Apartments,
Ramanathapuram,
Coimbatore- 641 045.

Sub: NHAI, RO Chennai – PIU , Coimbatore – System Integrator for implementation of


Hybrid ETC system, video surveillance system (PTZ Camera ), MSWIM at
Velampatti Toll Plaza at KM 28/815 on Avinashi to Avinashipalayam section of NH
– 381 in the state of Tamil Nadu – Installation of Temporary Toll Plaza – Change
of Scope Proposal – Comments furnished - Reg.

Ref:
1. Site Inspection and Minutes of Meeting held in PIU Coimbatore Dated 24.06.2023
2. PATH/NHAI/COIMB/2023-24/1813 Dated 23.06.2023.
3. NHAI e-mail Dated 08.03.2023
4. PATH/NHAI/COIMB/2022-23/1715 Dated 04.03.2023.
5. Annexure –A, B & C.
6. Quotation of SHIVANI INFOTECH.
7. State NH Letter No : EPC NH 381/2017-19/A1/ Dated 20.01.2022.
8. Contract Agreement Dated 21.09.2021.
-------
Sir,
With reference to the trailing e - mail ( 3 ) and the above said references, we
have checked the CoS proposal submitted by M/s PATH India Limited regarding the
supply and installation of Hybrid ETC equipment for Temporary Toll Plaza setup at
Velampatti Toll Plaza.

As per the discussion with the Authority and the representative of M/s PATH
India Ltd vide ref ( 1 ) and in the above submitted CoS proposal vide ref ( 2 ), ( 4 ) &
( 5 ) , the List of Equipments / Work mentioned are minimum Equipments / work
required for the Operation of Temporary Toll Plaza. The following works will be used
for Establishment / Construction of Temporary Toll Plaza as submitted Change of Scope
CoS proposal by M/s PATH India Limited vide ref ( 2 ) are stated below:
Amount
Sl. Amount
Description of Items Rate Qty GST with Tax without
No Tax
HETC Assets Plaza Dis-
1 50,000 1 18 % 59,000 50,000
mantling with labour
HETC Assets Plaza & Lane
Level Cabling / Networking /
2 Installation / Commissioning 5,00,000 1 18% 5,90,000 5,00,000
of all equipment ( Without
civil work )
Internet Shifting , Installation
3 35,000 1 18% 41,300 35,000
/ Commissioning
Total Amount 6,90,300 5,85,000

The following Hybrid ETC Equipments is not functioning , which has handed over
by the State NH wing vide ref ( 7 ) , also not feasible to support the innovative
technology of Hybrid ETC and shall be needed for an effective functioning of Toll Plaza
as submitted Change of Scope CoS proposal by M/s PATH India Limited vide ref ( 4 ) &
( 5 ) are stated below:

Amount
Sl. Amount
Description of Items Rate Qty GST with Tax without
No Tax
Automatic Vehicle
1 Classification (PIR – Image 1,40,000 8 18% 13,21,600 11,20,000
processing profiler)
2 User Fare Display ( UFD ) 15,000 8 18% 1,41,600 1,20,000
3 Plaza UPS Battery set 56,000 1 28% 71,680 56,000
4 ICS Camera 20,500 8 18% 1,93,520 1,64,000
Total Amount 17,28,400 14,60,000

The Hybrid ETC Equipments is quoted in the Annexure – B ( Proposal for MSWIM
Shifting ) vide ref ( 5 ) is no more required as it was already installed / mounted in all 8
lanes of Toll Plaza Canopy area.

Temporary Toll Plaza are established with feasible furniture items for an
effective functioning of Toll Plaza as submitted Change of Scope CoS proposal by M/s
SHIVANI INFOTECH vide ref ( 6 ) are stated below:
Amount
Sl.
Description of Items Rate Qty without
No Tax
1 Ms Fabricated Office Cabin of Size 40’ * 12’ * 8.5‘ 6,90,000 2 13,80,000
2 Executive Table 3’ * 1.9’ with chair 24,000 4 96,000
3 LG/Voltas/Daikin Air conditioner 1.5 Tn 47,500 2 95,000
4 Power panel Distribution box 16 MCB breaker 32,000 2 64,000
Electrification incl shifting of DG and connecting
5 78,000 1 78,000
charges
6 Fabrication of Ladder and staircase 2,25,000 1 2,25,000
Total Amount 19,38,000

In this regard, the above mentioned Equipments of Hybrid ETC vide ( 2 ) , ( 4 ),


( 5 ) & ( 6 ) is recommended for in-principle approval and also the payment of Rs.
39,83,000/- (Thirty Nine Lakhs Eighty Three Thousand only) by the IE and submitted to
the Authority for further course of action.

Thanking you,

Yours faithfully,

Team Leader,
Bloom Companies LLC.

Encl :

1. Annexure – A ( 1 Page ).
2. Annexure – C ( 1 Page ).
3. SHIVANI INFOTECH Quotation – 3 Pages.