BLK31-NE-BP-IM-IMR-0062

PSVM

IDSNo='BLK31-NE-BP-IM-IMR-0062' AND Revision='02'

Updated 26 Aug 2008 13:13 CET Updated By Spence, Rob


Preliminary Status
IR Title
IR in preparation
URF1 Test Ring requirements - Flowline Valves Final Status
Final Response Issued
IR No Rev No Date Originated
BLK31-NE-BP-IM-IMR-0062 02 25 Jul 2008 08:45 CET

Originating Person Originating Company Responding Company


Spence, Rob BP Prog URF1 (HMC)

PART 1 - RAISE INTERFACE REQUEST (IR)


Requesting Party Interface Description:
Level 1 (Package) * SURF (Valves)
Level 2 (System) * Valves
Level 3 (Schedule Reference)
Interface ID

Interface Data Required: *


Spence, Rob 25 Jul 2008 NN

Company supply of Test Rings to HMC for weld qualification.

Please confirm the proposed quantities of Test Rings below is acceptable.

300mm long:

12" Production - Clad     3off
12" Service - Un-Clad     3off
10" Production - Clad     3off
10" Service - Un-Clad     3off
2" Production - 625 (5.5mm WT)   3off
2" Service - 625 (7.1mm WT)   3off
1/2" Production - 625 (3.7mm WT)   3off

Total 21off

Schedule Preliminary Info * Final Info


Required By Dates: 01-Aug-08 01-Aug-08

Requesting Party Initiator Date Date

Spence, Rob 25 Jul 2008

Printed by: Tijn, van Dokkum. 15-Sep-2008 12:59, (ID=1874). Concept By Omega AS. Page 1 of 3
PART 2 - ACCEPTANCE OF INTERFACE REQUEST
Requesting Party Interface Eng: Accepted Date: Accepted Date:
Doyle, Tom 29 Jul 2008

BP Requesting Party Delivery Lead: Acknowledged Date: Acknowledged Date:


Spence, Rob 31 Jul 2008
BP Requesting Party Interface Eng: Acknowledged Date: Acknowledged Date:
Doyle, Tom 29 Jul 2008

Responding Party Interface Eng: Accepted Date: Accepted Date:


VerDult, Cor 30 Jul 2008

Nominated Responder: Nominated Responder:


van Dokkum, Tijn
BP Responding Party Interface Eng: Accepted Date: Accepted Date:
Hawthorn, Phil 30 Jul 2008
BP Responding Party Delivery Lead: BP Responding Party Delivery Lead:
Crawford, Michael
Acknowledged Date: Acknowledged Date:
30 Jul 2008

BP Additional BP Additional

Acknowledged Date: Acknowledged Date:

PART 3 - INTERFACE RESPONSE - PRELIMINARY INFORMATION

van Dokkum, Tijn (HM) 12 Aug 2008 01

Yes, we can confirm the proposed quantities of Test Rings are acceptable.

PART 4 - ACCEPTANCE OF PRELIMINARY INTERFACE RESPONSE


Responding Party Interface Eng: Accepted: Date:
VerDult, Cor
BP Responding Party Delivery Lead: Acknowledged: Date:

BP Requesting Party Delivery Lead: Acknowledged: Date:


Spence, Rob
Requesting Party Interface Eng: Accepted: Date:
Doyle, Tom
Requesting Party Initiator: Accepted: Date:
Spence, Rob
BP Additional: Acknowledged: Date:

Printed by: Tijn, van Dokkum. 15-Sep-2008 12:59, (ID=1874). Concept By Omega AS. Page 2 of 3
Preliminary Response Rejected/Comment:
Acceptor: Add comment to explain rejection or proposed change
Acknowledger: Add comment or see Interface team (Note: Acknowledger cannot reject)

PART 5 - INTERFACE RESPONSE - FINAL INFORMATION

van Dokkum, Tijn (HM) 12 Aug 2008 02

Yes, we can confirm the proposed quantities of Test Rings are acceptable.

PART 6 - ACCEPTANCE OF FINAL INTERFACE RESPONSE


Responding Party Interface Eng: Accepted: Date:
VerDult, Cor 12 Aug 2008
BP Responding Party Delivery Lead: Acknowledged: Date:
Crawford, Michael 13 Aug 2008
BP Requesting Party Delivery Lead: Acknowledged: Date:
Spence, Rob 26 Aug 2008
Requesting Party Interface Eng: Accepted: Date:
Doyle, Tom
Requesting Party Initiator: Accepted: Date:
Spence, Rob 26 Aug 2008
BP Additional: Acknowledged: Date:

Final Response Rejected/Comment:


Acceptor: Add comment to explain rejection or proposed change
Acknowledger: Add comment or see Interface team (Note: Acknowledger cannot reject)

Printed by: Tijn, van Dokkum. 15-Sep-2008 12:59, (ID=1874). Concept By Omega AS. Page 3 of 3