PROJECT : EL RETIRO

LOCATION : # 20 OUTLOOK DRIVE, BAGUIO CITY


SUBJECT : ADDITIONAL WORKS
DATE : March 21, 2023

ITEM # DESCRIPTION OF WORK QTY UNIT UNIT COST TOTAL COST REMARKS

I Estate Lightings
Earthworks 2.00 cu m 900.00 1,800.00
Painting of Poles (Primer + Black Paint) 30.00 ln m 250.00 7,500.00
Supply and Installation of 50w Flood 2.00 pcs 15,000.00 30,000.00
Lights including Wiring and erection of
poles (Without Pedestal)
Supply and Installation of 50w Flood 3.00 pcs 33,000.00 99,000.00
Lights including Wiring and erection of
poles (With Pedestal)
II Spike Lighting
Supply and Installation of Spike Lights 18.00 pcs 4,200.00 75,600.00
Earthworks 1.00 cu m 900.00 900.00
III Additional Electrical Works for Tennis
Court
Supply and Installation of Submeter for 1.00 lot 40,000.00 40,000.00
Tennis Court
Breaker for Tennis Court of Submeter for 1.00 lot 30,000.00 30,000.00
Tennis Court
284800

Prepared By:
TRIPLE B