CHB PLANT
Location : Sitio Calumpang, Brgy. San Jose, Antipolo City
Region/Area : Rizal
Floor Area : 1000 m²
Cost per m² : ₱1,710.06
Total Cost : ₱1,710,061.55
Item Description Quantity Unit Material Labor Unit Cost Total Amount
I GENERAL REQUIREMENTS
Mobilization/Demobilization 1.00 lot 50,000.00 50,000.00 50,000.00
Sub Total 50,000.00
II EARTHWORKS
Excavation Works - Manual 187.00 cu.m 225.00 225.00 42,075.00
Backfilling with compaction 187.00 cu.m 115.00 115.00 21,505.00
Gravel Bedding (100mm thk) 54.00 cu.m 1,600.00 528.00 2,128.00 114,912.00
Base Course Bedding 17.93 cu.m 600.00 100.00 700.00 12,547.50
Consumables 1.00 lot 3,500.00 3,500.00
WATER SUPPLY
Deep Well Drilling Service 1.00 set - - 200,000.00 200,000.00
SANITARY SYSTEM
PVC PIPES SERIES 1000
100mmØ dia. 15.00 pcs 580.00 406.00 986.00 14,790.00
50mmØ dia. 4.00 pcs 280.80 196.56 477.36 1,909.44
PVC FITTINGS SERIES 1000
Wye Equal
100mmØ dia. 12.00 pcs 131.00 91.70 222.70 2,672.40
Wye Reducer
Item Description Quantity Unit Material Labor Unit Cost Total Amount
Lights - -
LED Pinlight 9.5W 220V socket type
daylight (Phillips or GE) with 6" Akari 12.00 pcs 235.00 70.50 305.50 3,666.00
housing
LED Bulb 10W 220V socket type
20.00 pcs 165.00 49.50 214.50 4,290.00
receptacle daylight
LED tube 1x20W daylight (Phillips) 220V
4.00 pcs 355.00 106.50 461.50 1,846.00
with box type housing
Switches (2 gang) National brand 26.00 pcs 135.00 40.50 175.50 4,563.00
Outlets (1 gang, 2 gang) National brand 16.00 pcs 155.00 46.50 201.50 3,224.00
Jasan Marañon
Jomel Tarrayo
Item Description Quantity Unit Material Labor Unit Cost Total Amount
Juli-Ann Tarrayo