Well: TADOM-1

Rig: HAKURYU-5
Date: 13 Apr 2023 21 DAYS LOOK AHEAD Drilling Supervisors:
Logistics Coordinator:
Anuar / Chewy
Abg Marzuki (Office) / Troy (ASB) / Sabtry (Hak-5)
Initial POB:
MAX POB: 145
141
0 HAKURYU-5 Page 1
Thu 13 April Fri 14 April Sat 15 April Sun 16 April Mon 17 April Tue 18 April Wed 19 April
0000 Install diverter and bell nipple 0000 Drill out cement with SW, sweep with Barazan D. 0000 Drill 12.25" Hole to +/- 800m 0000 RUN 1a: TRIPLE COMBO - MCI (GR-Triaxial 0000 RUN 2: NMR MRIL 0000 RUN 3: RDT PRESSURE & SAMPLING (OPS & 0000 RUN 4: HRSCT (RSWC XL)
Displace well to 9.7ppg SBM RES-NEU-DEN)* DPS)
0100 0100 0100 0100 0100 0100 0100

0200 0200 0200 0200 0200 0200 0200

0300 0300 0300 0300 0300 0300 0300

0400 R/D riser handling equipment. R/U 5-1/2'' 0400 0400 0400 0400 0400 0400
handling equipment.
0500 M/U Jetting tool with BOP isolation test tool. Jet 0500 0500 Circulate Hole Clean (1-2 BU) 0500 0500 0500 0500
WH.
0600 Land BOP test plug 0600 0600 0600 0600 0600 0600

0700 0700 Drill 3m into new formation. Circulate & Condition 0700 POOH 12.25" Drilling BHA - OH 0700 RUN 1B: OMRI-XSI 0700 0700 0700
mud.
0800 Pressure test LMRP stack connector, BOP 0800 0800 POOH 12.25"Drilling BHA to surface - CH 0800 0800 0800 Check trip 0800
wellhead connector.
0900 0900 Perform LOT to 11.84ppg EMW 0900 R/B 12.25" Drilling BHA. 0900 0900 0900 0900

1000 Perform full BOP function test (Rams, Annulars 1000 1000 1000 1000 1000 1000
and Fail safe valves). Perform Drawdown test.
1100 POOH BOP test plug & L/D. Function test BSR. 1100 Fingerprinting prior drill ahead. 1100 1100 1100 1100 1100

1200 1200 Drill 12.25" Hole to +/- 800m 1200 1200 1200 1200 1200

1300 Dedicated run to RIH and set Nominal Bore 1300 1300 1300 1300 1300 1300
Protector. POOH NBP Running tool
1400 1400 1400 R/U Wireline Equipment 1400 1400 1400 1400

1500 P/U & M/U 12.25" Drilling BHA. 1500 1500 1500 1500 1500 1500

1600 1600 1600 RUN 1a: TRIPLE COMBO - MCI (GR-Triaxial 1600 1600 1600 1600
RES-NEU-DEN)*
1700 1700 1700 1700 1700 1700 1700

1800 1800 1800 1800 RUN 2: NMR MRIL 1800 RUN 3: RDT PRESSURE & SAMPLING (OPS & 1800 1800
DPS)
1900 1900 1900 1900 1900 1900 RUN 4: HRSCT (RSWC XL) 1900

2000 2000 2000 2000 2000 2000 2000 R/D Wireline Equipment

2100 2100 2100 2100 2100 2100 2100

2200 RIH 12.25" Drilling BHA , wash down last stand 2200 2200 2200 2200 2200 2200
and tag TOC
2300 Choke drill 2300 2300 2300 2300 2300 2300 M/U & RIH Jetting Tool & WB RT. Jet WH Area,
Retrieve WB. POOH
EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG
SETIA HIJRAH SETIA HIJRAH SETIA HIJRAH
Maintenance Maintenance Food containers
Batch Mixer + cement chemicals
EXECUTIVE BALANCE 7" liner hanger package + cement head
8-1/2" bit 7" liner handling gear
8-1/2" BHA Top up fuel and water
8-1/2" Fishing Package
6-1/2" Drilling Jar
5-1/2" HWDP IOT
7" Casing
9-5/8" centralizers + stop collar
Top up fuel and water

EXECUTIVE BALANCE SETIA HIJRAH


LPWHH & HPWHH (backup) + RGB Food containers
Excess 30" + Top hole casing handlig Eq 13-3/8" casing + HPWHH + WFT 20" handling eq
Top Hole Fising Package + BHAs Top Hole BHAs
Excess WBM chemicals
VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS
EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE >> ASB EXECUTIVE BALANCE @ ASB EXECUTIVE BALANCE @ ASB EXECUTIVE BALANCE @ ASB (Loading) EXECUTIVE BALANCE >> HAK5 EXECUTIVE BALANCE @ HAK5
SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH >> ASB SETIA HIJRAH >> ASB SETIA HIJRAH @ ASB SETIA HIJRAH @ ASB SETIA HIJRAH @ ASB (Loading)
HAI DUONG 06 >> HAK5 HAI DUONG 06@ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5

Chopper from Miri Chopper from Miri Chopper from Miri Chopper from Miri
6 JDC Technical 6 4 JDC Drilling 4 6 JDC Barge 6 1 Baroid Mud Engineer 1
2 JDC Catering 2 1 JDC Catering 1 1 Baroid Mud Engineer 1 1 WFD TRS 1
1 DSV (Suhaimi/Anuar) 1 1 WFD TRS ROV 3
1 SSE (Natalie) 1 2 Baker Cementer 2 1 Hornbill 1
1 Halliburton Wireline 2 Halliburton Wireline 1 Nustar 1
1 JDC Drilling 1 1 Wellsite Geologist (Trainee)
Baker Cementer 1 PCSB Geomatic 1
NuStar 1
1 Baker DD 1

Setia Hijrah
Bintang SS surveyor 5

12 12 0 0 12 15 0 0 9 12 2 2 0 0
Predicted POB 141 Predicted POB 141 Predicted POB 138 Predicted POB 138 Predicted POB 135 Predicted POB 135 Predicted POB 135
Thu 13 April Fri 14 April Sat 15 April Sun 16 April Mon 17 April Tue 18 April Wed 19 April

Open
Well: TADOM-1
Rig: HAKURYU-5
Date: 13 Apr 2023 21 DAYS LOOK AHEAD Drilling Supervisors:
Logistics Coordinator:
Anuar / Chewy
Abg Marzuki (Office) / Troy (ASB) / Sabtry (Hak-5)
Initial POB: 124
MAX POB: 150
HAKURYU-5 Page 2
Thu 20 April Fri 21 April Sat 22 April Sun 23 April Mon 24 April Tue 25 April Wed 26 April
0000 M/U & RIH Jetting Tool & WB RT. Jet WH Area, 0000 Release & POOH 9-5/8" CH RT, B/O & L/D 0000 Drill out cement, float collar, float shoe. Cleanout 0000 Circulate Hole Clean 0000 RUN 1a: TRIPLE COMBO - MCI (GR-Triaxial 0000 RUN 2: NMR MRIL 0000 RUN 3: RDT PRESSURE & SAMPLING (OPS &
Retrieve WB. POOH cement head rathole. Displace hole to heavier mud at 10.7ppg. RES-NEU-DEN)* DPS)
0100 0100 0100 Drill 3m into Formation. Circulate Hole Clean and 0100 POOH 8-1/2" BHA to shoe - OH 0100 0100 0100
condition mud before LOT
0200 0200 0200 0200 0200 0200 0200

0300 R/U 9 5/8" Csg Handling Equipment 0300 0300 M/U SES, Perform LOT (Require FG: ____) 0300 0300 RUN 1B: OMRI-XSI 0300 0300

0400 0400 0400 Fingerprinting at various drilling flow rate + 0400 POOH 8-1/2" BHA to surface - CH. Take liner 0400 0400 0400
recording the paddle return flow % parameters for 7'' liner run later.
0500 M/U & RIH 9-5/8" shoe track assembly, test 0500 0500 0500 0500 0500 0500

0600 M/U & RIH 9-5/8" Csg as per Tally (55 jt?) 0600 M/U, RIH & Jet WH, Set 9-5/8" WB 0600 Drill 8.5" Hole to FTD 0600 L/D 8-1/2" Drilling BHA 0600 0600 0600

0700 0700 0700 0700 0700 0700 0700

0800 0800 POOH WB RT 0800 0800 0800 0800 RUN 3: RDT PRESSURE & SAMPLING (OPS & 0800
DPS)
0900 0900 0900 0900 0900 0900 0900

1000 1000 P/U & M/U 8-1/2" Drilling BHA 1000 1000 1000 1000 1000

1100 1100 1100 1100 R/U Wireline Equipment 1100 1100 1100

1200 1200 1200 1200 1200 1200 1200

1300 1300 1300 1300 RUN 1a: TRIPLE COMBO - MCI (GR-Triaxial 1300 1300 1300
RES-NEU-DEN)*
1400 C/O to DP handling equipment 1400 1400 1400 1400 1400 1400

1500 M/U 9-5/8" casing hanger with dummy hanger 1500 RIH 8-1/2" Drilling BHA , wash down last stand 1500 1500 1500 1500 1500
and annulus seal. R/D 9-5/8'' casing handling and tag TOC
1600 Cont RIH 9-5/8" Csg on Landing String. 1600 Choke drill 1600 1600 1600 1600 1600 Check trip

1700 P/U & M/U cementing head assy, Wash down, 1700 Drill out cement, float collar, float shoe. Cleanout 1700 1700 1700 1700 1700
land 9-5/8'' casing hanger rathole. Displace hole to heavier mud at 10.7ppg.
1800 Circulate 150% Casing Volume 1800 1800 1800 1800 1800 1800

1900 1900 1900 1900 1900 RUN 2: NMR MRIL 1900 1900

2000 Pump & displace cement slurry 2000 2000 2000 2000 2000 2000

2100 2100 2100 2100 2100 2100 2100

2200 Bump plug. P/test to _____psi (subject to the 2200 2200 2200 2200 2200 2200
DST requirement) . Set seal assy, Ptest packoff
2300 2300 2300 Circulate Hole Clean 2300 2300 2300 2300

EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG
HAI DUONG 06
Light weight cement?
Cement chemicals
Top up fuel and water
Filtration Unit
Seperator /
Well Test Equipment??
Food containers

VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS


EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE >> ASB EXECUTIVE BALANCE >> ASB
SETIA HIJRAH >> HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5
HAI DUONG 06 >> ASB HAI DUONG 06 >> ASB HAI DUONG 06 @ ASB HAI DUONG 06 @ ASB HAI DUONG 06 @ ASB HAI DUONG 06 @ ASB (Loading) HAI DUONG 06 >> HAK5

Chopper from Miri Chopper from Miri Chopper from Miri Chopper from Miri
1 PCSB Matco 1 1 PCSB NDSV (Yen / Chewy) 1 4 JDC Barge 4 WFD TRS 1
1 JDC Barge 5 JDC Drilling 6 3 JDC catering 3 1 Exlog ML 1
7 JDC Technical 8 3 JDC catering 3 2 Baker Liner Hanger
1 JDC Catering 1 Haliburton Wireline Well Testing??
1 NuStar

11 9 0 0 10 10 0 0 7 7 3 2 0 0
Predicted POB 137 Predicted POB 137 Predicted POB 137 Predicted POB 137 Predicted POB 137 Predicted POB 138 Predicted POB 138
Thu 20 April Fri 21 April Sat 22 April Sun 23 April Mon 24 April Tue 25 April Wed 26 April

Open
Well: TADOM-1
Rig: HAKURYU-5
Date: 13 Apr 2023 21 DAYS LOOK AHEAD Drilling Supervisors:
Logistics Coordinator:
Anuar / Chewy
Abg Marzuki (Office) / Troy (ASB) / Sabtry (Hak-5)
Initial POB:
MAX POB: 150
141
0 HAKURYU-5 Page 3
Thu 27 April Fri 28 April Sat 29 April Sun 30 April Mon 01 May Tue 02 May Wed 03 May
0000 Check trip 0000 RUN 4: HRSCT (RSWC XL) 0000 RUN 6: CAST-CBL 0000 P/U cement head, wash down to bottom. 0000 Run and set BOP test plug, Perform full BOP 0000 Reverse circulate seawater in string 0000 P/u and M/U flowhead to landing jt
Circulate until gas free. Set liner hanger , release pressure test and BOP function test. POOH BOP
0100 0100 RUN 5: Zero Offset VSP 0100 0100 0100 0100 Rig down pumping assembly 0100 L/D flowhead to deck.

0200 0200 0200 0200 0200 0200 POH WBCO BHA to DST & DST Pkr setting 0200 M/U and RIH TCP and DST assemblies
depth.
0300 0300 0300 0300 Primary cement 7" liner 0300 0300 Scrape across DST packer and BP setting depth 0300

0400 RUN 4: HRSCT (RSWC XL) 0400 0400 0400 0400 P/test surface equipment and 9-5/8'' casing 0400 0400

0500 0500 0500 0500 0500 R/U wireline sheaves and surface equipment 0500 RIH WBCO BHA to bottom. 0500

0600 0600 0600 0600 0600 0600 Pump cleanout pill train. Circulate hole clean w/ 0600
Brine until required TSS
0700 0700 0700 0700 Pressure test 7'' liner. Set liner packer. P/test 0700 Perform CBL logging on 7" and 9-5/8" cement 0700 0700
same. L/D cement head, P/U LHRT above TOL,
0800 0800 0800 M/U liner cementing head to pup joint and TIW. 0800 0800 0800 0800
L/D same.
0900 0900 0900 R/U 7'' liner handling equipment 0900 0900 0900 0900

1000 1000 1000 P/U float shoe and F.collar. Test float. P/U 1000 POOH RT on DP inside casing/riser 1000 1000 POOH WBCO BHA to 1 stand below wellhead 1000
intermediate joint and landing collar, test float
1100 1100 1100 1100 1100 1100 1100

1200 1200 1200 M/U and RIH 7'' liner (estimate 58jt with 150m 1200 L/D LHRT. Breakout and L/D cement head ' 1200 1200 1200
liner lap)
1300 1300 1300 1300 1300 1300 1300

1400 1400 1400 1400 Run jetting tool, jet clean wellhead and BOP. 1400 1400 RIH and jet BOP / WH area 1400

1500 1500 1500 1500 1500 1500 POOH and L/D jet sub + WBCO BHA 1500

1600 1600 RUN 6: CAST-CBL 1600 1600 Run and set BOP test plug, Perform full BOP 1600 1600 1600
pressure test and BOP function test. POOH BOP
1700 1700 1700 1700 1700 M/U and RIH WBCO BHA 1700 1700

1800 1800 1800 1800 1800 R/U pumping assembly. Pump ___ bbls 1800 P/U & M/U subsea dummy hanger 1800
seawater.
1900 1900 1900 M/U Liner Hanger, stab in the wiper plugs. 1900 1900 Close BOP. Bleed off pressure in string. 1900 RIH Subsea dummy hanger across BOP 1900
inspect packer condition. Take P/U, S/O weight.
2000 2000 2000 C/O to DP 2000 2000 2000 2000

2100 2100 2100 Run on DP (landing string) 2100 2100 2100 POOH Subsea dummy hanger to surface. 2100

2200 2200 2200 2200 2200 Perform inflow test - monitor with Horner plot 2200 2200

2300 2300 2300 2300 2300 2300 P/u and M/U flowhead to landing jt 2300

EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG EQUIPMENT TO RIG
EXECUTIVE BALANCE
WBCO BHA
H2S package
Subsea Test Tree, flowhead
TCP guns + DST assemblies
Well Test Equipment??

SETIA HIJRAH
SBM + SBM chemicals
8-1/2" BHA

VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS VESSELS


EXECUTIVE BALANCE @ ASB EXECUTIVE BALANCE @ ASB (Loading) EXECUTIVE BALANCE >> HAK5 EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE @ HAK5 EXECUTIVE BALANCE @ HAK5
SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH @ HAK5 SETIA HIJRAH >> ASB SETIA HIJRAH @ ASB SETIA HIJRAH @ ASB
HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5 HAI DUONG 06 @ HAK5

Chopper from Miri Chopper from Miri Chopper from Miri Chopper from Miri
1 PCSB SSE (Joseph/Natalie) 1 5 JDC Drill 5 6 JDC Barge 4 2 Exlog DE/ML 2
7 JDC Tech 6 3 JDC Catering 3 Well Testing??
2 ROV 2 RTPP 2
1 WFD TRS DDX/MWD 2
DD 1 Well Testing??

11 10 0 0 8 12 0 0 6 4 2 2 0 0
Predicted POB 139 Predicted POB 139 Predicted POB 135 Predicted POB 135 Predicted POB 137 Predicted POB 137 Predicted POB 137
Thu 27 April Fri 28 April Sat 29 April Sun 30 April Mon 01 May Tue 02 May Wed 03 May