Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Date:-11-06-2011

President (works)
the undersigned reached site at 3.0PM on 10-06-2011, visited the plant &
observed following point as follow:-
1:- 8” vent line to be provided in main air header.
2:- N0-2 air blower suction & delivery line & motor to be restored.
3:-Pellets discharge metering screw –bucket elevator –silo to be re-engineering.
4:- HBL pump no-1 is not available, suction & delivery pipe to be restored.
5:- pit pump to be restored.
6:- venture circulation delivery line 6” valve to be provided.
7:- Venture discharge control valve to be restored.
8:- P.C inlet cooling water inlet manual valve to be restored.
9:- All manual valve to be made free.
10:-HBL line suction strainer drain valve to be restored.
11:-One HBL pump having flow 15 m3 /hr & H-50M to be provided as existing
pump is not suitable.
13:-3” line is cooling system to be restored.
14:-Grit cyclone screw feed conveyor & charcoal educator to be re-engineering.
15:- jacketed cooling water funnel to be provided & discharge to be given in
cooling tower.
16:-4” fresh water inlet line to be provided.
17:- Pit delivery line to WBL tank & drain to be provided.
18:-PLC to be restored.
19:-Firing gun to be lowered.
20:- All auto control valves to be checked.
21:- Although chloride level of WBL is very high we can attempt five times to
stabilize the operating parameters.
22 HP steam to be provided for charcoal educator for better creating vacuum.
23:- Auto diesel burner to be reset.
24:-After re stabilization of plant additional six effects LTV to be installed for
running the plant conveniently.
25:- Blower having 8700 m3/hr (5116 SCFM) & other is 6000 m3/hr (3528 SCFM)
which will create obstacle while running both the blowers. So same capacity of
(5116 SCFM) of blower to be provided for uniform pressure & volume.
S.K SINGH
Consultant

You might also like