Professional Documents
Culture Documents
Design Knowhow - Low Voltage Substation Layouts, Earthing, Fire Protection and Tests - EEP
Design Knowhow - Low Voltage Substation Layouts, Earthing, Fire Protection and Tests - EEP
Design Knowhow - Low Voltage Substation Layouts, Earthing, Fire Protection and Tests - EEP
Save 50% on all Video Courses with Enterprise Membership Plan and study
Premium Membership ♕ specialized LV/MV/HV technical articles and guides.
MORE INFORMATION »
advertisement
Home / Technical Articles / Design Knowhow: Low voltage substation layouts, earthing, fire protection and tests
advertisement
SUBSCRIBE
Design
Design Knowhow:
Knowhow: Low
Low voltage
voltage substation
substation layouts,
layouts, earthing,
earthing, fire
fire protection
protection and
and tests
tests
Since this type of substation is implemented to feed and distribute power to an entire project,
learning about the major design considerations and the required clearances inside the room
becomes necessary.
The design of a substation inside a building may have different design layouts that need to
be studied to know more about how electrical equipment, such as transformers, LV panels,
RMUs etc., are installed inside the room.
Different layouts are elaborated on in this article. The equipment inside the substations
MUST be protected from potential fire incidents, which means that a substation must contain
different types of firefighting and fire alarm systems that are interfaced together to provide
full protection in case of fire.
This article will reveal the interfacing between these systems inside the substation.
Although understanding the interior of a substation and how it should be protected
from fire incidents is vital, learning more about the required testing procedures
that will be performed for the panels before energizing a new substation is just as
important.
This article explains the major tests that need to be carried out step by step to deliver a
safe, reliable and protected substation.
Table of Contents:
1. Structure of an LV Substation
2. How to Start With the Design?
1. Equipment Clearances You MUST NOT Be Wrong About
2. Dozen of Layouts Available: How to Choose
1. BONUS! Most Common LV substation layouts (PDF)
3. Fire protection Interfacing Inside an LV substation
4. Earthing System inside an LV Substation
5. Requirements Before Testing LV Panels
1. General Notes
2. Pre-Commissioning Procedures
6. Tests After Erection of LV Panels
1. Insulation Resistance Test (IR)
2. Cable Continuity and Polarity Check
3. Phase Rotation Check
4. Functional Test
1. Structure of an LV Substation
An LV substation or an LV room typically contains standing switchboards and other
equipment required for the room to function, such as bus ducts and cable containments,
panel boards, capacitor banks, air conditioning system, fire alarm system, firefighting system,
lighting, small power etc. The latter systems are required to build a typical indoor LV
substation.
However, before indulging into more details about the LV substation’s structure, it is crucial
to have a brief on how the medium voltage substations, including the MV switchgear and the
transformer, supply an LV substation.
Electricity is first generated in power plants or stations with a voltage of 11kV, then stepped
up using step-up transformers to increase the voltage to between 100 kV to 700kV
depending on the distance it will be transferred to; the longer the distance, the higher the
voltage.
After that, electricity is transmitted via overhead electrical lines, which you can see when you
drive between cities (see bottom for ‘Commercial load’).
Figure
Figure 11 –– A
A 24-bus
24-bus system,
system, showing
showing generation,
generation, transmission,
transmission, subtransmission,
subtransmission, industrial,
industrial, and
and commercial
commercial loads
loads
The transmission of these lines is aimed at reaching several receiving HV substations. When
electrical power reaches a receiving station, the voltage decreases to 33kV and 66kV. It is
then sent to transmission lines from this receiving station to electrical substations close to
cities, villages, and urban areas. When electrical power reaches a substation, it is stepped
down once more by a step-down transformer to voltages closer to what it was generated at,
usually around 11kV.
From here, the transmission phase graduates to the distribution phase, and electrical power
is used to meet demand from primary and secondary consumers. This is done by installing
an MV voltage switchgear/ RMU (Ring Main Unit) that can supply several low-voltage
transformers that decrease this voltage to 500V or less for distribution and utilization
purposes.
By looking at the figure below, we can understand more what makes up an LV substation.
Figure
Figure 22 –– Low
Low voltage
voltage substation
substation
In other words, at least 20% spare capacity should be provided for every equipment inside
the room, including cable trays, trunks, LV switchboards, etc. Below are some major
requirements that must be complied with inside an LV substation.
Figure
Figure 33 –– MV/LV
MV/LV substation
substation installation
installation layout
layout (all
(all dimensions
dimensions are
are in
in millimeters)
millimeters)
This is why dimension considerations must be made during the design stage.
Electrical authorities might only supply the building with power if the requirements are met.
In a typical LV substation, cable trays are installed to facilitate the outgoing and incomer
cables. These trays should be designed to be located with sufficient clearances around them
to permit adequate access for the installation and maintenance of cables.
Check out each plan’s benefits and choose the membership plan that works best for you or
your organization.
Good to know 💥 – Get 50% discount on all video courses by purchasing Enterprise plan.
Log In » Purchase »
advertisement
Three-phase basics and How to design the power Learn how to interpret and
terms that students often mix supply for data centres and design single-line diagrams
airports while megawatts of (SLD) for complex projects
loads rise fast
Premium Membership
Get access to premium HV/MV/LV technical articles, electrical engineering guides, research
studies and much more! It helps you to shape up your technical skills in your everyday life
as an electrical engineer.
MORE INFORMATION
Mohammed Ayman
I earned my degree from Eastern Mediterranean University (Turkey,
North Cyprus) in B.S Electrical & Electronic Engineering; shortly after,
I began my career as an electrical site engineer in a mega-scale
project in Qatar which allowed me to monitor and supervise electrical
site installations. I indulged in the design field of the electrical low
voltage distribution systems and have accomplished more than 10 projects with the
compliance of the national codes & international standards.
Leave a Comment
Tell us what you're thinking. We care about your opinion! Please keep in mind that
comments are moderated and rel="nofollow" is in use. So, please do not use a spammy
keyword or a domain as your name, or it will be deleted. Let's have a professional and
meaningful conversation instead. Thanks for dropping by!
EMAIL ADDRESS *
+ 87 = Eighty Eight
SUBMIT COMMENT
© 2023 EEP - Electrical Engineering Portal. All Rights Reserved | Privacy Policy | Terms and Conditions The content is copyrighted to EEP and may not be reproduced on other websites.