Professional Documents
Culture Documents
Installation Manual Ei
Installation Manual Ei
Installation Manual Ei
INSTALLATION MANUAL
Caution
1. Steam outlet size is 40A when the piping part is provided.
PIPING CONNECTION EH-1000F
PIPING CONNECTION EH-1500X
Caution
1. Steam outlet is 65A when the piping part is provided.
2. Install the tee in the feed water piping in the strainer inlet side at site to provide
the chemical feed check(15A).
3. The vibration isolator stopper is attached to the blower during transportation.
Remove it after installing the boiler.
PIPING CONNECTION EI-1000H
Caution
1. Power should be always supplied.
PIPING CONNECTION EI-1500H
Caution
1. Steam outlet is 65A when the piping part is provided.
2. Power should be always supplied.
3. Install the tee in the feed water piping in the strainer inlet side at site to provide
the chemical feed check(15A).
PIPING CONNECTION EI-2000S
Caution
1. Steam outlet is 65A when the piping part is provided.
2. Power should be always supplied.
3. Install the tee in the feed water piping in the strainer inlet side to provide the
chemical feed check(15A).
4. The vibration isolator stopper is attached to the blower during transportation.
Remove it after installing the boiler.
VENTILATION
To secure enough air for combustion and prevent the boiler room temperature from
rising too much, ventilation as follows is necessary.
Required minimum air supply opening area and minimum ventilation opening area
(cm2)
Area of louver Opening Area
EH-500F EH-750F EH-1000F EH-1500X
No louver 3500 5300 7000 10500
Steal louver 7000 10500 14000 21000
Wooden louver 8800 13100 17500 26200
Punching louver 11700 17500 23300 34900
EH-500F Under 50
EH-750F Under 60
EH-1000F Under 70
EH-1500X Under 70
EI-1000H Under 40
EI-1500H Under 70
EI-2000H Under 80
Please follow the instructions.
1. GENERAL INSTRUCTIONS
l When you carry a boiler or boiler accessories in, avoid extremely leaning or
impacting on them.
l The prescribed lifting components should be used.
In case of four point lifting, after all casing should be fixed, lift four points of the
boiler. Otherwise, an accident might be caused.
l Any combustibles should not be put around the boiler.
l The boiler should be free from splashes of water or oil.
l There should be an appropriate air supply opening and a ventilating opening in
the boiler room and the room temperature should be under 50 ℃.
2. BOILER
2-1 Boiler
l Completely fix the boiler with anchor bolts or others. If you use a hole in anchor
instead of an anchor bolt, it should be properly drove in following the maker’s
instructions.
l For some types of boiler, during transportation, the vibration isolator stopper is
stuck to the rubber vibration isolator to prevent the blower from vibration. It
should be removed after installation of the boiler.
2-2 Piping
l The strainer piping should be installed in a place 150 mm higher from the floor
and also 150 mm away from the wall to be easily cleaned.
l Attach an union or a flange to the valves, the strainers and others for
replacement.
2-3 Fuel piping
l Completely fix the piping to avoid vibration. After pipe laying, make sure that
there is not any oil leakage.
2-4 Feed water piping
l The piping should be one size larger than that of the feed water pump inlet.