Activity Schedule/Program for the Construction of Retaining Wall

Text1 Task Name Duration Start Finish Resource Names Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22
04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29

Retaining Wall 79 days Mon 11/04/22 Thu 28/07/22


Site Clearance 5 days Mon 11/04/22 Fri 15/04/22
100 Mobilization of equipment to site 2 days Mon 11/04/22 Tue 12/04/22
110 Pull up Trees and Shrubs 1 day Wed 13/04/22 Wed 1 (bulldozer) operator,1 1 (bulldozer) operator,1 supervisor
13/04/22 supervisor
120 Strip Topsoil/Rubbish Off Site 2 days Thu 14/04/22 Fri 15/04/22 1 (bulldozer) operator,1 1 (bulldozer) operator,1 supervisor
supervisor
Excavation & Foundation 8 days Mon 18/04/22 Wed 27/04/22
200 Setting out & Excavation for 3 days Mon 18/04/22 Wed 1 Engineer,2 labour,1 1 Engineer,2 labour,1 (trencher) operator,1 supervisor
foundation 20/04/22 (trencher) operator,1 supervisor
210 Treatment work & Pour concrete 2 days Thu 21/04/22 Fri 22/04/22 1 (mixer) operator,8 1 (mixer) operator,8 labourers,1 craftsman
for foundation - blinding labourers,1 craftsman
220 Form work for foundation - base 3 days Mon 25/04/22 Wed 27/04/224 carpenters,2 labourers 4 carpenters,2 labourers
Reinforcement 10 days Thu 28/04/22 Wed 11/05/22
300 Reinforcement for base of 4 days Thu 28/04/22 Tue 03/05/22 4 Iron benders,2 labourers 4 Iron benders,2 labourers
retaining wall
310 Reinforcement for stem of 6 days Wed 04/05/22 Wed 4 Iron benders,2 labourers 4 Iron benders,2 labourers
retaining wall 11/05/22
To retaining wall Stem 13 days Thu 12/05/22 Mon 30/05/22
400 Pour concrete for retaining wall 1 day Thu 12/05/22 Thu 12/05/22 4 operators (mixer & 4 operators (mixer & vibrator),2 craftsmen,18 labourers,1 supervisor
base vibrator),2 craftsmen,18
labourers,1 supervisor
410 Remove formwork for retaining 1 day Fri 13/05/22 Fri 13/05/22 6 carpenters,2 labourers 6 carpenters,2 labourers
wall base
420 Form work for retaining wall - stem
3 days Mon 16/05/22 Wed 18/05/226 carpenters,2 labourers 6 carpenters,2 labourers
430 Scaffolding work 5 days Thu 19/05/22 Wed 25/05/226 carpenters,2 labourers 6 carpenters,2 labourers
440 Installation of drainage pipe 1 day Thu 26/05/22 Thu 26/05/22 2 labourers 2 labourers
450 Pour concrete for retaining wall 1 day Fri 27/05/22 Fri 27/05/22 2 operators (mobile concrete 2 operators (mobile concrete mixer),2 nozzle operators,4 artisans,1 supervisor
stem mixer),2 nozzle operators,4
artisans,1 supervisor
460 Remove formwork for retaining 1 day Mon 30/05/22 Mon 6 carpenters,2 labourers 6 carpenters,2 labourers
wall stem 30/05/22
Retaining wall Stem 28 days Tue 31/05/22 Thu 07/07/22
500 Spray water on retaining wall 28 days Tue 31/05/22 Thu 07/07/22 1 operator,2 labourers 1 operator,2 labourers
stem - curing
Coping & Backfilling 15 days Fri 08/07/22 Thu 28/07/22
600 Form work for coping of 2 days Fri 08/07/22 Mon 4 carpenters,2 labourers 4 carpenters,2 labourers
retaining wall stem 11/07/22
610 Pour concrete for retaining wall 1 day Tue 12/07/22 Tue 12/07/22 1 (mixer) operator,4 1 (mixer) operator,4 labourers,1 craftsman
coping labourers,1 craftsman
620 Fill hardcore to the face of 7 days Wed 13/07/22 Thu 21/07/22 1 operator (power shovel),2 1 operator (power shovel),2 labourers,1 supervisor
retaining wall labourers,1 supervisor
630 Backfill with earth material 3 days Fri 22/07/22 Tue 26/07/22 1 operator (power shovel),2 1 operator (power shovel),2 labourers,1 superviso
labourers,1 supervisor
640 Tidy up site 2 days Wed 27/07/22 Thu 28/07/22 2 labourers 2 labourers

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Retaining Wall Split External Tasks Inactive Summary Manual Summary Progress
Date: Tue 12/04/22 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only