Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

www.aps.org.

uk

APS
BRIEFING
Building Safety Act 2022
Briefing Note 1 Overview

This briefing note explains the requirements of the Building Safety Act 2022 and the Government’s proposals for secondary
legislation. The requirements of the Act will not change, although the dates for implementation may. The proposals indicate the
Government’s current thinking but may change. Readers should not assume that all proposals will become law. Readers should
also be aware that changes to timings and Government thinking could occur over the next 12 – 18 months. APS will endeavour to
update our Briefing Notes in line with changes. This briefing note has been prepared in conjunction with The Property Institute.
1

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Table of Contents
Introduction 2
Summary 2
The Building Safety Act 2022 2
Legislative program 3
Building Safety Regulator (BSR) 4
Statutory Committees 4
Enforcement officers 4
Enforcement 4
Compliance Notices 4
Fees and charges 4
Changes to the Building Act 1984 5
Part 3 of the Building Safety Act 2022 5
New building control regime 5
Changes to Building Regulations 6
Industry Competence and Dutyholders 6
Competence and Capability 6
Clients 7
Domestic clients 7
Designers 7
Principal Designer 7
Contractors 7
Principal Contractor 7
Suitable arrangements 7
Building Regulations 2010 - Relevant requirements 8
Building Regulations 2010 Regulation - Requirements relating to building work 8
Building Regulations 2010 Schedule 1 8
Industry competence 8
Demonstrating Competence 9
Higher-risk Buildings 9
Higher-risk buildings – Design and Construction Phases 9
Higher-risk building – Occupation Phase 9
Determining height of a building 10
Building Regulations for Higher-Risk Buildings 10
The Gateways 11
Gateway 1 11
Gateway 2 11
Building control approval applications for new HRB following a staged approach 11
Determining an application for building control approval 11
Between Gateway 2 and 3 11
Site inspections during construction 11
Gateway 3 12
Building Control Approval Applications 13
Competence declaration 13
Construction Control Plan 13
Change control plan 13
Change Control 14
Mandatory Occurrence Reports 14
Design and & Build Approach Statement 14
Fire and Emergency File 14
Golden Thread of Information 15
Planning statement 15
Commencement notice 16
New Clients 16
Notification of a Principal Contractor or Principal Designer 16
Completion notice 16
Completion certificate 16
Compliance declarations 17
Golden thread information and key building information 17
Partial completion 17
Partial Completion Strategy 17
Assessing completion certificate applications 17
Construction Products 18
Consultations 18
Citizen space for all open building safety consultations 18
HTML versions (accessible versions) 18
Further Information 18
Bibliography 18
2

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Introduction Summary The Building Safety Act 2022


On 14 June 2017, a fire broke out at The Building Safety Act 2022 received The Building Safety Act 2022 contains six
Grenfell Tower, a 24-storey residential Royal Assent on the 28th April 2022. parts and nine Schedules and provisions
tower block in West Kensington, London. intended to secure the safety of people
Starting on the fourth floor, the fire quickly Much of the Act requires secondary in or about buildings and to improve the
spread throughout the building and legislation to bring the provisions into standard of buildings.
resulted in 72 fatalities. force and many aspects of the regime
will be taken forward through secondary Part 1 provides an overview of the Act.
Following the fire, the Government legislation.
asked Dame Judith Hackitt to lead an Part 2 establishes a new Building Safety
independent review of Building Regulations The Act’s provisions will extend and apply Regulator within the Health and Safety
and fire safety. The review’s final report, in the main to England only. Executive and sets out its functions in
Building a Safer Future1, was published on relation to buildings in England.
17 May 2018. Part 2 of the Act will establish the new
Building Safety Regulator [BSR] within the Part 3 amends the Building Act 1984 as it
The review found the current system of Health and Safety Executive [HSE] and sets applies to England and Wales, and defines
building regulations and fire safety to out its objectives and functions. the scope and provisions for:
be not fit for purpose and that a culture
change was required to support the The BSR has already been established • prescribed appointments to be made in
delivery of buildings that are safe, both in shadow form in the Health and Safety relation to any building work to which the
now and in the future. Executive. Building Regulations apply;
• competence requirements to be imposed
The Building Safety Act 20222 (the Act): Changes to building regulations in clause on any appointed person, or any
• is intended to deliver the fundamental 31 of the Building Safety Act 2022 will prescribed person;
reform of the building safety system enable the new building control regime for • the regime during the design and
called for in Dame Judith Hackitt’s Higher-risk buildings [HRBs]. construction phase for higher-risk
Independent Review of Building buildings; and
Regulations. Changes to building regulations in clause • the registration of building inspectors
• acts as the vehicle for wider 32 of the Building Safety Act 2022 will and building control approvers;
improvements including changes to the enable the building control procedures for
Architects Act 19975, the Housing Act building work on buildings that are not in Part 4 is concerned with management of
19966, provisions to establish a National scope of the new regime for Higher-risk building safety risk in higher-risk residential
Regulator for Construction Products and buildings [HRBs] to be improved. buildings in England when they are
a New Homes Ombudsman. occupied and defines and places duties on
• takes forward in Section 156 further The Department for Levelling Up, Housing the Accountable Person (the dutyholder in
changes to the Regulatory Reform (Fire and Communities is currently consulting on occupation).
Safety) Order 20057. their proposals for the new regimes.
Part 5 details other provisions, including:
The objectives of the Act are to learn the • provisions about remediation and
lessons from the Grenfell Tower fire and to redress;
remedy the systemic issues identified by • provision requiring a new homes
Dame Judith Hackitt by strengthening the ombudsman scheme to be established;
whole regulatory system for building safety. • powers to make provision for regulation
of construction products for the UK;
This Briefing Note provides an overview of • changes to the Fire Safety Order;
the Building Safety Act 2022; and looks at • provision about the regulation of
the new Building Safety Regulator [BSR]; architects, allowing disciplinary
and the new building control procedures orders made against architects by the
for building work on both Higher-risk Professional Conduct Committee of the
Buildings [HRBs] and on buildings that are Architects Registration Board to be listed
not in scope of the new regime for HRBs. alongside an architect’s entry in the
Register of Architects; and
• provision about housing complaints.

Part 6 contains the technical clauses


related to the Act, including Crown
application and provision for liability of
officers.
3

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Legislative program
April
Much of the Act requires secondary Planning Gateway 1 Introduced
2021
legislation to bring the provisions into
force and many aspects of the regime
will be taken forward through secondary
BSI Flex 8670, Built environment
legislation. Aug
Core criteria for building safety in
2021
competence frameworks published

28th
Building Safety Act 2022 Competency standards published
April
received Royal Assent PAS 8671 Principal Designer
2022

Consultation Secondary
July Competency standards published
Legislation
2022 PAS 8672 Principal Contractor
20th July to 12th October 2022

Competency standards published


Dec
Residents Panel established PAS 8673 Safety management
2022
in residential buildings

Additional powers for the April Regulatory Reform (Fire Safety)


regulation of construction products 2023 Order changes made

Mandatory registration of
HSE takes lead on technical
high-rise residential
building standards
buildings starts

Building Advisory and Building control inspectors


Sept
Industry Competence six month registration period
2023
Committee established commences

New requirements for construction


Accountable persons duties come
products to be safe / strengthened
into force for higher-risk buildings
powers for national regulator

Building Regulation
Gateways 2 and 3 come into
Competence and Dutyholder
force for higher-risk buildings
requirements come into force

Golden Thread of Information

Mandatory registration of Mandatory registration of


Oct
Building Inspectors and high-rise residential
2023
Building Control (completed Oct 24) buildings ends

New regimes for building control Building safety regulator starts


April
inspectors competence and assessing safety cases and issuing
2024
building control body performance building assessment cetificates

March Building safety regulator reaches


2024 business as usual
4

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Building Safety Regulator


(BSR)
Part 2 of the Building Safety Act 2022 Failure to comply with either notice will consultation opened on the 1st Aug 2022
establishes the Health and Safety be a criminal offence, with a maximum and closes on the 7th Oct 2022.
Executive [HSE] as the Building Safety penalty of up to two years in prison and an
Regulator [BSR]. unlimited fine. BSR will seek to recover the costs for
chargeable functions as:
The objectives of the regulator are to: Compliance notices • a fixed fee; and/or
• provide assistance and encouragement • will require work to be corrected by a • a charge for the costs of BSR’s
to: certain date. regulatory effort (hours worked) and any
o residents of higher-risk buildings, • must only be issued against one additional costs for any relevant authority
o persons who have duties in relation to contravention of building regulations or or third-party support that was required.
Building Regulation compliance, and one requirement imposed under building
o accountable persons. regulations. This means that where there The fees and charges set out in the
so that they secure the safety of are multiple contraventions of building charging scheme will be charged to the:
people in or about higher-risk buildings regulations, a compliance notice must • client: the person for whom a project is
by managing the building safety risks be served for each contravention of carried out;
higher-risk buildings; a building regulation or requirement • principal accountable person/
• keep safety and standards of buildings imposed under regulations. accountable person: the duty holders in
under review; and the occupation phase;
• facilitate improvement in competence of Stop notices: • applicant: for either the registration of
industry and building inspectors. • will require non-compliant work to be building control approvers/ building
stopped until the non-compliant action inspectors or for a review of a decision of
The BSR will be allowed to charge fees and has been addressed. the regulator (BSR);
recover charges from those it regulates in • building control professions: The relevant
relation to its functions. can only be issued against: building control bodies or building
• a contravention of specific building control professional;
Statutory Committees regulations; • appellant: the person/body appealing
The Act requires the BSR to establish and • a contravention of a compliance notice against a decision of a local authority or
maintain: or registered building approver; and
• a Building Advisory Committee to give • a contravention of building regulations • regulated party: The party against whom
advice and information to them about which can cause serious harm to any enforcement action is taken by BSR.
matters connected with any of their people in or around a building if the
functions. contravention is not corrected. The proposed Building Safety (Fees
• an Industry Competence Committee and Charges) Regulations will be made
[ICC] concerned with the competence of Section 39 of the Act will amend the in exercise of the powers conferred by
persons in the built environment industry, Building Act 1984 and introduce the sections 15(4) and 28 of the Building Safety
• a Residents Panel comprising residents following enforcement measures that can Act 2022 and section 105B of the Building
of higher-risk buildings to give advice be used by regulators during the design Act 1984.
to them about matters connected with and construction of all buildings:
their functions that relate to higher-risk • the penalty for a breach of building The proposed regulations set out
buildings. regulations under section 35 of the provisions in relation to fees and charges
Building Act 1984 has increaed to a of the building safety regulator. The
The committees are current operating as maximum penalty of an unlimited fine chargeable functions include:
interim committees. and/or two years in prison; • the determination of a building control
approval application;
Enforcement officers Section 35 of the Building Act 1984 will • the inspection and testing of:
The Act allows the BSR to authorise apply not only to breach of provisions of o any work to which building regulations
individuals so that they can exercise building regulations, but also to breach are applicable; or
specified powers to carry out ‘relevant of individual requirements imposed under o a building on which such work has
building functions’ on behalf of the BSR building regulations; and been, is being or will be carried out,
including enforcement-related functions. • section 36 of the Building Act 1984 will to ensure that the work is or would
  been amended to extend the time limit be compliant with the applicable
Enforcement to take action to correct non-compliant requirements of building regulations;
The Act will give regulators stronger work under this section to ten years. • the determination of a change control
enforcement powers. This will make sure application;
those responsible for non-compliance are Fees and charges • the determination of a completion
held accountable and provide a strong The BSR will be allowed to charge fees and certificate application or a partial
deterrent against non-compliant action. recover charges from those it regulates in completion certificate application;
relation to its functions. • the determination of an application for
Section 38 of the Act will amend the registration of a higher-risk building;
Building Act 1984 and permit the BSR and The government is currently consulting on • the determination of an application for a
local authorities to issue compliance and the Building Safety (Fees and Charges) building assessment certificate;
stop notices against non-compliant work. Regulations and charging scheme10. The • the review of a safety case report.
5

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

• any action taken by the regulator with a Changes to the Building Act
view to or in connection with securing 1984
compliance with a building enactment;
• any action taken by the regulator with Part 3 of the Building Safety Act 2022
a view to or in connection with the • modifies the Building Act 1984 and
imposition of a sanction in respect of a introduces the ability to make secondary
contravention of a building; and legislation
• the conduct of an appeal against • facilitates three major changes to the
decisions or actions of a local authority design and construction regulatory
or registered building control approver. framework covering:
o Building Control Authorities;
o Building Regulations for all building
work;
o Building Regulations for higher-risk
buildings.

Building Control Building Regulations 2010 Building Safety Fees


Regulations (as amended) Regulations

Industry Competence
Functional Procedural
and Dutyholders
Requirements Provisions
Regulations

Higher-risk
YES
Building

Building Regulations
NO for Higher-Risk Buildings
(The Gateways)

Building work on Buildings Construction Products Building work on


other than Higher-risk Buildings Regulations Higher-risk Buildings
6

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

New building control regime Changes to Building Regulations • Client


• Principal Designer
The Building Safety Act includes provisions Changes to building regulations in Section • Designers
to improve competence levels and 32 of the Building Safety Act 2022 will • Principal Contractor
accountability in the building control enable the building control procedures for • Contractors
sector by creating a new professional and building work on buildings that are not in
regulatory structure for building control. scope of the new regime for HRBs to be Competence and Capability
improved. It is proposed that any person carrying out
The BSR will establish and maintain a any building work or any design work must
register of: Details of what is proposed was set out in have:
• Registered building inspectors the draft Building (Appointment of Persons, • where the person is an individual, the
(individuals); and Industry Competence and Dutyholders) skills, knowledge, experience and
• Building control approvers (either (England) Regulations (BAPICD)3 which behaviours necessary, or
organisations or individuals). have now been withdrawn. The Department • where the person is not an individual, the
for Levelling Up, Housing and Communities organisational capability,
The Building Safety Act removes the ability are currently consulting on their proposals to carry out:
for a person carrying out building work on for the new regime.9 • the building work in accordance with all
high-rise residential and other in-scope relevant requirements;
buildings to choose their own building The guidance in the following section sets • the design work so that, if built, the
control body where building control is out what is detailed in the consultation. building work to which the design relates
required. would be in accordance with all relevant
requirements; and
The changes introduced by the Act are Industry Competence and • to fulfil their duties under the Regulations
substantial, and therefore creates new titles Dutyholders in relation to the work.
for individuals and organisations.
It is proposed that the new dutyholders It is proposed that a person who is
‘Approved Inspectors’ who wish to will mirror the dutyholder structure of the responsible for appointing a designer or
continue undertaking building control work Construction (Design and Management) contractor to carry out any building work or
will need to register as ‘building control Regulations 20158 but be entirely separate any design work must take all reasonable
approvers’. from it. steps to satisfy themself that any:
• person they wish to appoint has the
The role of a registered building inspector The Government however expects that necessary skills, knowledge, experience
being introduced in the Act is new. new building regulations dutyholder roles and behaviours (SKEB); and
will be undertaken by the same person • organisation has the necessary
Building control authorities and registered or organisation who is undertaking organisational capability.
building control approvers will need the roles under CDM 2015, subject to
to obtain and consider the advice of them having demonstrated the right Organisational capability is defined
a registered building inspector before competence or organisational capability as appropriate management policies,
carrying out certain functions, and will also to undertake both roles on the project procedures, systems and resources to
have to carry out certain activities through they are engaged on. On any project ensure individuals under the control of the
a registered building inspector. involving both dutyholder roles it should organisation who are carrying out any building
be clear how the statutory roles have work or any design work comply with:
These functions and activities will be set been allocated. The client may decide • general competence requirements; and
out in secondary legislation. that the same person or organisation • where relevant, the specific competency
is competent or has the organisational requirements of:
The BSR will: capability to fulfil both roles, as intended o the Principal Designer; or
• set the criteria for registration of by the Government. Alternatively, the client o the Principal Contractor.
inspectors that is linked to a common could make separate appointments of a
competence framework; Principal Designer or Principal Contractor Behaviours include:
• set out a common code of conduct for for CDM, and a Principal Designer • compliance with relevant requirements,
inspectors; or Principal Contractor for building including refusing to carry out:
• set operational standards rules defining regulations purposes after considering the o any building work which is not
the minimum performance standards different statutory requirements and the in compliance with any relevant
that building control bodies must meet; person’s competence or organisation’s requirement;
• set reporting requirements to collect organisational capability. o any design work if the building work
information and will continuously assess to which the design relates cannot
and analyse the performance of building It is proposed that new regulations will set be carried out in compliance with all
control bodies; and out the duties of those who commission, relevant requirements;
• manage a disciplinary process. design and undertake building work to • cooperation with other persons in
which building regulations apply. They relation to the work; and
will set out who the dutyholders are and • refusing to carry out work which
impose duties on them. The dutyholders is beyond their skills, knowledge
will be: or experience, and asking for the
assistance of other persons where
necessary.
7

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Where the role of Principal Designer and of the design phase of the project will be A Principal Designer must have:
Principal Contractor is carried out by the Principal Designer; and the contractor • where the person is an individual, the
an organisation, the organisation will be in control of the construction phase of the skills, knowledge, experience and
responsible for fulfilling all their duties project will be the Principal Contractor. behaviours necessary,
as the Principal Designer or Principal • where the person is not an individual,
Contractor. In doing so, they will be relying Designers the organisational capability, to fulfil the
on their organisational capability, including Any person who, in the course or duties of a Principal Designer under the
having in place a robust management furtherance of a business, carries out any Regulations in relation to the design work
system and a team of people with relevant design work, or arranges for or instructs, included in the project.
competence. In practice, organisations someone under their control to carry out
will usually have individuals, with the design work, will be a designer. In addition Contractors
relevant competence who lead, oversee to the general duties, it is proposed that Any person who, in the course or
and manage the project, supported by a designers must: furtherance of a business carries out,
team with a range of expertise. This should • not start design work unless satisfied manages or controls any building work
enable the organisation to fulfil its duties that the client is aware of their duties; will be a contractor. It is proposed that, in
as the Principal Designer or the Principal • when carrying out design work the addition to the general duties contractors
Contractor for the design or building work designer, ensure that, if built, the building should have the following duties:
included in any particular project. work to which the design relates would • to not start building work unless satisfied
be in compliance with all relevant that the client is aware of their duties;
It is proposed that where the role is carried requirements; and
out by an organisation, reasonable steps • in providing a design, take all reasonable • to provide each worker under their
must be taken to ensure that the individual steps to provide sufficient information control with appropriate supervision,
or individuals designated, who are fulfilling about the design, construction and instructions and information so as
the functions of the Principal Designer maintenance of the building to assist the to ensure that the building work
or the Principal Contractor for a specific client, other designers and contractors to is in compliance with all relevant
project, have the appropriate SKEB. comply with all relevant requirements; requirements.
• where they are carrying out only part of
Clients the design of the building work which Principal Contractor
It is proposed that clients will need to have comprises a project, consider other The Principal Contractor is a contractor
suitable arrangements in place to ensure design work which directly relates to that appointed to be in control of the whole
that the design work and the building work building work and report any concerns project during the construction phase. It is
can be completed in accordance with as to compliance with all relevant proposed that the Principal Contractor will
building regulations. requirements to the Principal Designer; have similar duties to those of the Principal
and, Designer, but in relation to the building
This requires them to appoint the right • if requested to do so, provide advice to work.
people, with the right competencies for the the Principal Designer or the client on In addition to the general and the
work, and ensure those they appoint have whether any work, to which a design it is contractor duties, the Principal Contractor
systems in place to ensure compliance preparing or modifying relates, is higher- will need to:
with building regulations. risk building work. • plan, manage and monitor all the building
work;
Where there is more than one contractor Principal Designer • co-ordinate matters relating to the
working on the project, the Client will need It is proposed that the Principal Designer is building work to ensure that it complies
to appoint: a designer appointed to be in control of all with building regulations;
• a Principal Designer; and the design work. • ensure that they, and the contractors in
• a Principal Contractor. the team, co-operate, communicate and
They can be an individual or organisation. co-ordinate their work with the client, the
Domestic clients They will need to: Principal Designer and other contractors;
A similar approach to that taken in the • plan, manage and monitor the design • liaise with the Principal Designer and
Construction (Design and Management) work, ensuring that the design, if built, share information relevant to the building
Regulations 2015 is proposed for domestic would comply with building regulations; work; and,
clients. Where the client is a domestic • co-ordinate matters relating to the design • assist the client in providing information
client, their duties that must be carried out work to ensure that, if built, the building to other designers and contractors.
by: work to which that design relates will
• the contractor (where there is only one comply with building regulations; Suitable arrangements
contractor for a project); or • ensure that they, and the designers in It is proposed that a client will need to
• the Principal Contractor or the Principal the team, cooperate, communicate and make suitable arrangements for planning,
Designer (where there is more than one coordinate their work with the Client, managing and monitoring a project
contractor) if the client and the Principal the Principal Contractor, and other (including the allocation of sufficient time
Designer has agreed this in writing. designers; and other resources) so as to ensure
• liaise with the Principal Contractor, and compliance with all relevant requirements.
If a domestic client fails to make the share information relevant to the building
appointments of the Principal Designer and work; and
Principal Contractor, the designer in control • assist the client in providing information
to other designers and contractors.
8

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Relevant requirements was defined in draft Regulations as: to the extent relevant to the Industry competence
building work or design work in question, the requirements of regulations 4, 6, 7, 8, 22, It is proposed that requirements will be
23, 25B, 26, 26A, 28, 36, 41(2)(a), 42(2)(a) and 43(2)(a) of, and Schedule 1 to, the Building imposed on Principal Designers, Principal
Regulations 20104. This may change, however it has been confirmed that all building Contractors and anyone carrying out any
work, including that on HRB’s will need to comply with Schedule 1. design or building work to be competent
for their roles.
Building Regulations 2010 - Relevant requirements
Regulations 4 - Requirements relating to building work It is also proposed that a duty will also be
Regulation 6 - Requirements relating to material change of use placed on those who appoint them to take
Regulation 7- Materials and workmanship reasonable steps to ensure that the people
Regulation 8 - Limitation on requirements they appoint meet this requirement.
Regulation 22 - Requirements relating to a change to energy status Individuals will need to have the skills,
Regulation 23 - Requirements relating to thermal elements knowledge, experience and behaviours
Regulation 25B - Minimum energy performance requirements for new buildings necessary for their role.
Regulation 26 / 26A - CO2 emission rates for new buildings
Regulation 28 - Consequential improvements to energy performance Organisations, will need to have the
Regulation 36 - Water efficiency of new dwellings organisational capability – the ability of
Regulation 41(2)(a)- Sound insulation testing an organisation to carry out its functions
Regulation 42(2)(a) - Mechanical ventilation air flow rate testing properly. This involves:
Regulation 43(2)(a) - Pressure testing • having appropriate management
  systems, processes, policies and
Building Regulations 2010 Regulation - Requirements relating to building work resources to carry out its functions under
Requirements relating to building work - building work shall be carried out so that: the Regulations; and
• it complies with the applicable requirements contained in Schedule 1; and • ensuring that individuals who carry out
• in complying with any such requirement there is no failure to comply with any other such the work for them have the appropriate
requirement. skills, knowledge, experience and
behaviours for their roles.
Building Regulations 2010 Schedule 1
The government intends to provide
statutory guidance, in the form of an
A1 - Loading H4—Building over sewers Approved Document, to support these
A2 - Ground movement H5 – Separate systems of drainage requirements.
B1 - Means of Warning and Escape H6—Solid waste storage
B2 - – Internal Fire Spread (linings) J1—Air Supply
B3 – Internal fire spread (structure) J2—Discharge of Products of Combustion
B4 – External Fire Spread J3—Warning of release of carbon monoxide
B5 – Access & Facilities for the Fire Service J4—Protection of building [combustion
C1 – Preparation of site and resistance to appliances and flue-pipes]
contaminants J5—Provision of information [hearth, fireplace,
C2—Resistance to Moisture flue or chimney]
D1 – Cavity Insulation J6—Protection of liquid fuel storage systems
E1—Protection against sound from other parts of J7 – Protection against pollution
the building and adjoining buildings K1 – Stairs, ladders and ramps
E2 – Protection against sound within a dwelling- K2 – Protection from falling
house etc. K3 – Vehicle barriers and loading bays
E3 – Reverberation in common internal parts of K4 – Protection against impact with glazing
buildings containing flats or rooms for K5.1 – Protection from collision with open
residential purposes windows etc.
E4—Acoustic conditions in schools K5.2 – Manifestation of glazing.
F1—Means of Ventilation K5.3 – Safe opening and closing of windows.
G1—Cold water supply K5.4 – Safe access for cleaning windows etc.
G2 –Water efficiency K6 – Protection against impact from trapping by
G3 – Hot water supply and systems doors
G4 – Sanitary conveniences and washing facilities L1—Conservation of fuel and power
G5 – Bathrooms M1 – Access and use
G6 – Kitchens and food preparation areas M2 – Access to extensions
H1—Foul water drainage M3 – Sanitary conveniences in extensions to
H2—Wastewater treatment systems and buildings other than dwellings
cesspools M4 – Sanitary conveniences in dwellings
H3 – Rainwater drainage P1 – Electrical Safety – Design and installation

The Building Regulations 2010 will be amended or replaced. However, it is believed that
the relevant requirements are likely to remain largely the same.
9

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Demonstrating Competence published in late July and comes into Higher-risk Buildings
There will be a number of ways in which effect on the 31st July 2022;
a person involved in the construction • PAS 8672 Built environment – The Building Safety Act 2022 introduces
project can demonstrate that they meet Framework for competence of Individual requirements and facilitates secondary
the competence requirements for the Principal Contractors – Specification legislation which will affect the construction
role or tasks they are to undertake. As a published in late July and comes into and the management during occupation
minimum, those carrying out work will be effect on the 31st July 2022; and of higher-risk buildings. The Act defines a
expected to meet the standards set by higher-risk building as:
their sector, for example, relevant training These standards and the industry • a building in England that:
and qualifications recognised by accredited competence frameworks will be key to o is at least 18 metres in height or has at
institutions, membership of an established supporting dutyholders in meeting the least 7 storeys, and
trade or professional body, or relevant competence requirements and dutyholders o contains at least 2 residential units.
experience of the type of work they will will be expected to demonstrate that they
undertake. meet the standards and competence Further details about what constitutes a
frameworks. Robust accreditation higher-risk building are to be provided in
The government has been working with the arrangements by a publicly recognised the Higher Risk Buildings (Descriptions and
British Standards Institution (BSI) to create third-party body are vital to ensure Supplementary Provisions) Regulations
a suite of national competence standards consistency in the application of the consultation for which ended on the 21st
for construction duty holders. These frameworks and rebuild confidence in July 2022.
include: the industry. The Government has stated
• BSI Flex 8670 Core Criteria for Building in the consultation that they expect that The draft regulations align the definition of
Safety in Competence Framework organisations wishing to assess individuals ‘building’ with the Building Act 1984 and
– Code of Practice, which sets out against the British Standards Institution’s define a building as including any structure
key principles to be used by different and sector-specific frameworks will be or erection, and any part of a building, as
sectors to develop their sector-specific third-party accredited. so defined, but does not include plant or
competence frameworks which was machinery comprised in a building.
published in August 2021. It is in the The competency standards for duty
process of being converted to a British holders under CDM 2015 remain. Higher-risk buildings – Design and
Standard; Designers, contractors and others with Construction Phases
• PAS 8671 Built environment – duties under both to the dutyholder and During the design and construction phases,
Framework for competence of Individual competence regulations and CDM 2015 higher-risk buildings are defined as:
Principal Designers – Specification will need to demonstrate competence to • buildings which contains at least two
both standards. residential units (the Building Safety Act
defines residential unit as a dwelling or
any other unit of living accommodation,
PAS 91:2013+A1:2017 BSI FLEX 8670 Built Environment for example a flat or rooms in a university
Construction Prequalification Overarching framework for hall of residence where amenities are
Questionnaires competence of individuals shared);
• care homes; and
• hospitals.

It is proposed that the following buildings


are excluded from the definition and
BUILDING
therefore the duties that will be imposed:
CDM 2015 SAFETY BILL
• secure residential institutions (e.g.
PART 3
prisons).
• temporary leisure establishments (e.g.
hotels); and
• military premises (e.g. military barracks).

Higher-risk building – Occupation Phase


PEOPLE PEOPLE PEOPLE USING Part 4 of the Building Safety Act 2022 will
PEOPLE
MAINTAINING USING AS A NON apply to buildings which contain at least
CONSTRUCTING
& CLEANING WORKPLACE WORKPLACE two residential units but will not apply to:
• a care home;
• a hospital;
• a secure residential institution;
• a temporary leisure establishment; or
• military premises.
10

APS Briefing:
Building Safety Act 2022

Determining height of a building If proposing to construct or create a higher-risk building (HRB) an applicant must submit a building
For the purposes of the Building Act 1984 control approval application to the Building Safety Regulator (BSR) with plans and new prescribed
documents. Work cannot commence without BSR approval.
and the Building Safety Act 2022:

WORK COMMENCES
BEFORE BUILDING
• the height of a building is to be measured
from ground level to the top floor surface BSR will consult its multi-disciplinary team, including fire and rescue authority and sewerage undertaker
of the top storey of the building (ignoring and determine application within 12 weeks
any storey which is a roof-top machinery
or plant area or consists exclusively of
machinery or plant rooms); and If application is approved, the BSR will agree a bespoke inspection schedule with the applicant. The
BSR must be notified at these stages for inspection to take place. Building works can then commence
• when determining the number of storeys (subject to any BSR imposed requirements)
a building has:
o any storey which is below ground level
is to be ignored; and
o any mezzanine floor is a storey if its BSR Carries out Dutyholders must comply If applicant proposes to deviate from the original building
inspections at agreed with dutyholder and control approval application, they must determine whether it
internal floor area is at least 50% of stages. Inspections can competence duties: constitutes a ‘major’ or ‘minor ‘ amendment
CONSTRUCTION PHASE

the internal floor area of the largest also be carried out without mandatory occurrence
notice reporting requirements;
storey in the building which is not and golden thread
below ground level. requirements. CDM 2015
requirements also apply.
MAJOR MINOR
Applicant submits change Applicant submits change
A storey is treated as below ground level control application to the control notification to the
if any part of the finished surface of the BSR who has has six BSR who has ten days to
weeks to determine consider notification. If the
ceiling of the storey is below the ground application. Change cannot BSR has not intervened,
be made without BSR the change can be made
level immediately adjacent to that part of approval once the prescribed period
the building. has elapsed.

The method of measurement matches that


set out in Approved Document B Volume
1: Dwellings. Diagrams D5 and D6 on page FULL COMPLETION PARTIAL COMPLETION
BUILDING WORK COMPLETE

144 provide a good explanation of how to


Building work on HRB is complete. Applicant must submit a Building work on relevant HRB is complete. Applicant must
measure. completion certificate application to the BSR for approval submit a partial completion certificate application to the
  and golden thread information must be handed over to the BSR for approval and golden thread information must be
Accountable Person (AP) handed over to the Accountable Person (AP)
Building Regulations for Higher-Risk
Buildings
Details of what is proposed in relation to BSR assesses the application and carries out final BSR assesses the application and carries out final
inspections of the relevant building work. inspections of the relevant building work.
the management of building regulations
compliance on higher-risk buildings was
set out in the draft Building (Higher-Risk If satisfied that the completed part of the HRB including all
If satisfied that the HRB including all relevant building work
relevant building work complies with all applicable building
Buildings) (England) Regulations [Building complies with all applicable building regulations, the BSR
regulations, the BSR will issue a partial completion
will issue a completion certificate for that specific work.
(HRB) Regulations]. The draft regulations certificate for that specific work.
have been withdrawn. The Department for
Levelling Up, Housing and Communities
are currently consulting on their proposals AP can register the building for occupation.
AP can register the building for occupation. Only the part of the building for which there is a completion
for the new regime. This is separate to the building control process certificate, can be occupied.
This is separate to the building control process
OCCUPATION

The guidance in the following section sets


out what is detailed in the consultation.

The new building control process for Building works on other


Fire Safety Order and AP’s
parts of the building
creating higher-risk buildings will operate continues. The above
duty to assess and manage
building safety risks apply
as shown in the following diagram. completion certificate
once occupation
application process applies
commences. CDM
each time HRB work is
requirements continue to
completed on a new part of
apply
the builing
11

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

The Gateways form, which includes information about: It is proposed that the application for
Amendments to the Building Act 1984 set • the principles, concepts and approach building control approval is be submitted
out in the Building Safety Act, coupled relating to fire safety that have been to the BSR in writing and signed by the
with existing powers both in the Building applied to each building in the applicant.
Act 1984 and in new the Building (HRB) development
Regulations, will allow for the creation of a • the site layout Prior to submitting a building control
new Gateway regime. • emergency vehicle access and water approval application, dutyholders will be
supplies for firefighting purposes encouraged to engage with the BSR early
There will be three gateways: • what, if any, consultation has been to discuss the development including draft
• Planning Gateway one – at the planning undertaken on issues relating to the fire plans and documentation they intend to
application stage safety of the development; and what submit to the BSR formally.
• Gateway two – before building work account has been taken of this
starts • how any policies relating to fire safety in It is proposed that all applications for
• Gateway three – when building work is relevant local development documents higher-risk buildings, including all plans,
completed. have been taken into account documents and information, should be
submitted electronically to the BSR, via a
It is proposed that new Regulations will Gateway 2 digital system.
replace, for higher-risk building work, the It is proposed that Gateway 2 will:
procedural provisions of regulation 12 to 18 • replace the building control deposit of Building control approval applications
of Building Regulations 2010. plans stage, before building work starts, for new HRB following a staged
for higher-risk buildings; approach
Higher-risk building work must be carried • be a stop/go point and building control The government recognise that there
out so that the design and the execution of approval must be obtained from the may be legitimate scenarios where some
the building work achieve compliance with Building Safety Regulator before relevant information required for building control
the functional requirements of the Building building work starts; and approval of a higher-risk building is
Regulations 2010. • require applicants to demonstrate how unavailable and waiting for it could delay
the proposals comply with building construction, such as, in complex builds.
Higher-risk building work including design regulations requirements. In these scenarios, it is proposed that
work will be required to be carried out in a the BSR will be able to allow a ‘staged
workmanlike and professional manner. Building regulations should be considered approach’ to building control approval for
holistically with an outcome focused construction, where it is satisfied that all
Gateway 1 approach which includes appropriate the information cannot be provided upfront
Changes to the planning system, known consideration of building safety. but that the proposed building work
as ‘planning Gateway one’ have been will comply with all applicable building
introduced via the Town and Country All plans and documents must be regulations’ requirements.
Planning (Development Management realistic for the building and not rely on
Procedure and Section 62A Applications) unreasonable assumptions about the Where a staged approach is proposed,
(England) (Amendment) Order 2021 and management, maintenance and behaviours dutyholders will still be required to provide
went live on 1 August 2021. and characteristics of residents in the a comprehensive building control approval
occupied building once built. application with plans and all prescribed
Planning gateway one has two key documents, as well as a staged work
elements: It is proposed that applicants will have to statement providing a detailed description
• to require the developer to submit demonstrate that they have appropriate of the proposed stages of the work,
a fire statement setting out fire strategies to manage the construction including an estimate of the time when
safety considerations specific to the phase to support building regulations each stage of the work will commence.
development with a relevant application compliance and reduce the possibility
for planning permission for development of building safety risks arising: This will A staged approach will still represent a
which involves one or more relevant include: ‘hard stop’ but will be managed through
buildings, and • the evidencing of compliance; ‘hard stops in stages’ which are bespoke
• to establish the Health and Safety • change management; to the specific higher-risk building project.
Executive as a statutory consultee for • competence management;
relevant planning applications • golden thread management; and Determining an application for building
• mandatory occurrence reporting. control approval
Relevant buildings It is intended that, for higher-risk buildings,
• contain two or more dwellings or The requirement to seek building the BSR will be the building control
educational accommodation and control approval from the BSR will apply authority.
• meet the height condition of 18m or irrespective of whether building work
more in height, or 7 or more storeys in a higher-risk building has planning Before determining an application for
permission before the new building control building control approval, they will be
Fire statements must be submitted on a regime comes into force, as planning required to consult relevant enforcing
form published by the Secretary of State permission and building control are two authorities when determining building
(or a form to similar effect) contain the entirely separate regimes. control approval applications. For
particulars specified or referred to in the buildings that are, or will be covered, by
12

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

the Regulatory Reform (Fire Safety) Order There will be increased on-site monitoring Gateway 3
2005, they will be required to consult the and inspection by the BSR with the power Gateway 3:
relevant enforcing authority under the Fire to de-construct elements if they are • will occur at the current completion/final
Safety Order (usually the fire and rescue suspicious of non-compliance. certificate stage when relevant building
authority) and the relevant sewerage work is complete.
undertaker, where it is appropriate to do so. In addition, during the construction phase, • is a stop/go point, building control
where the BSR finds building work not to approval must be obtained from the
The BSR will be able to approve a building be in compliance with relevant building Regulator before registering and
control approval application, with or regulations, the BSR should check that commencing occupation of a higher-risk
without requirements, or reject it. there are suitable arrangements in place building.
for assessing the competence of the • requires applicants to demonstrate how
The approval could, for example, include a person, including whether the person the building work complies with building
requirement: who designed or carried out the work has regulations requirements to provide
• to provide the BSR with a particular committed a serious infraction. assurance that buildings are safe to
document, or revised version of a occupy.
particular document by a certain date, if, Site inspections during construction
for example, some relatively minor details It is proposed that the BSR and applicant An application will be required including
were missing from the application; or will work together to agree an inspection plans and documents that reflect the ‘as-
• that building work does not proceed schedule tailored to the individual higher- built’ building.
beyond a specified stage until a risk building project. The BSR will produce
particular document, or revised version guidance setting out when inspections are Completion certificates will be issued by
of a particular document has been likely to be required to provide industry Regulator if a gateway three application is
approved by the BSR. For example, with more certainty about requirements approved.
when a dutyholder has opted for the whilst still allowing a flexible approach to
staged approval, they may be required be taken towards individual higher-risk Only once Gateway three has been passed
to ensure that the building work does building projects. (either for partial or full completion) can the
not proceed beyond a specified stage, new building be registered with the BSR for
such as laying the foundations, until occupation.
the dutyholder has provided detailed
plans and a design and build approach
document covering the superstructure.
GATEWAY 3 Building
Building Control GATEWAY 1
Completion Regulations
In line with existing practice, the BSR will Certificate
Approval
Drawings CONTENTS
Application
have to decide an application for building GATEWAY 1
Dutyholder Review
Fire Construction
control approval within a statutory time- Statement
Contract Details Policy GATEWAY 2
Control Plan
CONTENTS
limit. It is proposed that the prescribed GATEWAY 2
Project
Competence
Contents
Building Control Strategy
timescale is 12 weeks. Submission
Description
and Records Fire &
Emergency File
Schedule of Contents
Change Control Competence
Personnel
Where the BSR has not reached a decision Records Declaration
Appointed
within the prescribed timescale and the Mandatory
Compliance Construction
applicant has not taken action, either by Declaration Control Plan
Occurrence
System Statement
agreeing to an extension or submitting Mandatory Construction
GATEWAY 3 Completion
D&B Approach CONTENTS Certificate
their application to the Secretary of State Occurrence
Document
Management
Reports Arrangements
under the Section 30A non-determinations
Golden Thread Change Control
procedure, it is proposed that the Completion Arrangements Arrangements
application will be deemed refused. Certificate
Management
Fire &
and Maintenance
Emergency File
Arrangements
Between Gateway 2 and 3
During construction, it is proposed Planning Building Safety
Statement Risk Register
that those involved in the design and
construction process will be required to: GOLDEN THREAD
Partial Compliance
Completion Approach
• comply with their duties, co-operate, co- CONTENTS AT GATEWAYS Strategy Statement

ordinate, communicate
• be competent or have organisational
capability;
• follow statutory change control
requirements;
• meet robust record-keeping
requirements;
• develop and maintain the golden thread;
• report fire and structural safety
occurrences in line with their mandatory
occurrence reporting requirements.
13

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Building Control Approval Applications the measures the dutyholder who made It is proposed that the change control plan
It is proposed that a building control the appointment will take to mitigate the should include the strategies, policies
approval application must be made in effects of the appointment. and procedures the client has adopted to
writing, signed by the applicant, and must ensure:
include: Construction Control Plan • any controlled change takes place
• the name, address, telephone number The purpose of the proposed construction in accordance with change control
and (if available) an email address of: control plan is to ensure that, before requirements; and
• the client; construction starts, dutyholders have clear • each controlled change is logged
• the Principal Contractor (or sole strategies in place to ensure compliance in accordance with record-keeping
contractor); and with all applicable building regulations will requirements.
• the Principal Designer (or sole or lead be maintained during building work.
designer); The plan must explain:
• a description of the existing building It is proposed that the construction • how proposed changes will be identified
where the work is on an existing building; control plan should focus on cooperation, and to whom they must be reported;
and coordination, communication and • how the impacts of proposed changes
• a description of the proposed HRB work. competence and must set out the are identified and considered;
strategies, policies and procedures the • in relation to proposed changes, the
Applications must accompanied by: client has adopted: decision-making procedures adopted
• a scale plan showing the size and • for planning, managing and monitoring for agreeing a change including whose
position of the building and its the higher-risk building work so as to advice is to be sought;
relationship to adjoining boundaries and ensure compliance with: • how changes are recorded and by when;
the size, position and use of every other o the applicable requirements of the • the procedure to identify which changes
building or proposed building and any building regulations and to record require notification to the Building Safety
street within the curtilage; evidence of that compliance; Regulator and which changes require
• such other plans as necessary to show o which dutyholder is responsible for a change control application to the
that the HRB work would comply with all meeting the dutyholder duties; Building Safety Regulator before the
applicable requirements of the building • to identify, assess and keep under review change can occur; and
regulations; the competence of the persons carrying • how the effectiveness of the change
• ‘a competence declaration’; out the higher-risk building work or control strategy will be reviewed by
• ‘a construction control plan’; involved in the design of the higher-risk dutyholders.
• ‘a change control plan’; building. This must include the steps
• ‘a design and build approach document’; taken to determine whether the person It is also proposed that the change control
• ‘a fire and emergency file’; has committed a serious infraction, plan should include a change control log
• the client’s arrangements for maintaining and the detailed consideration of their that includes the following information:
‘the golden thread information’; previous conduct, which might call into • the name of the individual recording the
• a copy of the ‘key building information’ question their competence in relation to change;
for the proposed building; the work in question; • a description of the proposed change;
• ‘a planning statement’. • to support co-operation between • an explanation of the reason why the
designers, contractors and any other change has been proposed;
Competence declaration persons involved in the higher-risk • whether the change is a notifiable
A competence declaration is a signed building work, including the sharing of all change or a major change;
statement by the client confirming that necessary information; • a list of the name and occupation of
they have taken all reasonable steps to be • A construction control plan must include: each person, if any, whose advice was
satisfied that the Principal Designer and o a schedule giving the name of sought in relation to the proposed
Principal Contractor (the principal duty each person who at the date of the change and a brief summary of any
holders) they have appointed have satisfied application was appointed by the advice provided;
the requirements of the Dutyholder client or the principal duty holders. • an assessment of which agreed
Regulations. o the policies the client has adopted to document is affected by the proposed
review the construction control plan. change and confirmation that a revised
It is proposed that the declaration must   version has been produced; and,
be accompanied by documentation Change control plan • an explanation, in relation to the
setting out the step the client has taken The purpose of the proposed change proposed change, of how:
to satisfy themselves of the competence control plan is to ensure that dutyholders o the higher-risk building work will,
of the Principal Designer and Principal carefully consider the implications of after the proposed change is carried
Contractor. This must include the steps changes from their original building control out, meet all applicable building
taken to determine whether the person approval before they are made, and that all regulations; and
(organisation) has committed a a serious controlled changes are recorded to ensure o the strategies, policies and procedures
infraction, and the detailed consideration that plans and prescribed documents are in relation to the higher-risk building
of their previous conduct, in particular updated to reflect the building work ‘as work (including in relation to controlled
any serious infraction, which might call built’ rather than ‘as-designed’. changes, mandatory occurrence
into question their competence in relation reporting, competence of persons
to the work in question, their reasons or sharing of information and co-
for appointing them nonetheless and operation) will, after the proposed
change is carried out, meet relevant
requirements.
14

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Change Control Mandatory Occurrence Reports Design and Build Approach Statement
Before any controlled change can be Mandatory occurrence reporting will require The purpose of the proposed design and
carried out, the client must ensure: dutyholders to report safety occurrences to build approach document is to encourage
• a record is made of the controlled the BSR. dutyholders to carefully consider how
change; and compliance will be achieved for each
• a revised version of any agreed A safety occurrence will be defined as: applicable building regulation requirement
document affected by the controlled • in relation to a design, an aspect of the before construction starts. As part of the
change is produced. design relating to the structural integrity design and build approach document,
or fire safety of a higher-risk building that they will be required to set out whether
Controlled changes are: would, if built, meet the risk condition; they intend to follow any guidance to meet
• to carry out work otherwise than in • otherwise, an incident or situation the building regulations requirements (e.g.
accordance with the current plans; relating to the structural integrity or fire Approved Documents, British Standards,
• to depart from the strategies, policies safety of a higher-risk building that meets Design Codes, etc.).
and procedures described in the current the risk condition.
construction control plan (including a The government consider this vital as
change to the mandatory occurrence The proposed definition of the “risk following Approved Documents is a
reporting system); condition” is that use of the building in common means to try to ensure building
• to change the arrangements to create question without the incident or situation work complies with building regulations
and maintain the golden thread being remedied would be likely to present and whilst this approach may be
information from those described in the a risk of a significant number of deaths, entirely appropriate for typical building
current statement. or serious injury to a significant number of work scenarios, it does not guarantee
people. compliance, as the Approved Documents
A controlled change must be recorded by are not relevant to all situations. It is
entering the following information in the Where there is a safety occurrence during therefore important that dutyholders
change control log: the construction phase, a Principal carefully consider their approach to
• the name of the individual recording the Designer and Principal Contractor (the complying with building regulations and
change; principal dutyholders) must on becoming whether it is appropriate for their specific
• a description of the proposed change; aware of the occurrence: project.
• an explanation of the reason why the • notify the regulator of the safety
change has been proposed; occurrence by the quickest practicable It is proposed that a design and build
• whether the change is a notifiable means without undue delay; and approach document must set out the
change or a major change; • provide the regulator with a written report approach taken in designing the HRB and
• a list of the name / occupation of each of the occurrence within 10 calendar the building standards to be applied, in
person, if any, whose advice was sought days. particular:
in relation to the proposed change and a It is proposed that the notification and • any assumptions made in the design
brief summary of any advice provided; report must include: of the building as to the intended
• an assessment of which agreed • the date and time of the safety occupiers of the building and their likely
document is affected by the proposed occurrence; characteristics and behaviours, and the
change; • the address of the site at which the intended management or maintenance of
• an explanation, in relation to the occurrence happened; the building, and justification for making
proposed change, of how: • name and contact details of the principal those assumptions;
o the work will, after the proposed dutyholder making the report; • the approach taken in relation to
change is carried out, meet all • the type and details of the occurrence each element of the building to
applicable building regulations, and (including the nature of the risk). ensure compliance with all applicable
o the strategies, policies and procedures requirements of the building regulations;
in relation to the work will, after the Where, in relation to HRB work, the client • where compliance is not intended to
proposed change is carried out, meet appoints principal duty holders, they be achieved by following an approach
the requirements the regulations. must take all reasonable steps to satisfy specified in an approved document,
  themselves that the persons appointed the reasons for adopting an alternative
are able to fulfil the requirements for a approach to compliance together with
mandatory occurrence reporting system an explanation of why the alternative
and mandatory occurrence reporting. approach is appropriate for the building
  and how it ensures compliance with all
applicable requirements of the building
regulations.
15

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Fire and Emergency File design phase of the project, and the • finalising the golden thread and
The purpose of the proposed fire and Principal Contractor who will update and handing it over to the client at building
emergency file is to ensure that building manage it through the building phase. completion;
safety risks are appropriately considered It is expected that the design and • ensuring that the golden thread meets
before construction starts and that construction phases will overlap and the required standards/principles; and,
assumptions behind the designs and how influence each other, rather than run • cooperating, collaborating and sharing
the building will be used are realistic and consecutively. information with the Principal Designer
carefully considered, with a clear rationale as necessary.
behind those assumptions. The arrangements must include:
• arrangements for an electronic facility It is proposed that the client, Principal
It is proposed that a fire and emergency file to be created and maintained by the Designer and Principal Contractor are
must explain: client (or someone on their behalf) for placed under a duty to ensure that the
• the matters that were considered when the purpose of holding the golden thread information and prescribed documents in
assessing how the building safety risks information; and the golden thread should be maintained
could impact the proposed building; • procedures for persons involved with the and managed so that the golden thread
• the proposals adopted in designing the HRB work to maintain any golden thread remains relevant, useful and proportionate.
proposed building to ensure compliance information in the electronic facility
with the applicable requirements of provided. Other dutyholders will be required to
the building regulations relating to the provide information and be responsible for
building safety risks; On a new HRB, the golden thread and updating information when necessary. They
• the measures, strategies and policies it the systems for storing the golden thread may not interact directly with the golden
is proposed the building owner should must be in place before the building control thread IT/digital system - they may instead
adopt in order to manage and maintain approval application at Gateway 2. It is provide information to be input into the
the proposed building; desirable however, for the golden thread to system by the Principal Designer or the
• any assumptions made in those be started at the earliest possible stage. Principal Contractor.
measures, strategies and proposals
as to the intended occupiers of the It is proposed that all the information that Although the golden thread during
building and their likely characteristics the applicant has to submit as part of construction needs to contain evidence
and behaviours, and the intended the building control approval application that the building satisfies all the applicable
management or maintenance of the should be stored in the golden thread. functional requirements of the building
proposed building; regulations, the golden thread during
• the approach taken in relation to the It is proposed that the Principal Designer occupation will only need to contain
proposed building to ensure compliance will be specifically responsible for: information relating to building safety risk.
with all applicable requirements of • creating and developing the golden
the building regulations relating to the thread (although initial information about The Golden Thread is both:
building safety risks. the building may be provided by the • the information about a building that
client) and managing and updating this allows someone to understand a building
Golden Thread of Information throughout the design phase; and keep it safe; and
The golden thread during design and • finalising the golden thread and handing • the information management to ensure
construction of higher-risk buildings should it over to the Principal Contractor on the information is accurate, easily
enable the right people at the right time to completion of the design phase; understandable, can be accessed by
have information to support compliance • collaborating with the Principal those who need it and is up to date.
with all applicable building regulations, Contractor to ensure any design work The Golden Thread will:
including those relating to building safety. done during the construction phase is • apply through design, construction,
Managing the information is a key part of captured in the golden thread; occupation, refurbishment and ongoing
the golden thread to ensure that people • ensuring that the golden thread meets management of buildings
can trust that the information is accurate the required standards/principles; and • show that the building was compliant
and up to date and can access and share • cooperating and sharing information with with all applicable functional
this information as required. the Principal Contractor as necessary. requirements of building regulations
during its construction.
On buildings within the scope of the During construction sufficient information • provide evidence of meeting the
new regulatory system for higher-risk (evidence) must be captured to show: requirements of the new building
buildings, it is proposed that the client is • how the building work itself conforms to control route throughout the design and
responsible for ensuring there are suitable the design that was approved, including construction and refurbishment of a
arrangements in place for the creation, any approved changes; and building
maintenance and management of the • how the building satisfies all the • identify, understand, manage and
golden thread. applicable functional requirements. mitigate building safety risks in order
to prevent or reduce the severity of the
Although the client will have a high-level It is proposed that the Principal Contractor consequences of fire spread or structural
of overall responsibility for ensuring will be specifically responsible for: collapse throughout the life cycle of a
the arrangements are in place, it is the • managing and updating the golden building
Principal Designer who will update and thread throughout the construction • be stored, managed, maintained and
manage the golden thread through the phase; retained in line with the golden thread
principles.
16

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

The information stored in the golden thread New Clients knowledge the higher-risk building,
will be reviewed and managed so that the It is proposed, where a person ceases to as built, complies with all applicable
information retained, at all times, achieves be the client in relation to the work, they requirements of the building regulations;
these purposes must, with 28 days, provide the new client • a statement, signed by both the client (or
with: someone on behalf of the client) and the
The golden thread covers both the • a copy of the golden thread information; relevant person, confirming that a copy
information and documents and the • information (including plans, drawings of the golden thread information and the
information management processes (or and other documents) which is sufficient key building information was provided
steps) used to support building safety. to detail the work comprised in the to the relevant person and the relevant
project; person has received them.
The golden thread information should be • a document explaining the arrangements • a description of the HRB work, that
stored as structured digital information. made under regulation 3 (suitable includes the:
arrangements) of the Dutyholder o location of the HRB created by the
The golden thread must: Regulations; work;
• be accurate and trusted; • notify the regulator of the date they o details of the intended use of the HRB
• facilitate residents feeling secure in their ceased to be the client and the name, and the intended use of each storey;
homes; address, telephone number and (if o height of, and number of storeys in,
• enable culture change; available) an email address of the new the HRB;
• be the single source of truth; client o provision to be made for the drainage
• be secure; of the HRB including any required
• drive improved accountability; Where the client dies, becomes insolvent precautions taken in the building
• be understandable and consistent; or is incapacitated, these requirements over a drain, sewer or disposal main
• be simple to access; apply to the administrator. to comply with applicable building
• be easily handed over and maintained regulations; and
over the entire lifetime of a building; and Notification of a Principal Contractor or o steps taken to comply with any local
• be relevant and proportionate. Principal Designer enactment that applies.
It is proposed that if, at any time after • a scale plan showing the size and
Planning statement building control approval for HRB work position of the building and its
The purpose of the proposed planning is granted the client appoints a Principal relationship to adjoining boundaries etc.;
statement is to ensure the BSR is aware of Contractor or Principal Designer, then the • such other plans that are necessary to
the planning status (if any) of the proposed client must send to the regulator a signed show that the HRB work complied with
building work. It is proposed that a notice that provides: applicable building reg requirements;
planning statement confirms that planning • the name and contract details of the PD • the following prescribed documents:
permission: or PC; and o the construction control plan and
• is not required, • confirmation that the PD or PC has confirmation that it has been followed;
• has been granted and specifies if any the necessary SKEB or organisational o the change control plan and
optional requirement applies to the work, capability. confirmation it has been followed;
and if so, which, or o the design and build approach
• has not yet been granted, and that the Completion notice document and confirmation it has
required information will be supplied It is proposed that after the HRB work is been followed;
before the end of the period of 28 days completed, and before or at the same time o a fire and emergency file;
beginning with the day after the date on as the completion certificate application • compliance declarations.
which planning permission is granted. for the work is submitted, the client, or
someone on behalf of the client must notify
Commencement notice the regulator in writing that the HRB work
It is proposed, that at least two working has been completed.
days before the day the HRB work
commences, the client, or someone on Completion certificate
behalf of the client, must give a notice to It is proposed that after completing HRB
the regulator setting out their intention to work a written application for a completion
commence the work. certificate must be made, signed by the
client or someone on behalf of the client,
and must include:
• the name and contact details of the
client;
• the name and contact details of the
principal duty holders;
• a statement confirming that the
completion certificate application is
made under the new regulations;
• a statement, signed by the client
or someone on behalf of the client,
confirming that to the best of the client’s
17

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Compliance declarations It is proposed that the information to be • the proposals adopted in designing
It is proposed that the following must handed over to the relevant person will be: for occupation of each part of the
be included in a completion certificate • the information required to be submitted proposed building to be completed to
application for an HRB: to the Building Safety Regulator in a ensure compliance with the applicable
• A statement, signed by the client or completion certificate application (the requirements of the building regulations;
someone on their behalf such as the prescribed documents); • the measures, strategies and policies it
company’s director, confirming that to • the relevant information and evidence is proposed the building owner should
the best of the client’s knowledge the required to support the prescribed adopt in order to manage and maintain
higher-risk building, as built, complies documents; each such part of the proposed building;
with all applicable requirements of the • the completion certificate issued by and,
building regulation. The client will not be the Building Safety Regulator under the • any assumptions made in those
able to delegate responsibility for signing building regulations; and, measures, strategies and proposals as to
the statement to an external organisation • any further information that is relevant to the intended occupiers of each such part
such as the Principal Designer or the ongoing safety of the building and is of the proposed building and their likely
Principal Contractor; not covered by the material above – this characteristics and behaviours, and the
• A compliance declaration signed by each could include documents/information intended management or maintenance of
Principal Designer involved in the project required to be submitted to the Building each such part of the proposed building.
at any stage with their contact details; Safety Regulator at building control
dates of appointment; and a statement approval stage, and information required Assessing completion certificate
confirming that they took all reasonable through the statutory change control applications
steps to fulfil their duties as a Principal process during the construction phase. As proposed and as should be the case
Designer under the proposals set out with building control approval applications
in the previous section on dutyholders; It is also proposed that the client and and change control applications, it is
and, relevant person must co-sign a statement expected that the BSR must also consult
• A compliance declaration signed by confirming that a copy of the design and relevant enforcing authorities, for example
each Principal Contractor involved in the construction golden thread information fire and rescue authorities.
project at any stage with their contact was provided to the relevant person, and
details; dates of appointment; and a the relevant person has received that In line with the approach taken for
statement confirming that they took all information. building control approval applications, it is
reasonable steps to fulfil their duties as a proposed that the BSR must not determine
Principal Contractor under the proposals Partial completion the completion certificate application
set out in the previous section on The government intends to permit partial before 15 working days after the date
dutyholders. completion for higher-risk buildings. on which the plans were provided to the
However the occupation of a higher-risk fire and rescue authority and sewerage
Golden thread information and key building in phases must never come at the undertaker has passed, or until both parties
building information expense of resident safety and it must not have provided a response (if sooner than
It is proposed that as part of the introduce greater risk than only allowing the 15 working days).
completion certificate application, the client occupation once all building work is
must hand over the golden thread to the complete. Before determining a completion certificate
relevant person. The relevant person will be application the BSR must arrange an
different depending on whether the building Section 76 of the Building Safety Act 2022 inspection of the completed work to
is in scope of the occupation regime. ensures that no residential unit within a assess whether the work complies with the
new higher-risk building can be occupied building regulations.
Every building in scope of the new regime without a relevant completion certificate,
to which Part 4 of the Building Safety Act as evidence that the building work in that
2022 will apply (multi-occupied high-rise part complies with building regulations’
residential buildings) will have a principal requirements. This will ensure that there
accountable person. The principal is a ‘hard stop’ for buildings occupied in
accountable person will be the relevant stages.
person.
Partial Completion Strategy
For buildings that are in scope of the It is proposed that where a dutyholder
design and construction regime but are intends to occupy a higher-risk building
not in scope of the occupation regime in phases, a partial completion strategy
(for instance, in-scope hospitals and care is provided at Gateway 2 to compel
homes), the Fire Safety Order and the dutyholders to think ahead to the safety
Housing Act 2004 will continue to regulate of residents in the occupied building
how standards are enforced to manage the right from the design stage. The Partial
overall safety of residents. Therefore, for Completion Strategy will need to explain
these buildings the relevant person will be the following:
the Responsible Person.
18

APS Briefing:
Building Safety Act 2022
Briefing Note 1 Overview

Construction products
The Building Safety Act 2022 creates powers to make regulations to:
• require construction products to be safe before they can be placed on the UK market; and
• create a statutory list of ‘safety critical’ construction product standards.

Secondary legislation, which will be subject to consultation in the Summer, will require construction products to be safe before they can be placed
on the UK market, minimising any risk to health and safety through their use.

The Government will work with industry to identify ‘safety critical’ construction products that could cause death or serious injury if they were to fail.
These will be required to perform to specific standards.

Bibliography Consultations
1. Building a Safer Future: Independent Review of Building Building Safety Act Secondary Legislation
Regulations and Fire Safety: Final Report https://assets. The Department of Levelling Up, Housing and Communities [DLUHC] are
publishing.service.gov.uk/government/uploads/system/ consulting on the requirements of the Building Safety Act 20222 that they
uploads/attachment_data/file/707785/Building_a_Safer_ propose to implement through secondary legislation. This consultation will
Future_-_web.pdf last for 12 weeks from 20 July 2022 to 12 October 2022.
2. Building Safety Act 2022 https://www.legislation.gov.uk/
ukpga/2022/30/contents/enacted DLUHC are not consulting on the draft regulations but on the policy and
3. Building Act 1984 https://www.legislation.gov.uk/ technical requirements that they propose to set in regulations. This is
ukpga/1984/55 the because the focus of the consultation is on getting feedback from
4. The Building Regulations 2010 https://www.legislation.gov.uk/ stakeholders on the policy and not on discussing the specific legal drafting of
uksi/2010/2214/contents/made the regulations.
5. The Architects Act 1997 https://www.legislation.gov.uk/
ukpga/1997/22/contents Readers of this guidance are encouraged to take part in the consultation
6. The Housing Act 1996 https://www.legislation.gov.uk/ details of which can be found using the links below.
ukpga/1996/52/contents
7. The Regulatory Reform (Fire Safety) Order 2005 https://www. Citizen space for all open building safety consultations
legislation.gov.uk/uksi/2005/1541/contents/made Building Safety Consultations -Citizen Space
8. Construction (Design and Management) Regulations 2015
https://www.legislation.gov.uk/uksi/2015/51/contents/made HTML versions (accessible versions)
9. Building Safety Consultations -Citizen Space Part 3 –Design and Construction –changes to the Building Regulations
https://consult.levellingup.gov.uk/building-safety- Implementing the new Building Control Regime for Higher-Risk buildings and
consultations/ wider changes to the Building Regulations for all buildings
10. Fees and Charges Consultation Part 4 –In occupation
https://consultations.hse.gov.uk/bsr/fees-and-charges-regs/ The In-occupation Regime for Occupied Higher-Risk Buildings

The Building Safety (Fees and Charges) Regulations 202[3] and


charging scheme
Further information
This government are also consultating on the Building Safety (Fees
and Charges) Regulations and an underpinning charging scheme.
The Building Safety Act 2022
The consultation will last for 10 weeks from the 1st August 2022 to 7th
https://www.legislation.gov.uk/ukpga/2022/30/contents/enacted
October 2022.

This practice note can be accessed in alternative About APS


formats by contacting APS
The Association for Project Safety [APS] is a
Copyright professional body dedicated to eliminating
The ownership of this material is asserted by the Association for deaths, reducing injury and tackling ill-health
Project Safety Ltd. Any infringements of copyright may be actionable associated with construction. APS aims
by APS. to improve, and promote excellence in,
professional practice in design and construction
Status of this guidance health & safety risk management, helping
The contents of this practice note are intended for information and everyone manage risk and implement building
general guidance only. If you need guidance on how to approach the regulations effectively and proportionately.
challenges associated with specific situations and projects, you should The association contributes to the national
seek advice from a suitably qualified person. debate on building and infrastructure safety,
regulation and legislation, providing training,
APS 5 New Mart Place @apstalk education and support and member networking
Edinburgh EH14 1RW opportunities. APS works with other bodies
T: 0131 442 6600 lnkedin.company/com/ and partners to improve – through good
E: info@aps.org.uk associationforprojectsafety design and throughout the life-cycle of projects
and buildings – health & safety for everyone
involved in construction and use.

You might also like