Risk Assessment

Assessment Type: Assessment Carried out by: Date of Assessment:


Project Title: Company:
References:

S# Hazard Who might be harmed & how S L Risk Rating Existing Control Measures S L Risk Rating Additional Control Measures
1. No fire extinguisher: - Materials burns incase of fire 3 1 3 - Need to ensure the
3
- Fire. - Workers burn in case of fire 3 9 - Fire Extinguisher need to be availability of proper
- Damage or loss the - Facility destruction incase of available as per fire prevention inspected fire
materials and fire. plan and as per civil defense extinguisher.
property. standard.
- In case of emergency
no response of first
line of defense.

2. Damage Extension: Injuures to workers 3 5 15 - Must to replace the damage 3 1 3 - Always as pre inspection
- Electric shock. Skin irritation extension immediately or rectify must be conducted by
- Fire. Burn injuries due to fire the damage one. maintenance team.
- Fluctuation. - Maintenance team to check
- Damage to the properly all the extensions.
materials - Always as pre inspection must be
conducted by maintenance
team.
-

4. Poor house keeping: Injuries to workers 3 2 6 Clean the studio B as soon as possible, 3 2 3 TBT must be connected before
- Fire Falling of tools and other materials can And keep all the material and others starting activity
-Sip trip and fall Uncollected / hit nearby workers things in a specific designated place. Safe Work Procedure should be
scattered rubbish Property damage discussed & shared,
Protruding object / materials at , The activity shall be monitored by
the site supervisor

5. Improper materials storage Injuries to workers 3 2 6 All materials shall be stacked properly as 3 1 3 TBT must be connected before
- Loose tools & materials Falling of tools and other materials can per standard starting activity
hit nearby workers Barricades shall be provided to storage of Safe Work Procedure should be
- Trippping hazard Property damage materials discussed & shared,
Access shall be open to ease incase of The activity shall be monitored by
emergency supervisor

6. Poor housekeeping Accident resulting injury to worker 3 6 Area shall be cleared after completion of 3 3 TBT must be connected before
2 1
-Fire Property Damage job starting activity
-Sip trip and fall Uncollected / All combustible materials shall be removed Safe Work Procedure should be
scattered rubbish to prevent fire hazard discussed & shared,
Protruding object / materials at All unwanted materials shall be dispose in The activity shall be monitored by
the site Skip bin supervisor

7. Poor cable Management Accident resulting injury to worker 4 8 All cable shall be routed in such a manner 4 4 TBT must be connected before
2 1
Electrocution Property Damage that could not pose slipping hazard starting activity
Sipping Hazard Skin irritation Trainied electrician shall be routing the Safe Work Procedure should be
Spark Burn cable and do electrical work discussed & shared,
All cable shall be free from damage The activity shall be monitored by
supervisor
8. Observed step ladder has been Unstable Ladder or lose Ladder condition 4 1 4 TBT must be connected before
3
tied with steel rope and binding may result into Falling of Ladder 4 12 Ladder shall be erected by trained starting activity
wire. resulting in personnel injuries employee Safe Work Procedure should be
Falling of Personnel Ladder shall be installed at 75 angle discussed & shared,
Falling of Materials 3 point contact shall be maintained while The activity shall be monitored by
working on ladder supervisor
9.
10.

11.

12.

All rights reserved. This document is the proprietary to MBC Studios. This document or part of it should ne be reproduced, copied, & published in any form by any means (electronic or mechanical), nor should the document be disclosed to external party without expressing written authorization from MBC Studio’ HSE department.