Professional Documents
Culture Documents
Critical Path Analysis
Critical Path Analysis
Critical Path Analysis
Worked example
The owners of Company XYZ have identified various activities required in the planning and
construction of a given project. These are shown in the table below:
1. Completion of a critical path diagram for Company XYZ showing the earliest starting
time (EST) and the latest finishing time (LFT) for each activity.
10 E6
2
10
A10 J7
17
5
17
10 F7
B9 4
10
0 24 K10 34
1 7 8
0 24 34
H6
D6
C4 I3
6 G12 18
3 6
9 21
= Critical path
EST = Earliest starting time
LFT = Latest finishing time
= A dummy
EST
Number
LFT
= Activity node
Note:
When calculating the EST of an activity, you work from left to right and you add the duration of
the next activity to the previous EST; always choose the largest number to add on if given a
choice.
When calculating the LFT of an activity, you work from right to left and you subtract the
duration from the previous LFT; always choose the largest number to subtract if given a
choice.
2. Identification of the critical path. The critical path is: activity A, a dummy, F, J, K.
Practice question
The table below shows the production process of a GPS device.
1. Complete the diagram below based on the information given in the table above, by
calculating the earliest starting time (EST) and latest finishing time (LST) for each
activity.
3. Calculate the free and total float for each activity in the table below.
I