This document provides a final account summary for the Nadeen School of Dilmunia project. It lists the contract sum as BD7,300,000 and shows amounts for various bill items including preliminaries, main building, external works, and provisional sums. The totals include the contract amount, variations, works executed, retention amounts, amounts from previous certificates, and the net claim of BD554,047.821 inclusive of VAT.
This document provides a final account summary for the Nadeen School of Dilmunia project. It lists the contract sum as BD7,300,000 and shows amounts for various bill items including preliminaries, main building, external works, and provisional sums. The totals include the contract amount, variations, works executed, retention amounts, amounts from previous certificates, and the net claim of BD554,047.821 inclusive of VAT.
This document provides a final account summary for the Nadeen School of Dilmunia project. It lists the contract sum as BD7,300,000 and shows amounts for various bill items including preliminaries, main building, external works, and provisional sums. The totals include the contract amount, variations, works executed, retention amounts, amounts from previous certificates, and the net claim of BD554,047.821 inclusive of VAT.
This document provides a final account summary for the Nadeen School of Dilmunia project. It lists the contract sum as BD7,300,000 and shows amounts for various bill items including preliminaries, main building, external works, and provisional sums. The totals include the contract amount, variations, works executed, retention amounts, amounts from previous certificates, and the net claim of BD554,047.821 inclusive of VAT.
Client : Ithmaar Development Company Supervising Consultant/Engineer : Mohamed Salahuddin Consulting Engineering Bureau (MSCEB) Quantity Surveyor : DJ Jones & Partners Contractor: Alghanah Group W.L.L.
Contract Sum: BD7,300,000.000 Period Ending:
S U M MA R Y
Contract Amount CLAIM AMOUNT ( BD )
Bill No. Bill Description BD Last Certified This Month Cumulative
Bill No 3.2 Preliminaries 332,919.900 317,378.380 15,541.520 332,919.900
Bill No 3.3 Main Building 5,592,382.024 5,494,603.399 97,778.625 5,592,382.024
Bill No 3.4 External Works 1,116,588.576 1,111,801.754 4,786.822 1,116,588.576
Bill No 3.5 Provisional Sums 98,542.500 93,417.500 5,125.000 98,542.500