P172 - Appendix 5 - Cost Summary June 2023
Original Contract Start Date : 16 January 2022
Original Contract Completion Date : 15 May 2023
Revised Contract Completion Date : 15 August 2023
Approved Variance to
Total Approved Unapproved Estimate to Complete Estimate @ Last Reported EAC As
S.NO Original Budget (Addition / Current Budget Earned To‐date Actual To‐date CPI To Date CPI @ Completion Previous Report
Description Budget Budget (ETC) Completion (EAC) Of May /2023
Omission) EAC
A B C=A+B D E =C+D F G H = F/G I J = ( G+ I) K=E/J L M = L‐J
A Revenue
Approved 189,650,000 ‐ 189,650,000 ‐ 189,650,000 96,721,500 96,721,500 92,928,500 189,650,000 1 189,650,000 ‐
UnBilled / Uncertified Revenue ‐ ‐
Total Revenue 189,650,000 ‐ 189,650,000 ‐ 189,650,000 96,721,500 189,650,000 189,650,000
B Indirect Cost
Labor 8,720,473 ‐ 8,720,473 8,720,473 6,698,739 12,942,513 0.52 4,137,563 17,080,076 0.51 17,080,076 0.00
Material 2,987,293 ‐ 2,987,293 2,987,293 2,068,932 3,669,205 0.56 520,964 4,190,169 0.71 4,190,169 0.00
Subcontracts 4,280,000 ‐ 4,280,000 4,280,000 4,274,250 4,045,195 1.06 371,474 4,416,669 0.97 4,416,669 ‐
Others 19,526,178 ‐ 19,526,178 19,526,178 6,001,890 8,057,464 0.74 2,736,161 10,793,624 1.81 14,564,257 3,770,633.06
Equipment 3,385,795 ‐ 3,385,795 3,385,795 3,047,216 5,891,987 0.52 3,715,068 9,607,054 0.35 5,836,421 (3,770,633.06)
Total Indirect 38,899,739 ‐ 38,899,739 ‐ 38,899,739 22,091,027 34,606,363 0.64 11,481,229 46,087,593 0.84 46,087,593 ‐
C Direct Cost
Labor 8,046,374 ‐ 8,046,374 8,046,374 4,730,954 17,308,505 0.27 3,604,643 20,913,148 0.38 17,374,436 (3,538,711.95)
Material 47,425,842 ‐ 47,425,842 47,425,842 11,602,792 6,518,867 1.78 37,947,504 44,466,370 1.07 44,466,370 (0.00)
Subcontracts 71,503,208 ‐ 71,503,208 71,503,208 19,620,125 12,583,940 1.56 46,325,410 58,909,350 1.21 62,448,062 3,538,711.95
Total Direct 126,975,424 ‐ 126,975,424 ‐ 126,975,424 35,953,871 36,411,312 0.99 87,877,556 124,288,868 1.02 124,288,868.31 (0.00)
D Other/Contingecies 2,339,740 2,339,740 2,339,740 ‐ ‐ ‐ 2,339,740 2,339,740 1.00 2,339,740 2,339,740
E Total Cost
Labor 16,766,847 ‐ 16,766,847 16,766,847 11,429,692 30,251,018 0.79 7,742,205 37,993,224 0.44 34,454,512 (3,538,711.95)
Material 50,413,135 ‐ 50,413,135 50,413,135 13,671,725 10,188,072 2.34 38,468,468 48,656,540 1.04 48,656,540 (0.00)
Subcontracts 75,783,208 ‐ 75,783,208 75,783,208 23,894,375 16,629,135 2.62 46,696,884 63,326,019 1.20 66,864,731 3,538,711.95
Others 19,526,178 ‐ 19,526,178 19,526,178 6,001,890 8,057,464 0.74 2,736,161 10,793,624 1.81 14,564,257 3,770,633.06
Equipment 3,385,795 ‐ 3,385,795 3,385,795 3,047,216 5,891,987 0.52 3,715,068 9,607,054 0.35 5,836,421 (3,770,633.06)
Contingency 2,339,740 ‐ 2,339,740 2,339,740 ‐ ‐ ‐ 2,339,740 2,339,740 1.00 2,339,740 ‐
Total Cost 168,214,904 ‐ 168,214,904 ‐ 168,214,904 58,044,898 71,017,675 0.82 101,698,526 172,716,202 0.97 172,716,202 (0.00)
F Margin (SR) 21,435,096 21,435,096 21,435,096 25,703,825 16,933,798 16,933,798
G Margin% 11.30% 11.30% 11.30% 26.58% 8.93% 8.93%
H Risks (SR)
I Opportunity (SR)
J Margin after Risks & Opportunity (SR) 21,435,096.1 0.0 21,435,096 0 21,435,096 0 25,703,825 0 0 16,933,798 0 16,933,798
K Margin % after Risks & Opportunity 11.30% 11.30% 11.30% 26.58% 8.93% 8.93%
Note:
Revenue amount is calculated based on the Approved/Submitted billing amount
Legend :
Variance to Last Month EAC
‐ Ve : Increase in Cost