(Topic 2) Project Cost Planning Part 1
(Topic 2) Project Cost Planning Part 1
• ASSESSMENTS (15%)
Test 2 : 10%
Case Study : 5%
ND03122022
innovative • entrepreneurial • global | www.utm.my
3
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
4
Quick Recall: Topic 1
Project Resource Planning
ND03122022
innovative • entrepreneurial • global | www.utm.my
5
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
6
Basic Principle of Project Cost
Types of Cost
1 2 3
Direct Cost Indirect Cost Total Cost
4
Profit
(Contractor’s Mark Up)
ND03122022
innovative • entrepreneurial • global | www.utm.my
7
Basic Principle of Project Cost Cont.
Types of Cost
1 • Cost or expenditure that directly
Direct Cost related to project or site
requirements:
1. Construction material
~90% 2. Hiring and purchasing of
machinery
3. Manpower/
labour cost
ND03122022
innovative • entrepreneurial • global | www.utm.my
8
Basic Principle of Project Cost Cont.
Types of Cost
• Indirectly 2 Examples:
related to Indirect Cost 1. Staff Salary
project or site 2. Office Rental
requirements 3. Office
• Also known as ~10% Equipment &
Overhead or Facility
Fixed Cost 4. Other related
• Daily, weekly, management
monthly or costs
annually
ND03122022
innovative • entrepreneurial • global | www.utm.my
9
Basic Principle of Project Cost Cont.
Types of Cost
3
Direct Cost Indirect Cost Total Cost
ND03122022
innovative • entrepreneurial • global | www.utm.my
10
Basic Principle of Project Cost Cont.
Types of Cost
Contract Value Client’s Liability
3
Total Cost Contractor’s
Liability
+
4
Profit
(Contractor’s Mark Up)
ND03122022
innovative • entrepreneurial • global | www.utm.my
11
Basic Principle of Project Cost
Monthly Cost vs. Time
Cost
Direct Cost
Indirect Cost
Time
ND03122022
innovative • entrepreneurial • global | www.utm.my
12
Basic Principle of Project Cost Cont.
Cumulative Cost vs. Time
Cost
Direct Cost
Indirect Cost
Time
ND03122022
innovative • entrepreneurial • global | www.utm.my
13
Basic Principle of Project Cost Cont.
Total Cumulative Cost vs. Time
Cost
Total Cost
S-Curve
Time
ND03122022
innovative • entrepreneurial • global | www.utm.my
14
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
15
Requirement of Project Cost
ND03122022
innovative • entrepreneurial • global | www.utm.my
16
Requirement of Project Cost Cont.
Cost Scheduling (Gantt Chart)
ND03122022
innovative • entrepreneurial • global | www.utm.my
17
Requirement of Project Cost Cont.
Cost Scheduling (Gantt Chart)
Duration (Month)
No. Activity Cost (RM)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 Site Preparation 1500 1500
2 Excavation 1200 1200
3 Formwork 4000 2000 2000
4 Basement Excavation 1200 1200
5 Basement Formwork 4600 2300 2300
6 Drainage 4000 2000 2000
7 Plumbing 5000 1000 1000 1500 1500
8 Superstructure 12000 4000 4000 4000
9 Roofing 4000 2000 2000
10 Brickworks 10000 2000 2000 2000 2000 2000
11 Utilities 2000 500 500 500 500
12 Flooring 5000 2000 1000 1000 1000
Total Monthly Cost 54500 1500 1200 3200 6300 4300 5000 5000 5500 3500 2000 4000 3000 3000 3500 2500 500 500
Cumulative Cost 1500 2700 5900 12200 16500 21500 26500 32000 35500 37500 41500 44500 47500 51000 53500 54000 54500
Monthly Duration 1 1 2 3 2 2 2 2 2 1 2 2 2 3 2 1 1
Cumulative Duration 1 2 4 7 9 11 13 15 17 18 20 22 24 27 29 30 31
ND03122022
innovative • entrepreneurial • global | www.utm.my
18
Requirement of Project Cost Cont.
S-Curve Cumulative Cost
ND03122022
innovative • entrepreneurial • global | www.utm.my
19
Requirement of Project Cost Cont.
Definition of S-Curve
• A tool or indicator to show project progress
• Both in terms of project duration and cost
• Use at project planning stage
• Delay tracking tool
• To be submitted to client to obtain the project
• Client may ask for both Gantt Chart and S-
Curve
• Client may reject poor S-Curve
ND03122022
innovative • entrepreneurial • global | www.utm.my
20
Requirement of Project Cost Cont.
Types of S-Curve
1 2
Physical Financial
Activity Duration/ Monthly Cost Distribution
Work Effort (Cumulative)
ND03122022
innovative • entrepreneurial • global | www.utm.my
21
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
22
Forecasting of Project Cashflow
Definition of Forecasting
• The projection of income and expense during
the life of the project
• Income = Inflow
• Outcome = Outflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
23
Forecasting of Project Cashflow Cont.
Importance of Forecasting
1 3
To ensure To be made
adequate cash available at
by the appropriate
contractor time
2
To convince the
lender or
financier
ND03122022
innovative • entrepreneurial • global | www.utm.my
24
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
25
Preparation of Cashflow Data
Information Gathering Data Analysis
(Cost Distribution) Cash In and Cash Out
Normally obtained from Data includes occurrence
project schedule duration or time
Step 2 Step 4
Step 1 Step 3
ND03122022
innovative • entrepreneurial • global | www.utm.my
26
Preparation of Cashflow Data Cont.
Typical Cashflow Graph
Maximum
cash
requirement
Cash out
Cost
(contractor
expenditure)
Cash in
(payment
received from
client)
Time
ND03122022
innovative • entrepreneurial • global | www.utm.my
27
Preparation of Cashflow Data Cont.
Typical Cashflow Graph
Maximum
cash
requirement
Cash out
Cost
(contractor
expenditure)
Cash in
(payment
received from
client)
Time
ND03122022
innovative • entrepreneurial • global | www.utm.my
28
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
29
Factors Affecting Cashflow
Payment
Frequency
Payment
Term
Delay
Factor
Front End
Loading
Contract
Value
Over-
payment
Profit
Margin
Work
Subcontracting
Retention
Fund
Advanced
Payment
ND03122022
innovative • entrepreneurial • global | www.utm.my
30
TOPIC OUTLINES
1 2
Quick Basic
Recall: Principle of
Topic 1 Project Cost
6 7 3
Factors Example Requirement
Affecting of Cashflow of Project
Cashflow Forecasting Cost
5 4
Preparation Forecasting
of Cashflow of Project
Data Cashflow
ND03122022
innovative • entrepreneurial • global | www.utm.my
31
Example of Cashflow
Forecasting
Based on the given table for culvert construction
planning, tender value and cost for each activity
were stated. Plan the cashflow prior to project
start where according to contract term, the
payment will be made two months after each
submission of payment claim at the end of the
month. Calculate the maximum cash requirement
to construct the project.
ND03122022
innovative • entrepreneurial • global | www.utm.my
32
Example of Cashflow Cont.
Forecasting
Activity Contract Cost Start Date Finish Date
Value (RM) (RM)
Excavation 17,000 15,000 1 May 31 May
Piling work 80,000 70,000 15 May 15 Jul
Pile cap 60,000 55,000 1 Jul 15 Aug
Culvert wall 70,000 75,000 1 Aug 30 Sept
Culvert cover 65,000 68,000 1 Sept 30 Oct
Backfill 25,000 16,000 15 Oct 15 Nov
Clearance 15,000 8,000 1 Nov 30 Nov
Total 332,000 307,000
ND03122022
innovative • entrepreneurial • global | www.utm.my
33
Example of Cashflow Cont.
Forecasting
Activity Value Cost Start Start May June July Aug Sept Oct Nov
Date Date
Excavation 17 15 1/5 31/5
ND03122022
innovative • entrepreneurial • global | www.utm.my
34
Example of Cashflow Cont.
Forecasting
Item (RM x 1000)/ April May June July Aug Sept Oct Nov Dis Jan Feb
Month Start Finish
1. Monthly Cost - 32.5 35 54.2 55.8 71.5 42 16
2. Cum. Monthly - 32.5 67.5 121.7 177.5 249 291 307 307 307 307
Cost (Cash Out)
3. Monthly Value - 37 40 60 55 67.5 45 27.5
ND03122022
innovative • entrepreneurial • global | www.utm.my
35
Example of Cashflow Cont.
Forecasting
ND03122022
innovative • entrepreneurial • global | www.utm.my
Thank You!