Project Name : PNP Building Project Manager : ET Academy Project Timespan : 5-May-22 - 6-Jun-22 (28)

Weekend : Friday only Show Progress : No

29-Apr-22 6-May-22 13-May-22 20-May-22 27-May-22 3-Jun-22


ID Work Breakdown Structure Planned Date Relationships Actual Date 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
Duration %
# W Type Activities Names Start Date End Date Ref. Activity Type Lag Start Date End Date 0 Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th Fr Sa Su Mo Tu We Th
1 1 W Earth work 5-May-22 () 8 5-May-22 14-May-22 51%
### ### T Excavation 5-May-22 () FS 5 5-May-22 10-May-22 70%
### ### T Backfilling 2 ↖ FS 3 40%
### ### T Soil Replacement 2 ↖ FS 3 30%
### ### W Concrete work 15-May-22 () 10 15-May-22 25-May-22 100%
### ### T PC footings 4 ↖ FS 5 20%
### ### T RC footings 6 ↖ FS 3 50%
### ### T Tie beams 6 ↖ FS 2 100%
### ### T Plain Concrete Under Slab on Grade 7 ↖ FS 1 100%
### ### T Slab on Grade 8 ↖ FS 3 100%
### ### W Thermal and moisture protection 25-May-22 () 1 25-May-22 25-May-22 0%
### ### T waterproofing for Footings 9 ↖ FS 1
### ### W Super Structure 11-May-22 () 13 11-May-22 25-May-22 0%
### ### T GR. Slab & Beams 2 ↖ FS 1
### ### T Columns 9 ↖ FS 1
### ### W Final Finishes 11-May-22 () 23 11-May-22 6-Jun-22 0%
### ### T Metal Doors 15 ↖ FS 3
### ### T Aluminum Louvers 2 ↖ FS 1
### ### T Metal Louvers 17 ↖ FS 3
### ### T Suspended Ceiling 15 ↖ FS 2
### ### T Painting 19 ↖ FS 3
### ### T Flooring Finishes 20 ↖ FS 3
### ### M Raised Floor 21 ↖ FS 1
### ### T Steel Steps 2 ↖ FS 3
() FS