Earth Work Qty
Name of Work:-C/O Motorable road from N.H. 05 to Village Runang km 0/000 to 5/955.
Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and
disposing of excavated earth with thelift upto 1.5 mtr. and a lead upto 20 mtr. As per technical per
1 specification clause 1603.1 40249.12 cubic 211.9 8528789.00
metre
Excavation in hilly area in Hard Rock requiring blasting by mechanical means, lift upto 1.5 mtr. And disposal of
excavated rock upto a lead 20 mtr. As per technical specification clause 1603.2 per
2 60373.67 cubic 525.90 31750513.00
metre
Construction of embankment with approved materials deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and compacted to meet requirement of table 300-2. per
2 11677.76 cubic 115.00 1342942.00
metre
per
Recovery for Jump work @ 1/10
2012.46 cubic 300 603738.00
metre
per
Recovery for Hard Rock @ 1/3
20124.56 cubic 300 6037368.00
metre
Total (A) 6641106.00
G.Total (A-B) ₹ 3,49,81,138.00
Says Rs in (lacs) ₹ 349.81
Cost Per km ₹ 58.74
Name of Work:-C/O Motorable road from N.H. 05 to Village Runang km 0/000 to 5/955.
SH : Formation Cutting
1
KM 0/00 to 5/955 20124.56 20124.56 60373.67 100622.79
TOTAL 11677.76