Professional Documents
Culture Documents
Sample Schedule
Sample Schedule
Sample Schedule
Actual Work
Remaining Work Page 1 of 3
Critical Remaining Work
CONSTRUCTION OF HAWIYAH STORAGE TANKS
Activity ID Activity Name Start Finish 2021 2022
June July August S October N D January F March April May
2 20 1 1 20 1 1 23 0 1 22 0 1 12 0 0 1 23 0 1 22 0 1 12 0 0 12 2 0 11 2 0 11 2 0 01 2 3 01 2
Nozzle - N14 Installation
Installa (Roof) 13-Mar-2022 A 20-Mar-2022 A
Testing 03-Mar-2022 A 23-Apr-2022
Vacuum Box Test 03-Mar-2022 A 08-Mar-2022 A
Tank Hydro Test 22-Mar-2022 A 23-Apr-2022
Coating 24-Apr-2022 21-May-2022
Tank External and Internal
In Coating 24-Apr-2022 21-May-2022
Utility / Fire Water Tank : 734-D-0047 06-Jul-2021 A 16-May-2022
Client Deliverables 06-Jul-2021 A 20-Apr-2022
Tank Bottom Assembly 08-Aug-2021 A 26-Apr-2022
Bottom Plate Installa
Installation 08-Aug-2021 A 03-Feb-2022 A
Drip Plate 21-Apr-2022 26-Apr-2022
Shell Assembly 05-Oct-2021 A 23-Feb-2022 A
Shell Course 1 Installation
Insta 05-Oct-2021 A 27-Nov-2021 A
Shell Course 2 Installation
Insta 27-Oct-2021 A 25-Nov-2021 A
Shell Course 3 Installation
Insta 27-Nov-2021 A 15-Dec-2021 A
Shell Course 4 Installation
Insta 16-Dec-2021 A 30-Dec-2021 A
Shell Course 5 Installation
Insta 01-Jan-2022 A 20-Jan-2022 A
Shell Course 6 Installation
Insta 09-Oct-2021 A 23-Feb-2022 A
Assembly and Welding of the Roof Frame and Decking 13-Nov-2021 A 13-Feb-2022 A
Roof Installation 13-Nov-2021 A 13-Feb-2022 A
Internal Piping and Related
Rel Items Installation 11-Jan-2022 A 20-Mar-2022 A
Sump Pit with Piping - N9 (Shell 1) 11-Jan-2022 A 17-Feb-2022 A
Gauge Hatch Piping - N13 (Roof) 06-Mar-2022 A 10-Mar-2022 A
Inlet Piping - N1 (She
(Shell 6) 06-Mar-2022 A 13-Mar-2022 A
FW Pump Test Piping
Pipin - N5 (Shell 6) 06-Mar-2022 A 13-Mar-2022 A
FW Outlet with Vortex
Vorte Breaker - N2 (Shell 1) 06-Mar-2022 A 20-Mar-2022 A
Ladder, Platforms and H Hand-Rails Installation 05-Apr-2022 A 25-Apr-2022
Spiral Stair Way and Ladder Installation 05-Apr-2022 A 24-Apr-2022
Walk Way and Platform
Platfo Installation 09-Apr-2022 A 25-Apr-2022
Hand-Rails Installation
Installati 11-Apr-2022 A 24-Apr-2022
Man Ways Installation 06-Mar-2022 A 23-Mar-2022 A
Man Way - M1 Instal
Installation (Shell 1) 06-Mar-2022 A 20-Mar-2022 A
Man Way - M2 Instal
Installation (Shell 1) 09-Mar-2022 A 23-Mar-2022 A
Man Way - M3 Installation
Instal (Roof) 06-Mar-2022 A 16-Mar-2022 A
Man Way - M4 Installation
Instal (Roof) 07-Mar-2022 A 17-Mar-2022 A
Nozzle Installation 06-Mar-2022 A 21-Mar-2022 A
Nozzle - N3 Installation
Installati (Shell 1) 06-Mar-2022 A 12-Mar-2022 A
Nozzle - N4 Installation
Installati (Shell 6) 06-Mar-2022 A 14-Mar-2022 A
Nozzle - N6 Installation
Installati (Shell 1) 09-Mar-2022 A 17-Mar-2022 A
Nozzle - N10 Installation
Installa (Shell 1) 13-Mar-2022 A 21-Mar-2022 A
Nozzle - N11 Installation
Installa (Shell 6) 07-Mar-2022 A 15-Mar-2022 A
Nozzle - N12 Installation
Installa (Shell 6) 08-Mar-2022 A 14-Mar-2022 A
Nozzle - N15 Installation
Installa (Shell 6) 09-Mar-2022 A 15-Mar-2022 A
Nozzle - N16 Installation
Installa (Shell 6) 10-Mar-2022 A 16-Mar-2022 A
Nozzle - N19 Installation
Installa (Shell 6) 12-Mar-2022 A 17-Mar-2022 A
Nozzle - N7 Installation
Installati (Roof) 13-Mar-2022 A 19-Mar-2022 A
Nozzle - N8 Installation
Installati (Roof) 09-Mar-2022 A 15-Mar-2022 A
Nozzle - N17 Installation
Installa (Roof) 10-Mar-2022 A 16-Mar-2022 A
Nozzle - N18 Installation
Installa (Roof) 12-Mar-2022 A 17-Mar-2022 A
Nozzle - N14 Installation
Installa (Roof) 13-Mar-2022 A 20-Mar-2022 A
Testing 03-Mar-2022 A 17-Apr-2022 A
Vacuum Box Test 03-Mar-2022 A 08-Mar-2022 A
Tank Hydro Test 22-Mar-2022 A 17-Apr-2022 A
Coating 19-Apr-2022 16-May-2022
Tank External and Internal
In Coating 19-Apr-2022 16-May-2022
Actual Work
Remaining Work Page 2 of 3
Critical Remaining Work
CONSTRUCTION OF HAWIYAH STORAGE TANKS
Activity ID Activity Name Start Finish 2021 2022
June July August S October N D January F March April May
2 20 1 1 20 1 1 23 0 1 22 0 1 12 0 0 1 23 0 1 22 0 1 12 0 0 12 2 0 11 2 0 11 2 0 01 2 3 01 2
Handover 17-Mar-2022 A 21-May-2022
Utility / Fire Water Tank : 734-D-0040 19-Mar-2022 A 21-May-2022
Utility / Fire Water Tank : 734-D-0047 17-Mar-2022 A 16-May-2022
Actual Work
Remaining Work Page 3 of 3
Critical Remaining Work