Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

P-3 CELL

INTERNSHIP REPORT
By
Aditya Deokate

Under the guidance


Of
Ms. Archana Sonawane
(ME Department Head)

DEPARTMENT OF MANUFACTURING ENGINEERING


ENDURANCE TECHNOLOGIES PVT. LTD.
AURANGABAD
2022-23

1
P-3 CELL

CERTIFICATE

MGM’s JAWAHARLAL NEHRU ENGINEERING COLLAGE,


AURANGABAD
DEPARTMENT OF MECHANICAL ENGINEERING

This is to certify that Internship Report submitted by Aditya Deokate


having PRN (2021321612014) is his work during the internship at Endurance
Technologies Pvt. Ltd. and submitted in partial fulfillment of the requirements for
the award of the degree of Bachelor of Technology in MECHANICAL
ENGINEERING of Dr. Babasaheb Ambedkar Technological University, Loner
during the academic year 2022-23.

Netaji Pawar
Mfg. Dept.

2
P-3 CELL

Acknowledgement

I am very thankful to Endurance Technologies Pvt. Ltd. For


giving me the opportunity to undertake my summer training at their
prestigious plant. It was a very good learning experience for me to have
worked at this site. An Internship is a golden opportunity for learning and
self-development. I am indeed a verylucky and honored to get chance to
complete this in Endurance Technologies Pvt. Ltd. where I have so
many wonderful industry managers, staff and guide who led me through
in completion of this internship.
I would like to give my heartfelt thanks to HR manager Mr. Vishal
Dalvi who heartily welcome me for the internship. Mrs. Archana
Sonawane (ME Dept. Head) who guided and encourage me all through
summer training and imported in-depth knowledge of the program and
guided me whenever I needed, also, I would like to thank Mr. P.S.
Maslekar ( Plant Head) and all the department heads of Endurance for
giving their precious time and valuable guidance during my internship
program. I am already thankful to Dr. M S Kadam head of the department
mechanical engineering of MGMs JNEC Aurangabad. I extend my
grateful thanks to Mr. Khedekar and Mr. Sable who took time to hear,
guide and keep me on the correct path. I would like to thank to our beloved
Principal, Dr. H. H. Shinde for his efforts and help provided to me get
such an excellent opportunity. There were so many who shared valuable
information directly or indirectly that helped me in the successful
completion of the activity. The data collected from all the people from
industry have indirectly played a very important role in the fulfilment of
the study.
Thank you.

ADITYA DEOKATE

3
P-3 CELL

INDEX

Sr.no. Topic Page no


1. About Endurance Technologies 05
2. Introduction of various departments 06
3. Information of Manufacturing Department 07
4. Problem Statement 08
5. Introduction 08
6. Cell Layout 09
7. Operation Sequence and tool specifications 10
8. Dent Damage Study 12
9. Analysis 20

Table Index

SR. No. Topic Page no.

1 Operations Sequence 10

2 Operation wise Tool Specifications 10

3 Dent Mark summary 13-16

4 Burr Locations summary 17-18

4
P-3 CELL

1. About Endurance Technologies

Endurance Technologies Pvt. Ltd. is an Indian multinational company that


specializes in the manufacturing of automobile component system. The company
was founded in 1983 by Anurag Jain and its headquarters is located in Aurangabad,
Maharashtra India. Endurance Technologies has a global presence with 25
manufacturing plants spread across 10 countries. Some of its key products includes
suspension system, braking system in Pune, Maharashtra India by Mr. Anurag Jain.
Today the company has the global foot print, with operations in 9 countries across 3
continents.
Endurance Technologies produces a wide range of components and systems
for the automotive industries, including suspension system, brakes, transmission,
engine components and Aluminium castings. The company’s products are used in
two wheelers, three wheelers passenger cars and commercial vehicles.
Endurance Technologies is known for its focus on innovation and quality. The
company has several research and development centres in India and Europe, where
it develops advance technologies and designs products that meet the highest
standards of performance and safety.
With over 26000 employees and a customer base that includes some of the
world’s leading automakers, Endurance Technologies is one of the most trusted
names of the automotive industry. The company is committed to sustainability and
social responsibility, and it has received several awards and recognition for its efforts
in this areas.

5
P-3 CELL

2. Introduction of Departments

Endurance Technologies casting plant consists of various department.


Detail information of these departments is as given below.

1. Human Resources Department: The HR Department is responsible for


managing of the work force of the company. This department handle
recruiting and hiring, employee training and development, compensation and
benefits and employee relations. They also ensure compliance with labour
laws and regulations and maintain employee recorded.
2. Research and Development Department: The R&D department is responsible
for developing new products or services and improving existing ones. This
department usually works with engineers, scientist and other expert to conduct
research and experimentation. They also work with other departments such as
production and marketing to ensure that new product meet customer needs
and are commercially viable.
3. Production department: The production department responsible for the actual
production of goods and services. This departments oversees the assembly
line, machinery and worker, ensuring that everything is running smoothly and
efficiently. There main goal is to maximize the output of goods and services
while minimizing cost and waste. In order to achieve this goal, they also work
closely with other department such as procurement, supply chain
management, and quality control to ensure that all the necessary resources are
available.
4. Quality department: The quality department is responsible for ensuring that
all the goods produced by the company meet the required standards and are of
the high quality. They develop and implement quality control systems,
perform inspections and audits and conduct tests and analysis to identify any
defects or issues with the products.

6
P-3 CELL

3. Manufacturing Department

Manufacturing department in companies are responsible for the production of


goods or products that the company sells. These departments are often the backbone
of a company’s operations and play a critical role in the success of the company.
The manufacturing department typically contains a range of skilled personnel,
including engineers, technicians, production supervisors and workers. The
department is responsible for various tasks, including:
1. Production planning: the manufacturing department is responsible for
planning the production process including scheduling of resources, production
time and materials. This includes determine the required production capacity,
estimating the raw materials requirements and making sure that the production
process runs smoothly.
2. Production process improvement: The manufacturing department is
responsible for continuously improving the production process by making it
more efficient, reducing cost, and increasing productivity. They analyse the
production data, identify inefficiencies and implement solutions to improve
the process.
3. Maintenance and Repair: The manufacturing department is responsible
ensuring that the machinery and equipment are well maintained, repaired, and
up-to-date. They conduct regular maintenance checks, set up preventive
maintenance programs and keep records of all repairs and maintenance.

7
P-3 CELL

4. Problem Statement
Dent marks are observed on casting of P-3 cell i.e. CT 100 crankcase casting.
The castings are made of aluminium alloy material. Various processes such as
Milling, Drilling & Tapping, Bore finishing are performed on the casting on CNC
Milling machines. During this processes the face resting on the resting pad is prone
to dent marks. These dent marks on crankcase are undesirable as they may later
create a problem of oil leakage or oil starvation. Thus this increases the rejection of
the cell which in turn increases the revenue losses. Along with dent damage, issue
of handling damage also needs to be reduced.

5. Introduction
When machining brass, copper or aluminium alloys, it is noticed that the part
has dents when it was clamped during the CNC milling process. Dent marks are the
small indentions on the machining surface. Dent marks occur due to various reasons
such as high clamping pressure, remains of burr on fixture, ineffective flushing by
coolant, etc. Generally, it is observed that when burr remains on fixture and new job
is clamped on the fixture then due to the clamping force the burr trapped between
resting pad and resting face creates a dent mark on the resting face of the casting.
Dent marks on aluminium alloy die casting are smooth dents on most of the thick
surface of the die casting. This increase the rejection of material. The root cause
being the burr remaining on fixture or on the casting increases the chances of dent
mark. Thus, reducing the amount of burr remaining on fixture or the casting can
significantly reduce the chances of dent mark. This can be achieved by regularly
cleaning the fixture, considering all design attributes of fixture design and effective
flushing of the casting during the machining process which will ensure that
maximum burr is flushed out with the coolant. Fixture design attributes such resting
pads, dowel, supporting blocks design play important role. Hence to reduce dent
mark on casting, a complete root cause analysis is needed to be done. This project
consists of various studies which helped to identify contribution of various factors
in dent damage study.

8
P-3 CELL

6. Machines And Layouts


P-3 cell consists of total 14 Machines which includes 11 VMC, 2 HMC and 1 for
washing. Cell layout is as given below:
P-3 Cell Layout CT 100 CC

VMC=11,
Rough Rough
HMC=2, Full Finish & R-Face
Boring Boring
Washing=1
Total=
14

1m16s 2m42s 3m2s


63/hr 35/hr 34/hr

M0425 M0487 M0488


← OP40 RH & LH OP20 RH ← OP10 RH

Cell-A
↑ ↙ ←

M4022
M490 M489
OP30 RH & LH ← OP20 LH ← OP10 LH
Makino

3m44s 2m19s 2m16s


63/hr 35/hr 34/hr
Conveyer belt

1m16s 2m19s 2m32s


70/hr 36/hr 34/hr

M4011 M0434 M4085


← OP40 RH & LH OP20 RH ← OP10 RH

↑ ↙ ← Cell-B
M4023
M0474 M0486
OP30 RH & LH ← OP20 LH ← OP10 LH
Makino
1m42s 2m26s 3m6s
70/hr 36/hr 34/hr

Final
→ Washing → Gauging → Inspection

Fig 1. P-3 Cell Layout

9
P-3 CELL

7. Operation Sequence And Tools


The casting undergoes various processes. These processes are grouped into set of
operations as given below.
Operations for RH Name Operations for LH Name
OP-10 OP-10
Rough Boring Rough Boring
OP-20 OP-20
OP-30 Full finishing OP-30 Full finishing
OP-40 R- Face OP-40 R- Face
Table 1. Operations Sequence
Specification of Tools required for various processes in each operations are as given
below:
OP-10
L.H RH
D11.5 PCD Reamer D20*50FL*100*SHD20 End Mill
PCD Reamer D8*FL35*OAL80 Drill D10.5*11.1
PCD Reamer D14 M12*1.5 Tap
PSSC Drill D5.48*21Sl*105 OAL NTC PCD Reamer D8*FL35*OAL80
HSSE Roll Tap M6*1p 6HSH6 SQ4.9 PCD Reamer D14
OL80
D20*50FL*100*SHD20 End Mill SC Drill D5.48*D55FL*110 OAL
D51.5*15.35L*80 HSSE Roll Tap M6*1P 6H SH6
SQ4.9 OL80
- PSSC Drill D7.35*42FL*80 OAL*
SH8 TC
- HSSE Roll Tap M8*1.25 6H SH8
SQ6.2 OL90
- D51.5*13.8SL*80
Table 2.1. OP-10 Tool Specs.

10
P-3 CELL

OP-20

R.H L.H

PSSC Drill D7.35*43FL*80 OAL*SH8 TC HSS Drill D4*85FL*136 OAL

HSSE Roll Tap M8*1.25 6H SH8 SQ6.2 OL90 SC Drill D5.48*D55FL*110 OAL

D20*50FL*100*SHD20 End Mill D9.4*D20 SF

D8*D13 Hole Mill HSS Roll Tap M10*1.25P 6H SH7 SQ5.5


OL100
SC Drill D5.48/*D55FL*110 OAL HSSE Roll Tap M6*1P 6H SH6 SQ4.9 OL80

HSSE Roll Tap M6*1P 6H SH6 SQ4.9 OL80 -

D12 CHMFR Tool -

Table 2.2. OP-20 Tool Specs.

OP-30 OP-40
D100 Milling Cutter PCD Reamer D36*22SL/D41*110 OAL SHK D20
PSSC Drill D7.35*25SL*D9*40FL*100 D52 P6 Remax Head
NTC
PCD Reamer D10H8 SH10 OAL95 PCD Reamer D8*15 BLA LEN*35FL*80
HSSE Roll Tap M8*1025 6H SH8 SQ6.2 D4 Identification Drill
OL90
SC Drill D5.48*D55FL*110 OAL HSSE PCD Reamer D16H8 * 180 OAL Shank DAH81
Roll Tap M6*1P 6H SH6 SQ4.9 OL80
D12 CHFR Tool PCD Reamer D13*D32*D40
- D52 H7 Remax Head
- PCD Reamer D28 P6* 40FL *OAL100*SH20
- PCD Reamer D8*14/D13*16/D22*OAL
125SHD20
- PCD Reamer D13*D24*D32*D40
- PCD Reamer D108.0H8*5.5SL*150 *96OAL Z4
- Reamer PCD D10 H8 FL15 SH D12-OAL 100
Table 2.3. OP-30 & OP-40 Tool Specs.

11
P-3 CELL

8. Dent Damage Study


To locate position of the dent mark on the job, a coordinate system was created
as shown below. This coordinate system helped to identify the position of dent.

1 1 2

Fig 2.1. LH P- Face Fig 2.2. RH P- Face

2 3
1 4
A

Fig 2.3. LH Q- Face Fig 2.4. RH Q- Face

12
P-3 CELL

8.1. Operation wise Dent Mark tracking:


To identify the amount of dents contributed by each operation we conducted
a operation wise study. In this 50 jobs each for all operations were observed and
location of dent marks was traced for both LH and RH. During this process it was
observed that OP-20 and OP-40 were the major contributor and generally dents
occurred on P-face. Table shows dent marks contributed by each operations.
Date: Part: Crankcase RH
Quantity.: 50 jobs each Model: CT100 ( A-CELL)
OP-10 OP-20 OP-30 OP-40 WASH.T FINAL INSP. TOTAL
A1 - - - - - - -
A2 - - - - - 2 2
A3 - - - - - - -
A4 - 1 - 1 - 1 3
B1 - - 1 - - - 1
B2 - - - - - - -
B3 - - - - - - -
B4 - - - - - - -
C1 - - - 1 - - 1
C2 - - - - - - -
C3 - - - - - - -
C4 - 1 1 2 - 2 6
D1 - - - - 1 1
D2 - - - - - 2 2
D3 - - - - - - -
D4 - - - - - - -
E1 - 1 - - - - 1
E2 - 1 - - - - 1
E3 - - - - - -
E4 - - - - -
F1 - - - - - - -
F2 - - - - - - -
F3 - - - - - - -
F4 - - - - - - -
G1 - - - - - 1 1
G2 - - - - - - -
G3 - - - - - - -
G4 - - - - - - -
H1 2 - - - - - 2
H2 - - - - - - -
H3 - - - - - - -
H4 1 - - - - - 1
TOTAL 3 4 2 4 - 9 -
Table 3.1. Operation wise Dent Mark A-Cell (RH)

13
P-3 CELL

Date: Part: CT100 Crankcase RH


Quantity.: 50 jobs each Model: CT100 ( B-CELL)
CT100 Crankcase DDS RH Summary (B-Cell)
OP-10 OP-20 OP-30 OP-40 WASH.T TOTAL
A1 - - - - - -
A2 - - - - - -
A3 - - - - - -
A4 - - - - - -
B1 - - - - - -
B2 - - - - - -
B3 - - - - - -
B4 - - - - - -
C1 - - 1 - - 1
C2 - - - - - -
C3 - - - - - -
C4 - - - - - -
D1 - - - - -
D2 - 1 - 1 - 2
D3 - - - - - -
D4 - - - - - -

E1 - - - - - -
E2 - - - - - -
E3 - - - - - -
E4 - - - -
F1 - - - - - -
F2 - - - - - -
F3 - - - - - -
F4 - - - - - -
G1 1 - - - - 1
G2 - - - - - -
G3 - - - - - -
G4 - - - - - -
H1 - - - - - -
H2 - - - - - -
H3 - - - - - -
H4 - - - - - -
TOTAL 1 1 1 1 -
Table 3.2. Operation wise Dent Mark B-Cell (RH)

14
P-3 CELL

Date: Part: CT100 Crankcase LH


Qut.: 50 jobs each Model: CT100 ( A-CELL)
CT100 Crankcase DDS LH Summary
OP-10 OP-20 OP-30 OP-40 WASHING FINAL INSP. TOTAL
A1 - - - - - - -
A2 - - - - - - -
A3 - 1 - - - - 1
A4 - - - - - - -
B1 - - - - - - -
B2 - - - - - - -
B3 - - - - - - -
B4 - - 1 - - - 1
C1 - 1 1 - - - 2
C2 - - - - - - -
C3 - - - - - - -
C4 - - 2 - - 2
D1 - - - - - -
D2 - - - - - - -
D3 - - - - - - -
D4 - - - 2 - - 2

E1 - - - - - - -
E2 - - - - - - -
E3 - - - - - - -
E4 1 - - - - 1
F1 - - - - - 1 1
F2 - - - - - - -
F3 - - - - - - -
F4 - - - - - 1 1
G1 - - - - - - -
G2 - - - - - - -
G3 - - - - - - -
G4 - - - - - - -
H1 - - - - - - -
H2 - - - - - - -
H3 - - - - - - -
H4 - - - - - - -
TOTAL 1 2 2 4 - 2 11
Table 3.3. Operation wise Dent Mark A-Cell (LH)

15
P-3 CELL

Date: Part: CT100 Crankcase LH


Qut.: 50 jobs each Model: CT100 ( B-CELL)
CT100 Crankcase DDS LH Summary
OP-10 OP-20 OP-30 OP-40 WASHING TOTAL
A1 - - - - - -
A2 - - - - - -
A3 - - - 1 - 1
A4 - - - - - -
B1 - - - - - -
B2 - - - - - -
B3 - - - - - -
B4 - - 1 - - 1
C1 - 1 - - - 1
C2 - - - - - -
C3 - - - - - -
C4 - - - - - -
D1 - - - - - -
D2 - - - - - -
D3 - - - 1 - 1
D4 - - - - - -

E1 - - - - - -
E2 - - - - - -
E3 - - - - - -
E4 - - - - - -
F1 - - - - - -
F2 - - - - - -
F3 - - - - - -
F4 - - - - - -
G1 - - - - - -
G2 - - - - - -
G3 - - - - - -
G4 - - - - - -
H1 - - - - - -
H2 1 - - - - 1
H3 - - - - - -
H4 - - - - - -
TOTAL 1 1 1 2 - 5
Table 3.4. Operation wise Dent Mark B-Cell (LH)

16
P-3 CELL

8.2. Burr Trapping Location study:


The main reason for dent marks was the presence of burr on fixture. To
eliminate this burr it was important to ensure that no burr remains in the pockets,
drill holes, dowels, etc. which in turn remained on fixture resting pads. A study was
conducted to identify burr trapping locations of all operations for both LH and RH.
50 jobs of each machine were observed. This helped to identify the highlight
locations in which burr was trapping. The highlight locations of each operations are
given in table.
Date: Part: CT100 Crankcase LH
Qut.: 50 jobs each Model: CT100 ( A&B-CELL)
OP-10 OP-20 OP-30 OP-40 WASHING FINAL INSP.
A1 - - - - - -
A2 - - - - - -
A3 - - - - - -
A4 - - - - - -
B1 - - - - - -
B2 30 - - - - -
B3 - - - - - -
B4 37 - - - - -
C1 45 - - - - -
C2 - - - - - -
C3 - - - - - -
C4 40 - - - - -
D1 - - - - -
D2 43 - - - - -
D3 22 - - - - -
D4 20 - - - - -
E1 - - - - - -
E2 - - - - - -
E3 - 32 - - - -
E4 - - - - -
F1 - - - - - -
F2 - - - - - -
F3 - - - - - -
F4 - - - - - -
G1 - - - - - -
G2 - - - - - -
G3 - - - - - -
G4 - - - - - -
H1 - - - - - -
H2 - - - - - -
H3 - - - - - -
H4 - - - - - -
TOTAL 237 32 0 0 0 0

Table 4.1. Burr Trapping Study (LH)

17
P-3 CELL

Date: Part: CT100 Crankcase RH


Qut.: 50 jobs each Model: CT100 ( A&B-CELL)
OP-10 OP-20 OP-30 OP-40 WASH.T FINAL INSP.
A1 - - - - - -
A3 - - - - - -
A4 - - - - - -
B1 25 - - - - -
B2 - - - - - -
B3 - - - - - -
B4 - - - - - -
C1 - - - - - -
C2 - - - - - -
C3 - - - - - -
C4 18 - - - - -
D1 - - - - - -
D2 - - - - - -
D3 - - - - - -
D4 - - - - - -

E1 - 15 - - - -
E2 - 22 - - - -
E3 - - - - - -
E4 - - - - - -
F1 - - - - - -
F2 - - - - - -
F3 - - - - - -
F4 - - - - - -
G1 - - - - - -
G2 - - - - - -
G3 - - - - - -
G4 - - - - - -
H1 - - - - - -
H2 - - - - - -
H3 - 25 - - - -
H4 - - - - - -
TOTAL 43 62 0 0 0 0

Table 4.2. Burr Trapping Study (RH)

18
P-3 CELL

8.3. Clamps and Resting Pad Location:

Fig 3.1. L.H. Resting Pads location summary

Fig 3.2. R.H. Resting Pads location summary

19
P-3 CELL

9. ANALYSIS

A set of processes were followed in order to complete the Dent Mark Study.
This included dent mark position identifying, which helped to find the major
contributing operation. Then burr trapping study was conducted to identify
the locations at which burr/chips were remaining after each operation.
Followed by this clamping and resting locations were traced. It was found that
the location’s at which burr was trapping, dent marks generally occurredat the
same milling face locations. This included various drill holes and dowel holes
near the clamping and resting pad locations.
Based on daily inspection data, the dent damage daily trend was observed.
This included data from 17th March to 30th April. The results came out are
summarized below.

P-3 Cell Dent Mark Summary

12.00
11.08

10.00 9.58
8.76
8.41 8.42
8.02
8.00 7.67
7.10
6.65 6.68
6.06
6.00 5.51
5.21
4.94
4.73 4.78 4.56 4.69
4.42 4.25
4.14
3.77 3.81
4.00 3.56 3.53
3.07 3.23
2.83 2.74 3.00
2.71
2.20 2.33
1.91
2.00
1.10

0.00 0.00 0.00 0.000.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00

Percentage

Fig 4. DDS Summary

20

You might also like