Doc. No.: 2957080037 Rev.

No: 02/02-23

Job Completion Report


This Form is for Instrumentation Department to report Work Completion & only can be filled after job is completed.
Job Number Complaint Service
☐ ☒
To be filled by the Work Team Lead
Mr. Irfan/ Mr. Amir Baig Dandot Cement Factory
Client Name Site name
Dandot Cement Factory, Khewra 14-04-23 To 17-04-23
Client Address Inspection Date
Mr. Irfan/Mr. Amir Baig Shahid, Ammar, Shehzad
Work Site Inspected By Work Team
Brief Description of All Work Completed
• AC 200KV Voltage Withstand Test of 132kv Transformer for 60 Sec.

Comment Section for Customer


Would you like to use our Services again? ☒YES ☐NO
Have all issues been resolved to your complete satisfaction? ☒YES ☐NO
If NO, Explain?

Additional Comments or Suggestions:

Overall Rating: ☆☆☆☆☆


☐Excellent ☐Very Good ☒Satisfactory ☐Needs improvement ☐Unsatisfactory

Mr. Shahid 14-04-23 to 17-04-23

Application Engr. Name Application Engr. Signature Date

Mr. Irfan/ Mr. Amir Baig 14-04-23 to 17-04-23

Client Representative Client Signature/Stamp Date