Estimasi Proyek KIMKO (DT R.

10)
RAB
Target(Bulanan) 20,000 Ton
Harga/Ton 250 Rupiah
Lokasi Kerja PJP
Jarak 58 Kilometer
Jam Kerja Efektif (Double Shift) 20 Jam
Jumlah DT 10 ea
Muatan DT/Rit 25 Ton
Target Ritase/Hari 4 Rit
Target Angkut/Hari 1 DT 100 Ton
Target Angkut/Hari 10 DT 1,000 Ton
Efektif hari kerja 20 hari
Total 1 DT / efektif hari kerja 2,000 ton
Total 10 DT / efektif hari kerja 20,000 ton
Grand Total Omset 290,000,000 Rupiah

Biaya Operasional Per Bulan


Sewa Unit
Rate unit LV 20,000,000
Rate 1 unit 20,000,000
Grand Total Driver Premi Rp 20,000,000.00
Driver Premi
Jumlah Driver (5 DT)
Premi 1 Driver Per Ritase
Premi 10 Driver 40 Ritase per hari Rp -
Total premi 20 hari kerja Rp -
Grand Total Driver Premi Rp -
Personnel Basic & meals
Jumlah Personnel 6
Gaji Foreman 2 person Rp 8,000,000.00
Gaji Helper Mekanik 1pax
Gaji Cheker 1pax
Gaji Wakar 1pax
Grand Total Personnel Basic Rp 8,000,000.00
Uang Makan all in 1pax Rp 20,000.00
Uang Makan 6 Personnel Rp 10,800,000.00

Grand Total Meals Rp 10,800,000.00


Fuel Consumption Liter Harga Solar Rp 9,700.00
1 LV full tank 75 727,500
Pemakaian Solar LV /Hari 35 Rp 339,500.00
Pemakaian Solar LV 30 hari Rp 10,185,000.00
Grand Total Fuel Rp 10,185,000.00
Kas Site Project Kimko
Biaya Tak Terduga 15,000,000
Grand Total Maintenance Rp 15,000,000.00
Grand Total Omset Rp 290,000,000.00
Grand Total OPS Rp 63,985,000.00
Profit (Omset - Cost) Rp 226,015,000.00