Professional Documents
Culture Documents
Typd. Notes
Typd. Notes
Claimants operate a Sponge Iron and Hot Rolled Coil Plant in Dalvi, Raigarh –
Maharashtra.
For Sponge Iron, the basic ingredient of Hot Rolled Coil Plant, the Claimant
required natural gas in large quantity.
Accordingly, Claimant entered into a contract with GAIL for continuous supply of
gas on 10.09.1991.
Gas was to be supplied as per requirement subject to a maximum of 1.00 MSCM
Cl. 5 per day, provided that during the first year of gas supply, the Claimant would give
a quarterly forecast of the quantity of gas required for each one month in advance.
While agreed quantity of gas was not supplied, GAIL has raised invoices for fixed
transportation charges under both the above contracts.
Claimant claims to have made several representations for this including one dt.
05.06.2002 which was given an evasive reply dt. 15.07.2002 by the Respondent.
It said that: b/w April 1995 to July 2003, Claimants paid Rs. 58, 70, 22, 196 by
way of Fixed Transportation costs and also that the Respondent had recovered its
cost of laying the pipelines.
Summary of SoD:
Claims are barred by limitation and not arbitrable.
Post signature of Supplementary Agreement (30.03.98) all disputes deemed
to have been waived.
Supply started in 1994, Claimant raised disputes relating to collection of
excess transportation charges only in 2000 (any claims prior to 3 years if
the date of commencement of arbitration are barred by limitation).
Parties agreed for fixed transportation charges under the 1998 contract in
place of a variable charge under the 1991 contract, therefore collection of
the same is lawful.
Claimant entered into the Tripartite Agreement after fully knowing the gas
supply position of India.
GAIL has made huge investments for construction and maintenance of
pipeline system.
Pg. 7 All consumers were conscious of the short supply of gas and entered into contracts
OMP/PD
with negotiations and full knowledge of government control, regulation, and supply
position.
The Claimant entered the first agreement + second agreement within the
knowledge of the claimant that natural gas is a scarce resource, hence gas is
allocated by Gas Linkage Committee (GLC) which allocates gas out of projected
availability.
Claimants are obliged to pay the agreed fixed transportation charges of Rs. 38, 67,
Pg. 8 600 p.m.
OMP/PD
Also, 80% of maximum quantity agreed was always supplied. (Ann A of SOD)
Does the Respondent prove that under terms of the Contract, the extent of supply
to the Claimant of gas was dependant upon the availability of gas at the material
time as well as upon direction of the GoI at that point of time.
Issues 2&3 were decided in favour of GAIL on the basis that in view of the
Government’s policy, GAIL was justified in not supplying the contracted quantity
of gas to the Claimant.
The force majeure clause was also attracted in favour of the respondent.
However,
Issues no. 4&5 where decided against GAIL by ordering refund of fixed
transportation charges on account of short supply of gas.
The arbitral tribunal further found that Article 10 does not exempt the claimant
from its performance.
However interpreted article 4.03 (available at page 98 of OMP/PD) contrary to its
plain language on ‘business efficacy’ and ‘partial failure of consideration.’
Rule of business efficacy cannot be pressed into service to rewrite the clauses of a
contract.
The theory of Partial failure of consideration has also been invoked without any
basis.
Fixed monthly transportation/service charge is that all the costs above must be
paid for even if pipeline throughout is zero. The transportation charges and
monthly service charges are intended to recoup the transaction cost.
Respondent after having used the supplied gas for 10 years being aware of the gas
market in India, has allegedly raised the issue of fixed transportation costs
charged.
Refund: 14.67 crores owing to reduction in supply of gas and its proportionate
impact on transportation/service charges.
Issue 6: claimant not estopped from claiming a proportionate reduction in the
transportation costs for short supply during the period between June 1994 to Jan
2003.
Issue 7: Claims not barred by time since the invoices continued to be provisional.